Actions for Sydney metropolitan bus contracts

Sydney metropolitan bus contracts

Transport
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

On 9 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on Sydney Metropolitan Bus Service Contracts.
 
All scheduled bus services in the Sydney metropolitan area are provided under contracts with the public and private operators. The contracts allow Transport for NSW (TfNSW) to determine what bus services are provided and to whom. This audit assessed the effectiveness of TfNSW’s design and management of these contracts.
 
Bus services provided under the Sydney Metropolitan Bus Service Contracts have largely been effective and efficient. Operators are mostly meeting their key performance indicators. Customer satisfaction is better than under the previous contracts and improving, patronage is increasing, and the unit costs of providing services are now lower than under the previous contracts. 
 
However, punctuality remains a problem. Private operators are mostly starting their trips on time, but rarely meeting their mid and end-of-trip targets. State Transit Authority’s (STA) punctuality is improving but is worse than private operators, and other areas of performance are generally below private operators.
 
The current situation is a substantial improvement over what we found in our 2010 audit on the previous contracts.

 

Parliamentary reference - Report number #258 - released 9 September 2015

Published

Actions for Large construction projects

Large construction projects

Treasury
Transport
Health
Industry
Planning
Premier and Cabinet
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
 
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.

 

Parliamentary reference - Report number #252 - released 7 May 2015

Published

Actions for Country towns water supply and sewerage program

Country towns water supply and sewerage program

Industry
Planning
Environment
Internal controls and governance
Management and administration
Project management
Service delivery

The Country Towns Water Supply and Sewerage Program has effectively promoted adoption of better management practices by local water utilities, but will not achieve its objective of eliminating the water supply and sewerage infrastructure backlog in urban areas of country NSW.
 
The $1.2 billion Program aims to help local water utilities provide appropriate, affordable, cost effective and well-managed water supply and sewerage services in the urban areas of country NSW. It has two broad elements:

  • promoting adoption of better practices 
  • providing financial assistance towards the capital cost of infrastructure backlog works.

 

Parliamentary reference - Report number #251 - released 4 May 2015

Published

Actions for Signal failures on the metropolitan rail network

Signal failures on the metropolitan rail network

Transport
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery

Between 2004 and 2006, the number of signalling failures, signalling downtime and the number of trains delayed as a result of signal failures all fell. RailCorp’s on-time running performance improved over the same period. The fall in failures is a clear indication of improved performance. Changes in the definition of on-time and to the timetable during 2005 and 2006 however make it difficult to determine whether improvements in response downtime and signalling delays are due to a true performance improvement. To build upon this strong base, RailCorp needs to determine with more confidence the number and duration of signalling failures the network can tolerate without impacting on service levels.

 

Parliamentary reference - Report number #170 - released 15 August 2007

Published

Actions for Connecting with public transport

Connecting with public transport

Transport
Information technology
Infrastructure
Internal controls and governance
Management and administration
Project management
Service delivery
Workforce and capability

We see considerable potential for the Ministry of Transport to plan and manage interchanges more effectively, so as to make better use of our public transport network. We believe that the Ministry now needs to focus more on multi-modal transport planning and interchange performance. It needs to assign responsibility for the coordination and oversight of inter-modal operations to an entity resourced for the purpose. Without this it will continue to be very difficult to identify and address unmet needs, seek and secure stakeholder funding, and monitor and evaluate system performance.

 

Parliamentary reference - Report number #168 - released 6 June 2007

Published

Actions for Planning for road maintenance

Planning for road maintenance

Transport
Infrastructure
Management and administration
Project management

The Audit Office is of the opinion that the RTA is taking positive steps in planning for road maintenance and in many instances follows better practice. There are, however, some important improvements which need to be implemented in order to enhance the efficiency and effectiveness of that function.

 

Parliamentary reference - Report number #69 - released 1 December 1999