Reports
Actions for Planning and Environment 2016
Planning and Environment 2016
Auditor-General, Margaret Crawford released a report on the planning and environment cluster today, concluding that the quality of financial reporting is improving. However, the cluster can improve its financial controls and governance framework.
Actions for Transport 2016
Transport 2016
Financial reporting within the Transport Cluster continues to improve with reported misstatements down 96 per cent since 2011-12 to just three in 2015-16, according to a report released today by the NSW Auditor-General, Margaret Crawford.
Actions for CBD and South East Light Rail Project
CBD and South East Light Rail Project
Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford.
Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case.
Parliamentary reference - Report number #278 - released 30 November 2016
Actions for Implementation of the NSW Government’s program evaluation initiative
Implementation of the NSW Government’s program evaluation initiative
The NSW Government’s ‘program evaluation initiative’, introduced to assess whether service delivery programs achieve expected outcomes and value for money, is largely ineffective according to a report released today by NSW Auditor-General, Margaret Crawford.
Government services, in areas such as public order and safety, health and education, are delivered by agencies through a variety of programs. In 2016–17, the NSW Government estimates that it will spend over $73 billion on programs to deliver services.
Parliamentary reference - Report number #277 - released 3 November 2016
Actions for Agency compliance with the GIPA Act
Agency compliance with the GIPA Act
In a report released today, the NSW Auditor-General, Margaret Crawford found some NSW Government agencies were not publicly releasing all the required information on contracts with the private sector, nor were they publishing it in a timely manner.
This report assessed whether 13 agencies were complying with Part 3 Division 5 of the Government Information (Public Access) Act 2009 (GIPA Act), relating to Government contracts with the private sector.
Actions for Areas of focus in 2015
Areas of focus in 2015
This report focuses on key observations from financial and performance audits in 2015. The findings have been broadly classified into four themes, which has informed the focus of financial and performance audits for 2016.
Actions for Realising the benefits of the Service NSW initiative
Realising the benefits of the Service NSW initiative
The current benefits realisation approach for Service NSW needs to improve so benefits and savings can be effectively measured, reported and realised, according to a report released today by the NSW Acting Auditor-General, Tony Whitfield.
Customers are finding that Service NSW provides a convenient and practical way to access all government transaction services.
Parliamentary reference - Report number #266 - released 17 February 2016
Actions for Franchising of Sydney Ferries Network services
Franchising of Sydney Ferries Network services
Franchising services on the Sydney Ferries Network was justified, and Transport for NSW’s management of the franchise has been largely effective according to a report released today by the NSW Acting Auditor-General, Tony Whitfield.
'Franchising has resulted in cost savings, good service performance, and effective risk transfer from government to the private sector operator', said Mr Whitfield.
Parliamentary reference - Report number #265 - released 4 February 2016
Actions for Liverpool to Parramatta Bus Transitway
Liverpool to Parramatta Bus Transitway
Several of my recent audits have identified a need to improve our public transport system – both for the benefit of travellers and to assist in achieving better air quality.
Bus Transitways can provide a good public transport solution for lower density population areas, potentially at a relatively low capital cost. This audit examines the transitway running between Liverpool and Parramatta, the first of several planned for Sydney. This audit should contribute to a better understanding of the lessons learnt from this first project, and so to future transitways providing better value for money.
But this audit also raises broader issues.
It highlights the importance of accurately projecting the total cost of major infrastructure projects before governments lock in their decisions. It also highlights the need for sound decision-making processes when government agencies compete with the private sector. The principles and recommendations flowing from these issues are ones I would draw to the attention of all agencies, and to the Government.
Parliamentary reference - Report number #146 - released 5 December 2005
Actions for Managing Disruptions to Cityrail Passenger Services
Managing Disruptions to Cityrail Passenger Services
About one in every twelve Sydney people travels by train each weekday.
Unplanned disruptions to services are inevitable, even on the best-run railways.
Because of the complexities of Sydney’s rail network, a single event can disrupt many services.
From a passenger’s perspective, three issues are important –
- how quickly the disruption is fixed (“When will my train arrive?”)
- the accuracy of information provided about the disruption (“Should I change my travel/meeting/other arrangements?”)
- how often the disruptions occur (“Should I give up on rail travel?”).
In this audit, we looked at how well RailCorp responds when there are routine disruptions to its CityRail passenger services. We focused on how RailCorp manages passenger journeys and informs passengers.
This report informs Parliament and the community about the limitations of the current system, and what more needs to be done in order to minimise the impact of disruptions on passengers.
It should also help passengers judge the extent to which they can rely on the information they receive, and to better understand some of the obstacles faced by staff.
Parliamentary reference - Report number #139 - released 22 June 2005