Actions for Implementation of the NSW Government’s program evaluation initiative
Implementation of the NSW Government’s program evaluation initiative
The NSW Government’s ‘program evaluation initiative’, introduced to assess whether service delivery programs achieve expected outcomes and value for money, is largely ineffective according to a report released today by NSW Auditor-General, Margaret Crawford.
Government services, in areas such as public order and safety, health and education, are delivered by agencies through a variety of programs. In 2016–17, the NSW Government estimates that it will spend over $73 billion on programs to deliver services.
Parliamentary reference - Report number #277 - released 3 November 2016
Actions for Public sector management reforms
Public sector management reforms
The Public Service Commission is making good progress with leading the implementation of public sector management reforms, according to a report released today by the Acting New South Wales Auditor-General, Tony Whitfield.
'The Commission developed a sound evidence base for the reforms and gained wide public sector support by engaging with agency heads and using public sector working groups to develop options', said the Acting Auditor-General. 'They developed good guidance for government agencies and have improved the senior executive structure in the NSW public sector', he added.
Parliamentary reference - Report number #264 - released 28 January 2016
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.
Parliamentary reference - Report number #252 - released 7 May 2015
Actions for Country towns water supply and sewerage program
Country towns water supply and sewerage program
The Country Towns Water Supply and Sewerage Program has effectively promoted adoption of better management practices by local water utilities, but will not achieve its objective of eliminating the water supply and sewerage infrastructure backlog in urban areas of country NSW.
The $1.2 billion Program aims to help local water utilities provide appropriate, affordable, cost effective and well-managed water supply and sewerage services in the urban areas of country NSW. It has two broad elements:
- promoting adoption of better practices
- providing financial assistance towards the capital cost of infrastructure backlog works.
Parliamentary reference - Report number #251 - released 4 May 2015
Actions for Security of critical IT infrastructure
Security of critical IT infrastructure
Roads and Maritime Services and Transport for NSW have deployed many controls to protect traffic management systems but these would have been only partially effective in detecting and preventing incidents and unlikely to support a timely response. There was a potential for unauthorised access to sensitive information and systems that could have disrupted traffic.
Until Roads and Maritime Services’ IT disaster recovery site is fully commissioned, a disaster involving the main data centre is likely to lead to higher congestion in the short-term as traffic controllers would be operating on a regional basis without the benefit of the Traffic Management Centre.
Parliamentary reference - Report number #248 - released 21 January 2015
Actions for Volume Six 2011 focus on Environment, Water and Regional Infrastructure
Volume Six 2011 focus on Environment, Water and Regional Infrastructure
The Environment Protection Authority’s expenditure for the financial year 2010/11 was $92 million - $76 million of this was for environment protection and regulation. The Office of Environment and Heritage and the Environment Protection Authority commenced 145 prosecutions for environmental offences and 106 were completed in the financial year 2010/11, down from the 134 prosecutions completed in 2009/10. Financial penalties for 2010/11 totalled $969,000 down from $1,403,000 in 2009/10. The average fine decreased from $10,468 in 2009/10 to $9,141 in 2010/11.
Actions for Transport of Dangerous Goods
Transport of Dangerous Goods
Dangerous goods make up 10-15% of domestic freight and have potential to harm people, property and the environment. They include substances such as explosives, flammable liquids and gases, and oxidising agents. However, Government inspection programs were limited. The Office of Environment and Heritage carried out very few checks in the four years up to 2010, with no inspections made in the metropolitan area. This is despite Port Botany handling around 50,000 containers of dangerous goods per year. Statewide, only 303 inspections were made in 2009/10 and only 20 in 2008/09.
Parliamentary reference - Report number #212 - released 10 May 2011
Actions for Volume One 2011
Volume One 2011
The level of non compliance with the requirements of this Premier’s Memorandum is concerning, particularly considering the NSW Procurement Reforms were effective since 2006. The implementation strategy for procurement reform was announced as early as 2001. We recommend the governing bodies of agencies and management review, not only the processes their agencies have in place to comply with procurement reforms and requirements, but also more broadly how agencies identify and comply with laws, regulations, Treasury policy pronouncements, Premier’s memoranda and other obligations.