Actions for Volume Eight 2011 Focus on Transport and Ports

Volume Eight 2011 Focus on Transport and Ports

Transport
Industry
Asset valuation
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effectiveness of program initiatives for increasing container freight movements by rail. The Corporation should review the underlying causes hindering growth in the rail mode and develop and implement strategies to address the unfavourable trend.

Published

Actions for Volume Five 2011 focus on Superannuation, Compensation and Housing

Volume Five 2011 focus on Superannuation, Compensation and Housing

Finance
Treasury
Asset valuation
Compliance
Financial reporting
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Shared services and collaboration

The audits of the New South Wales Government controlled superannuation entities financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. Findings show that Treasury should review the structure and number of public sector superannuation funds and consider whether efficiencies and cost savings could be achieved through consolidation.

Published

Actions for Solar Bonus Scheme

Solar Bonus Scheme

Premier and Cabinet
Compliance
Infrastructure
Management and administration
Project management
Regulation
Risk
Service delivery

A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme.

By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced from 60 to 20 cents reducing the estimated cost to $1.954 billion.

It was a statutory requirement that when 50 mega watts of installed capacity was reached, the Government would review the Scheme. By the time the review was completed the installed capacity had reached 101 mega watts.

Published

Actions for Planning for road maintenance

Planning for road maintenance

Transport
Infrastructure
Management and administration
Project management

The Audit Office is of the opinion that the RTA is taking positive steps in planning for road maintenance and in many instances follows better practice. There are, however, some important improvements which need to be implemented in order to enhance the efficiency and effectiveness of that function.

 

Parliamentary reference - Report number #69 - released 1 December 1999

Published

Actions for Review of Walsh Bay

Review of Walsh Bay

Finance
Infrastructure
Management and administration
Procurement
Project management

The decision to seek development of Walsh Bay without a Master Plan and/or detailed study as to the state of the precinct presented significant problems throughout the life of the project. Now, four years later, negotiations still continue on the details of the final scheme. Based on the latest estimates, it will not provide a financial return as was originally expected. The audit found no evidence to indicate why the former Government wished to expedite Walsh Bay, but it is aware that there was an election due. Many of the problems which have been encountered could have been avoided with more careful and more extensive consideration at the start, particularly in the light of Property Services Group's recommendations.

 

Parliamentary reference - Report number #58 - released 17 December 1998

Published

Actions for The coordination of bushfire fighting activities

The coordination of bushfire fighting activities

Justice
Management and administration
Service delivery
Shared services and collaboration
Workforce and capability

The NSW model of rural fire fighting is complex, and requires an extensive amount of coordination and cooperation to function properly. This has inherent risks. In general, the model has been made to work quite well and much improvement in rural fire fighting has been achieved over the past decade. The efforts of all concerned should be recognised and applauded especially since any change must be developed cooperatively between a number of agencies and groups.

Nevertheless, past tensions and difficulties have left pockets of disagreement and resistance. The rural fire fighting culture which was developed over the course of a century has always been highly dedicated, as it is today. However, changed organisational, technical, legal, financial and environmental factors have necessitated major and continuing changes.

 

Parliamentary reference - Report number #57 - released 2 December 1998

Published

Actions for Management of research - NSW Health: Infrastructure Grants Program

Management of research - NSW Health: Infrastructure Grants Program

Health
Internal controls and governance
Management and administration
Shared services and collaboration

NSW Health has progressed in identifying and addressing key R&D issues in a complex and difficult environment. The Infrastructure Grants Program (IGP) is an innovative program and reflects a commitment by Government to support research infrastructure. The IGP has as its aims the provision of significant funding accompanied by clear research objectives and criteria for accountability and introduces a rational basis for the allocation of infrastructure grants.

While NSW Health has progressed, there is an opportunity to make the IGP more efficient and effective. These opportunities are in the areas of addressing longer term planning issues in health, streamlining and clarifying eligibility and selection criteria, improving decision-making structures and processes and improving accountability.

 

Parliamentary reference - Report number #56 - released 25 November 1998

Published

Actions for Planning statewide services

Planning statewide services

Health
Information technology
Management and administration
Service delivery
Shared services and collaboration

The Audit Office is of the view that:

  • there is no system wide plan for the location of emergency departments. This function is undertaken by each Area Health Service

  • coordination between the Department and the NSW Ambulance Service could be improved in aspects such as the collocation of facilities and direct communications between ambulances and emergency departments

  • there is no policy framework that recognises the increasing role and impact of private providers

  • the Department’s guidelines do not take into account demographic factors, the number of patients treated or the acuity of presentations as criteria for determining the size of an emergency department or the level and scope of emergency services that should be available at that location.

  • the Department has introduced a range of initiatives over a period of time to improve the performance of emergency departments such as the establishment of the Integrated Bed Management Committee. Some have been quite effective, whilst others have had mixed success. There has been an overall improvement in emergency department waiting times for urgent cases. However, there has been little improvement in waiting times for less urgent cases and a decline in performance for access block (the time taken to be admitted to a hospital ward from the emergency department after a decision has been made that this is required).

 

Parliamentary reference - Report number #54 - released 21 October 1998

Published

Actions for Redevelopment proposal for East Fairfield (Villawood) Estate

Redevelopment proposal for East Fairfield (Villawood) Estate

Community Services
Infrastructure
Management and administration
Procurement
Project management
Service delivery

This audit examines the processes which led to the Government’s decision to demolish and sell the East Fairfield (Villawood) housing estate at a cost of nearly $32m gross ($17m net). In doing so, the audit focuses on whether the decision process demonstrates that it is an efficient and effective use of government funds.

The audit raises a number of concerns about the decision-making process. Although demolition and redevelopment may have been the most efficient and effective outcome, The Audit Office is not able to confirm this from the evidence presented. Audit found that the process used to arrive at this decision was not transparent, nor was it adequately justified by available evidence.

 

Parliamentary reference - Report number #46 - released 29 January 1998