Actions for Sydney metropolitan bus contracts
Sydney metropolitan bus contracts
On 9 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on Sydney Metropolitan Bus Service Contracts.
All scheduled bus services in the Sydney metropolitan area are provided under contracts with the public and private operators. The contracts allow Transport for NSW (TfNSW) to determine what bus services are provided and to whom. This audit assessed the effectiveness of TfNSW’s design and management of these contracts.
Bus services provided under the Sydney Metropolitan Bus Service Contracts have largely been effective and efficient. Operators are mostly meeting their key performance indicators. Customer satisfaction is better than under the previous contracts and improving, patronage is increasing, and the unit costs of providing services are now lower than under the previous contracts.
However, punctuality remains a problem. Private operators are mostly starting their trips on time, but rarely meeting their mid and end-of-trip targets. State Transit Authority’s (STA) punctuality is improving but is worse than private operators, and other areas of performance are generally below private operators.
The current situation is a substantial improvement over what we found in our 2010 audit on the previous contracts.
Parliamentary reference - Report number #258 - released 9 September 2015
Actions for Country towns water supply and sewerage program
Country towns water supply and sewerage program
The Country Towns Water Supply and Sewerage Program has effectively promoted adoption of better management practices by local water utilities, but will not achieve its objective of eliminating the water supply and sewerage infrastructure backlog in urban areas of country NSW.
The $1.2 billion Program aims to help local water utilities provide appropriate, affordable, cost effective and well-managed water supply and sewerage services in the urban areas of country NSW. It has two broad elements:
- promoting adoption of better practices
- providing financial assistance towards the capital cost of infrastructure backlog works.
Parliamentary reference - Report number #251 - released 4 May 2015