Actions for Responses to homelessness

Responses to homelessness

Community Services
Justice
Management and administration
Project management
Service delivery

What the report is about

The report assessed how effectively the Department of Communities and Justice is responding to homelessness through the NSW Government’s Homelessness Strategy.

It also assessed the effectiveness of the department’s efforts to address street homelessness in its COVID-19 response.

What we found

The strategy was designed to build evidence to inform future state-wide action rather than to end homelessness.

The department received significantly less funding than it sought for the strategy.

Actions delivered under the strategy have a narrow reach in terms of locations and number of people targeted for assistance.

The strategy will have limited short-term impact on homelessness across NSW, but it is building evidence on what works to prevent and reduce homelessness.

The department effectively implemented a crisis response to assist over 4,350 people sleeping rough into temporary accommodation during the pandemic.

While there was an effective crisis response to assist people sleeping rough during the pandemic, more will need to be done to ensure a sustainable response which prevents people returning to homelessness.

What we recommend

The department should:

  • provide advice to the NSW Government on sustainably addressing demand and unmet need for homelessness supports
  • commence development of a comprehensive strategy to address homelessness, linked to the government’s 10-year plan for social housing and 20-year housing strategy
  • enable input to key decisions on homelessness policy from partner agencies, the specialist homelessness services sector, the community housing sector, Aboriginal people, and people with lived experience of homelessness
  • partner with Aboriginal stakeholders and communities to design and implement a strategy for early identification and responses to the needs of Aboriginal people vulnerable to homelessness; and build the capacity and resourcing of the Aboriginal Community Controlled Sector to deliver homelessness services
  • evaluate the homelessness response to COVID-19, integrate the lessons learned into future practice, and develop protocols to inform actions in future emergencies or disasters
  • regularly collect client outcomes data and feedback and use this to drive improvements to responses to homelessness.

Fast facts

Homelessness Strategy
  • $169m total additional and existing funding allocated to the strategy.
  • 22% of the number of people in NSW experiencing homelessness in 2016 may be supported by strategy actions.
COVID-19 response 1 April 2020 to 31 January 2021
  • 400 people sleeping rough in temporary accommodation were assisted with two year rentals and wrap around support packages.
  • 72% of people sleeping rough provided with temporary accommodation were estimated to have left with unknown housing outcomes.

Further information

Please contact Ian Goodwin, Deputy Auditor-General on 9275 7347 or by email.

Homelessness exists when a person does not have suitable accommodation alternatives. A person is considered to be experiencing homelessness if their current living arrangement:

  • is in a dwelling that is inadequate; or
  • has no tenure, or if their initial tenure is short and not extendable; or
  • does not allow them to have control of, and access to space for social relations.

The number of people experiencing homelessness in New South Wales increased by 37 per cent between the last two censuses, from 27,479 in 2011, to 37,715 in 2016. New South Wales recorded the largest increase of all the states and territories in both the number of people experiencing homelessness and in the homeless rate (from 40.8 to 50.4 persons per 10,000).

The NSW Government's primary service response to homelessness is crisis, temporary and transitional accommodation, and support services, funded at more than $1.0 billion over four years from 2018–19. These are ‘commissioned services’ delivered by non‑government organisations under contracts with the Department of Communities and Justice (the Department) and out of scope for this audit. We assessed how the Department manages contracts for specialist homelessness services in our 2019 audit 'Contracting non‑government organisations'.

The policy framework for the NSW Government's response to homelessness is the NSW Homelessness Strategy 2018–23 (the Strategy), which is examined in this audit. The Department is responsible for the development, implementation, monitoring and evaluation of the Strategy. The Strategy comprises 21 actions, ten of which directly target people at risk of, or already experiencing, homelessness through measures such as:

  • screening high school students for the risk of homelessness and providing supports
  • assisting vulnerable people to maintain their tenancies in social housing or the private rental market
  • providing purpose‑built social housing.

These ten actions comprise $160 million of the Strategy's $169 million funding.

In December 2019, the first evidence of the COVID‑19 virus emerged. People sleeping without shelter or in public places (sleeping rough) typically live in communal arrangements, with some having limited access to basic hygiene supplies or showering facilities. These factors may increase the risk of transmission of COVID‑19 amongst this population.

In response to the pandemic, the NSW Government provided additional funding for the Department to institute a range of actions aimed at preventing vulnerable people from becoming homeless, and people sleeping rough from contracting or transmitting the virus. These were informed by, but separate to, actions under the Homelessness Strategy.

This audit focused on the temporary accommodation provided to individuals experiencing street homelessness during the pandemic, and the new 'Together Home' program established in 2020 to transition people with experience or history sleeping rough from temporary accommodation into more sustainable longer‑term housing.

This audit assessed how effectively the Department is implementing the Homelessness Strategy and addressing street homelessness in its COVID‑19 response. In making this assessment, the audit examined whether the Department:

  • has effectively developed an evidence‑based Strategy and established supporting arrangements to implement it
  • is ensuring the Strategy is achieving its objectives and outcomes
  • is effectively supporting people sleeping rough into temporary accommodation during COVID‑19 and to transition into more sustainable longer‑term housing.

Conclusion

The $169 million Homelessness Strategy will have a limited short‑term impact on homelessness across New South Wales.

The Department designed the Strategy to build evidence to inform future state‑wide action rather than to end homelessness. The Department also received significantly less funding than it sought, and as a result, the Strategy's actions have a narrow reach in terms of the locations and the number of people targeted for assistance.

The Department has clearly communicated its aims to intervene early to prevent people from experiencing homelessness; to provide effective supports to people experiencing homelessness; and to create an integrated person‑centred system. While these objectives are clear, they are not being pursued state‑wide.

The Department recognised in its advice to government on Strategy resourcing that growing demand could not be met within current funding and housing supply, and that there was limited proof on effective preventative and early interventions in the available evidence base. Given the evidence threshold for new funding, the Department designed the Strategy to pilot approaches which help to identify the best prevention and early intervention measures for state‑wide roll out after the Strategy's five‑year term, subject to budget approval.

The Department received significantly less funding than it sought for the Strategy. It repurposed existing resources, dropped some proposed actions and scaled others down to fit within the final funding envelope. While seeking to demonstrate what works to prevent homelessness or intervene earlier, the Department directed 95 per cent of the final Strategy funding to concrete actions supporting people at risk of, or experiencing, homelessness.

The Department has put in place governance and operational arrangements which are supporting the implementation and evaluation of the Strategy, and it is broadly on track with reaching the target number of clients expected. The Department’s data shows that more than 4,100 people have received direct supports under Strategy actions. However, the reach of the Strategy remains constrained. Once fully implemented, most Strategy actions will be available in only a quarter of the state's local government areas, supporting around 8,200 people ‑ what equates to around 22 per cent of the number of people experiencing homelessness in New South Wales at the last census in 2016.

There is a risk that future funding will not be secured – and Strategy actions not continued or scaled up – if the evidence on effectiveness is incomplete, mixed or unclear when the Strategy concludes. This sits against a backdrop of increasing need for housing and homelessness supports in the state that may become more acute once the full economic impacts of the COVID‑19 pandemic are felt.

The Department effectively planned and implemented a crisis response to assist people sleeping on the streets during the COVID‑19 pandemic. The Department will need to do more to ensure a sustainable longer‑term response which prevents people returning to street homelessness.

The Department's crisis response focused on people sleeping rough due to the public health risk of COVID‑19 transmission amongst this group. Of the approximately 32,500 people provided with temporary accommodation between 1 April 2020 and 31 January 2021, 4,355 were sleeping rough. As at 13 May 2021, only one case of COVID‑19 had been detected to date among the individuals who received assistance. The Department advises that around one‑quarter of all those placed in temporary accommodation were assisted into social housing or private rental accommodation.

Within metropolitan Sydney, the Department established a dedicated team and contracted provider to connect people sleeping rough placed in hotels with support services, and to assist and monitor their transition to longer‑term housing. The Department’s data suggests that almost 38 per cent of the approximately 1,800 people who received this support were able to move to social housing or private rental accommodation. However, the Department did not track the housing outcomes for clients who were not provided with this support, or who were not engaged with housing or funded support services.

The Department offers supports to people in temporary accommodation to assist them in finding longer term housing, and it has a policy to not knowingly exit someone from temporary accommodation into homelessness. However, it does not track housing outcomes for every client if they do not engage with the Department's housing or funded support services.

The Department cannot precisely identify how many people sleeping rough assisted during COVID‑19 have returned to rough sleeping or other forms of homelessness. The Department’s data suggests that 72 per cent of the approximately 4,000 people sleeping rough assisted with temporary accommodation between April 2020 and April 2021 who exited left with an unknown housing outcome. The Department intends to conduct research in the future to better understand what happens to people who leave temporary accommodation without seeking further assistance.

The Department also has limited data to understand whether the enhanced temporary accommodation program was more effective in helping to connect participants with services and support them into stable accommodation, than previous approaches.

The Department extended an existing initiative for community housing providers to head lease properties in the private rental market and ensure support services for people who were sleeping rough before being assisted into enhanced temporary accommodation. As at April 2021, the Together Home program has assisted 400 people to obtain accommodation and supports for two years. However, the number of Together Home places is significantly less than what is required to provide housing for the more than 4,350 individuals who were sleeping rough prior to entering enhanced temporary accommodation.

The Department advises it is using a combination of ‘business‑as‑usual’ options to assist other people sleeping rough into stable accommodation where Together Home places are not available, including social and affordable housing and supported transitional accommodation. It also intends to secure longer‑term housing options for Together Home clients after the two‑year support ends. But it is not clear how it will overcome longstanding housing challenges to do so, given the complexity of needs amongst this client group, the limited availability of affordable rental properties and the existing scale of unmet need for social housing in New South Wales.

1. Key findings: the Homelessness Strategy

The Strategy's geographical and client reach is limited because it is building the evidence base on what works

The Department's objectives to intervene early, provide effective supports and create an integrated person‑centred system to address homelessness are clear, but are not being pursued state‑wide.

There were existing gaps in the available evidence which made it difficult for the Department to develop a holistic, state‑wide, long‑term solution to homelessness. Some of the actions under the Strategy have a degree of supporting evidence. Other actions are intended to generate evidence through pilots and by evaluating existing programs more robustly.

At least one Strategy action is available in each of the Department's 16 districts, and there are examples of the Department rolling out practice changes from Strategy pilots across the state. However, progress towards the Strategy aims is confined to pockets where actions are being trialled.

Once fully implemented, Strategy actions will be available in only a quarter of the state's 128 local government areas and will support approximately 8,200 people ‑ which equates to around 22 per cent of the number of people who were experiencing homelessness at the time of the last census in New South Wales in 2016 more than 37,000 people. This does not include the number of people at risk of homelessness.

A key gap in Strategy actions is addressing Aboriginal homelessness.

The Department received significantly less funding than sought and designed the Strategy to build the evidence base rather than eliminate homelessness

The Department could not meet the evidence threshold for a cost benefit analysis required by a Treasury business case, given the limited evidence available locally and internationally on what works to prevent homelessness or intervene earlier. The Department sought new, targeted investment to extend a small number of initiatives with proven effect, and to build the evidence base about other measures that work, rather than the quantum of funding required to end homelessness in New South Wales.

Even so, approved funding was significantly less than that sought by the Department. It repurposed existing resources, dropped some proposed actions and scaled others down to fit within the final funding envelope. It directed 95 per cent of the total Strategy funding to supports and accommodation for people at risk of or experiencing homelessness.

The Department intends to use the gathered data from implementation of the Strategy to expand effective prevention and early intervention measures after it concludes, subject to budget approval. It expects that, over time, these initiatives will reduce the demand for crisis services.

Actions may not be scaled up at the end of the Strategy's term, perpetuating the Strategy's limited reach and narrow impact on homelessness

The Department's approach of testing interventions and building the evidence base through the Strategy was well described and provided a clear rationale in its original advice to government. An evaluation framework has been designed to generate sufficient evidence on the overall Strategy and its individual actions for a cost benefit analysis to support a future budget bid.

The Department intends to use the findings from interim evaluation reports, due by September 2021, to determine the programs and pilots with promising evidence that should continue to the end of the Strategy term. It expects this to enable more qualitative and quantitative data to be available to the evaluations, as well as to support service continuity.

However, delays in delivery of some actions under the Strategy, and the time taken for outcomes to be achieved and show up in the data, will impact on the strength of the evidence available at the mid‑term and final Strategy evaluation points. This raises a risk that future funding for a comprehensive Strategy will not be secured ‑ and prevention and early intervention activities not continued or scaled up beyond pilot sites ‑ if the evidence on effectiveness is incomplete, mixed or unclear when the Strategy concludes.

Given its limited reach, even if the existing Strategy actions were retained, and no expansion occurred, it would continue to have a narrow impact on homelessness in New South Wales. This sits against a backdrop of increasing need for housing and homelessness supports in the state that may become more acute once the full economic impacts of the COVID‑19 pandemic are felt.

2. Key findings: the COVID‑19 response to homelessness

The Department effectively planned and implemented its homelessness response to the pandemic and reduced the risk of transmission of COVID‑19 for people sleeping rough

The Department's crisis response focused on people sleeping rough due to the public health risk of COVID‑19 transmission amongst this group.

The Department engaged with the specialist homelessness services sector from mid‑March 2020 to modify service delivery, advise on infection control and plan extra supports. It explored options with temporary accommodation providers to support self‑isolation for clients, and scaled up its assertive outreach patrols by staff, specialist caseworkers and health professionals to support people sleeping rough into crisis or temporary accommodation for safety.

The Minister directed the Department to address street homelessness in the COVID‑19 response using the Government’s second stage of stimulus funding. The Department procured hotel, motel or serviced apartment accommodation for 400 people who were sleeping rough, or unable to physically distance in large crisis accommodation centres, within a week of the ministerial direction, building on existing programs. The Department provided advice to the Minister on the need to adjust existing policy settings to meet the forecast demand for temporary accommodation services.

The Department secured additional temporary accommodation when and where it was required, to accommodate the number of people sleeping rough who wanted support. Between 1 April 2020 and 31 January 2021, the Department provided temporary accommodation to 32,158 individuals, of which 4,355 people were sleeping rough, totalling more than 70,000 nights of temporary accommodation and services.

The Department met regularly with NSW homelessness peak organisations and established a Taskforce involving other government agencies, peak organisations, and service providers, to assist in quickly executing the measure and resolving issues arising. The Taskforce built on existing collaborative arrangements in place to support cross‑sectoral coordination, enabling it to respond quickly to COVID‑19.

The Department worked with NSW Health and health providers to ensure its COVID‑19 response to homelessness was in line with health guidelines. As of May 2021, just one participant in the Department's enhanced temporary accommodation program had contracted COVID‑19.

The Department does not know how many people sleeping rough who were assisted with enhanced temporary accommodation have returned to homelessness

Within metropolitan Sydney, the Department established a specialist housing team, and contracted a non‑government provider, to connect people placed in hotels with support services, provide tailored support, and to assist and monitor their transition to longer‑term housing.

The Department’s data indicates that between May 2020 and 31 January 2021, over 1,800 people who had previously been sleeping rough had been engaged in this program, more than four times the expected client numbers. Almost half moved into further accommodation when they left the program, including people supported with longer‑term housing such as social housing, community leasing under the Together Home program, and private rental arrangements.

However, the Department did not track the housing outcomes for clients who were not provided with this support, or who disengaged from services. The Department advises that this would have required additional resourcing to do so.

The Department offers assistance to people in temporary accommodation to find longer term options, and has a policy to not knowingly exit someone from temporary accommodation into homelessness. However, it does not track housing outcomes for every client if they do not engage with the Department's housing or funded support services. It intends to conduct research in the future to better understand what happens to people who leave temporary accommodation without seeking further assistance from the Department.

The Department cannot identify precisely how many people sleeping rough who were assisted during COVID‑19 have returned to rough sleeping or other forms of homelessness. The Department’s data suggests that 72 per cent of the approximately 4,000 people formerly sleeping rough who left temporary accommodation between April 2020 and April 2021 left with an unknown housing outcome. This includes people who were not eligible for social housing, were stranded due to border closures, or who disengaged from the Department or funded support services.

The Department also has limited data to understand whether the enhanced temporary accommodation program was more effective in helping to connect participants with services and support them into stable accommodation, than previous approaches.

The Together Home program was established quickly to assist people into more permanent accommodation but will not meet demand as a standalone response

The Department established the Together Home program in September 2020 to provide longer‑term accommodation to people who were sleeping rough during the pandemic. Community housing providers head‑lease properties in the private rental market for two years and sub‑lease these to clients, while ensuring they receive additional support, such as health services, to help them maintain the lease.

Under the initial tranche of funding, the Together Home program aimed to support 400 people sleeping rough. This target was met by April 2021. Due to increased rental demand in many areas of the state, there were some delays in securing properties in certain areas. In addition, people on temporary visas, or with existing public housing debt, are ineligible for this program.

A further $29.0 million was provided to this program through the 2020–21 NSW Budget, creating 400 additional program places. However, the total number of 800 Together Home places will not be sufficient to provide housing for the more than 4,000 individuals who were sleeping rough prior to entering enhanced temporary accommodation.

The Department advises it is using a range of ‘business‑as‑usual’ options to assist other people sleeping rough into stable accommodation outside of the Together Home program. These options include social housing, supported transitional accommodation, subsidised private rental, boarding houses, and referral to mental health and substance addiction rehabilitation facilities.

The Department’s latest annual state‑wide street count suggested that the number of people sleeping rough across New South Wales decreased by 13 per cent between February 2020 and February 2021. The Department has acknowledged that it could do more to monitor and support the housing outcomes for people in temporary accommodation after they exit.

The Department has plans to secure longer‑term housing options for Together Home clients after the two‑year program, through commissioned community housing and private rental assistance. However, it is not clear how this will overcome existing housing challenges given the complexity of needs amongst this client group, the limited availability of affordable rental properties and the existing scale of unmet need for social housing.

3. Recommendations

By July 2022, the Department of Communities and Justice should:

  1. use data and analysis identified through the Homelessness Strategy 2018–2023 and provide advice to the NSW Government on sustainably addressing demand and unmet need for homelessness supports

  2. use the evidence obtained through the Homelessness Strategy 2018–2023 to commence development of a comprehensive strategy to address homelessness, linked to the government’s ten‑year plan for social housing and 20‑year housing strategy

  3. establish and sustain governance arrangements that enable input to key decisions on homelessness policy from partner agencies, the specialist homelessness services sector, the community housing sector, Aboriginal people and people with lived experience of homelessness

  4. in partnership with Aboriginal stakeholders and communities, design and implement a strategy for early identification and responses to the needs of Aboriginal people vulnerable to homelessness; and build the capacity and resourcing of the Aboriginal Community Controlled Sector to deliver homelessness services

  5. evaluate the homelessness response to COVID‑19 and integrate the lessons learned into future practice; and develop protocols to inform actions in future emergencies/disasters

  6. establish and sustain a means to regularly collect client outcomes data and feedback; and use this to drive improvements to responses to homelessness.

This chapter considers how effectively the NSW Homelessness Strategy was developed and is currently being implemented by the Department of Communities and Justice.

This chapter examines how effectively the Department of Communities and Justice addressed homelessness in its response to the COVID‑19 pandemic, and how well it is applying lessons learned from the pandemic to future policy and service development.

Appendix one – Response from agency

Appendix two – Actions within the NSW Homelessness Strategy 2018–23

Appendix three – Reported progress on Homelessness Strategy actions to date (unaudited)

Appendix four – Key homelessness data collections

Appendix five – Temporary accommodation for people sleeping rough standard practice vs COVID 19 response

Appendix six – Key measures in the COVID 19 response to homelessness

Appendix seven – About the audit

Appendix eight – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #350 - released (4 June 2021).

Published

Actions for One TAFE NSW modernisation program

One TAFE NSW modernisation program

Education
Finance
Management and administration
Project management
Shared services and collaboration

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the management of the One TAFE NSW modernisation program.

In 2016, the Government released 'A Vision for TAFE NSW' which stated that TAFE NSW needed to become more flexible, efficient and competitive. It set out the need to progressively reduce significant cost inefficiencies, including by moving away from separate institutes to a single institute model. TAFE NSW established the One TAFE NSW modernisation program to deliver on that vision.

The Auditor General found that the One TAFE NSW modernisation program did not deliver against its key objectives within planned timeframes. The modernisation program originally aimed to realise $250 million in annual savings from 2018–19. Because of project delays and higher than expected transition costs, TAFE NSW did not meet the original savings target. TAFE NSW has made progress on key elements of the program and anticipates that savings will be realised in coming years.

The report makes two recommendations to improve governance arrangements for delivering on commercial objectives and increasing transparency of non commercial activities. 

The report also identifies a series of lessons for future government transformation programs.

TAFE NSW is the public provider of Vocational Education and Training (VET) in New South Wales. In 2018, TAFE NSW enrolled 436,000 students in more than 1,200 courses at around 130 locations across the State.

There have been major policy changes impacting TAFE NSW over the past decade. Under the Smart and Skilled reform, TAFE NSW started to compete with other Registered Training Organisations (RTOs) for a share of the student market.

In 2016, the NSW Government released 'A Vision for TAFE NSW'. The Vision stated that a failure to adapt to market circumstances had left TAFE NSW with unsustainable costs and inefficiencies. To address this, TAFE NSW needed to become more flexible, efficient and competitive. It set out that TAFE NSW must progressively reduce significant cost inefficiencies, including by moving away from a model of separate institutes to a One  TAFE NSW model. The NSW Government set TAFE NSW a target to achieve savings through implementing the Vision.

TAFE NSW established the One TAFE NSW modernisation program to deliver on that vision. The program initially aimed to deliver savings of $250 million per year from 2018–19, but this target was reviewed and updated as the program was being delivered.

This audit assessed whether TAFE NSW effectively managed the One TAFE NSW modernisation program to deliver on the NSW Government's vision for TAFE NSW. In making this assessment, the audit examined whether:

  • delivery of the program was well planned
  • the program was driven by sound governance arrangements
  • TAFE NSW is making progress against the intended outcomes of the program.

The audit focused on the effectiveness of planning, governance and reporting arrangements. It examined five projects within the overall modernisation program as case studies.

Conclusion

The One TAFE NSW modernisation program was an ambitious plan to deliver on the NSW Government’s vision for TAFE NSW, while achieving ongoing savings. Several factors contributed to TAFE NSW not effectively managing the program to deliver on planned timeframes and objectives. These factors include unclear expectations of the primary role of TAFE NSW, unrealistic timeframes, undertaking a large number of complex projects concurrently, governance arrangements that were not fit-for-purpose and poor-quality data.

Planning for the modernisation program and its projects was driven by top-down savings targets and pre-determined timeframes. This led to TAFE NSW attempting to deliver a large number of programs concurrently within tight timeframes. Program management capability was underdeveloped at the commencement of the program and this affected the quality of planning for delivery.

There was a lack of clarity around TAFE NSW's primary purpose. Part of the NSW Government's vision for TAFE NSW was for it to be more commercial, competitive and efficient. These objectives were not fully supported by existing legislation. The commercial objectives of the modernisation program conflicted with legislated social objectives for TAFE NSW. TAFE NSW did not have the autonomy to operate like a government-owned business in a market environment. And while TAFE NSW received separate funding to support students facing disadvantage this did not cover the costs of other non-commercial activities undertaken for social purposes, such as delivering uneconomic courses. The role of the TAFE Commission Board was ambiguous during the initial years of the program, which increased reporting requirements and blurred accountabilities for decision-making.

TAFE NSW's Strategic Plan 2016-22 nominated ten key milestones for delivery by January 2019. TAFE NSW has made progress against several important milestones, including that TAFE ‘is a single TAFE NSW brand’ and has 'industry specific TAFE NSW SkillsPoints'. Other key elements have yet to be delivered, including that TAFE NSW achieves 'integrated enterprise-wide business systems'. Because of delays to projects and higher than expected transition costs, TAFE NSW reported that it did not meet the originally targeted $250 million in annual savings for 2018–19 (which was reviewed and updated as the program was being delivered). 

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #346 - released 17 December 2020

Published

Actions for Procurement management in Local Government

Procurement management in Local Government

Local Government
Internal controls and governance
Management and administration
Procurement
Regulation
Service delivery

The Auditor‑General for New South Wales, Margaret Crawford, released a report today examining procurement management in Local Government.

The audit assessed the effectiveness of procurement management practices in six councils. All six councils had procurement management policies that were consistent with legislative requirements, but the audit found compliance gaps in some councils. The audit also identified opportunities for councils to address risks to transparency and accountability, and to ensure value for money is achieved when undertaking procurement.

The Auditor‑General recommended that the Department of Planning, Industry and Environment review the Local Government (General) Regulation 2005 and publish updated and more comprehensive guidance on procurement management for the Local Government sector. The report also generated insights for the Local Government sector on opportunities to strengthen procurement practices.

Effective procurement is important in ensuring councils achieve their objectives, demonstrate value for money and deliver benefits to the community when purchasing goods and services. Procurement also comes with risks and challenges in ensuring the purchased goods and services deliver to expectations. The risks of fraud and conflicts of interest also need to be mitigated.

The legislative requirements related to procurement in the Local Government sector are focused on sourcing and assessing tender offers. These requirements are included in the Local Government Act 1993 (the Act), the Local Government Amendment Act 2019 (the Amendment), the Local Government (General) Regulation 2005 (the Regulation), the Tendering Guidelines for NSW Local Government 2009 (the Tendering Guidelines), the Government Information (Public Access) Act 2009 (the GIPA Act) and the State Records Act 1998.

General requirements and guidance relevant to councils are also available in the Model Code of Conduct for Local Councils in NSW 2018 (the Model Code), the NSW Government Procurement Policy Framework 2019 and in publications by the Independent Commission Against Corruption (ICAC).1

Individual councils have developed their own procurement policies and procedures to expand on the legislative requirements. Understandably, these vary to reflect each council’s location, size and procurement needs. Nevertheless, the general principles of effective procurement management (such as transparency and accountability) and risk-mitigating practices (such as segregation of duties and the provision of training) are relevant to all councils.

The Audit Office of New South Wales Report on Local Government 2018 provided a sector-wide summary of aspects of procurement management in Local Government (see Section 2.1 of this report). This audit builds on this state-wide view by examining in detail the effectiveness of procurement management practices in six councils. This report also provides insights on opportunities to strengthen procurement management in the sector.

The selected councils for this audit were Cumberland City Council, Georges River Council, Lockhart Shire Council, Tweed Shire Council, Waverley Council and Wollongong City Council. They were selected to provide a mix of councils of different geographical classifications, sizes, priorities and levels of resourcing.

Conclusion

All six councils had procurement management policies and procedures that were consistent with the legislative requirements for sourcing and assessing tender offers. Their policies and procedures also extended beyond the legislative requirements to cover key aspects of procurement, from planning to completion. In terms of how these policies were applied in practice, the six councils were mostly compliant with legislative requirements and their own policies and procedures, but we found some gaps in compliance in some councils and made specific recommendations on closing these gaps.

There were also opportunities for councils to improve procurement management to mitigate risks to transparency, accountability and value for money. Common gaps in the councils’ procurement management approaches included not requiring procurement needs to be documented at the planning stage, not providing adequate staff training on procurement, not requiring procurement outcomes to be evaluated, and having discrepancies in contract values between contract registers and annual reports. These gaps expose risks to councils’ ability to demonstrate their procurements are justified, well managed, delivering to expectations, and achieving value for money. Chapter three of this report provides insights for the audited councils and the Local Government sector on ways to address these risks

Recommendations

  1. By June 2022, the Department of Planning, Industry and Environment should:
    1. publish comprehensive and updated guidance on effective procurement practices – including electronic tender submissions and procurements below the tender threshold
    2. review and update the Local Government (General) Regulation 2005 to reflect the increasing use of electronic tender submissions rather than paper copies.
  2. By December 2021, the six audited councils should consider the opportunities to improve procurement management in line with the improvement areas outlined in chapter three of this report.
  3. Cumberland City Council should immediately:
    1. ensure contract values are consistent between the contract register and the annual report
    2. introduce procedures to ensure supplier performance reviews are conducted as per the council’s policy
  4. Georges River Council should immediately:
    1. ensure contract values are consistent between the contract register and the annual report
    2. introduce procedures to ensure all the steps up to the awarding of a contract are documented as per the council’s policy
    3. introduce procedures to ensure outcome evaluations are conducted as per the council’s policy.
  5. Lockhart Shire Council should immediately:
    1. include additional information in the council’s contract register to ensure compliance with Section 29(b), (f), (g), (h) and (i) of the GIPA Act
    2. ensure contract values are consistent between the contract register and the annual report.
  6. Waverley Council should immediately ensure contracts are disclosed in the annual report as per Section 217(1)(a2) of the Regulation.

(1) The relevant ICAC publications include: Corruption Risks in NSW Government Procurement – The Management Challenge (2011), Corruption Risks in NSW Government Procurement – Suppliers’ Perception of Corruption (2011) and Corruption Risks in NSW Government Procurement – Recommendations to Government (2011).

While all six councils had procurement policies in place and were generally compliant with legislative requirements, this report has identified common gaps in processes and practices that expose risks to transparency, accountability and value for money.

This section discusses how councils can mitigate risks and ensure the best outcomes are achieved from their procurements.

Documented justification of procurement needs

The ICAC notes that determining what goods and services an agency requires is the first step of procurement, and the scope for corruption in how need is determined is significant. Without documenting how procurement needs have been justified, councils cannot demonstrate that they fulfill business needs, nor how the procurements may link to the councils’ strategic plans to deliver to the community.

This audit found that none of the six councils’ policies required them to document justification of procurement needs, and none did so consistently in practice. Councils can address this gap by building into their procurement planning process a requirement for staff to document the justification of procurement needs. For higher value procurements, this could be extended to include analysis of options, an assessment of risks and defining intended outcomes. Similarly, clearly establishing and documenting how relevant procurements relate to a council’s community strategic plans or operational plans helps ensure transparency.

Although a formal business case may not be required for many procurements (for example, low-value procurements or routine replacements), some form of documented justification for the expenditure should still be kept on record to demonstrate that the procurement relates to business purposes and is needed.

Segregation of duties

Segregation of duties is an effective control for reducing risks of error, fraud and corruption in procurement. It works on the principle that one person should not have end-to-end control of a procurement. Effective segregation of duties also often involves managerial or independent oversight that is built into the process. Four of the audited councils (Cumberland City Council, Georges River Council, Lockhart Shire Council and Wollongong City Council) appropriately addressed segregation of duties in their procurement frameworks. For example:

  • All procurements in Cumberland City Council required a delegated officer’s approval before commencing, and the requisitioning department is responsible for ensuring the completion of the goods, works or services associated with each contract. For contracts over $50,000, a specific ‘Authority to Procure’ form had to be completed by the requesting staff, signed by an approver and then forwarded to the procurement team.

  • Reflecting its small size, all procurements in Lockhart Shire Council were managed by one senior staff member. Nevertheless, this staff member had to bring contract management plans to the rest of the Executive Leadership Team for review and discussion, with large contracts such as those above the tender threshold referred to Council for approval.

The ICAC notes that segregation of duties helps to control discretion, which has particular risk implications for some types of procurement.This includes those involving low-value and high-volume transactions, restricted tenders, long-standing procurements and ‘pet projects’ (projects advocated by individual staff members). In cases where corruption risks are low, ICAC notes that monitoring staff’s involvement in procurement may be a cost-effective alternative to total segregation of duties.

Assessment of supplier performance

Councils need to monitor and assess supplier performance to ensure suppliers deliver the goods and services as agreed. The audit found that all six councils consistently monitored progress in capital works and for externally funded projects. Contract monitoring in these cases included ensuring timelines, funding, and legislative requirements were met. This is positive, as capital works made up the bulk of procurements (in terms of volume) in all of the audited councils.

That said, in all six councils, the level of scrutiny was lower for other types of procurements, and there is scope for improvement. For instance, the approach to monitoring capital works or externally funded projects could be replicated across other procurements of a similar nature and value. Conducting assessments and keeping records of supplier performance on all procurements does not need to be onerous, but instead provides useful information to inform future decision-making—including by helping ensure supplier pricing remains competitive, and avoiding re-engaging underperforming suppliers.

The NSW Government Procurement Policy Framework requires that NSW Government agencies establish systems and processes jointly with the suppliers to ensure compliance with contract terms and performance requirements. It also advises that agencies should drive continuous improvement and encourage innovation in coordination with suppliers and key stakeholders.

Centralised contract register

Centrally registering a contract provides improved transparency of procurement activities and facilitates monitoring and compliance checks. While councils are already required to maintain a contract register for all contracts above the reporting threshold (as per the GIPA Act), given the threshold is set at a relatively high benchmark ($150,000), there is merit in councils extending the practice to procurements below the reporting threshold. A central and comprehensive register of contracts helps avoid duplication of procurements and re-contracting of underperforming suppliers.

Three of the audited councils (Georges River Council, Tweed Shire Council and Wollongong City Council) had contract register policies that applied to procurements below the reporting threshold during the audited period. For example, Georges River Council required contracts valued at $10,000 or above to be registered with the procurement team, and Tweed Shire Council had a threshold of $50,000.

Evaluation of community outcomes and value for money

Councils may be progressing procurements to fulfill their strategic and business plans, or using them to fulfill commitments to the community. In these instances, outcomes evaluation is an important way to demonstrate to the community that the intended benefits and value for money have been delivered.

Five of the six audited councils did not require evaluations of community outcomes and value for money. While Georges River Council required contracts valued at $50,000 or more to be monitored, evaluated and reported on at least annually throughout the contract and also at its conclusion, in the procurements we examined the only ‘outcome evaluations’ that the council had conducted were community surveys that did not refer to individual procurements. Councils can miss opportunities to understand the impact of their work on the local community if evaluations of procurement outcomes are not completed. Evaluation findings are also valuable in guiding future resource allocation decisions.

Value for money in the procurement of goods and services is more than just having the specified goods delivered or services carried out. The NSW Government Procurement Policy Framework requires that state government agencies track and report benefits to demonstrate how value for money is being delivered. The framework notes that value for money is not necessarily the lowest price, nor the highest quality good or service, but requires a balanced assessment of a range of financial and non-financial factors, such as: quality, cost, fitness for purpose, capability, capacity, risk, total cost of ownership or other relevant factors.

Procurement training

Effective procurement management relies on the capability of staff involved in various stages of the process. Guidance can be provided through training, which is an important element of any procurement management framework. It ensures that staff members are aware of the councils' policies and procedures. If structured appropriately and provided in a timely manner, training can help to standardise practices, ensure compliance, reduce chances of error, and mitigate risks of fraud or corruption.

The ICAC notes that effective procurement management depends on the competence of staff undertaking procurements and the competence of those who oversee procurement activities. As the public sector is characterised by varying levels of procurement expertise, the ICAC notes that the sector would benefit from a structured approach to training and the application of minimum standards.3

At the time of this audit, only Wollongong City Council addressed staff training requirements in its procurement management framework. Exhibit 8 details its approach.

Exhibit 8: Wollongong City Council's approach to training
  • Wollongong City Council has a suite of procurement training available for staff, administered by a dedicated staff member who also monitors attendance and training needs
  • Staff must complete training before they can take part in a procurement or be a member of a tender assessment panel, and the council keeps a list of all accredited staff members.
  • Staff cannot access procurement files on the council's electronic records management system until they have received training and have been approved for access by the trainer.
  • Staff must be trained before they can receive a financial delegation.

Source: Audit Office of New South Wales analysis of Wollongong City Council's procurement policies and procedures 2020.
 

Two of the audited councils have now also introduced procurement training:

  • Georges River Council implemented online training, which is mandatory for new staff and serves as refresher training for existing staff. The council also provides in-person training for selected staff (covering contract management, contract specification writing and contractor relationship management) and has developed quick reference cards for all staff to increase awareness of the council's procurement processes.
  • Tweed Shire Council implemented mandatory online training for all staff members. The training covers the council's procurement policy and protocol as well as relevant legislation. It is linked to relevant council documents such as the Procurement Toolkit on the council's intranet, and includes a quiz for which training participants must score at least 80 per cent to have the training marked as completed.
(2) ICAC (2011) Corruption Risks in NSW Government Procurement – The Management Challenge.
(3) ICAC (2011) Corruption Risks in NSW Government Procurement – Recommendations to Government.

Appendix one – Responses from councils and the Department of Planning, Industry and Environment

Appendix two – Councils’ procurement contracts

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #345 - released 17 December 2020

Published

Actions for Waste levy and grants for waste infrastructure

Waste levy and grants for waste infrastructure

Planning
Environment
Management and administration
Regulation
Risk
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today that examined the effectiveness of the waste levy and grants for waste infrastructure in minimising the amount of waste sent to landfill and increasing recycling rates.  

The audit found that the waste levy has a positive impact on diverting waste from landfill. However, while the levy rates increase each year in line with the consumer price index, the EPA has not conducted a review since 2009 to confirm whether they are set at the optimal level. The audit also found that there were no objective and transparent criteria for which local government areas should pay the levy, and the list of levied local government areas has not been reviewed since 2014. 

Grant funding programs for waste infrastructure administered by the EPA and the Environmental Trust have supported increases in recycling capacity. However, these grant programs are not guided by a clear strategy for investment in waste infrastructure. 

The Auditor-General made six recommendations aimed at ensuring the waste levy is as effective as possible at meeting its objectives and ensuring funding for waste infrastructure is contributing effectively to recycling and waste diversion targets.

 

Overall, waste generation in New South Wales (NSW) is increasing. This leads to an increasing need to manage waste in ways that reduce the environmental impact of waste and promote the efficient use of resources. In 2014, the NSW Government set targets relating to recycling rates and diversion of waste from landfill, to be achieved by 2021–22. The NSW Waste and Resource Recovery (WARR) Strategy 2014–21 identifies the waste levy, a strong compliance regime, and investment in recycling infrastructure as key tools for achieving these waste targets.

This audit assessed the effectiveness of the NSW Government in minimising waste sent to landfill and increasing recycling rates. The audit focused on the waste levy, which is paid by waste facility operators when waste is sent to landfill, and grant programs that fund infrastructure for waste reuse and recycling.

The waste levy is regulated by the Environment Protection Authority (EPA) and is generally paid when waste is disposed in landfill. The waste levy rates are set by the NSW Government and prescribed in the Protection of Environment Operations (Waste) Regulation 2014. As part of its broader role in reviewing the regulatory framework for managing waste and recycling, the EPA can provide advice to the government on the operation of the waste levy.

The purpose of the waste levy is to act as an incentive for waste generators to reduce, re-use or recycle waste by increasing the cost of sending waste to landfill. In 2019–20, around $750 million was collected through the waste levy in NSW. The government spends approximately one third of the revenue raised through the waste levy on waste and environmental programs.

One of the waste programs funded through the one third allocation of the waste levy is Waste Less, Recycle More (WLRM). This initiative funds smaller grant programs that focus on specific aspects of waste management. This audit focused on five grant programs that fund projects that provide new or enhanced waste infrastructure such as recycling facilities. Four of these programs were administered by the Environmental Trust and one by the EPA.

Conclusion

The waste levy has a positive impact on diverting waste from landfill. However, aspects of the EPA's administration of the waste levy could be improved, including the frequency of its modelling of the waste levy impact and coverage, and the timeliness of reporting. Grant funding programs have supported increases in recycling capacity but are not guided by a clear strategy for investment in waste infrastructure which would help effectively target them to where waste infrastructure is most needed. Data published by the EPA indicates that the NSW Government is on track to meet the recycling target for construction and demolition waste, but recycling targets for municipal solid waste and commercial and industrial waste are unlikely to be met.

Waste levy

The waste levy rate, including a schedule of annual increases to 2016, was set by the NSW Government in 2009. Since 2016, the waste levy rate has increased in line with the consumer price index (CPI). The EPA has not conducted recent modelling to test whether the waste levy is set at the optimal level to achieve its objectives. The waste levy operation was last reviewed in 2012, although some specific aspects of the waste levy have been reviewed more recently, including reviews of waste levy rates for two types of waste. The waste levy is applied at different rates across the state. Decisions about which local government areas (LGAs) are subject to the levy, and which rate each LGA pays, were made in 2009 and potential changes were considered but not implemented in 2014. Currently, there are no objective and transparent criteria for determining which LGAs pay the levy. The EPA collects waste data from waste operators. This data has improved since 2015, but published data is at least one year out of date which limits its usefulness to stakeholders when making decisions relating to waste management.

Grants for waste infrastructure

All state funding for new and enhanced waste infrastructure in NSW is administered through grants to councils and commercial waste operators. The government's Waste and Resource Recovery (WARR) Strategy 2014–21 includes few priorities for waste infrastructure and there is no other waste infrastructure strategy in place to guide investment. The absence of a formal strategy to guide infrastructure investment in NSW limits the ability of the State Government to develop a shared understanding between planners, councils and the waste industry about waste infrastructure requirements and priorities. The Department of Planning, Industry and Environment is currently developing a 20-year waste strategy and there is an opportunity for the government to take a more direct role in planning the type, location and timing of waste infrastructure needed in NSW.

The grants administration procedures used for the grant programs reviewed in this audit were well designed. However, we identified some gaps in risk management, record-keeping and consistency of information provided to applicants and assessment teams. In four of the five programs we examined, there was no direct alignment between program objectives and the NSW Government's overall waste targets.

Achievement of the 2014–21 state targets for waste and resource recovery (WARR targets) is reliant in part on the availability of infrastructure that supports waste diversion and recycling. The state WARR targets dependent on waste infrastructure are:

  • Increase recycling rates to 70 per cent for municipal solid waste and commercial and industrial waste, and 80 per cent for construction and demolition waste.
  • Increase waste diverted from landfill to 75 per cent.

A further target — manage problem waste better by establishing or upgrading 86 drop-off facilities or services for managing household problem wastes state-wide — is dependent on accessible community waste drop-off facilities across NSW.

Exhibit 7 identifies the five grant programs that provide funding for new or enhanced waste infrastructure to increase capacity for reuse or recycling of waste. All five of these programs were examined in the audit.
In addition to the grant programs shown in Exhibit 7, other programs provide funding for infrastructure, but at a smaller scale. Examples of these include:

  • Bin Trim which provides rebates to small businesses for small scale recycling equipment such as cardboard and soft plastic balers.
  • Litter grants which provide funding for litter bins.
  • Weighbridges grants for installation of a weighbridge at waste facilities.
  • Landfill consolidation and environmental improvement grants for rural councils to replace old landfills with transfer stations or to improve the infrastructure at landfill sites.

Appendix one – Responses from audited agencies

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #343 - released 26 November 2020

Published

Actions for Governance and internal controls over local infrastructure contributions

Governance and internal controls over local infrastructure contributions

Local Government
Planning
Environment
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today on how well four councils managed their local infrastructure contributions during the 2017-18 and 2018-19 financial years. 

Local infrastructure contributions, also known as developer contributions, are collected from developers to pay for local infrastructure such as drainage, local roads, open space and community facilities. Controls over local infrastructure contributions help to ensure that all contributions owed are collected, funds are spent as intended, and any contributions paid in the form of works-in-kind or dedicated land are correctly valued.

The audit found that Blacktown City Council and City of Sydney Council provided effective governance over their local infrastructure contributions whereas Central Coast and Liverpool City Councils’ governance arrangements require improvement.

The audit found that three councils had spent local infrastructure contributions in accordance with approved contributions plans. Central Coast Council and the former Gosford City Council had spent $13.2 million on administration costs in breach of the Environmental Planning and Assessment Act 1979. These funds were repaid into the council’s local infrastructure fund during the course of the audit.

The Auditor-General made a number of recommendations for each council relating to improving controls over contributions and increasing transparency. 

Read full report (PDF)
 

This audit examined the effectiveness of governance and internal controls over local infrastructure contributions, also known as developer contributions, held by four councils during the 2017–18 and 2018–19 financial years.

This performance audit was conducted with reference to the legislative and regulatory planning framework that was in place during that period.

Our work for this performance audit was completed at the end of March 2020 when we issued the final report to the four audited councils and the Department of Planning, Industry and Environment. We received their respective formal responses to the report’s recommendations during April and May 2020.

Concurrently to this audit, we sought Crown Solicitor’s advice (the ‘Advice’) regarding the use of local infrastructure contributions collected by local councils under the Environmental Planning and Assessment Act 1979 (‘the EPA Act’) for our financial audit work. The Advice clarified the applicable legislative requirements with reference to the application, investment and pooling of local infrastructure contributions. The Advice is included in Appendix 2 of this report. The Advice has not impacted on the findings and recommendations of this report.

Councils collect Local Infrastructure Contributions (LICs) from developers under the Environmental Planning and Assessment Act (1979), the Local Government Act (1993) and the City of Sydney Act (2000) (EP&A Act, LG Act and City of Sydney Act) to fund infrastructure required to service and support new development. At 30 June 2018, councils across NSW collectively held more than $3.0 billion in LICs collected from developers. Just over $1.37 billion in total was held by ten councils. Councils collecting LICs must prepare a contributions plan, which outlines how LICs will be calculated and apportioned across different types of infrastructure. Councils that deliver water and sewer services prepare a development servicing plan (DSP) which allows them to collect contributions for water and sewer infrastructure.

Development timeframes are such that there is often several years between when LICs are collected and the infrastructure is required. Good governance and internal controls are needed over these funds to ensure they are available when needed and spent appropriately.

This audit assessed the effectiveness of governance and internal controls over LICs collected by four councils during the 2017–18 and 2018–19 financial years: Blacktown City Council, Central Coast Council, City of Sydney Council and Liverpool City Council. As at June 2018 these councils held the four highest LIC balances, each in excess of $140 million.

Audit Conclusion

Three of the four councils audited were currently compliant with legislation, regulations and Ministerial Directions regarding LICs. All had gaps in governance and controls over LICs which limited effective oversight.

Three of the councils included in the audit complied with legislation, regulations and Ministerial Directions relating to LICs. Central Coast Council breached the EP&A Act between 2001 and 2019 when it used LICs for administration costs. These funds were repaid in late 2019.

While controls over the receipt and expenditure of contributions funds were largely in place at all councils, there were some exceptions relating to valuing work and land delivered in lieu of cash. Three councils do not provide probity guidance in policies relating to LICs delivered through works-in-kind. Three of the councils had contributions plans that were more than five years old.

Staff at all four councils are knowledgeable about LICs but not all councils keep procedures up to date. Three councils' governance frameworks operate effectively with senior officers from across the council involved in decisions about spending LICs, entering into voluntary planning agreements (VPAs) and reviewing contributions plans.

Transparency over key information relating to LICs is important for senior management so they can make informed decisions, and for the community who pay LICs and expect infrastructure to be provided. During the period of the audit, none of the councils included in the audit provided sufficient information to senior management or their councillors about the projected financial status of contributions plans. This information would be valuable when making broader strategic and financial decisions. Information about LIC levies and intended infrastructure is available to the community but not always easy to find.

A strong governance framework is important at each council to ensure that the funds are managed well, available when needed and spent as intended. The audit examined the following features of each council's governance framework as they apply to LICs:

  • decision-making by councillors and council officers relating to LICs
  • monitoring delivery of contributions plans and DSPs including:
    • reviewing assumptions underlying the plans
    • monitoring projected status of plans.

Internal controls over LICs are important to promote accountability, prevent fraud and deliver infrastructure to the required standard at the best possible price. If financial controls are weak or are not implemented well, there is a risk that LICs are misspent or that councils pay too much for infrastructure.

Not all councils' internal controls adequately addressed risks associated with the administration of LICs

The audit examined a number of internal controls that manage risks related to LICs. These included:

  • financial controls over receipt and expenditure of LIC funds
  • management of conflicts-of-interest when dealing with developers
  • independent valuations of works-in-kind and dedicated land
  • ensuring delivery and quality of works-in-kind, and obtaining security from developers in the event of non-delivery or poor quality work
  • management of variations to VPAs and works-in-kind agreements.

We reviewed controls included in policies and procedures and then checked samples of work to ensure that controls were implemented. We found variation in the controls that councils implemented, and some weaknesses in controls. It is a matter for each council to assess their financial risk and develop internal controls that support the collection, management, and expenditure of LICs. However, councils must be able to assure their communities and developers that they are doing everything possible to collect all LICs owing and that work conducted by developers in lieu of cash payments is properly valued and carried out to the required standard.

Further information about audit findings in relation to internal controls for each council are included in chapters five to eight. The exhibit below demonstrates variation in several controls implemented in the audited councils.

In a 2018 report, the Independent Commission Against Corruption noted that 'the appetite for transparency is expanding in both the public and private sectors'.

The Practice Note and S64 Guidance refer to transparency, including the importance of transparency over:

  • calculation and apportionment of LICs
  • funding of infrastructure, including where and when infrastructure is delivered
  • arrangements made with developers through VPAs.

The LIC system is largely transparent for community members who know where to look

Contributions plans and DSPs are public documents, exhibited to the public before being adopted by council. Councils included in the audit publish their contributions plans and DSPs on their websites and meet statutory requirements with regard to reporting and accessibility of information.

However, other public information relating to the LIC system is fragmented across different websites and reports and varies in detail across councils.

Exhibit 10: Published information about LICs at the four audited councils
  Blacktown City Council Central Coast Council City of Sydney Council Liverpool City Council
Financial details about contributions collected and spent Financial statements Financial statements Financial statements Financial statements
Implementation plans for spending LICs Contribution plans S64 implementation plans in DSPs. S7.11 & S7.12 implementation plans developed annually within capital works plan Contribution plans Developed annually within capital works plan
Capital works underway or completed, funded by LICs Capital works plan and annual report Not published Not published Capital works plan
Source: Audit Office analysis.

The Practice Note states that councils are accountable for providing the infrastructure for which contributions are collected. Demonstrating that infrastructure has been provided is difficult with fragmented information. As an example of transparent reporting, Blacktown City Council's 2018–19 annual report includes information about infrastructure that has been delivered for every contributions plan, providing transparency over how LICs have been spent.

Use of LICs collected under VPAs is not always transparent

Contributions collected under VPAs are not required to demonstrate the same relationship to a development as LICs collected under section 7.11 of the EP&A Act. VPAs are often negotiated because a developer requests a change to a planning instrument, and it is important that these arrangements, and their outcomes, are transparent to the community.

The EP&A Regulation includes mechanisms to ensure that VPAs are partially transparent. VPAs are exhibited to the public and approved by the elected council. Councils must maintain a VPA Register and make the VPA Deeds of Agreement available on request. However, there is no obligation on council to report on the outcomes or delivery of developers' obligations under VPAs. The four audited councils vary in transparency and accessibility of information available about VPAs.

Exhibit 11: Published information about VPAs at the four audited councils
  Blacktown City Council Central Coast Council City of Sydney Council Liverpool City Council
VPA Register Council website and annual report Annual report Annual report Council website and annual report
VPA Deeds of Agreement Council website Available on request Available on request Council website
Intended use of LICs collected under VPAs In Deeds of Agreement In Deeds of Agreement In VPA Register and most Deeds of Agreement In VPA Register and most Deeds of Agreement
Completion of work funded by cash collected under VPAs Not published Not published Not published Not published
Delivery of works-in-kind or land negotiated under VPAs Not published Not published In VPA Register Not published
Source: Audit Office analysis.

The Practice Note suggests that councils incorporate the intended use of LICs collected under VPAs in the Deed of Agreement, but there is no guidance relating to transparency over where and when funds have actually been spent. There is merit in councils providing greater transparency over public benefits delivered through VPAs to give communities confidence in VPAs as a planning tool.

Credit arrangements with developers are not always well documented or monitored

When levying LICs, section 7.11(6) of the EP&A Act requires councils to take into account land, money, or works-in-kind that the developer has contributed on other development sites over and above their LIC obligations. This section of the EP&A Act allows a developer to offset a LIC owed on one site against land or works contributed on another. This leads to some developers carrying 'credits' for work delivered to councils, to be paid back by reduced LICs on a future development. Blacktown City Council and Central Coast Council allow developers to carry credits. Liverpool City Council and City of Sydney Council do not permit credits and instead pay the developers for any additional work undertaken.

Councils should formally document credit arrangements and have a robust process to validate and keep track of credit balances and report on them. Central Coast Council does not keep good track of credit arrangements and neither Blacktown City Council or Central Coast Council aggregate or report on outstanding credit balances.

Blacktown City Council manages the largest LIC fund in NSW and negotiates more VPAs than any other council. Overall, Blacktown City Council demonstrates effective governance over the LIC funds but there is scope for improved oversight of the projected financial status of contributions plans and credit arrangements with developers. Blacktown City Council also needs to update its operating procedures relating to LICs and improve security over key information.

Blacktown City Council is managing areas with high growth. There is a risk that Blacktown City Council will be unable to collect sufficient LICs to fund the infrastructure required to support that growth. However, Blacktown City Council does not assess and report to senior management or its Audit, Risk and Improvement Committee about the projected financial status of contributions plans.

Blacktown City Council has policies in place to guide the management of LICs although management of credit arrangements with developers requires greater oversight. Policies relating to works-in-kind agreements provide no guidance about probity in negotiations with developers and valuations of works-in-kind are not independent as they are paid for by the developer. Blacktown City Council's S7.11 committee structure could act as a model for other councils. Blacktown City Council is spending LICs according to its contributions plans. Staff managing LICs demonstrate good knowledge of the regulatory environment. However, a number of administrative processes need attention such as outdated procedures, lack of security over key spreadsheets, and inappropriate retention of sensitive personal data.

Recommendations

By December 2020, Blacktown City Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. update council's works-in-kind policy to address probity risks during negotiations with developers
  3. mitigate risks associated with lack of independence in valuations of works-in-kind
  4. improve public reporting about expenditure of cash collected under VPAs
  5. improve management oversight of credit arrangements with developers
  6. update procedures for managing LICs
  7. implement security measures over critical or personal information and spreadsheets. 

Central Coast Council's governance and internal controls over LICs were not fully effective. Between 2001 and 2019, more than $13.0 million in LICs was misspent on administration costs in breach of the EP&A Act. There is scope for improved oversight of the projected financial status of contributions plans and credit arrangements with developers. Policies and procedures from the two former councils are not aligned.

In May 2016, the newly amalgamated Central Coast Council inherited 53 contributions plans from the former Gosford City and Wyong Shire Councils. Managing this number of contributions plans fragments the available funds and increases complexity. Central Coast Council is currently working on consolidating these plans. Between June 2016 and June 2019, its LIC balance doubled from $90.0 million to $196 million. Central Coast Council does not assess and report to senior management or its Audit, Risk and Improvement Committee about the projected financial status of contributions plans. Central Coast Council has a LIC committee but it has no formal charter and senior officers do not regularly attend meetings. This limits the committee's effectiveness as a decision-making body. A draft policy relating to works-in-kind agreements provide no guidance about probity in negotiations with developers. Valuations of works-in-kind and land dedications are not independent as they are paid for by the developer.

Central Coast Council has adjusted its accounts in 2018–19 by $13.2 million to repay the LIC fund for administration expenses that were not provided for in 40 contributions plans.

Recommendations

By June 2020, Central Coast Council should:

1. obtain independent validation of the adjustment made to the restricted asset accounts and general fund to repay LICs spent on administration, and adjustments made to each infrastructure category within the contributions plans

2. publish current contributions plans from the former Gosford City Council on the Central Coast Council website.

By December 2020, Central Coast Council should:

3. regularly report to senior management on the projected financial status of contributions plans

4. increase transparency of information available to the public about LIC works planned and underway, including intended use of contributions collected under VPAs

5. consolidate existing plans, ensuring the new contributions plans includes a regular review cycle

6. develop a formal charter for the developer contributions committee and increase the seniority of membership

7. complete and adopt council's works-in-kind policy currently under development, ensuring it addresses probity risks during negotiations with developers

8. mitigate risks associated with lack of independence in valuations of works-in-kind and dedicated land

9. improve public reporting about expenditure of cash collected under VPAs

10. improve management oversight of credit arrangements with developers

11. implement security measures to ensure the integrity of key spreadsheets used to manage LICs

12. align policies and procedures relating to LICs across the amalgamated council including developing policies and procedures for the management of S64 LICs

13. update council's VPA policy to address increased or indexed bank guarantees to accommodate cost increases.

City of Sydney Council manages a complex development environment across the Sydney CBD and inner suburbs. Overall, governance and internal controls over LICs are effective although there is scope for improved oversight of the projected financial status of contributions plans.

City of Sydney Council maintains a large balance of LICs, although not excessive relative to the annual level of LIC expenditure. Unspent contributions are largely associated with open space infrastructure that cannot be delivered until suitable land is available. Thirty per cent of cash contributions are collected under VPAs and there is limited transparency over how these funds are spent. City of Sydney Council does not assess and report to management or its Audit, Risk and Compliance Committee about the projected financial status of contributions plans.

In 2017–18 and 2018–19, LICs were spent in accordance with the corresponding contributions plans. City of Sydney Council staff are knowledgeable about the regulatory environment and are supported by up-to-date policies and procedures.

Recommendations

By December 2020, City of Sydney Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. improve public reporting about expenditure of cash collected under VPAs
  3. periodically review the risk of unpaid LICs associated with complying development certificates and assess whether additional controls are required
  4. implement security measures to ensure the integrity of key spreadsheets used to manage LICs. 

During the audit period 2017–18 and 2018–19, Liverpool City Council did not have effective governance and internal controls over LICs. Liverpool City Council is addressing deficiencies and risks identified through an internal audit published in December 2018 although further work is required. There is scope for improved oversight of the projected financial status of contributions plans.

In the two years to 30 June 2019, the balance of unspent LICs increased by more than 60 per cent against a relatively low pattern of expenditure. Prior to an internal audit completed in late 2018, there was no regular reporting on the status of LICs and a lack of transparency when prioritising the expenditure of LIC funds. During 2019, and following the internal audit, Liverpool City Council engaged additional skilled resources to improve focus and accountability for LICs. A LIC committee has been established to manage contributions plans and support business units to initiate relevant infrastructure projects, although it is too early to assess whether this committee is operating effectively. From February 2019, Liverpool City Council commenced monthly reporting to its Chief Executive Officer (CEO) about the point-in-time status of LIC funds, and to its Audit, Risk and Improvement Committee about risks associated with LICs and the implementation of internal audit recommendations. There is limited reporting to senior management about the projected financial status of some contributions plans. Our audit found no evidence of misuse of funds during the audited period. Methods for valuing work and land are not aligned with policies and procedures and are implemented inconsistently. In addition, valuations of works-in-kind and land dedications are not independent as they are paid for by the developer. The policy relating to works-in-kind provides no guidance about managing probity risks when negotiating with developers.

Recommendations

By December 2020, Liverpool City Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. update council's policies and procedures to provide consistent guidance about how works and land offered by developers should be valued
  3. update council's Works-in-Kind and Land Acquisition Policy to address probity risks during negotiations with developers
  4. improve public reporting about expenditure of cash collected under VPAs
  5. mitigate risks associated with lack of independence in valuations of works-in-kind and dedicated land
  6. implement security measures over critical or private information. 

Appendix one – Responses from councils and the Department of Planning, Industry and Environment

Appendix two – Advice from the Crown Solicitor

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #339 - released 17 August 2020

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Destination NSW's support for major events

Destination NSW's support for major events

Treasury
Financial reporting
Management and administration
Procurement
Project management
Service delivery

This report focuses on whether Destination NSW (DNSW) can demonstrate that its support for major events achieves value for money.

The audit found that DNSW’s processes for assessing and evaluating the major events it funds are mostly effective, but its public reporting does not provide enough transparency.

DNSW provides clear information to event organisers seeking funding and has a comprehensive methodology for conducting detailed event assessments. However, the reasons for decisions to progress events from the initial assessment to the detailed assessment stage are not documented in sufficient detail.

DNSW does not publish detailed information about the events it funds or the outcomes of these events. This means that members of the public are unable to see whether its activities achieve value for money. However, DNSW’s internal reporting to its key decision‑makers, including the CEO, the Board and the Minister is appropriate.

The Auditor-General made four recommendations to DNSW, aimed at improving the transparency of its activities, improving the documentation of decisions and certain compliance matters, and streamlining its approach to assessing and evaluating events that receive smaller amounts of funding.

Read full report (PDF)

Destination NSW (DNSW) provides funding to attract a range of major events to New South Wales, including high-profile professional sports matches and tournaments, musicals, art and museum exhibitions, and participation-focused events such as festivals and sports events that members of the public can enter. The NSW Government's rationale for providing funding is to encourage event organisers to hold events in New South Wales, and to ensure that events held in New South Wales maximise the potential for attracting overseas and interstate visitors.

This audit assessed whether DNSW can demonstrate that its support for major events achieves value for money. In making this assessment, the audit examined whether:

  • DNSW effectively assesses proposals to support major events
  • DNSW effectively evaluates the impact of its support for major events.

This audit focused on DNSW's work to attract major events to New South Wales. It did not assess DNSW's tourism promotion or development work, which includes developing tourism strategies, marketing and advertising campaigns, national and international partnerships, and regional programs.

Conclusion

Destination NSW's processes for assessing event applications and evaluating its support for major events are mostly effective. DNSW's internal systems allow it to know whether its decisions are achieving value for money. Its public reporting does not provide enough information about its activities and their outcomes, although it is consistent with that of equivalent organisations in other Australian jurisdictions.

DNSW's process for assessing applications for funding from organisers of major events is mostly effective. Clear information is provided to event organisers seeking funding, and DNSW has a comprehensive methodology for conducting detailed event assessments. However, the reasons for decisions to progress events from the initial assessment to the detailed assessment stage are not documented in sufficient detail.

DNSW has a framework for disclosure and monitoring staff conflicts of interest. However, its forms for staff to disclose conflicts of interest on specific events they are working on are ambiguous. DNSW's management of gifts and benefits broadly complies with the minimum standards set by the Public Service Commission, but there are some gaps in its implementation of these.

DNSW conducts an evaluation of each major event it supports. DNSW articulates expected outcomes in contracts with event organisers and uses a sound methodology to evaluate events. Internal reporting to its key decision-makers, including the CEO, the Board and the Minister is appropriate. However, DNSW does not publish detailed information about the events it funds or the outcomes of these events. This means that members of the public are unable to see whether its activities achieve value for money.

Appendix one – Response from Destination NSW

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #332 - released 9 April 2020.

Published

Actions for Local Schools, Local Decisions: needs-based equity funding

Local Schools, Local Decisions: needs-based equity funding

Education
Internal controls and governance
Management and administration
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the Department of Education’s (the department’s) support and oversight of school planning and use of needs-based funding under the Local Schools, Local Decisions reform.

The report found the department has not had adequate oversight of how schools are using needs-based funding to improve student outcomes since it was introduced in 2014.

The department had not set measures or targets for needs-based equity funding. It had also not been clear enough in how it expected schools to report on the outcomes of additional funding. This means it has not been able to effectively demonstrate the impact of funding at a school, or state-wide level.

To assist with the transition to greater local decision-making, the department provided schools with guidance materials, additional resources and systems support. However, guidance material was not clear enough on the purpose of funding, school budgeting systems were not fit-for-purpose when initially introduced, and support for schools was spread across different areas of the department.

The department has recently increased executive oversight of progress to improve educational outcomes for Aboriginal students and students from a low socio-economic background. It has also developed a consistent set of school-level targets to be implemented from 2020. This may help the department more reliably monitor progress in lifting outcomes for students with additional learning needs.

The report makes eight recommendations aimed at clarifying requirements of schools, better coordinating support and strengthening oversight of the use of needs-based equity funding.

Read full report (PDF)

The Local Schools, Local Decisions reform was launched in 2012 to give public schools more authority to make local decisions about how best to meet the needs of their students. A major element of the reform was the introduction of a new needs-based school funding model. Core elements of the model address staffing and operational requirements, while needs-based elements reflect the characteristics of schools and students within them. This includes equity funding designed to support students with additional needs. The four categories of equity funding are:

  • socio-economic background
  • Aboriginal background
  • English language proficiency
  • low-level adjustment for disability. 

Around $900 million in equity funding was allocated in 2019. School principals decide how to use these funds and account for them through their school annual reports. The Department of Education (the department) supports schools in making these choices with tools and systems, guidelines, and good practice examples.

The objective of this audit was to assess the department's support and oversight of school planning and use of needs-based funding under the Local Schools, Local Decisions reform. To address this objective, the audit examined whether:

  • effective accountability arrangements have been established
  • effective support is provided to schools.  

Conclusion

The department has not had adequate oversight of how schools are using needs-based equity funding to improve student outcomes since it was introduced in 2014. While it provides guidance and resources, it has not set measures or targets to describe the outcomes expected of this funding, or explicit requirements for schools to report outcomes from how these funds were used. Consequently, there is no effective mechanism to capture the impact of funding at a school, or state-wide level. The department has recently developed a consistent set of school-level targets to be implemented from 2020. This may help it to better hold schools accountable for progress towards its strategic goal of reducing the impact of disadvantage.

A significant amount of extra funding has been provided to schools over recent years in recognition of the additional learning needs of certain groups of students facing disadvantage. Under the Local Schools, Local Decisions reform, schools were given the ability to make decisions about how best to use the equity funding in combination with their overall school resources to meet their students’ needs. However, multiple guidelines provided to schools contain inconsistent advice on how the community should be consulted, how funding could be used, and how impact should be reported. Because of this, it is not clear how schools have used equity funding for the benefit of identified groups. School annual reports we reviewed did not fully account for the equity funding received, nor adequately describe the impact of funding on student outcomes.

To help in the transition to greater local decision-making, the department provided extra support by; establishing peer support for new principals, increasing the number of directors, developing data analysis and financial planning systems, targeted training and showcasing good practice. Multiple roles and areas of the department provide advice to schools in similar areas and this support could be better co-ordinated.

Financial planning systems designed to help schools budget for equity and other funding sources were not fit-for-purpose when originally introduced. Schools reported a lack of trust in their budget figures and so were not fully spending their allocated funding. Since then, the department developed and improved a budgeting tool in consultation with stakeholder and user groups. It provided extra funding for administrative support and one-to-one training to help schools develop their capabilities. Despite this, schools we spoke to reported they were not yet fully confident in using the system and needed ongoing training and support. 

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #331 - released 8 April 2020.

Published

Actions for Ensuring teaching quality in NSW public schools

Ensuring teaching quality in NSW public schools

Education
Management and administration
Regulation
Service delivery
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford, has released a report on how the New South Wales Education and Standards Authority (NESA) and the Department of Education (the Department) ensure teaching quality in NSW public schools.

Around 2,200 NSW public school principals are responsible for accrediting their teachers in line with the Australian Professional Standards for Teachers. The report found that NESA does not oversight principals’ decisions to ensure that minimum standards for teaching quality are consistently met.

The Department does not effectively monitor teaching quality across the state. With limited data, it is difficult for the Department to ensure its strategies to improve teaching quality are appropriately targeted to improve teaching quality.

The Department’s Performance and Development Framework does not adequately support principals and supervisors to effectively manage and improve teacher performance or actively improve teaching quality. The Department manages those teachers formally identified as underperforming through teacher improvement programs. Only 53 of over 66,000 teachers employed by the Department were involved in these programs in 2018.

The report makes three recommendations towards NESA to improve accreditation processes, and four recommendations to the Department to improve its systems and processes for ensuring teaching quality across the State.

Australian research has shown that quality teaching is the greatest in-school influence on student engagement and outcomes, accounting for 30 per cent of the variance in student performance. An international comparative study of 15-year-old students showed the performance of New South Wales students in reading, mathematics and science has declined between 2006 and 2015.

The Australian Professional Standards for Teachers (the Standards) describe the knowledge, skills and understanding expected of effective teachers at different career stages. Teachers must be accredited against the Standards to be employed in NSW schools. The NSW Education Standards Authority (NESA) is responsible for ensuring all teachers in NSW schools are accredited. As part of the accreditation process the NSW Department of Education (The Department) assesses whether public school teachers meet proficient accreditation standards and advises NESA of its decisions.

The School Excellence Framework provides a method for the Department to monitor teaching quality at a school level across four elements of effective teaching practice. The Performance and Development Framework provides a method for teachers and their supervisors to monitor and improve teaching quality through setting professional goals to guide their performance and development.

The Department has a strategic goal that every student, every teacher, every leader and every school improves every year. In line with this goal, the Department has a range of strategies targeted to improving teaching quality at different career stages. These include additional resources to support new teachers, a program to support teachers to gain higher-level accreditation, support for principals to manage underperforming teachers, and a professional learning program where teachers observe and discuss each other's practice.

The objective of this audit was to assess the effectiveness of the NSW Department of Education's and the NSW Education Standards Authority's arrangements to ensure teaching quality in NSW public schools. To address this objective, the audit examined whether:

  • agencies effectively monitor the quality of teaching in NSW public schools
  • strategies to improve the quality of teaching are planned, communicated, implemented and monitored well.
The NSW Education Standards Authority does not oversight principals’ decisions to accredit teachers as proficient. This means it is not ensuring minimum standards for teaching quality are consistently met.
NESA does not have a process to ensure principals’ decisions to accredit teachers are in line with the Standards. The decision to accredit teachers is one of the main ways to ensure teaching quality. In New South Wales public schools, around 2,200 principals are tasked with making decisions to accredit their teachers as proficient. NESA provides training and guidelines for principals to encourage consistent accreditation decisions but regular turnover of principals makes it difficult to ensure that all principals are adequately supported. NESA has more oversight of provisional and conditional accreditation for beginning teachers, as well as higher-level accreditation for highly effective teachers. That said, there are only limited numbers of teachers with higher-level accreditation across the state.
The Department of Education does not effectively monitor teaching quality at a system level. This makes it difficult to ensure strategies to improve teaching quality are appropriately targeted.
The Department is not collecting sufficient information to monitor teaching quality across the state. No information on teacher assessment against the Performance and Development Framework is collected centrally. Schools self-assess their performance against the School Excellence Framework but this does not assess teaching quality for all teachers. The Department also surveys students about their experiences of teaching quality but schools opt-in to this survey, with 65 per cent of public schools participating in 2018. These factors limit the ability of the Department to target efforts to areas of concern.
We examined five key strategies that support the critical parts of a teacher’s career. Most strategies were based on research and consultation, planned, trialled, reviewed and adjusted before wider rollout. Guidance and training is provided to communicate requirements and help schools implement strategies at a local level. Monitoring of strategies implemented at a local level is variable. We identified several instances where Quality Teaching, Successful Students funding was used outside guidelines. Two strategies have not yet been evaluated, which prevents the Department from determining whether they are having the desired impact.
The Performance and Development Framework is not structured in a way that supports principals and supervisors to actively improve teacher performance and teaching quality.
There is limited opportunity for supervisors to set goals, conduct observations of teaching practice, or provide constructive written feedback on a teacher’s progress towards achieving their goals under this framework. Guidance on how to use the Standards to construct quality goals, observe teaching practice and provide valuable feedback is also insufficient. The framework focuses on teachers’ self-identified development goals but there is no requirement to align these with the Standards. These limitations reduce the ability of supervisors to use this framework to effectively manage teacher performance and improve teaching quality.
The Department manages those teachers formally identified as underperforming through teacher improvement programs. Only 53 of over 66,000 teachers employed by the Department were involved in these programs in 2018. By comparison, a report on inspections conducted in the United Kingdom assessed the quality of teaching as ‘inadequate’ in three per cent of schools.

Appendix one – Response from agencies

Appendix two – About the audit

Appendix three – Performance auditing

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary Reference: Report number #327 - released 26 September 2019

36