Refine search Expand filter

Reports

Published

Actions for Mental health post-discharge care

Mental health post-discharge care

Health
Internal controls and governance
Service delivery

On 17 December 2015 the NSW Acting Auditor-General, Tony Whitfield, released a report on the care that is provided to mental health patients in the first seven days after they are discharged from acute mental health units.
 
The audit examined models of care provided by five Local Health Districts: Northern NSW, Sydney, Western Sydney, Central Coast, and Murrumbidgee. The audit looked at how well these Local Health Districts implemented the Ministry of Health’s policy directive on the transfer of mental health patients from hospitals to the community.

 

Parliamentary reference - Report number #263 - released 17 December 2015

Published

Actions for Volume Five 2015 Premier and Cabinet

Volume Five 2015 Premier and Cabinet

Premier and Cabinet
Asset valuation
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management
Risk

Volume Five 2015 covered Premier and Cabinet agencies such as the Department of Premier and Cabinet, Office of Sport, Venues NSW, Barangaroo Delivery Authority and Infrastructure NSW.

Published

Actions for Community Housing

Community Housing

Community Services
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

On 16 September 2015 the NSW Acting Auditor-General, Tony Whitfield, released a report on community housing. The audit examines the Department of Family and Community Services’ transfer of public housing to non-government community housing providers.

The Department has worked collaboratively with community housing providers and industry groups to develop the community housing sector. Although there have been some delays, it has managed the transfer of public housing reasonably well and has improved the sustainability of the sector.

 

Parliamentary reference - Report number #259 - released 16 September 2015

Published

Actions for Sydney metropolitan bus contracts

Sydney metropolitan bus contracts

Transport
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

On 9 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on Sydney Metropolitan Bus Service Contracts.
 
All scheduled bus services in the Sydney metropolitan area are provided under contracts with the public and private operators. The contracts allow Transport for NSW (TfNSW) to determine what bus services are provided and to whom. This audit assessed the effectiveness of TfNSW’s design and management of these contracts.
 
Bus services provided under the Sydney Metropolitan Bus Service Contracts have largely been effective and efficient. Operators are mostly meeting their key performance indicators. Customer satisfaction is better than under the previous contracts and improving, patronage is increasing, and the unit costs of providing services are now lower than under the previous contracts. 
 
However, punctuality remains a problem. Private operators are mostly starting their trips on time, but rarely meeting their mid and end-of-trip targets. State Transit Authority’s (STA) punctuality is improving but is worse than private operators, and other areas of performance are generally below private operators.
 
The current situation is a substantial improvement over what we found in our 2010 audit on the previous contracts.

 

Parliamentary reference - Report number #258 - released 9 September 2015

Published

Actions for Transferring out-of-home care to non-government organisations

Transferring out-of-home care to non-government organisations

Community Services
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The audit assessed how well the Department of Family and Community Services has transferred the management of children in out-of-home care to non-government organisations (NGOs).
 
The Department has put considerable effort into developing the out-of-home care sector and is progressing well towards its goal of transferring all children in statutory care to NGOs. Since 2011, the number of children with an accredited NGO has more than doubled. This is a positive outcome as children are more likely to receive quality care because these providers meet NSW standards for outof-home care.
 
However, it is difficult to assess whether overall outcomes for children in care have improved. This is because the Department has yet to determine what wellbeing outcomes it wants to achieve, such as improvements in a child’s health, education and welfare. The Department is currently developing a quality assurance framework which will include such outcomes. We also found that the number of children in care returned to their birth family has declined, and the number of adoptions has remained relatively unchanged.

 

Parliamentary reference - Report number #257 - released 2 September 2015

Published

Actions for Large construction projects

Large construction projects

Treasury
Transport
Health
Industry
Planning
Premier and Cabinet
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
 
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.

 

Parliamentary reference - Report number #252 - released 7 May 2015

Published

Actions for Country towns water supply and sewerage program

Country towns water supply and sewerage program

Industry
Planning
Environment
Internal controls and governance
Management and administration
Project management
Service delivery

The Country Towns Water Supply and Sewerage Program has effectively promoted adoption of better management practices by local water utilities, but will not achieve its objective of eliminating the water supply and sewerage infrastructure backlog in urban areas of country NSW.
 
The $1.2 billion Program aims to help local water utilities provide appropriate, affordable, cost effective and well-managed water supply and sewerage services in the urban areas of country NSW. It has two broad elements:

  • promoting adoption of better practices 
  • providing financial assistance towards the capital cost of infrastructure backlog works.

 

Parliamentary reference - Report number #251 - released 4 May 2015

Published

Actions for Managing length of stay and unplanned readmissions in NSW public hospitals

Managing length of stay and unplanned readmissions in NSW public hospitals

Health
Management and administration
Service delivery

NSW Health has achieved considerable success over recent years in reducing average length of stay despite increasing pressure on hospital admissions by older and chronically ill patients. This success has been driven by changes in the way health services are delivered, such as the increasing use of same day care for treatments that previously required overnight hospital stays. 
 
There is a good level of length of stay information available and this information is actively used to manage the time patients spend in hospital.
 
Available data suggest that the rate of unplanned readmissions has not reduced in NSW despite various statewide and local strategies. NSW Health is undertaking research to better understand unplanned readmissions, their causes and the best ways to address them.
 
There are many local and statewide initiatives that aim to reduce length of stay and unplanned readmissions. However, the impact of some local and statewide initiatives on length of stay and unplanned readmissions are not well understood and quantified due to the lack of evaluations conducted.

 

Parliamentary reference - Report number #250 - released 23 April 2015

Published

Actions for Vocational education and training reform

Vocational education and training reform

Education
Industry
Management and administration
Procurement
Project management
Service delivery
Workforce and capability

The Department’s framework for VET reform has the potential to effectively achieve the government’s immediate objectives for the reform, which are associated with meeting its commitments under the National Partnership Agreement for Skills Reform without spending more. We found that the government is addressing VET reform objectives in the following order of priority: no extra cost (budget neutrality), TAFE viability, quality VET, access to VET for regions and equity groups, more contestability, student choice. Overall, we conclude that a more balanced approach, by putting more emphasis on increased contestability and student choice, is more likely to maximise the public value for the government’s investment in VET.

 

Parliamentary reference - Report number #249 - released 29 January 2015

Published

Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.

The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.

This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.

 

Parliamentary reference - Report number #247 - released 18 December 2014