Refine search Expand filter

Reports

Published

Actions for Solar Bonus Scheme

Solar Bonus Scheme

Premier and Cabinet
Compliance
Infrastructure
Management and administration
Project management
Regulation
Risk
Service delivery

A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme.

By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced from 60 to 20 cents reducing the estimated cost to $1.954 billion.

It was a statutory requirement that when 50 mega watts of installed capacity was reached, the Government would review the Scheme. By the time the review was completed the installed capacity had reached 101 mega watts.

Published

Actions for Two Ways Together - NSW Aboriginal Affairs Plan

Two Ways Together - NSW Aboriginal Affairs Plan

Community Services
Premier and Cabinet
Internal controls and governance
Management and administration
Project management
Service delivery

To date the Two Ways Together Plan (the Plan) has not delivered the improvement in overall outcomes for Aboriginal people that was intended. Stronger partnerships between the government and Aboriginal people are only beginning to emerge. The disadvantage still experienced by some of the estimated 160,000 Aboriginal people in NSW is substantial. For example, the unemployment rate for Aboriginal people is at least three times higher than the rate for all NSW residents and hospital admissions for diabetes are also around three times higher.

 

Parliamentary reference - Report number #213 - released 18 May 2011

Published

Actions for Agencies working together to improve services

Agencies working together to improve services

Premier and Cabinet
Treasury
Justice
Transport
Education
Internal controls and governance
Service delivery
Shared services and collaboration

In the cases we examined, we found that agencies working together can improve services or results. However, the changes were not always as great as anticipated or had not reached maximum potential. Establishing the right governance framework and accountability requirements between partners at the start of the project is critical to success. And joint responsibility requires new funding and reporting arrangements to be developed.

 

Parliamentary reference - Report number #149 - released 22 March 2006

Published

Actions for Relocating Agencies to Regional Areas

Relocating Agencies to Regional Areas

Premier and Cabinet
Internal controls and governance
Management and administration
Service delivery
Shared services and collaboration
Workforce and capability

Decisions to relocate government agencies to non-metropolitan areas are not made purely for cost reasons. They can also serve government policy objectives, such as promoting regional economic development.

Regardless of the policy objectives that may exist, I would expect that decisions on individual agency relocations would be based on sound business cases. Those business cases would show how the relocation achieves any relevant government objectives, what costs (or savings) would be involved, logistical considerations such as obtaining appropriate accommodation and staff, and any impacts on levels service to the public.

In my view, the existence of government policy objectives does not remove the need for individual decisions to be made in a transparent, rational and accountable manner. Responsible public servants should provide the appropriate information to government to allow it to judge how best to implement its policies.

 

Parliamentary reference - Report number #147 - released 14 December 2005

Published

Actions for Freedom of Information

Freedom of Information

Transport
Premier and Cabinet
Education
Management and administration
Regulation
Service delivery

Freedom of Information (FOI) Coordinators and their staff were supportive of the legislation. However, the agencies examined can do considerably more to fully achieve the intentions of the Act. On the positive side, all three agencies had processes in place to handle requests and had made a number of changes to improve the effectiveness of the FOI process. Fees and charges had also been kept to a minimum. No processing fees were requested in the majority of cases, and if charged, were not unreasonable.

 

Parliamentary reference - Report number #114 - released 28 August 2003