Refine search Expand filter

Reports

Published

Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.

The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.

This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.

 

Parliamentary reference - Report number #247 - released 18 December 2014

Published

Actions for Effectiveness of the New Death and Disability Scheme

Effectiveness of the New Death and Disability Scheme

Justice
Internal controls and governance
Management and administration
Risk
Service delivery

More NSW Police officers are returning to work after being injured and there are fewer medical discharges as a result of the new NSW Police death and disability scheme. The new scheme is also costing less and if early trends continue, costs may fall sufficiently to meet the government’s target.

 

Parliamentary reference - Report number #242 - released 22 May 2014

Published

Actions for NSW State Emergency Service Management of Volunteers

NSW State Emergency Service Management of Volunteers

Justice
Internal controls and governance
Management and administration
Project management
Risk
Service delivery
Workforce and capability

The SES needs to better understand the location, availability and skills of its volunteers so it can properly plan for emergency events. It needs to improve how it selects and retains the right volunteers and provide more up-to-date and focused training.

The SES has improved volunteer safety with injury claims falling by 40 per cent to 70 in the four years to 30 June 2013. The average cost of claims has fallen by 58 per cent to $3,547. The SES attributes this reduction to better equipment and work practices. 

 

Parliamentary reference - Report number #240 - released 15 April 2014

Published

Actions for Managing Injured Police

Managing Injured Police

Justice
Internal controls and governance
Management and administration
Service delivery
Workforce and capability

Overall, the NSW Police Force’s approach to managing injured officers since 2006 is appropriate, focusing on notification and early intervention and the development of successful return to work plans. Early intervention and return to work are the key factors in successfully managing injured officers and reducing the cost of workplace injuries. The Force has not done this well in the past. Through the establishment of the safety command, the Force has built a framework for managing injured officers that should optimise early return to work.

Parliamentary reference - Report number #184 - released 10 December 2008

Published

Actions for Improving Literacy and Numeracy in Public Schools

Improving Literacy and Numeracy in Public Schools

Education
Internal controls and governance
Management and administration
Service delivery
Workforce and capability

During the course of the audit we were impressed by the dedication and efforts of teachers in NSW public schools, particularly when dealing with the needs of students with learning difficulties. Although NSW schools perform well nationally and internationally, NSW has a high concentration of poor outcomes in some schools and some regions. Each year a group of between 5 and 15 per cent of children are at risk of not reaching the minimum level of achievement needed to progress at school. In this group, indigenous students are over represented.

 

Parliamentary reference - Report number #183 - released 22 October 2008

Published

Actions for Delivering Health Care out of Hospitals

Delivering Health Care out of Hospitals

Health
Management and administration
Project management
Service delivery
Workforce and capability

Area Health Services and hospitals have developed programs which can provide clinical outcomes as good for patients as in-hospital care and can reduce the time they spend in hospital. They have operated for several years and show considerable potential. Ageing of the population, increasing costs and higher expectations of health care will continue to challenge health systems. Sometimes, unfortunately, the system struggles to cope. 

 

Parliamentary reference - Report number #182 - released 24 September 2008

Published

Actions for Recycling and Reuse of Waste by the NSW Public Sector

Recycling and Reuse of Waste by the NSW Public Sector

Environment
Compliance
Internal controls and governance
Management and administration
Procurement
Shared services and collaboration

The Government’s WRAPP initiative has achieved its intended outcome. The public sector has reduced the proportion of waste going to landfill from 27 per cent to eight per cent over the last six years, and has increased its use of recycled content materials. Most agencies have played their part, identifying how waste can be reduced and changing practices accordingly.

 

Parliamentary reference - Report number #181 - released 11 June 2008

Published

Actions for Protecting our Rivers

Protecting our Rivers

Environment
Industry
Compliance
Internal controls and governance
Management and administration
Regulation
Shared services and collaboration

At the time of our 2003 audit agencies were unable to measure the water quality in NSW rivers as they had not established a comprehensive and ongoing monitoring system for water quality. Agencies are now developing a monitoring system to measure the progress against the State Plan 2006 target to improve the condition of riverine ecosystems by 2015. It may not be possible to identify an overall trend in the condition of riverine ecosystems by the State Plan target date of 2015. This is because riverine ecosystems do not respond rapidly to change in the environment. A long period of time is required to collect sufficient data to establish a baseline for all indicators being used and to determine trends, particularly given the prolonged drought.

 

Parliamentary reference - Report number #180 - released 21 May 2008

Published

Actions for Working with Hotels and Clubs to Reduce Alcohol-Related Crime

Working with Hotels and Clubs to Reduce Alcohol-Related Crime

Justice
Compliance
Management and administration
Regulation
Service delivery
Shared services and collaboration
Workforce and capability

In NSW alcohol-related assaults have almost doubled over the last ten years. In 2006-07 there were 20,475 alcohol-related assaults excluding domestic violence incidents, up from 10,305 in 1997-98. In fact, the number of these assaults is increasing at a faster rate than total assaults. Incidences of alcohol-related malicious damage and offensive conduct have also increased, rising by 87 and 70 per cent respectively. Working with hotels and clubs to reduce alcohol-related crime, however we found that the number of alcohol-related assaults has reduced or stabilised in the last two years in about 14 per cent of Police local area commands.

 

Parliamentary reference - Report number #179 - released 23 April 2008

Published

Actions for Managing the Amalgamation of the Greyhound and Harness Racing Regulatory Authority

Managing the Amalgamation of the Greyhound and Harness Racing Regulatory Authority

Industry
Information technology
Internal controls and governance
Management and administration
Project management
Shared services and collaboration
Workforce and capability

The Authority has achieved staff reductions and salary related savings in line with targets. That said, the amalgamation was not project managed effectively. It has been slow to implement some of its key objectives against plans and the costs of the amalgamation have increased to the extent that it is unable to meet key objectives. Stakeholders are dissatisfied with the amalgamation outcomes. This dissatisfaction would have been mitigated with better communication.The Authority’s approach to implementing the amalgamation varied from that originally proposed by government. But it did not record the changed approach in an amalgamation plan.

 

Parliamentary reference - Report number #178 - released 3 April 2008