Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Integrity of data in the Births, Deaths and Marriages Register

Integrity of data in the Births, Deaths and Marriages Register

Justice
Premier and Cabinet
Whole of Government
Cyber security
Fraud
Information technology
Internal controls and governance
Management and administration

This report outlines whether the Department of Customer Service (the department) has effective controls in place to ensure the integrity of data in the Births, Deaths and Marriages Register (the register), and to prevent unauthorised access and misuse.

The audit found that the department has processes in place to ensure that the information entered in the register is accurate and that any changes to it are validated. Although there are controls in place to prevent and detect unauthorised access to, and activity in the register, there were significant gaps in these controls. Addressing these gaps is necessary to ensure the integrity of information in the register.

The Auditor-General made nine recommendations to the department, aimed at strengthening controls to prevent and detect unauthorised access to, and activity in the register. These included increased monitoring of individuals who have access to the register and strengthening security controls around the databases that contain the information in the register.

The NSW Registry of Births Deaths and Marriages is responsible for maintaining registers of births, deaths and marriages in New South Wales as well as registering adoptions, changes of names, changes of sex and relationships. Maintaining the integrity of this information is important as it is used to confirm people’s identity and unauthorised access to it can lead to fraud or identity theft.

Read full report (PDF)

The NSW Registry of Births Deaths and Marriages (BD&M) is responsible for maintaining registers of births, deaths and marriages in New South Wales. BD&M is also responsible for registering adoptions, changes of name, changes of sex and relationships. These records are collectively referred to as 'the Register'. The Births, Deaths and Marriages Registration Act 1995 (the BD&M Act) makes the Registrar (the head of BD&M) responsible for maintaining the integrity of the Register and preventing fraud associated with the Register. Maintaining the integrity of the information held in the Register is important as it is used to confirm people's identity. Unauthorised access to, or misuse of the information in the Register can lead to fraud or identity theft. For these reasons it is important that there are sufficient controls in place to protect the information.

BD&M staff access, add to and amend the Register through the LifeLink application. While BD&M is part of the Department of Customer Service, the Department of Communities and Justice (DCJ) manages the databases that contain the Register and sit behind LifeLink and is responsible for the security of these databases.

This audit assessed whether BD&M has effective controls in place to ensure the integrity of data in the Births, Deaths and Marriages Register, and to prevent unauthorised access and misuse. It addressed the following:

  • Are relevant process and IT controls in place and effective to ensure the integrity of data in the Register and the authenticity of records and documents?
  • Are security controls in place and effective to prevent unauthorised access to, and modification of, data in the Register?

Conclusion

BD&M has processes and controls in place to ensure that the information entered in the Register is accurate and that amendments to the Register are validated. BD&M also has controls in place to prevent and detect unauthorised access to, and activity in the Register. However, there are significant gaps in these controls. Addressing these gaps is necessary to ensure the integrity of the information in the Register.

BD&M has detailed procedures for all registrations and amendments to the Register, which include processes for entering, assessing and checking the validity and adequacy of source documents. Where BD&M staff have directly input all the data and for amendments to the Register, a second person is required to check all information that has been input before an event can be registered or an amendment can be made. BD&M carries out regular internal audits of all registration processes to check whether procedures are being followed and to address non-compliance where required.

BD&M authorises access to the Register and carries out regular access reviews to ensure that users are current and have the appropriate level of access. There are audit trails of all user activity, but BD&M does not routinely monitor these. At the time of the audit, BD&M also did not monitor activity by privileged users who could make unauthorised changes to the Register. Not monitoring this activity created a risk that unauthorised activity in the Register would not be detected.

BD&M has no direct oversight of the database environment which houses the Register and relies on DCJ's management of a third-party vendor to provide the assurance it needs over database security. The vendor operates an Information Security Management System that complies with international standards, but neither BD&M nor DCJ has undertaken independent assurance of the effectiveness of the vendor's IT controls.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #330 - released 7 April 2020.

Published

Actions for Lease to Fox Studios Australia

Lease to Fox Studios Australia

Premier and Cabinet
Asset valuation
Infrastructure
Management and administration
Procurement
Project management

The audit found that the process for the lease and development of the Showground site commenced on the basis that no Government moneys would be provided and no theme park activities would be allowed. However despite this a State Government subsidy of between $84.8m and $106.8m (in net present value terms) is to be provided for the development and the area of the Showground to be leased to Fox was extended to comprise 24.3 hectares of the 28.8 hectare site to allow Fox also to develop a family entertainment park.

The audit also found that the process commenced under the former Government were intended to ensure that no one party was placed above another however, the actual processes employed up to the General Election in March 1995 were so flawed as not to be relied upon to select a preferred proponent or to justify dispensing with a tender process.

 

Parliamentary reference - Report number #44 - released 8 December 1997

Published

Actions for Review of Eastern Distributor

Review of Eastern Distributor

Transport
Infrastructure
Procurement
Project management

Following a resolution of the Legislative Council, the Audit Office has undertaken a performance audit of the Eastern Distributor. For a number of reasons, The Audit Office is not in the position to determine “whether the proposed toll and concession period represents the best deal”. In part this is the result of time constraints which do not allow a careful analysis of many toll and concession options. Similarly, the audit does not answer “whether the current proposal represents the best environmental outcome”. But each of these issues (toll and concession and environmental consequences) is discussed in the audit report.

The Audit Office recommends that the Roads and Traffic Authority (RTA), for any further major project of this type, ensures that it establishes a process which allows all decision makers to have a thorough understanding of the reasonableness of the proponents’ offers and their implications for the State and for the public. The Audit Office also recommends that the RTA should at the outset consult with TCorp in respect of each major project put to tender.

 

Parliamentary reference - Report number #42 - released 31 July 1997