Actions for Volume Twelve 2015 Part Two Water
Volume Twelve 2015 Part Two Water
The distributions to the NSW Government increased from $690 million in 2013-14 to $1.0 billion in 2014-15. The increase was largely due to a higher dividend from Sydney Water Corporation.
Actions for Volume Nine 2015 Planning and Environment
Volume Nine 2015 Planning and Environment
The NSW Environment Protection Authority has reduced the average time to assess contaminated sites from 203 days in 2013-14 to 73 days in 2014-15. It is also improving transparency by making more information on its performance publicly available.
In 2014-15, the Department of Planning and Environment increased new housing approvals across New South Wales by 12 per cent to 58,252, exceeding the State priority target of 50,000. It also reduced the time taken to assess major projects from about three years in 2013-14 to four months in 2014-15.
Actions for Volume Five 2015 Premier and Cabinet
Volume Five 2015 Premier and Cabinet
Volume Five 2015 covered Premier and Cabinet agencies such as the Department of Premier and Cabinet, Office of Sport, Venues NSW, Barangaroo Delivery Authority and Infrastructure NSW.
Actions for Government advertising 2015
Government advertising 2015
The Government Advertising Act 2011 requires the Auditor-General to conduct an annual performance audit to check NSW Government agency compliance with the Act.
This audit focused on the Department of Premier and Cabinet’s (DPC) role in monitoring government agencies compliance with government advertising requirements, and examined advertising campaigns run by Destination NSW and the Sydney Opera House.
Parliamentary reference - Report number #253 - released 22 June 2015
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.
Parliamentary reference - Report number #252 - released 7 May 2015
Actions for Country towns water supply and sewerage program
Country towns water supply and sewerage program
The Country Towns Water Supply and Sewerage Program has effectively promoted adoption of better management practices by local water utilities, but will not achieve its objective of eliminating the water supply and sewerage infrastructure backlog in urban areas of country NSW.
The $1.2 billion Program aims to help local water utilities provide appropriate, affordable, cost effective and well-managed water supply and sewerage services in the urban areas of country NSW. It has two broad elements:
- promoting adoption of better practices
- providing financial assistance towards the capital cost of infrastructure backlog works.
Parliamentary reference - Report number #251 - released 4 May 2015
Actions for Areas of focus from 2014
Areas of focus from 2014
Actions for Volume One 2012 focusing on themes from 2011
Volume One 2012 focusing on themes from 2011
The following overview of audits from 2011 found agency restructures significantly impacted agency financial reporting processes, agencies are having difficulty establishing and enforcing compliance with their own policies and procedures, agencies experienced problems complying with regulations and providing adequate documentation to support their financial statements, the poor quality of some financial statements with 1,256 misstatements identified, 540 so significant they had to be corrected, deficiencies in information security exist across many agencies, computer system disaster recovery plans for financial systems not existing or outdated, do not align with agencies’ business recovery requirements, do not properly identify and assess critical systems and processes and testing is incomplete.
Actions for Lease to Fox Studios Australia
Lease to Fox Studios Australia
The audit found that the process for the lease and development of the Showground site commenced on the basis that no Government moneys would be provided and no theme park activities would be allowed. However despite this a State Government subsidy of between $84.8m and $106.8m (in net present value terms) is to be provided for the development and the area of the Showground to be leased to Fox was extended to comprise 24.3 hectares of the 28.8 hectare site to allow Fox also to develop a family entertainment park.
The audit also found that the process commenced under the former Government were intended to ensure that no one party was placed above another however, the actual processes employed up to the General Election in March 1995 were so flawed as not to be relied upon to select a preferred proponent or to justify dispensing with a tender process.
Parliamentary reference - Report number #44 - released 8 December 1997