Actions for Solar Bonus Scheme

Solar Bonus Scheme

Premier and Cabinet
Compliance
Infrastructure
Management and administration
Project management
Regulation
Risk
Service delivery

A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme.

By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced from 60 to 20 cents reducing the estimated cost to $1.954 billion.

It was a statutory requirement that when 50 mega watts of installed capacity was reached, the Government would review the Scheme. By the time the review was completed the installed capacity had reached 101 mega watts.

Published

Actions for Volume Three 2011

Volume Three 2011

Whole of Government
Asset valuation
Compliance
Financial reporting
Internal controls and governance
Management and administration
Project management

On 31 October 2011, the Auditor-General, Mr Peter Achterstraat, released Volume Three Report to Parliament on the 2010-11 NSW Total State Sector Accounts. The audited budget surplus was $1,340 million. The Auditor-General issued a qualified independent auditor’s opinion as the State could not identify the full extent and value of its land and infrastructure holdings for the eighth year in a row. The government needs to address its processes for identifying, valuing and recording land and related assets it controls as a matter of priority so it can effectively manage the full extent of its land and infrastructure holdings.

Published

Actions for Prequalification Scheme: Performance and Management Services

Prequalification Scheme: Performance and Management Services

Premier and Cabinet
Finance
Compliance
Internal controls and governance
Management and administration
Regulation
Risk
Workforce and capability

There have been tangible improvements in the time it takes NSW Government agencies to engage consultants through the Government’s Prequalification Scheme. The Scheme was introduced in February 2008 to improve agencies’ procurement of consultants. More than 300 service providers have been prequalified and over $300 million worth of consultancy services have been provided. Ideally agencies should know what assignments each consultant has won, for what services, what their rates are and how well they have performed. Agencies should then be free to contact other agencies before engaging a consultant.

 

Parliamentary reference - Report number #216 - released 28 September 2011

Published

Actions for Two Ways Together - NSW Aboriginal Affairs Plan

Two Ways Together - NSW Aboriginal Affairs Plan

Community Services
Premier and Cabinet
Internal controls and governance
Management and administration
Project management
Service delivery

To date the Two Ways Together Plan (the Plan) has not delivered the improvement in overall outcomes for Aboriginal people that was intended. Stronger partnerships between the government and Aboriginal people are only beginning to emerge. The disadvantage still experienced by some of the estimated 160,000 Aboriginal people in NSW is substantial. For example, the unemployment rate for Aboriginal people is at least three times higher than the rate for all NSW residents and hospital admissions for diabetes are also around three times higher.

 

Parliamentary reference - Report number #213 - released 18 May 2011

Published

Actions for Volume Three 2010 focus on Total State Sector

Volume Three 2010 focus on Total State Sector

Whole of Government
Asset valuation
Compliance
Financial reporting
Internal controls and governance
Management and administration
Project management

The final Budget result for 2009-10 was a surplus of $994 million, originally budgeted to be a $990 million deficit. If the Commonwealth Government’s capital stimulus funding had been excluded, the result would have been a deficit of $861 million. Employee costs (excluding superannuation costs) increased by approximately 3.5 per cent compared to 7.5 per cent in the prior year.
 
“I have issued a qualified Independent Auditor’s Report as the State has not recognised the value of Crown Reserves and the infrastructure on those reserves that should be recorded as an asset,” Mr Achterstraat said. 

Published

Actions for Electronic Information Security

Electronic Information Security

Whole of Government
Cyber security
Internal controls and governance
Risk

The Government is not able to provide assurance that it is safeguarding its holdings of sensitive personal information because its policy has not been properly implemented. This is likely to remain the case until there are clear, mandatory, minimum standards that agencies sign up to, and scrutiny of performance against these standards is strengthened.

 

Parliamentary reference - Report number #207 - released 20 October 2010

Published

Actions for Severance Payments to Special Temporary Employees

Severance Payments to Special Temporary Employees

Premier and Cabinet
Compliance
Internal controls and governance
Management and administration
Workforce and capability

In reviewing both the severance pay guidelines and a sample of payments, we found the guidelines to be clear and all except two payments were made in accordance with them. In these two cases the severance payment was stipulated in the employment contract guaranteeing the STE a minimum of six months pay on termination, irrespective of the length of service.

 

Parliamentary reference - Report number #201 - released 16 June 2010