Reports
Actions for Implementation of the NSW Government’s program evaluation initiative
Implementation of the NSW Government’s program evaluation initiative
The NSW Government’s ‘program evaluation initiative’, introduced to assess whether service delivery programs achieve expected outcomes and value for money, is largely ineffective according to a report released today by NSW Auditor-General, Margaret Crawford.
Government services, in areas such as public order and safety, health and education, are delivered by agencies through a variety of programs. In 2016–17, the NSW Government estimates that it will spend over $73 billion on programs to deliver services.
Parliamentary reference - Report number #277 - released 3 November 2016
Actions for Red tape reduction
Red tape reduction
Overall, NSW Government initiatives and processes to prevent and reduce red tape were not effective, according to a report released today by the NSW Auditor-General.
In 2015, the Government reported that its red tape reduction initiatives, implemented between 2011 and 2015, had resulted in $896 million in savings. While these initiatives resulted in some savings, the total value of savings is unknown because estimates for some initiatives were based on unverified assumptions, cost transfers or unrealised projections.
Parliamentary reference - Report number #272 - released 25 August 2016
Actions for Government advertising 2015
Government advertising 2015
The Government Advertising Act 2011 requires the Auditor-General to conduct an annual performance audit to check NSW Government agency compliance with the Act.
This audit focused on the Department of Premier and Cabinet’s (DPC) role in monitoring government agencies compliance with government advertising requirements, and examined advertising campaigns run by Destination NSW and the Sydney Opera House.
Parliamentary reference - Report number #253 - released 22 June 2015
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.
Parliamentary reference - Report number #252 - released 7 May 2015
Actions for Country towns water supply and sewerage program
Country towns water supply and sewerage program
The Country Towns Water Supply and Sewerage Program has effectively promoted adoption of better management practices by local water utilities, but will not achieve its objective of eliminating the water supply and sewerage infrastructure backlog in urban areas of country NSW.
The $1.2 billion Program aims to help local water utilities provide appropriate, affordable, cost effective and well-managed water supply and sewerage services in the urban areas of country NSW. It has two broad elements:
- promoting adoption of better practices
- providing financial assistance towards the capital cost of infrastructure backlog works.
Parliamentary reference - Report number #251 - released 4 May 2015