Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006
Actions for Agencies working together to improve services
Agencies working together to improve services
In the cases we examined, we found that agencies working together can improve services or results. However, the changes were not always as great as anticipated or had not reached maximum potential. Establishing the right governance framework and accountability requirements between partners at the start of the project is critical to success. And joint responsibility requires new funding and reporting arrangements to be developed.
Parliamentary reference - Report number #149 - released 22 March 2006
Actions for Freedom of Information
Freedom of Information
Freedom of Information (FOI) Coordinators and their staff were supportive of the legislation. However, the agencies examined can do considerably more to fully achieve the intentions of the Act. On the positive side, all three agencies had processes in place to handle requests and had made a number of changes to improve the effectiveness of the FOI process. Fees and charges had also been kept to a minimum. No processing fees were requested in the majority of cases, and if charged, were not unreasonable.
Parliamentary reference - Report number #114 - released 28 August 2003
Actions for Lease to Fox Studios Australia
Lease to Fox Studios Australia
The audit found that the process for the lease and development of the Showground site commenced on the basis that no Government moneys would be provided and no theme park activities would be allowed. However despite this a State Government subsidy of between $84.8m and $106.8m (in net present value terms) is to be provided for the development and the area of the Showground to be leased to Fox was extended to comprise 24.3 hectares of the 28.8 hectare site to allow Fox also to develop a family entertainment park.
The audit also found that the process commenced under the former Government were intended to ensure that no one party was placed above another however, the actual processes employed up to the General Election in March 1995 were so flawed as not to be relied upon to select a preferred proponent or to justify dispensing with a tender process.
Parliamentary reference - Report number #44 - released 8 December 1997