NSW Government agencies have sound processes for implementing performance audit recommendations in Auditor-General’s Reports to Parliament. There are many cases of good practice. For example, some agencies formed a steering committee and developed a detailed plan to implement recommendations. Another incorporated the implementation of recommendations into both its business plan and the work plans of individual officers who were managing projects. Most agencies also used their Audit and Risk Committees to monitor recommendations.
 
We found some cases where agencies can improve how they coordinate actions to address recommendations. Most agencies were not revisiting these actions to determine whether they remain appropriate.

 

Parliamentary reference - Report number #254 - released 24 June 2015

Published

Actions for Government advertising 2015

Government advertising 2015

Premier and Cabinet
Environment
Whole of Government
Compliance
Internal controls and governance
Procurement
Project management

The Government Advertising Act 2011 requires the Auditor-General to conduct an annual performance audit to check NSW Government agency compliance with the Act.

This audit focused on the Department of Premier and Cabinet’s (DPC) role in monitoring government agencies compliance with government advertising requirements, and examined advertising campaigns run by Destination NSW and the Sydney Opera House.

 

Parliamentary reference - Report number #253 - released 22 June 2015

Published

Actions for Large construction projects

Large construction projects

Treasury
Transport
Health
Industry
Planning
Premier and Cabinet
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
 
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.

 

Parliamentary reference - Report number #252 - released 7 May 2015

Published

Actions for Country towns water supply and sewerage program

Country towns water supply and sewerage program

Industry
Planning
Environment
Internal controls and governance
Management and administration
Project management
Service delivery

The Country Towns Water Supply and Sewerage Program has effectively promoted adoption of better management practices by local water utilities, but will not achieve its objective of eliminating the water supply and sewerage infrastructure backlog in urban areas of country NSW.
 
The $1.2 billion Program aims to help local water utilities provide appropriate, affordable, cost effective and well-managed water supply and sewerage services in the urban areas of country NSW. It has two broad elements:

  • promoting adoption of better practices 
  • providing financial assistance towards the capital cost of infrastructure backlog works.

 

Parliamentary reference - Report number #251 - released 4 May 2015

Published

Actions for Security of critical IT infrastructure

Security of critical IT infrastructure

Transport
Planning
Compliance
Information technology
Internal controls and governance
Management and administration
Risk

Roads and Maritime Services and Transport for NSW have deployed many controls to protect traffic management systems but these would have been only partially effective in detecting and preventing incidents and unlikely to support a timely response. There was a potential for unauthorised access to sensitive information and systems that could have disrupted traffic.
 
Until Roads and Maritime Services’ IT disaster recovery site is fully commissioned, a disaster involving the main data centre is likely to lead to higher congestion in the short-term as traffic controllers would be operating on a regional basis without the benefit of the Traffic Management Centre.

 

Parliamentary reference - Report number #248 - released 21 January 2015

Published

Actions for Freedom of Information

Freedom of Information

Transport
Premier and Cabinet
Education
Management and administration
Regulation
Service delivery

Freedom of Information (FOI) Coordinators and their staff were supportive of the legislation. However, the agencies examined can do considerably more to fully achieve the intentions of the Act. On the positive side, all three agencies had processes in place to handle requests and had made a number of changes to improve the effectiveness of the FOI process. Fees and charges had also been kept to a minimum. No processing fees were requested in the majority of cases, and if charged, were not unreasonable.

 

Parliamentary reference - Report number #114 - released 28 August 2003

Published

Actions for Northside Storage Tunnel Project

Northside Storage Tunnel Project

Planning
Environment
Infrastructure
Internal controls and governance
Procurement
Project management
Service delivery

The Northside Storage Tunnel was the first major public sector construction project using an alliance approach. In our opinion, the outcome of the project suggests that an alliance approach, when applied to a suitable project and managed appropriately, can support positive project outcomes. And in many respects the Alliance worked well. There are, however, a number of issues that we believe need to be addressed for future alliances.

 

Parliamentary reference - Report number #113 - released 24 July 2003