Refine search Expand filter

Reports

Published

Actions for Procurement of services for the Park'nPay app

Procurement of services for the Park'nPay app

Finance
Local Government
Information technology
Internal controls and governance
Procurement
Project management

What this report is about

The report assesses whether the Department of Customer Service (the department) complied with legislation and NSW government policy when it directly negotiated with Duncan Solutions to procure backend services relating to the Park'nPay app.

The Park'nPay app, developed by the department, enables users to locate and pay for parking remotely using their smart mobile device.

The audit found

The department failed to establish the grounds for entering a direct negotiation procurement strategy, without any competitive tendering, for services for the Park'nPay app. It rushed a decision to trial the app in The Rocks, without considering how this might affect its procurement obligations.

There is no evidence that the procurement achieved value for money. Despite being required by legislation, as well as mandatory NSW government policy, the department did not consider how it would ensure value for money, nor did it demonstrate an adequate understanding of what is meant by value for money on this occasion.

The department failed to implement key probity requirements. There was no effective management of conflicts of interest. Key decisions were not documented. There was a lack of clarity, transparency, and oversight of the relationship between the Minister's office and staff in the department.

The audit made recommendations about

  1. making and retaining complete and accurate records, particularly on decisions to commit or expend public money
  2. ensuring department staff understand how to exercise their financial delegations and procurement processes
  3. ensuring that only staff with appropriate delegations are committing or approving the spending of public money
  4. consistency with the contract extension provisions of the NSW Government Procurement Policy Framework, particularly regarding ensuring value for money
  5. protocols to guide the interactions between department staff and Minister and Minister's staff
  6. the need for proper management and oversight of contingent workers, such as contractors.

 

On 27 February 2019 the then Minister for Finance, Services and Property announced the commencement of a Park’nPay app trial in The Rocks precinct of Sydney.

The app was intended to enable users to locate and pay for parking remotely, using their smart mobile device such as a phone or tablet, rather than needing to physically be at a parking meter.

In July 2019, following a direct negotiation procurement conducted by the then Department of Finance, Services and Innovation, a contract was executed with Duncan Solutions for an estimated value of $1,260,600 over three-years, with three single-year options to extend. The contract required Duncan Solutions to provide development services to link the Park'nPay app to its Parking Enterprise Management System platform and to provide ongoing software support services.

This audit assessed whether the department complied with the procurement obligations that applied at the time it procured these services from Duncan Solutions.

This audit focussed on the department's processes and decision-making relating to:

  • the direct negotiation with Duncan Solutions at the exclusion of any other potential supplier
  • the negotiation, execution and management of the contract with Duncan Solutions.

As this audit focusses on the department's procurement and contract management processes, it does not comment on the activities of Duncan Solutions. The detailed audit objective, criteria and audit approach are in Appendix three.

The auditee is the Department of Customer Service. As a result of machinery of government changes, the Department of Finance, Services, and Innovation became the Department of Customer Service from 1 July 2019. To avoid confusion, this report simply uses ‘the department’ to refer to either. Where the report refers to the Minister, it relates to the former Minister in office at the time.

Conclusion

The department failed to establish the grounds for entering a direct negotiation procurement strategy for services for the Park'nPay app. It rushed a decision to trial the app in The Rocks, without considering how this might affect its procurement requirements.

As part of a direct negotiation process, the department was required to, but did not:

  • undertake a comprehensive analysis of the market and all relevant factors to demonstrate that a competitive process does not need to be conducted
  • conduct a risk assessment for the procurement approach
  • follow the internal delegation process, including obtaining approval of the department's delegate and endorsement of the Chief Procurement Officer.

There is no evidence that the procurement to support Park'nPay represented value for money. Despite it being required by legislation, as well as mandatory NSW Government policy, the department did not consider how to ensure value for money, nor demonstrate an adequate understanding of what is meant by value for money in this case.

The department issued no tender or expression of interest documents against which any proposal could be assessed, and it had no tender evaluation plan, committee, or criteria. Without any objective standards against which the supplier's proposal could be assessed, it was not possible for the department to determine if value for money was achieved, and no value for money has been demonstrated.

The department failed to implement key probity requirements. There was no effective management of conflicts of interest. Key decisions were not documented. There was a lack of clarity, transparency, and oversight of the relationship between the Minister's office and staff in the department.

No conflict of interest declarations were made by staff until almost one year after the direct negotiations commenced and even then they were not made by all members of the negotiation team and key decision-makers.

The department did not document the reasons for its decisions or minute key meetings, such as when, why and by whom the decision was made to transform the procurement from a 'trial' to a contract of up to six years duration. The department had no policies guiding the interactions between the Minister, the Minister's office and staff in the department (including contractors) in relation to this initiative, resulting in blurred and uncertain roles, responsibilities, and accountabilities.

The department initially sought to withhold information from the Audit Office pertaining to Park'nPay. When questions were raised through external scrutiny, there was little evidence of genuine inquiry or review into its practices to ensure improvement and compliance.

The department deliberately sought to withhold information from the Audit Office of NSW when initial inquiries were lawfully made about the Park'nPay project in the context of the audit of the department's financial statements in May 2021.

There is also limited evidence to demonstrate the department has reviewed the decisions and practices around the Park'nPay project, despite receiving internal legal advice at the time that questioned the characterisation of the procurement as a 'pilot', and external scrutiny via the NSW Parliament's Budget Estimates Committee hearings. This indicates a risk that opportunities to review and improve the department's procurement practices based on learnings from this process have been missed.

 

Appendix one – Response from auditee

Appendix two – Key requirements of the department's procurement manual 

Appendix three – About the audit 

Appendix four– Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #387 - released 14 December 2023

 

Published

Actions for Natural disasters

Natural disasters

Community Services
Environment
Finance
Local Government
Planning
Transport
Treasury
Whole of Government
Asset valuation
Compliance
Financial reporting
Infrastructure
Regulation
Risk
Service delivery

What this report is about

This report draws together the financial impact of natural disasters on agencies integral to the response and impact of natural disasters during 2021–22.

What we found

Over the 2021–22 financial year $1.4 billion from a budget of $1.9 billion was spent by the NSW Government in response to natural disasters.

Total expenses were less than the budget due to underspend in the following areas:

  • clean-up assistance, including council grants
  • anticipated temporary accommodation support
  • payments relating to the Northern Rivers Business Support scheme for small businesses.

Natural disaster events damaged council assets such as roads, bridges, waste collection centres and other facilities used to provide essential services. Additional staff, contractors and experts were engaged to restore and repair damaged assets and minimise disruption to service delivery.

At 30 June 2022, the estimated damage to council infrastructure assets totalled $349 million.

Over the first half of the 2022–23 financial year, councils experienced further damage to infrastructure assets due to natural disasters. NSW Government spending on natural disasters continued with a further $1.1 billion spent over this period.

Thirty-six councils did not identify climate change or natural disaster as a strategic risk despite 22 of these having at least one natural disaster during 2021–22.

Section highlights

  • $1.4 billion from a budget of $1.9 billion was spent by the NSW Government in response to natural disasters during 2021–22.
  • Budget underspent for temporary housing and small business support as lower than expected need.

Section highlights

  • 83 local council areas were impacted by natural disasters during 2021–22, with 58 being impacted by more than one type of natural disaster.
  • $349 million damage to council infrastructure assets at 30 June 2022.

 

Published

Actions for Planning and managing bushfire equipment

Planning and managing bushfire equipment

Community Services
Justice
Planning
Environment
Local Government
Asset valuation
Compliance
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Regulation
Risk
Shared services and collaboration
Workforce and capability

What the report is about

This audit assessed the effectiveness of the NSW Rural Fire Service (RFS) and local councils in planning and managing equipment for bushfire prevention, mitigation, and suppression.

What we found

The RFS has focused its fleet development activity on modernising and improving the safety of its firefighting fleet, and on the purchase of new firefighting aircraft.

There is limited evidence that the RFS has undertaken strategic fleet planning or assessment of the capability of the firefighting fleet to respond to current bushfire events or emerging fire risks.

The RFS does not have an overarching strategy to guide its planning, procurement, or distribution of the firefighting fleet.

The RFS does not have effective oversight of fleet maintenance activity across the State, and is not ensuring the accuracy of District Service Agreements with local councils, where maintenance responsibilities are described.

What we recommended

  1. Develop a fleet enhancement framework and strategy that is informed by an assessment of current fleet capability, and research into appropriate technologies to respond to emerging fire risks.
  2. Develop performance measures to assess the performance and capabilities of the fleet in each RFS District by recording and publicly reporting on fire response times, fire response outcomes, and completions of fire hazard reduction works.
  3. Report annually on fleet allocations to RFS Districts, and identify the ways in which fleet resources align with district-level fire risks.
  4. Develop a strategy to ensure that local brigade volunteers are adequate in numbers and appropriately trained to operate fleet appliances in RFS Districts where they are required.
  5. Establish a fleet maintenance framework to ensure regular update of District Service Agreements with local councils.
  6. Review and improve processes for timely recording of fleet asset movements, locations, and maintenance status.

This audit assessed how effectively the NSW Rural Fire Service (the RFS) plans and manages the firefighting equipment needed to prevent, mitigate, and suppress bushfires. This audit also examined the role of local councils in managing bushfire equipment fleet assets. Local councils have vested legal ownership of the majority of the land-based firefighting fleet, including a range of legislated responsibilities to carry out fleet maintenance and repairs. The RFS has responsibilities to plan and purchase firefighting fleet assets, and ensure they are ready for use in response to fires and other emergencies.

This report describes the challenges in planning and managing the firefighting fleet, including a confusion of roles and responsibilities between the RFS and local councils in relation to managing certain land-based rural firefighting fleet – a point that has been made in our Local Government financial audits over several years. This role confusion is further demonstrated in the responses of the RFS and local councils to this audit report – included at Appendix one.

The lack of cohesion in roles and responsibilities for managing rural firefighting vehicles increases the risk that these firefighting assets are not properly maintained and managed, and introduces a risk that this could affect their readiness to be mobilised when needed.

While the audit findings and recommendations address some of the operational and organisational inefficiencies in relation to rural firefighting equipment management, they do not question the legislative arrangements that govern them. This is a matter for the NSW Government to consider in ensuring the fleet arrangements are fit for purpose, and are clearly understood by the relevant agencies.

The NSW Rural Fire Service (hereafter the RFS) is the lead combat agency for bushfires in New South Wales, and has the power to take charge of bushfire prevention and response operations anywhere in the State. The RFS has responsibilities to prevent, mitigate and suppress bushfires across 95% of the State, predominantly in the non-metropolitan areas of New South Wales. Fire and Rescue NSW is responsible for fire response activity in the cities and large townships that make up the remaining five per cent of the State.

The RFS bushfire fleet is an integral part of the agency's overall bushfire risk management. The RFS also uses this fleet to respond to other emergencies such as floods and storms, motor vehicle accidents, and structural fires. Fleet planning and management is one of a number of activities that is necessary for fire mitigation and suppression.

The Rural Fires Act 1997 (Rural Fires Act) imposes obligations on all landowners and land managers to prevent the occurrence of bushfires and reduce the risk of bushfires from spreading. Local councils have fire prevention responsibilities within their local government areas, principally to reduce fire hazards near council owned or managed assets, and minor roads.

The RFS is led by a Commissioner and is comprised of both paid employees and volunteer rural firefighters. Its functions are prescribed in the Rural Fires Act and related legislation such as the State Emergency Rescue Management Act 1989. The RFS functions are also described in Bush Fire Risk Management Plans, the State Emergency Management Plan, District Service Agreements, and RFS procedural documents. Some of the core responsibilities of the RFS include:

  • preventing, mitigating, and suppressing fires across New South Wales
  • recruiting and managing volunteer firefighters in rural fire brigades
  • purchasing and allocating firefighting fleet assets to local councils
  • establishing District Service Agreements with local councils to give the RFS permissions to use the fleet assets that are vested with local councils
  • carrying out fleet maintenance and repairs when authorised to do so by local councils
  • inspecting the firefighting fleet
  • supporting land managers and private property owners with fire prevention activity.

In order to carry out its legislated firefighting functions, the RFS relies on land-based vehicles, marine craft, and aircraft. These different firefighting appliance types are referred to in this report as the firefighting fleet or fleet assets.

RFS records show that in 2021 there were 6,345 firefighting fleet assets across NSW. Most of the land-based appliances commonly associated with firefighting, such as water pumpers and water tankers, are purchased by the RFS and vested with local councils under the Rural Fires Act. The vesting of firefighting assets with local councils means that the assets are legally owned by the council for which the asset has been purchased. The RFS is able to use the firefighting assets through District Service Agreements with local councils or groups of councils.

In addition to the land-based firefighting fleet, the RFS owns a fleet of aircraft with capabilities for fire mitigation, suppression, and reconnaissance during fire events. The RFS hires a fleet of different appliances to assist with fire prevention and hazard reduction works. These include aircraft for firefighting and fire reconnaissance, and heavy plant equipment such as graders and bulldozers for hazard reduction. Hazard reduction works include the clearance of bush and grasslands around major roads and protected assets, and the creation and maintenance of fire trails and fire corridors to assist with fire response activity.

The RFS is organised into 44 RFS Districts and seven Area Commands. The RFS relies on volunteer firefighters to assist in carrying out most of its firefighting functions. These functions may include the operation of the fleet during fire response activities and training exercises, and the routine inspection of the fleet to ensure it is maintained according to fleet service standards. Volunteer fleet inspections are supervised by the RFS Fire Control Officer.

In 2021 there were approximately 73,000 volunteers located in 1,993 rural fire brigades across the State, making the RFS the largest volunteer fire emergency service in Australia. In addition to brigade volunteers, the RFS has approximately 1,100 salaried staff who occupy leadership and administrative roles at RFS headquarters and in the 44 RFS Districts.

Local councils have legislative responsibilities relating to bushfire planning and management. Some of the core responsibilities of local councils include:

  • establishing and equipping rural fire brigades
  • contributing to the Rural Fire Fighting Fund
  • vested ownership of land-based rural firefighting equipment
  • carrying out firefighting fleet maintenance and repairs
  • conducting bushfire prevention and hazard reduction activity.

The objective of this audit was to assess the effectiveness of the RFS and local councils in planning and managing equipment for bushfire prevention, mitigation, and suppression. From the period of 2017 to 2022 inclusive, we addressed the audit objective by examining whether the NSW RFS and local councils effectively:

  • plan for current and future bushfire fleet requirements
  • manage and maintain the fleet required to prevent, mitigate, and suppress bushfires in NSW.

This audit did not assess:

  • the operational effectiveness of the RFS bushfire response
  • the effectiveness of personal protective equipment and clothing
  • the process of vesting of rural firefighting equipment with local councils
  • activities of any other statutory authorities responsible for managing bushfires in NSW.

As the lead combat agency for the bushfire response in NSW, the RFS has primary responsibility for bushfire prevention, mitigation, and suppression.

Three local councils were selected as case studies for this audit, Hawkesbury City Council, Wagga Wagga City Council and Uralla Shire Council. These case studies highlight the ways in which the RFS and local councils collaborate and communicate in rural fire districts.

Conclusion

The RFS has focused its fleet development activity on modernising and improving the safety of its land-based firefighting fleet, and on the purchase of new firefighting aircraft

The RFS has reduced the average age of the firefighting fleet from approximately 21 years in 2017, to approximately 16 years in 2022. The RFS has also enhanced the aerial fleet with the addition of six new aircraft to add to the existing three aircraft.

Recommendations from inquiries into the 2019–20 bushfires have driven significant levels of fleet improvement activity, mainly focused on the addition of safety features to existing fleet appliances. The RFS has dedicated most of its efforts to purchasing and refurbishing firefighting appliances of the same type and in the same volumes year on year.

However, the RFS is unable to demonstrate how the composition, size, or the locations of the NSW firefighting fleet is linked to current fire prevention, mitigation, and suppression requirements, or future fire risks.

There is limited evidence that the RFS has undertaken strategic fleet planning or assessment of the capability of the firefighting fleet to respond to current bushfire events or emerging fire risks

The RFS has not established a methodology to assess the composition or volumes of the firefighting fleet against fire activity and fire risks in the 44 NSW Rural Fire Districts. The RFS has not developed performance measures or targets to assess or report on fire response times in each of its districts, nor has it developed measures to assess the effectiveness of responses according to fire sizes and fire types. Similarly, the RFS has limited performance measures to assess fire prevention activity, or to assess fuel load reduction works, so it is not possible to assess whether its fleet capabilities are fit for these purposes.

The RFS does not have an overarching strategy to guide its planning, procurement, or distribution of the firefighting fleet

RFS fleet planning and fleet allocations are based on historical fleet sizes and compositions, and distributed to locations where there are appropriately trained brigade volunteers.

The RFS takes an asset protection approach to bushfire prevention and planning that is based on the Australian and New Zealand Standard for Risk Management. This approach requires that the RFS identify assets at risk of fire, and develop treatment plans to protect these assets. However, fleet requirements are not linked to NSW asset protection plans, meaning that fleet is not allocated according to the identified risks in these plans. Further, the RFS does not develop fire prevention plans for areas where there are no identified assets.

The RFS has not conducted future-focused fleet research or planning into technologies that match fleet capabilities to emerging or future fire risks. Since the significant fire events of 2019–2020, the RFS has not changed its approach to planning for, or assessing, the operational capabilities of the fleet. The RFS advises it is scoping a project to match resources to risk, which it plans to commence in 2023.

The RFS does not have effective oversight of fleet maintenance activity across the State, and is not ensuring the accuracy of District Service Agreements where maintenance responsibilities are described

The RFS does not have a framework to ensure that District Service Agreements with local councils are accurate. Almost two thirds of service agreements have not been reviewed in the last ten years, and some do not reflect actual maintenance practices. There is no formalised process to ensure communication occurs between the RFS and local councils for fleet management and maintenance.

RFS fleet management systems at the central level are not integrated with RFS district-level databases to indicate when fleet assets are in workshops being maintained and serviced. The RFS has a new centralised Computer Aided Dispatch System that relies on accurate fleet locations and fleet condition information in order to dispatch vehicles to incidents and fires. A lack of interface between the district-level fleet systems and the centralised RFS fleet dispatch system, may impact on operational responses to bushfires. 

The RFS has not made significant changes to the size or composition of the firefighting fleet in the past five years and does not have an overarching strategy to drive fleet development

Since 2017, the RFS has made minimal changes to its firefighting fleet volumes or vehicle types. The RFS is taking a fleet renewal approach to fleet planning, with a focus on refurbishing and replacing ageing firefighting assets with newer appliances and vehicles of the same classification and type. While the RFS has adopted a fleet renewal approach, driven by its Appliance Replacement Program Guide, it does not have a strategy or framework to guide its future-focused fleet development. There is no document that identifies and analyses bushfire events and risks in NSW, and matches fleet resources and fleet technologies to meet those risks. The RFS does not have fleet performance measures or targets to assess whether the size and composition of the fleet is meeting current or emerging bushfire climate hazards, or fuel load risks across its 44 NSW Fire Districts.

The RFS fleet currently comprises approximately 4,000 frontline, operational firefighting assets such as tankers, pumpers, and air and marine craft, and approximately 2,300 logistical vehicles, such as personnel transport vehicles and specialist support vehicles. Of the land-based firefighting vehicles, the RFS has maintained a steady number of approximately 3,800 tankers and 65 pumpers, year on year, for the past five years. This appliance type is an essential component of the RFS land-based, firefighting fleet with capabilities to suppress and extinguish fires.

Since 2017, most RFS fleet enhancement activity has been directed to upgrades and the modernisation of older fleet assets with new safety features. There is limited evidence of research into new fleet technologies for modern firefighting. The RFS fleet volumes and fleet types have remained relatively static since 2017, with the exception of the aerial firefighting fleet. Since 2017, the RFS has planned for, and purchased, six additional aircraft to add to the existing three aircraft in its permanent fleet.

While the RFS has made minimal changes to its fleet since 2017, in 2016 it reduced the overall number of smaller transport vehicles, by purchasing larger vehicles with increased capacity for personnel transport. The consolidation of logistical and transport vehicles accounts for an attrition in fleet numbers from 7,058 in 2016, to 6,315 in 2017 as shown in Exhibit 2.

The firefighting fleet management system is not always updated in a timely manner due to insufficient RFS personnel with permissions to make changes in the system

The RFS uses a fleet management system known as SAP EAM to record the location and status of firefighting fleet assets. The system holds information about the condition of the firefighting fleet, the home location of each fleet asset, and the maintenance, servicing, and inspection records of all assets. The RFS uses the system for almost all functions related to the firefighting fleet, including the location of vehicles so that they can be dispatched during operational exercises or fire responses.

Staff at RFS Headquarters are responsible for creating and maintaining asset records in the fleet management system. RFS District staff have limited permissions in relation to SAP EAM. They are able to raise work orders for repairs and maintenance, upload evidence to show that work has been done, and close actions in the system.

RFS District staff are not able to enter or update some fleet information in the system, such as the location of vehicles. When an RFS District receives a fleet appliance, it cannot be allocated to a brigade until the location of the asset is accurately recorded in the system. The location of the asset must be updated in the SAP EAM system by staff at RFS Headquarters. District staff can request system support from staff at RFS Headquarters to enter this information. At the time of writing, the position responsible for updating the fleet management system at RFS Headquarters was vacant, and RFS District personnel reported significant wait times in response to their service requests.

The RFS conducts annual audits of SAP EAM system information to ensure data is accurate and complete. RFS staff are currently doing data cleansing work to ensure that fleet allocations are recorded correctly in the system.

Communication between brigades, local councils and the RFS needs improvement to ensure that fleet information is promptly updated in the fleet management system

RFS brigade volunteers do not have access to the fleet management system. When fleet assets are used or moved, volunteers report information about the location and condition of the fleet to RFS District staff using a paper-based form, or by email or phone. Information such as vehicle mileage, engine hours, and defects are all captured by volunteers in a logbook which is scanned and sent to RFS District staff. RFS District staff then enter the relevant information into the fleet management system, or raise a service ticket with RFS Headquarters to enter the information.

Brigade volunteers move fleet assets for a range of reasons, including for fire practice exercises. If volunteers are unable to report the movement of assets to RFS District staff in a timely manner, this can lead to system inaccuracies. Lapses and backlogs in record keeping can occur when RFS staff at district offices or at Headquarters are not available to update records at the times that volunteers report information. A lack of accurate record keeping can potentially impact on RFS operational activities, including fire response activity.

Brigade volunteers notify RFS District staff when fleet appliances are defective, or if they have not been repaired properly. District staff then enter the information into the fleet management system. The inability of volunteers to enter information into the system means they have no visibility over their requests, including whether they have been approved, actioned, or rejected.

Local councils are responsible for servicing and maintaining the firefighting fleet according to the Rural Fires Act, but this responsibility can be transferred to the RFS through arrangements described in local service agreements. Council staff record all fleet servicing and maintenance information in their local systems. The types of fleet information that is captured in local council records can vary between councils. RFS staff described the level of council reporting, and the effectiveness of this process, as 'mixed'.

Councils use different databases and systems to record fleet assets, and some councils are better resourced for this activity than others

Firefighting fleet information is recorded in different asset management systems across NSW. Each council uses its own asset management system to record details about the vested fleet assets. All three councils that were interviewed for this audit had different systems to record information about the fleet. In addition, the type of information captured by the three councils was varied.

Exhibit 10: Systems used by local councils to manage the firefighting fleet
System Hawkesbury City Council Uralla Shire Council Wagga Wagga City Council
Financial asset management system TechnologyOne Civica Assetic
Asset management system TechnologyOne Manual MEX

Source: Audit Office analysis of information provided by the RFS and local councils.

Local councils have varying levels of resources and capabilities to manage the administrative tasks associated with the firefighting fleet. Some of the factors that impact on the ability of councils to manage administrative tasks include: the size of the council; the capabilities of the information management systems, the size of the staff team, and the levels of staff training in asset management.

Uralla Shire Council is a small rural council in northern NSW. This council uses financial software to record information about the firefighting fleet. While staff record information about the condition of the asset, its replacement value, and its depreciation, staff do not record the age of the asset, or its location. Staff manually enter fleet maintenance information into their systems. Uralla Shire Council would like to purchase asset maintenance software that generates work orders for fleet repairs and maintenance. However, the council does not have trained staff in the use of asset management software, and the small size of the fleet may not make it financially worthwhile.

The Hawkesbury City Council uses a single system to capture financial and asset information associated with the firefighting fleet. Hawkesbury is a large metropolitan council located north-west of Sydney, with a relatively large staff team in comparison with Uralla Shire Council. The Hawkesbury City Council has given RFS District staff access to their fleet information system. RFS District staff can directly raise work orders for fleet repairs and maintenance through the council system, and receive automated notifications when the work is complete.

Two of the three audited councils report that they conduct annual reviews of fleet assets to assess whether the information they hold is accurate and up-to-date.

More than half of the fleet maintenance service agreements between the RFS and local councils have not been reviewed in ten years, and some do not reflect local practices

Local councils have a legislated responsibility to service, repair, and maintain the firefighting fleet to service standards set by the RFS. Councils may transfer this responsibility to the RFS through District Service Agreements. The RFS Districts are responsible for ensuring that the service agreements are current and effective.

The RFS does not have monitoring and quality control processes to ensure that service agreements with local councils are reviewed regularly. The RFS has 73 service agreements with local councils or groups of councils. Sixty-three per cent of service agreements had not been reviewed in the last ten years. Only four service agreements specify an end date and, of those, one agreement expired in 2010 and had not been reviewed at the time of this audit.

The RFS does not have a framework to ensure that service agreements with local councils reflect actual practices. Of the three councils selected for audit, one agreement does not describe the actual arrangements for fleet maintenance practices in RFS Districts. The service agreement with Hawkesbury City Council specifies that the RFS will maintain the firefighting fleet on behalf of council when, in fact, council maintains the firefighting fleet. The current agreement commenced in 2012, and at the time of writing had not been updated to reflect local maintenance practices.

When District Service Agreements are not reviewed periodically, there is a risk that neither local councils nor the RFS have clear oversight of the status of fleet servicing, maintenance, and repairs.

RFS District Service Agreements set out a requirement that RFS and local councils establish a liaison committee. Liaison committees typically include council staff, RFS District staff, and RFS brigade volunteers. While service agreements state that liaison committees must meet periodically to monitor and review the performance of the service agreement, committee members determine when and how often the committee meets.

RFS District staff and staff at the three audited councils are not meeting routinely to review or update their service agreements. At Wagga Wagga City Council, staff meet with RFS District staff each year to report on activity to fulfil service agreement requirements. Uralla Shire Council staff did not meet routinely with RFS District staff before 2021. When liaison committees do not meet regularly, there is a risk that the RFS and local councils have incorrect or outdated information about the location, status, or condition of the firefighting fleet. Given that councils lack systems to track and monitor fleet locations, regular communication between the RFS and local councils is essential.

The RFS has not established processes to ensure that local councils and RFS District personnel meet and exchange information about the fleet. Of the three councils selected for this audit, one council had not received information about the number, type, or status of the fleet for at least five years, and did not receive an updated list of appliances until there was a change in RFS District personnel. This has impacted on the accuracy of council record keeping. Councils do not always receive notification about new assets or information about the location of assets from the RFS, and therefore cannot reflect this information in their accounting and reporting.

RFS area commands audit system records to ensure fleet inspections occur as planned, but central systems are not always updated, creating operational risks

RFS District staff are required by the Rural Fires Act to ensure the firefighting fleet is inspected at least once a year. Regular inspections of the fleet are vital to ensure that vehicles are fit-for-purpose and safe for brigade volunteers. Inspections are also fundamental to the operational readiness and capability of RFS to respond to fire incidents.

RFS Area Command personnel conduct audits of fleet maintenance data to ensure that fleet inspections are occurring as planned. These inspections provide the RFS with assurance that the fleet is being maintained and serviced by local council workshops, or third-party maintenance contractors.

Some RFS Districts run their own fleet management systems outside of the central management system. They do this to manage their fleet inspection activity effectively. Annual fleet inspection dates are programmed by staff at RFS Headquarters. Most of the inspection dates generated by RFS Headquarters are clustered together and RFS Districts need to separate inspection times to manage workloads over the year. Spreading inspection dates is necessary to avoid exceeding the capacity of local council workshops or third party contractors, and to ensure that fleet are available during the bushfire season.

The fleet inspection records at RFS Headquarters are not always updated in a timely manner to reflect actual inspection and service dates of vehicles. District staff are not able to change fleet inspection and service dates in the central management system because they do not have the necessary permissions to access the system. The usual practice is for RFS District staff to notify staff at RFS Headquarters, and ask them to retrospectively update the system. As there is a lag in updating the central database, at a point in time, the actual inspection and service dates of vehicles can be different to the dates entered in the central fleet management system.

Fleet inspection and maintenance records must be accurately recorded in the central RFS management system for operational reasons. RFS Headquarters personnel need to know the location and maintenance status of fleet vehicles at all times in order to dispatch vehicles to incidents and fires. The RFS fleet management system is integrated with a new Computer Aided Dispatch System. The Computer Aided Dispatch System assigns the nearest and most appropriate vehicles to fire incidents. The system relies on accurate fleet locations and fleet condition information in order to dispatch these vehicles.

There is a risk that RFS Headquarters' systems do not contain accurate information about the location and status of vehicles. Some may be in workshops for servicing and repair, while the system may record them as available for dispatch. As there are many thousands of fleet vehicles, all requiring an annual service and inspection, a lack of accurate record keeping has wide implications for State fire operations.

RFS is currently exploring ways to improve the ways in which fleet inspections are programmed into the fleet management system.

RFS provides funds to councils to assist with maintaining the firefighting fleet, but does not receive fleet maintenance cost information from all local councils

Each year the RFS provides local councils with a lump sum to assist with the cost of repairing and maintaining the firefighting fleet. This lump sum funding is also used for meeting the costs of maintaining brigade stations, utilities, and other miscellaneous matters associated with RFS business.

In 2020–21, the RFS provided NSW local councils with approximately $23 million for maintenance and repairs of appliances, buildings, and utilities. Ninety councils were provided with lump sum funding in 2021, receiving on average $257,000. The amounts received by individual councils ranged from $56,200 to $1,029,884.

Some councils provide itemised repairs and maintenance reports to RFS District staff, showing the work completed and the cost of that work. However, not all councils collect this information or provide it to the RFS. Local councils collect fleet maintenance information in their local council systems. In some cases, the responsibility for fleet maintenance is shared across a group of councils, and not all councils have oversight of this process.

The RFS has not taken steps to require local councils to provide itemised maintenance costings for the firefighting fleet. Thus, the RFS does not have a clear understanding of how local councils are spending their annual fleet maintenance funding allocations. The RFS does not know if the funding allocations are keeping pace with the actual cost of repairing and maintaining the fleet.

RFS District staff report that funding shortfalls are impacting on the prioritisation of fleet servicing and maintenance works in some council areas. When fleet servicing and maintenance is not completed routinely or effectively, there is a risk that it can negatively impact the overall condition and lifespan of the vehicle. Poor processes in relation to fleet maintenance and repair risk impacting on the operational capabilities of the fleet during fire events.

The timeliness and effectiveness of fleet servicing and maintenance is affected by resource levels in RFS Districts and local councils

Local councils have a legislated responsibility to service and maintain the firefighting fleet to the service standards set by the RFS. Fleet maintenance is usually done by the entity with the appropriate workshops and resources, and the maintenance arrangements are described in District Service Agreements. RFS District staff conduct annual inspections to ensure that the firefighting fleet has been serviced and maintained appropriately, and is safe for use by brigade volunteers. If the fleet has not been maintained to RFS service standards or timelines, RFS District staff may work with local councils to support or remediate these works.

The effectiveness of this quality control activity is dependent on relationships and communication between the RFS Districts and local councils. While some RFS staff reported having positive relationships with local councils, others said they struggled to get fleet maintenance work done in a timely manner. Some councils reported that funding shortfalls for fleet maintenance activity was impacting on the prioritisation of RFS fleet maintenance works. When fleet maintenance work is not completed routinely or effectively, it can negatively impact on the overall condition and lifespan of the vehicle. It can also reduce the capacity of the RFS to respond to fire events.

Fleet quality control activities are carried out by RFS District staff. In some of the smaller RFS Districts, one person is responsible for liaising with local councils and brigade volunteers about fleet maintenance and repairs. In the regions where resources are limited, there is less ability to maintain ongoing communication. This is impacting on fleet service and maintenance timelines and the timeliness of fleet monitoring activity.

The RFS has mutual support arrangements with agencies in NSW and interstate, though shared fleet levels are yet to be quantified

The RFS has arrangements with state, federal, and international fire authorities to provide mutual support during fire incidents. In NSW, the RFS has agreements with the three statutory authorities – Fire and Rescue NSW, the Forestry Corporation of NSW, and the NSW National Parks and Wildlife Service. The agreement with Fire and Rescue NSW provides a framework for cooperation and joint operations between the agencies. The agreements with the Forestry Corporation of NSW and the NSW National Parks and Wildlife Service describe the control and coordination arrangements for bush and grass fires across NSW. These arrangements are set out in legislation and incorporated into local Bush Fire Risk Management Plans.

The RFS has agreements with fire authorities in three of the four Australian states and territories that share a border with NSW – the Australian Capital Territory, Queensland, and South Australia. Each agreement sets out the arrangements for mutual assistance and joint operations, including arrangements for sharing aircraft. The agreement between the RFS and Victoria had lapsed. The RFS told the NSW Bushfire Inquiry that the agreement with Victoria would be finalised by June 2020. In June 2022, the RFS reported that the agreement was in the process of being finalised.

The arrangements for mutual aid from Western Australia, Northern Territory and Tasmania, are managed by the National Resource Sharing Centre. These agreements set out the arrangements for interstate assistance between Australian fire services, emergency services, and land management agencies in those states and territories.

These mutual support arrangements may assist during state-based fire events. However, when there are competing demands for resources, such as during the bushfires of 2019–2020, there can be limits on fleet availability. During the 2019–2020 fires, resources were stretched in all jurisdictions as these fires affected NSW, Victoria, and Queensland.

There are opportunities for the RFS and other NSW agencies to quantify fleet resources across the State and identify assets that can be mobilised for different fire activities. This form of fleet planning may be used to enhance surge capabilities during times of high fire activity. There are also opportunities for the RFS and other agencies to match the levels of shared assets to projected bushfire risks.

Appendix one – Responses from agencies 

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #376 - released 27 February 2023

 

Published

Actions for Development applications: assessment and determination stages

Development applications: assessment and determination stages

Planning
Local Government
Internal controls and governance
Management and administration
Service delivery

What the report is about

Local councils in New South Wales are responsible for assessing local and regional development applications.

Most development applications are assessed and determined by council staff under delegated authority. However, some development applications must be referred to independent local planning panels or Sydney and regional planning panels for determination.

Councils provide support to local planning panels. The Department of Planning and Environment provides support to Sydney and regional planning panels.

This audit assessed whether Byron Shire Council, Northern Beaches Council and The Hills Shire Council had effectively assessed and determined development applications in compliance with legislative and other requirements.

It also assessed whether The Hills Shire Council, Northern Beaches Council and the Department of Planning and Environment had provided effective support to relevant independent planning panels.

What we found

All councils had established clear roles, responsibilities and delegations for assessment and determination of development applications and had also established processes to ensure quality of assessment reports.

Northern Beaches Council and The Hills Shire Council have established comprehensive approaches to considering and managing risks related to development assessment.

Northern Beaches Council's approach to publishing its assessment reports promotes transparency.

Across a sample of development applications assessed and determined between 2020–22:

  • Northern Beaches Council and The Hills Shire Council had assessed and determined applications in compliance with legislative and other requirements. However, The Hills Shire Council could do more to transparently document any conflicts of interest within assessment reports.
  • Byron Shire Council had assessed most applications in compliance with legislative and other requirements. However, we found opportunities for the Council to:
    • ensure determinations were made in line with delegations
    • strengthen its approach to transparent management of conflicts of interest and quality review of assessments.

The Hills Shire Council and Northern Beaches Council had effectively supported their respective local planning panels.

The Department of Planning and Environment had processes that meet requirements for supporting regional planning panels but could do more to promote consistency in approach, share information across panels and measure the effectiveness of its support.

What we recommended

We made recommendations to Byron Shire Council, The Hills Shire Council and the Department of Planning and Environment to address the gaps identified and improve the transparency of processes.

Local councils in New South Wales are responsible for assessing local and regional development applications under the Environmental Planning and Assessment Act 1979 (EP&A Act).

In assessing development applications, councils consider:

  • whether the proposed development application is compliant with legislation and environmental planning instruments
  • whether the proposed development meets local planning controls and objectives
  • any environmental, social and economic impacts
  • any submissions from impacted properties, neighbours and interested parties
  • the public interest.

Once assessed, a development application will be determined by council staff under delegated authority, the elected council, or an independent planning panel.1 

The involvement of a particular independent planning panel is established under legislative and policy instruments, and depends on the type and value of the proposed development. Most development applications are assessed and determined by council staff under delegated authority.

In determining development applications, independent planning panels must manage any potential, real or perceived conflicts of interest of panel members for a given development application, meet and vote on development applications, and publish their decisions and reasons.

Under the EP&A Act, and as required by statutory instruments and procedures, councils and the Department of Planning and Environment (DPE) must provide secretariat and other support functions to independent planning panels.

Previous reviews and inquiries have identified several significant risks that are present within the processes involved in the assessment and determination of development applications. These risks include possible non-compliance with complex legal and policy requirements, potential improper influence from developers and other stakeholders, and a perceived lack of transparency within the planning system and planning outcomes.

There are several planning pathways for development in New South Wales. This audit focuses on local and regional development that requires assessment and determination by a local council and/or an independent local planning panel or Sydney or regional planning panel in three Local Government Areas (LGAs): Byron Shire Council, Northern Beaches Council, The Hills Shire Council.

Audited councils were selected from a range of criteria, including:

  • the number, value and types of development applications determined in 2018–19
  • average determination timeframes
  • appeals against determinations and Land and Environment Court outcomes
  • LGA demographics.

The audit also avoided councils that had previously been subject to a performance audit.

The objective of this audit was to assess whether:

  • selected councils have effectively assessed and determined development applications in compliance with relevant legislation, regulations and government guidance
  • selected councils and DPE effectively support independent planning panels to determine development applications in compliance with relevant legislation, regulations and government guidance.

Conclusion – Byron Shire Council

Byron Shire Council has established clear roles, responsibilities and delegations for assessment and determination of development applications. However, the effectiveness of the Council's approach is limited by gaps in governance, risk management and internal controls.

Byron Shire Council has established clear roles, responsibilities and delegations for assessment and determination of development applications. However, the Council does not have a consolidated policy and procedure for development assessment, has not adequately followed up on the outcomes of internal reviews that identified opportunities to strengthen its assessment and determination procedures and approach, and has not demonstrated that it has managed relevant risks effectively.

The Council has not ensured that delegations have been consistently followed in the assessment of development applications.

Byron Shire Council's approach to managing conflicts of interest in development assessments does not provide transparency over potential conflicts of interest.

Byron Shire Council manages the risk of conflicts of interest for development assessment under its Code of Conduct. The Council has also implemented a separate policy that details additional requirements for managing conflicts of interest relevant to the development assessment process, but has not regularly updated this policy and requirements between it and the Code of Conduct have not been aligned. This creates a risk that planning staff may be following inconsistent or outdated advice in managing conflicts of interest.

Across the period of review, the Council did not require staff to provide a disclosure of interest for individual development applications to be contained within assessment reports. Including these disclosures would increase transparency and ensure that staff are sufficiently considering any conflicts of interest relevant to each separate assessment process.

Byron Shire Council has processes that promote compliance with legislation, regulation and government policy, but can improve how it undertakes some aspects of these that would ensure transparency, quality and consistency.

Our review of a sample of completed development applications from the Council indicated that most assessments were completed in compliance with relevant legislation, regulations and government guidance, but that there were some opportunities to improve elements of the assessment process, including: transparency of any conflicts of interest involved in the assessment process, ensuring compliance with delegated authority limits, and consideration of modification application provisions.

The Council has established templates to guide planners through relevant assessment considerations required by legislation, regulations and other guidance. However, it could do more to strengthen its approach to peer or manager review, monitoring legislative changes, and how it monitors the completion of relevant training by planning staff. 

 

Conclusion – Northern Beaches Council

Northern Beaches Council has established processes to support compliant and effective assessment and determination of development applications.

The Council has a clear governance and risk management framework for development assessment that sets out roles, responsibilities and delegations.

Northern Beaches Council has established clear roles, responsibilities and delegations for development application assessment and determination. The Council has identified development assessment related risks, and has put in place controls and mitigating actions to manage the risks to within risk tolerances.

Northern Beaches Council's approach to managing conflicts of interest promotes transparency.

Northern Beaches Council manages the risk of conflicts of interest for development assessment under its Code of Conduct. The Council has implemented an additional framework for planning staff to respond to the risk of conflicts of interest in development assessment processes. This framework requires its staff to disclose any conflicts of interest as a formal step in assessing development applications and includes declarations of any interests within assessment reports or planning panel minutes.

Our review of a sample of completed development applications indicated that the assessment reports had been compliant with the Council's approach to transparently documenting conflicts of interest.

Northern Beaches Council has established processes to deliver consistent, quality assessment of development applications.

Northern Beaches Council staff use an electronic development assessment tool that provides guidance, links to legislative and policy instruments and other applications that support assessment and drive consistency in approach. The Council applies a peer review process in which a manager or team member in a more senior position reviews an assessment report prior to determination to ensure that expected standards of quality and consistency have been met.

Our review of a sample of completed development applications indicated that assessments were undertaken in compliance with relevant legislation, regulations and government guidance.

Northern Beaches Council transparently documents assessment reports, supporting information and determination outcomes.

Northern Beaches Council has implemented a transparent approach to how it assesses and determines development applications. The Council publishes assessment reports, supporting technical reports, plans and submissions for all development applications. Notices of determination and final plans are also published alongside the assessment reports, allowing for greater transparency to the public.

Northern Beaches Council has established processes to effectively support the Northern Beaches Local Planning Panel.

Northern Beaches Council has established processes to support the Northern Beaches Local Planning Panel as required under legislative and policy instruments. The Council has processes to ensure that development applications required to be referred to a planning panel are identified and monitored, supports identification and documentation of any conflicts of interest, and transparently documents decisions of the panel.

Our review of a sample of meeting records held across the audit period of review indicated that these requirements were met and were transparently documented. 

 

Conclusion – The Hills Shire Council

The Hills Shire Council has established processes to support compliant and effective assessment and determination of development applications.

The Council has established a comprehensive governance and risk management framework for development assessment that sets out clear roles, responsibilities and delegations.

The Hills Shire Council has established a comprehensive framework for managing risks related to development assessment. Such risks are clearly identified and associated controls are in place to reduce or mitigate the risks. The Council has undertaken regular internal audits of development assessments, including reviewing completed applications to ensure compliance with relevant legislative and policy requirements.

The Council has established clear roles, responsibilities and delegations, and its staff assessing and determining development applications are supported by a standard set of policies and procedures for undertaking assessment and determination of applications.

The Hills Shire Council is managing conflicts of interest in line with Code of Conduct requirements but could more transparently document these.

The Hills Shire Council manages conflicts of interest for those involved in development application processes through provisions under its Code of Conduct. Under this Code of Conduct, staff must declare any conflicts of interest to their manager. However, the Council does not require staff to disclose any conflicts of interest in development application assessment reports which limits transparency to reviewing managers or any other determination bodies.

The Hills Shire Council has established processes to deliver consistent, quality assessment of development applications.

The Hills Shire Council has established templates to guide planners through relevant development assessment and determination considerations required by legislation, regulations and other guidance. The Council requires a peer review to occur prior to any determination which ensures a check on the compliance and quality of the assessment report prepared.

Our review of a sample of completed development applications from the Council indicated that assessments were performed in compliance with relevant legislation, regulations and government guidance.

The Hills Shire Council has established processes to effectively support The Hills Shire Local Planning Panel.

The Hills Shire Council has met requirements to provide secretariat and other support to The Hills Shire Local Planning Panel as required under legislative and policy instruments. It has processes to ensure that development applications required to be referred to a planning panel are identified and monitored, supports identification and documentation of any conflicts of interest, and transparently documents decisions of the panel.

Our review of a sample of meeting records held across the audit period of review indicated that these requirements were met and were transparently documented. 

 

Conclusion – Department of Planning and Environment

The Department of Planning and Environment (DPE) has established processes that meet its statutory and policy requirements to support Sydney and regional planning panels.

DPE has established processes to provide secretariat and other support to planning panels. It has met requirements to provide administrative support to the panels through its planning panels secretariat including undertaking administrative functions, supporting recruitment of panel members, and addressing complaints about the panel processes.

DPE has not ensured collection of annual pecuniary interest declarations for all panel members for the three Sydney and regional planning panels in scope for this audit. DPE could not provide annual pecuniary interest declarations for part of the audit period for three of the 47 members of these panels, as is required by DPE's Code of Conduct for Regional Planning Panels.

DPE does not formally measure its effectiveness in providing support to panels, but panel chairs consulted as part of this audit advised that they had no concerns with the level of secretariat support provided by DPE.

DPE could do more to facilitate information sharing between panels and could formalise how it provides comparative information to panels to improve consistency and standardisation in approach and share good practice. DPE has identified these gaps in reviews of its services and functions and has a plan in place to address them.

DPE has effectively documented planning panel decisions and made them available to all stakeholders. It also effectively documented interests declared as part of consideration of development applications for in-scope panels. 


1 Prescribed councils within designated Sydney districts are required to refer contentious development applications to local planning panels for determination. If the proposed development is above a threshold for estimated cost of works, or meets other prescribed criteria, the EP&A Act may require it to be referred to a Sydney or regional planning panel.

This audit continues a series of audits examining the development assessment process in NSW local councils and is focused on the assessment and determination stages.

The Audit Office of New South Wales previously considered local government development assessments in our 2019 performance audit: 'Development assessment: pre-lodgement and lodgement in Camden Council and Randwick City Council'.

Appendix one – Response from agencies

Appendix two – Council profile: Byron Shire Council

Appendix three – Council profile: Northern Beaches Council

Appendix four – Council profile: The Hills Shire Council

Appendix five – About the audit 

Appendix six – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #370 - released 12 December 2022

 

Published

Actions for Audit Insights 2018-2022

Audit Insights 2018-2022

Community Services
Education
Environment
Finance
Health
Industry
Justice
Local Government
Premier and Cabinet
Planning
Transport
Treasury
Universities
Whole of Government
Asset valuation
Cross-agency collaboration
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Service delivery
Shared services and collaboration
Workforce and capability

What the report is about

In this report, we have analysed the key findings and recommendations from our audit reports over the past four years.

This analysis includes financial audits, performance audits, and compliance audits of state and local government entities that were tabled in NSW Parliament between July 2018 and February 2022.

The report is framed by recognition that the past four years have seen significant challenges and emergency events.

The scale of government responses to these events has been wide-ranging, involving emergency response coordination, service delivery, governance and policy.

The report is a resource to support public sector agencies and local government to improve future programs and activities.

What we found

Our analysis of findings and recommendations is structured around six key themes:

  • Integrity and transparency
  • Performance and monitoring
  • Governance and oversight
  • Cyber security and data
  • System planning for disruption
  • Resource management.

The report draws from this analysis to present recommendations for elements of good practice that government agencies should consider in relation to these themes. It also includes relevant examples from recent audit reports.

In this report we particularly call out threats to the integrity of government systems, processes and governance arrangements.

The report highlights the need for balanced advice to government on options and risks, for transparent documentation and reporting of directions and decisions, and for early and open sharing of information with integrity bodies and audit.

A number of the matters highlighted in this report are similar to those described in our previous Insights Report, (Performance Audit Insights: key findings from 2014–2018) specifically in relation to cyber and information security, to performance measurement, reporting and evaluation, and system and workforce planning and capability.

Fast facts

  • 72 audits included in the Audit Insights 2018–2022 analysis
  • 4 years of audits tabled by the Auditor-General for New South Wales
  • 6 key themes for Audit Insights 2018–2022.

picture of Margaret Crawford Auditor-General for New South Wales in black dress with city skyline as backgroundI am pleased to present the Audit Insights 2018–2022 report. This report describes key findings, trends and lessons learned from the last four years of audit. It seeks to inform the New South Wales Parliament of key risks identified and to provide insights and suggestions to the agencies we audit to improve performance across the public sector.

The report is framed by a very clear recognition that governments have been responding to significant events, in number, character and scale, over recent years. Further, it acknowledges that public servants at both state and council levels generally bring their best selves to work and diligently strive to deliver great outcomes for citizens and communities. The role of audit in this context is to provide necessary assurance over government spending, programs and services, and make suggestions for continuous improvement.

A number of the matters highlighted in this report are similar to those described in our previous Insights Report, (Performance Audit Insights: key findings from 2014–2018) specifically in relation to cyber and information security, to performance measurement, reporting and evaluation, and system and workforce planning and capability.

However, in this report we particularly call out threats to the integrity of government systems, processes and governance arrangements. We highlight the need for balanced advice to government on options and risks, for transparent documentation and reporting of directions and decisions, and for early and open sharing of information with integrity bodies and audit. Arguably, these considerations are never more important than in an increasingly complex environment and in the face of significant emergency events and they will be key areas of focus in our future audit program.

While we have acknowledged the challenges of the last few years have required rapid responses to address the short-term impacts of emergency events, there is much to be learned to improve future programs. I trust that the insights developed in this report provide a helpful resource to public sector agencies and local government across New South Wales. I would be pleased to receive any feedback you may wish to offer.

Margaret Crawford
Auditor-General for New South Wales

Integrity and transparency Performance and monitoring Governance and oversight Cyber security and data System planning Resource management
Insufficient documentation of decisions reduces the ability to identify, or rule out, misconduct or corruption. Failure to apply lessons learned risks mistakes being repeated and undermines future decisions on the use of public funds. The control environment should be risk-based and keep pace with changes in the quantum and diversity of agency work. Building effective cyber resilience requires leadership and committed executive management, along with dedicated resourcing to build improvements in cyber security and culture. Priorities to meet forecast demand should incorporate regular assessment of need and any emerging risks or trends. Absence of an overarching strategy to guide decision-making results in project-by-project decisions lacking coordination. Governments must weigh up the cost of reliance on consultants at the expense of internal capability, and actively manage contracts and conflicts of interest.
Government entities should report to the public at both system and project level for transparency and accountability. Government activities benefit from a clear statement of objectives and associated performance measures to support systematic monitoring and reporting on outcomes and impact. Management of risk should include mechanisms to escalate risks, and action plans to mitigate risks with effective controls. In implementing strategies to mitigate cyber risk, agencies must set target cyber maturity levels, and document their acceptance of cyber risks consistent with their risk appetite. Service planning should establish future service offerings and service levels relative to current capacity, address risks to avoid or mitigate disruption of business and service delivery, and coordinate across other relevant plans and stakeholders. Negotiations on outsourced services and major transactions must maintain focus on integrity and seeking value for public funds.
Entities must provide balanced advice to decision-makers on the benefits and risks of investments. Benefits realisation should identify responsibility for benefits management, set baselines and targets for benefits, review during delivery, and evaluate costs and benefits post-delivery. Active review of policies and procedures in line with current business activities supports more effective risk management. Governments hold repositories of valuable data and data capabilities that should be leveraged and shared across government and non-government entities to improve strategic planning and forecasting. Formal structures and systems to facilitate coordination between agencies is critical to more efficient allocation of resources and to facilitate a timely response to unexpected events. Transformation programs can be improved by resourcing a program management office.
Clear guidelines and transparency of decisions are critical in distributing grant funding. Quality assurance should underpin key inputs that support performance monitoring and accounting judgements. Governance arrangements can enable input into key decisions from both government and non-government partners, and those with direct experience of complex issues.     Workforce planning should consider service continuity and ensure that specialist and targeted roles can be resourced and allocated to meet community need.
Governments must ensure timely and complete provision of information to support governance, integrity and audit processes.          
Read more Read more Read more Read more Read more Read more

 

This report brings together a summary of key findings arising from NSW Audit Office reports tabled in the New South Wales Parliament between July 2018 and February 2022. This includes analysis of financial audits, performance audits, and compliance audits tabled over this period.

  • Financial audits provide an independent opinion on the financial statements of NSW Government entities, universities and councils and identify whether they comply with accounting standards, relevant laws, regulations, and government directions.
  • Performance audits determine whether government entities carry out their activities effectively, are doing so economically and efficiently, and in accordance with relevant laws. The activities examined by a performance audit may include a selected program or service, all or part of an entity, or more than one government entity. Performance audits can consider issues which affect the whole state and/or the local government sectors.
  • Compliance audits and other assurance reviews are audits that assess whether specific legislation, directions, and regulations have been adhered to.

This report follows our earlier edition titled 'Performance Audit Insights: key findings from 2014–2018'. That report sought to highlight issues and themes emerging from performance audit findings, and to share lessons common across government. In this report, we have analysed the key findings and recommendations from our reports over the past four years. The full list of reports is included in Appendix 1. The analysis included findings and recommendations from 58 performance audits, as well as selected financial and compliance reports tabled between July 2018 and February 2022. The number of recommendations and key findings made across different areas of activity and the top issues are summarised at Exhibit 1.

The past four years have seen unprecedented challenges and several emergency events, and the scale of government responses to these events has been wide-ranging involving emergency response coordination, service delivery, governance and policy. While these emergencies are having a significant impact today, they are also likely to continue to have an impact into the future. There is much to learn from the response to those events that will help the government sector to prepare for and respond to future disruption. The following chapters bring together our recommendations for core elements of good practice across a number of areas of government activity, along with relevant examples from recent audit reports.

This 'Audit Insights 2018–2022' report does not make comparative analysis of trends in public sector performance since our 2018 Insights report, but instead highlights areas where government continues to face challenges, as well as new issues that our audits have identified since our 2018 report. We will continue to use the findings of our Insights analysis to shape our future audit priorities, in line with our purpose to help Parliament hold government accountable for its use of public resources in New South Wales.

Appendix one – Included reports, 2018–2022

Appendix two – About this report

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for NSW planning portal

NSW planning portal

Planning
Industry
Environment
Local Government
Information technology
Project management
Risk

What the report is about

The ePlanning program is an initiative of the Department of Planning and Environment (the department) to deliver a digital planning service for New South Wales through the NSW planning portal (the portal).

Using the portal, relevant planning activities can be carried out online, including all stages of development applications.

The portal has been developed under three separate business cases in 2013, 2014 and 2020.

In late 2019, the government mandated the use of the portal for all development applications. This decision took effect across 2020–21.

This audit assessed the effectiveness of the department's implementation, governance and stakeholder engagement in delivering the NSW planning portal. 

What we found

Since implementation commenced in 2013, the NSW planning portal has progressively achieved its objectives to provide citizens with access to consolidated planning information, and allow them to prepare and submit development applications online.

Shortcomings in the department's initial planning and management of the program led to a significant time overrun. It has taken the department longer and cost significantly more to implement the portal than first anticipated. 

In recent years the department has improved the planning, implementation and governance of the ePlanning program, resulting in improved delivery of the portal’s core functions.

The department now has a clear view of the scope necessary to finalise the program, but has not yet published the services it plans to implement in 2022 and 2023.

Mandating the use of the portal for all development applications changed the program's strategic risk environment and required the department to work more closely with a cohort of stakeholders, many of whom did not want to adopt the portal.

Despite this change, the department kept its overall delivery approach the same.

While implementation of the portal has delivered financial benefits, the department has overestimated their value.

The Department has only reported benefits since 2019 and has not independently assured the calculation of benefits.

What we recommended

By December 2022, the department should:

  • publish a roadmap of the services it expects to release on the portal across 2022 and 2023
  • update its ePlanning program assumptions, benefits targets and change management approach to reflect the government's decision to mandate the use of the portal for all stages of a development application
  • independently assure and report publicly the correct calculation of ePlanning program benefits.

Fast facts

  • 10 years taken to implement the portal when completed
  • 3 years longer than initially planned to implement the portal
  • $146m capital expenditure on the portal when completed
  • $38.5m more spent than planned in the business cases.

The ePlanning program is an initiative of the Department of Planning and Environment (the department) to deliver a digital planning service for New South Wales through the NSW planning portal (the portal, or the planning portal). The department defines the portal as an online environment where community, industry and government can work together to better understand and meet their obligations under the Environmental Planning and Assessment Act 1979 (NSW). Using the portal, relevant planning activities can be carried out online throughout New South Wales. This includes, but is not limited to:

  • applying for and gaining planning approval
  • applying for and gaining approval for building works, sub-dividing land and similar activities
  • issuing occupancy and other certificates.

The portal has been developed under three separate business cases. The first business case in 2013 led to the creation of a central portal, which made planning information available to view by planning applicants and allowed some planning applications to be lodged and tracked online.

Under a second business case prepared in 2014, the department set out to improve and widen the functions available via the portal. The department prepared a third business case in 2020 to fund further improvements to the portal over the period July 2020 to June 2023. The third business case also extended the portal's functions to support the building and occupation stages of the planning cycle.

In late 2019, the government mandated the use of the portal for all stages of development applications. This decision took effect across 2020–21 and applied to all councils as well as certifiers and others involved in the planning process.

The objective of this performance audit was to assess the effectiveness of the department's implementation, governance and stakeholder engagement in delivering the NSW planning portal. We investigated whether:

  • delivery of the NSW planning portal was planned effectively
  • sound governance arrangements are in place to ensure effective implementation of the program
  • users of the NSW planning portal are supported effectively to adopt and use the system.
Conclusion

Since implementation commenced in 2013, the NSW planning portal has progressively achieved its objectives to provide citizens with access to consolidated planning information and allow them to prepare and submit development applications online. Implementation was initially hindered by deficiencies in planning and it has taken the department significantly longer and cost significantly more to implement the portal than first anticipated. While the portal's implementation has delivered financial benefits, the department has overestimated their value. As a result, the department cannot yet demonstrate that the portal has achieved overall financial benefits, relative to its costs.

In the first two years of the ePlanning program, the department delivered a portal that allowed planners, developers, certifiers and the public to view important planning information. However, the department found the delivery of a second, transactional version of the portal in 2017 to be much more challenging. This version was intended to offer more integrated information and allow development applications to be submitted and managed online. The department did not rollout this version after a pilot showed significant weaknesses with the portal's performance. A subsequent review found that this was partly because the department did not have a clear view of the portal’s role or the best way to implement it. In recent years the department has improved the planning, implementation and governance of the ePlanning program resulting in improved delivery of the portal’s core functions.

By the time the program reaches its scheduled completion in 2023, it will have taken the department ten years and around $146 million in capital expenditure to implement the portal. This will be significantly longer and more expensive than the department originally expected. This overrun is partly due to an increased scope of services delivered through the portal and an initial under-appreciation of what is involved in creating a standard, central resource such as the portal. The department also experienced some significant implementation difficulties – which saw the transactional portal discontinued after it was found to be not fit for purpose. Following this, the department re-set the program in 2017–18 and re-planned much of the portal's subsequent development.

In November 2019, the New South Wales Government decided to mandate the use of the portal for all stages of development applications by the end of 2020–21. The department had previously planned that the portal would be progressively adopted by all councils and other stakeholders over the five years to 2025. The decision to mandate the portal's use for all development applications brought forward many of the portal's benefits as well as the challenges of its implementation. The department did not change its overall delivery approach in response to the changed risks associated with the government's decision to mandate use of the portal.

The current version of the portal has given the department more timely and comprehensive planning information and has helped New South Wales to provide continuous planning services during COVID-19 lockdowns, which interrupted many other public functions. The portal has also delivered financial benefits, however the department has not independently assured benefits calculations carried out by its consultant, and the reported benefits are overstated. In addition, some stakeholders report that the portal is a net cost to their organisation. This has included some certifiers and some councils which had implemented or had started to implement their own ePlanning reforms when use of the portal was mandated in 2019. The department now needs to address the issues faced by these stakeholders while continuing to deliver the remaining improvements and enhancements to the portal. Over the remaining year of the program, it will be critical that the department focuses on the agreed program scope and carefully evaluates any opportunities to further develop the portal to support future planning reforms.

This part of the report sets out how:

  • the ePlanning program has been planned and delivered
  • users of the portal have been supported
  • the program has been governed.

This part of the report sets out the ePlanning program's:

  • expected and reported financial benefits
  • calculation of financial benefits.

In 2019, the department increased its expectations for net financial benefits

The department's three ePlanning business cases each forecast substantial financial benefits from the implementation of the planning portal. The department expected that most financial benefits would flow to planning applicants due to a quicker and more consistent planning process. It also expected that government agencies and councils would benefit from the portal.

Exhibit 6: Summary of the financial benefits originally expected
  Business case 1
($ million)
Business case 2
($ million)
Business case 3
($ million)
Total
($ million)
Benefits 90.0 44.3 270.9 405.2
Costs 43.3 29.4 89.8 162.5
Net benefits 46.7 15.0 181.1 242.7

Note: Benefits and costs are incremental. All amounts are calculated over ten years. Amounts for business case 1, 2 and 3 amounts are expressed in 2013, 2015 and 2019 dollars respectively. All amounts are discounted at seven per cent to show their value at the time when they were calculated. Amounts may not add due to rounding.
Source: Audit Office analysis of data provided by the Department of Planning and Environment.

In 2019 the department commissioned a review to explore opportunities to better identify, monitor and realise the benefits of the ePlanning program. Using this work, the department updated the expected benefits for business cases 1 and 2 to take account of:

  • errors and miscalculations in the original benefits calculations
  • slower delivery of the portal and changes to the take-up of portal services by councils
  • changes to the services supported by the portal.
Exhibit 7: Summary of the financial benefits expected for business case 1 and 2 after the 2019 update
  Original business case 1 and 2 (combined)
($ million)
New business case 1 and 2 (combined)
($ million)
Benefits 134.3 210.6
Costs 72.7 96.3
Net benefits 61.7 114.3

Note: Benefits and costs are incremental. All amounts are calculated over ten years. Amounts for the original business case 1 and 2 are expressed in 2013 and 2015 dollars respectively. The new combined amount is expressed in 2019 dollars. All amounts are discounted or inflated at seven per cent to show their value at the time when they were calculated. Amounts may not add due to rounding.
Source: Audit Office analysis of data provided by the Department of Planning and Environment.

Reported benefits significantly exceed the current targets

In September 2021, the department reported that the program had achieved $334 million of benefits over the three financial years up to June 2021 plus the first two months of 2021–22. These reported benefits were significantly higher than expected. 

Exhibit 8: Reported financial benefits from the ePlanning program
  2018–19
($ million)
2019–20
($ million)
2020–21
($ million)
July to August 2021
($ million)
Total
($ million)
Benefits 5.2 68.8 214.7 45.1 333.8
Target 2.5 14.4 56.7 19.2 92.8
Amount and per cent above target 2.7
108%
54.4
378%
158
279%
25.9
135%
241
260%

Source: Audit Office analysis of data provided by the Department of Planning and Environment.

The department attributes the higher-than-expected financial benefits to the following:

  • benefit targets have not been updated to reflect the impact of the 2019 decision to mandate the use of the portal for all development applications. This decision brought forward the expected benefits as well as potential costs of the program. However, the department did not update its third business case which was draft at the time. The business case was subsequently approved in July 2020
  • one-off cost savings for agencies not having to develop their own systems
  • public exhibitions of planning proposals continuing to be available online during 2020 when some newspapers stopping printing due to COVID-19.

The calculation of benefits is overstated

The department reported $334 million of benefits in September 2021 due to the ePlanning program. This calculation is overstated because:

  • a proportion of reported benefits is likely to be due to other planning reforms
  • the calculation of the largest single benefit is incorrect
  • the reported benefits may not fully account for dis-benefits reported by some stakeholders.

The program’s benefits are calculated primarily from changes in planning performance data, such as the time it takes to determine a planning development application. The department currently attributes the benefits from shorter planning cycles entirely to the effect of the ePlanning program. However, planning cycles are impacted by many other factors such as the complexity of planning regulations and the availability of planning professionals. Planning cycles may also be impacted by other departmental initiatives which are designed to improve the time that it takes for a planning application to be evaluated. The Introduction describes some of these initiatives.

The largest contribution to the department’s September 2021 benefit report was an estimated saving of $151 million for developers due to lower costs associated with holding their investment for a shorter time. However, the department’s calculation of this benefit assumes a high baseline for the time to determine a development application. It also assumes that all development applications except for additions or alterations to existing properties will incur financing costs. However, a small but material number of these applications will be self-financed. The calculation also includes several data errors in spreadsheets.

The calculation of some benefits relies upon an extrapolation of the benefits experienced by a small number of early-adopter councils, including lower printing and scanning costs, fewer forms and quicker processing times. However, some councils report that their costs have increased following the introduction of the portal, primarily because aspects of the portal duplicate work that they carry out in their own systems. The portal has also required some councils to re-engineer aspects of their own systems, such as the integration of their planning systems with other council systems such as finance or property and rating systems. It has also required councils to create new ways of integrating council information systems with the planning portal.

The department has published information to help councils and certifiers to automatically integrate their systems with the planning portal. This approach uses application programming interfaces (or APIs) which are an industry-standard way for systems to share information. In April and May 2021, the government granted $4.8 million to 96 regional councils to assist with the cost of developing, implementing and maintaining APIs. The maximum amount of funding for each council was $50,000. The department is closely monitoring the implementation of APIs by councils and other portal users. Once they are fully implemented the department expects APIs to reduce costs incurred by stakeholders.

The department has not yet measured stakeholder costs. It was beyond the scope of this audit to validate these costs.

The department has not independently assured the calculation of reported benefits

In 2020 the department appointed an external provider to calculate the benefits achieved by the ePlanning program. The department advised that it chose to outsource the calculation of benefits because the provider had the required expertise and because it wanted an independent calculation of the benefits. The process involves:

  • extraction and verification of planning performance data by the department
  • population of data input sheets by the department
  • calculation of benefits by the external provider using the data input
  • confirmation by the department that the calculation includes all expected benefit sources.

The department does not have access to the benefits calculation model which is owned and operated by the external provider. The department trusts that the provider correctly calculates the benefits and does not verify the reported benefit numbers. However, as the benefits model involves many linked spreadsheets and approximately 300 individual data points, there is a risk that the calculation model contains errors beyond those discussed in this audit.

The reported benefits have only been calculated since 2019

The department originally intended to track benefits from October 2014. However, it only started to track benefits in 2019 when it appointed an external provider to calculate the benefits achieved by the portal. Any benefits or dis-benefits between the introduction of the portal and 2019 are unknown and not included in the department’s calculation of benefits.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #366 - released 21 June 2022

Published

Actions for Local government business and service continuity arrangements for natural disasters

Local government business and service continuity arrangements for natural disasters

Local Government
Internal controls and governance
Management and administration
Project management
Risk
Service delivery

What the report is about

Natural disaster events, including bushfires and floods, have directly impacted some local councils in New South Wales over recent years. It is important for local councils to effectively plan so that they can continue operations through natural disasters and other disruptions.

This audit assessed the effectiveness of Bega Valley Shire Council and Snowy Valleys Council’s approaches to business and service continuity arrangements for natural disasters.

What we found

Bega Valley Shire Council has a documented approach to planning for business and service continuity that provides for clear decision making processes and accountability.

Bega Valley Shire Council has prepared for identified natural disaster risks to business and service continuity but can do more to monitor how it has implemented controls responding to these risks.

Bega Valley Shire Council did not follow all aspects of its business continuity plan in responding to the 2019–20 bushfires.

Bega Valley Shire Council can do more to ensure its business continuity management approach is regularly reviewed and updated, and that staff are regularly trained in its implementation.

Snowy Valleys Council did not have a finalised approach to ensure business and service continuity until October 2020. Now in place, this approach identifies governance, assigns roles and responsibilities, and includes procedures to retain or resume services. That said, the Council has not adequately documented key elements of its business continuity management approach.

Snowy Valleys Council's strategic risk register identifies that natural disasters may impact its ability to deliver services, but the Council has not identified controls to respond to these risks.

During the 2019–20 bushfires, in the absence of a business continuity plan, Snowy Valleys Council relied on the local knowledge of its staff to manage service continuity in line with directions from the Local Emergency Operations Controller and the combat agency (the Rural Fire Service).

Both councils advised that, during the 2019–20 bushfires, services were maintained, sometimes with adaptation and sometimes with support from other councils, NSW Government and Australian Government agencies.

What we recommended

Bega Valley Shire Council should update and regularly review its business continuity plans, provide business continuity training, and improve its monitoring of risk controls and actions, including for natural disaster impacts.

Snowy Valleys Council should document and monitor all disruption-related risks and controls, regularly review and update its business continuity plans, and progress planned actions to increase staff awareness of business continuity plans.

Across both councils, we recommended that recordkeeping relating to service delivery during natural disasters should be adequate to inform post incident reviews and future updates to business continuity.

Fast facts

  • Multiple natural disasters affected the audited councils in 2019–20:
    • bushfires in 2019–20
    • storms and floods in January 2020
    • storms and floods in July and August 2020
    • storms and floods in October 2020.
  • 6,279kmSize of Bega Valley Shire Council (area)
  • 2,203kmArea burnt within Bega Valley Shire Council in 2019–20 bushfires
  • 8,959kmSize of Snowy Valleys Council (area)
  • 3,339kmArea burnt within Snowy Valleys Council in 2019–20 bushfires.

Natural disaster events, including bushfires and floods, have directly impacted some local councils in New South Wales over recent years. Given their important role in delivering essential services to their communities, it is important for local councils to effectively plan so that they can continue operations through natural disasters and other disruptions.

Business continuity plans are a widespread mechanism used by governments and private sector organisations to ensure they are prepared to respond effectively to disruptions. In New South Wales, business continuity plans are widely used by local councils to help ensure continuity of service delivery, safety and availability of staff, availability of information technology systems and other systems, financial management and governance. There are no current sector-wide requirements or policies for business continuity management issued by the Department of Planning and Environment (DPE)1 for NSW councils. As such, councils can develop their own business continuity management frameworks.

Our 'Report on Local Government 2020' considered the financial and governance impacts from recent natural disaster events on local councils in New South Wales. It also considered sector-wide trends in business continuity planning, including how many councils enacted or updated their business continuity plans in 2019–20.

The report found that all councils were impacted by emergency events, and that some councils changed their governance, policies, systems, and processes to respond to the emergency events. Sixty-five per cent of councils updated their business continuity plan as a response to recent emergency events, and 43 per cent of councils updated their disaster recovery plan.

This audit follows on from the 'Report on Local Government 2020' with a detailed examination of the effectiveness of business and service continuity arrangements for natural disasters in two councils.

The selected councils for this audit were Bega Valley Shire Council and Snowy Valleys Council. They were selected because they had been heavily impacted by the 2019–20 bushfires and other natural disaster events, such as storms and floods between December 2018 to December 2020.

The objective of this performance audit was to assess the effectiveness of the councils' approaches to business and service continuity arrangements for natural disasters. In making this assessment, we considered whether the selected councils:

  • had documented approaches for identifying, mitigating, and responding to disaster-related risks to business and service continuity
  • effectively implemented strategies to prepare for identified disaster-related impacts
  • responses during selected disasters were effective in managing business and service continuity.

Conclusion - Bega Valley Shire Council

Bega Valley Shire Council has a documented approach to planning for business and service continuity that provides for clear decision-making processes and accountability.

Since 2018, the council has prepared for identified natural disaster risks to business and service continuity, but can do more to monitor how it has implemented controls responding to these risks.

Bega Valley Shire Council did not follow all aspects of its business continuity plan in responding to the 2019–20 bushfires.

The council can do more to ensure its business continuity management approach is regularly reviewed and updated, and that staff are regularly trained in its implementation.

Bega Valley Shire Council has a documented approach to business continuity management that is integrated with its broader approach to enterprise risk management and is supported by clear decision-making processes and accountability. This includes a business continuity plan (BCP), BCP subplans, and a business impact analysis (BIA). The council made changes to its BIA in 2019 following the 2018 Tathra bushfires within its local government area (LGA), but its BCP and BCP subplans have not been updated since 2016 and key information is out of date.

Bega Valley Shire Council has identified high-level controls and strategies to mitigate disaster-related risks and undertakes post incident reviews to capture lessons following a disaster, but many high-risk actions resulting from those reviews remain outstanding.

Bega Valley Shire Council identified risks, controls, and actions to prepare for natural disaster impacts between 2018 to 2020. However, the council has not effectively monitored implementation of the identified controls. Bega Valley Shire Council has only partially implemented the actions and recommendations from internal reviews that identified gaps in its business continuity management approach.

Bega Valley Shire Council did not follow all aspects of its business continuity plan in responding to the 2019–20 bushfires, instead relying on the local knowledge of its staff. The council has not provided BCP scenario training since 2015 and has not monitored completion rates of its online business continuity management training for staff.

Bega Valley Shire Council did not keep records of its decision of whether to enact its BCP during the 2019–20 bushfires, but advised its ability to follow the BCP was not possible due to the scale and impact of the bushfires surpassing the expectations included in its BCP and BCP subplans.

The council advised that essential council-led services were largely maintained during the disaster, sometimes with adaptation of services, and sometimes with support from other councils, NSW Government and Australian Government agencies.

As Bega Valley Shire Council did not maintain formal records of service disruptions for most services, did not follow all aspects of its BCP during the 2019–20 bushfires, and because it requested and received support from other agencies, we are unable to assess the impact of its planning and preparation activities on the continuity of services.

Bega Valley Shire Council took actions during the 2019–20 bushfires to communicate key service changes to staff, residents, and stakeholders, and regularly sought feedback on residents' experiences.

Bega Valley Shire Council could improve the effectiveness of its business continuity management approach by undertaking regular staff training (including scenario training) and ensuring that its business continuity management framework is routinely updated to reflect current practice and current staff. 

 

Conclusion - Snowy Valleys Council

Snowy Valleys Council did not have a finalised approach to ensure business and service continuity until October 2020. Now in place, this approach identifies governance, assigns roles and responsibilities and includes procedures to retain or resume services. That said, the council has not adequately documented key elements of its business continuity management approach.

Snowy Valleys Council's risk register identifies that natural disasters may impact its ability to deliver services, but the council has not identified controls to respond to these risks.

During the 2019–20 bushfires, in the absence of a business continuity plan (BCP) or BCP subplans, the council relied on the local knowledge of its staff to manage service continuity in line with directions from the Local Emergency Operations Controller and the combat agency (the Rural Fire Service).

Snowy Valleys Council did not have a finalised BCP, BCP subplans, or BIA until after the 2019–20 bushfires. The council finalised most of its business continuity management framework in late 2020 and this framework now establishes governance, including assigning roles and responsibilities, and identifies contingencies and procedures to retain or resume critical services.

There are gaps in how Snowy Valleys Council has documented key elements of its business continuity management approach. The council advised it has completed a BIA, but has not retained the completed version of this document as it was not managed under Snowy Valleys Council's record management procedures. Some of the council's BCP subplans have gaps in process information and contact details which means BCP subplan owners and other potential users may not have access to accurate, up to date information when responding to a disruption event.

The council advised it provided BCP scenario training in 2016, 2018, and 2021, but was unable to provide any evidence of the 2018 training. As the current BCP and BCP subplans were only finalised in 2021, the 2016 and 2018 training were based on the previous BCP framework, developed under the former Tumut Shire Council. Additionally, the council advised it has developed BCP awareness training for staff as part of induction training, but has not provided a clear timeframe for implementing this training.

The council undertakes post incident reviews after most service disruption events, but has not undertaken a post incident review of the 2019–20 bushfires, despite its significant impact within the Snowy Valleys Council LGA.

Snowy Valleys Council advised that it identifies and mitigates or controls for disaster related risks within broader enterprise-wide risk assessments. Snowy Valleys Council’s strategic risk register identifies the risk of natural disasters to service delivery, but does not identify preventative controls or resilience strategies to mitigate these risks. The council monitors and improves the resilience of some assets as part of its regular operations of maintaining assets but does not clearly link such actions to how they contribute to reducing the risk of natural disaster related impacts. Snowy Valleys Council advises it works with other agencies, such as the Rural Fire Service and the local Bush Fire Management Committee, to plan for bushfire risks.

In the absence of a BCP or BCP subplans, Snowy Valleys Council relied on individual team members to manage service continuity during the 2019–20 bushfires based on directions by the local Emergency Operations Controller, and the Rural Fire Service. The council advised that the delivery of essential council-led services was largely maintained during the 2019–20 bushfires, sometimes with adaptation and support from other NSW Government and Australian Government agencies. Snowy Valleys Council took actions during the 2019–20 bushfires to communicate key service changes to staff, residents, and stakeholders, and regularly sought feedback on residents' experiences.

As Snowy Valleys Council did not maintain formal records of any service disruptions and did not have a finalised business continuity management approach in place to guide its response during the 2019–20 bushfires, we are unable to assess the impact of its planning and preparation activities on the continuity of services.

 

 1 At the time of this audit, the Department of Planning and Environment is responsible for supporting and regulating local councils in New South Wales through the Office of Local Government. Prior to 21 December 2021, the Department of Planning and Environment was named the Department of Planning, Industry and Environment.

Appendix one – Responses from councils and the Department of Planning and Environment 

Appendix two – Emergency management arrangements for local councils 

Appendix three – About the audit 

Appendix four – Performance auditing 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #362 - released 17 February 2022.

Published

Actions for Procurement management in Local Government

Procurement management in Local Government

Local Government
Internal controls and governance
Management and administration
Procurement
Regulation
Service delivery

The Auditor‑General for New South Wales, Margaret Crawford, released a report today examining procurement management in Local Government.

The audit assessed the effectiveness of procurement management practices in six councils. All six councils had procurement management policies that were consistent with legislative requirements, but the audit found compliance gaps in some councils. The audit also identified opportunities for councils to address risks to transparency and accountability, and to ensure value for money is achieved when undertaking procurement.

The Auditor‑General recommended that the Department of Planning, Industry and Environment review the Local Government (General) Regulation 2005 and publish updated and more comprehensive guidance on procurement management for the Local Government sector. The report also generated insights for the Local Government sector on opportunities to strengthen procurement practices.

Effective procurement is important in ensuring councils achieve their objectives, demonstrate value for money and deliver benefits to the community when purchasing goods and services. Procurement also comes with risks and challenges in ensuring the purchased goods and services deliver to expectations. The risks of fraud and conflicts of interest also need to be mitigated.

The legislative requirements related to procurement in the Local Government sector are focused on sourcing and assessing tender offers. These requirements are included in the Local Government Act 1993 (the Act), the Local Government Amendment Act 2019 (the Amendment), the Local Government (General) Regulation 2005 (the Regulation), the Tendering Guidelines for NSW Local Government 2009 (the Tendering Guidelines), the Government Information (Public Access) Act 2009 (the GIPA Act) and the State Records Act 1998.

General requirements and guidance relevant to councils are also available in the Model Code of Conduct for Local Councils in NSW 2018 (the Model Code), the NSW Government Procurement Policy Framework 2019 and in publications by the Independent Commission Against Corruption (ICAC).1

Individual councils have developed their own procurement policies and procedures to expand on the legislative requirements. Understandably, these vary to reflect each council’s location, size and procurement needs. Nevertheless, the general principles of effective procurement management (such as transparency and accountability) and risk-mitigating practices (such as segregation of duties and the provision of training) are relevant to all councils.

The Audit Office of New South Wales Report on Local Government 2018 provided a sector-wide summary of aspects of procurement management in Local Government (see Section 2.1 of this report). This audit builds on this state-wide view by examining in detail the effectiveness of procurement management practices in six councils. This report also provides insights on opportunities to strengthen procurement management in the sector.

The selected councils for this audit were Cumberland City Council, Georges River Council, Lockhart Shire Council, Tweed Shire Council, Waverley Council and Wollongong City Council. They were selected to provide a mix of councils of different geographical classifications, sizes, priorities and levels of resourcing.

Conclusion

All six councils had procurement management policies and procedures that were consistent with the legislative requirements for sourcing and assessing tender offers. Their policies and procedures also extended beyond the legislative requirements to cover key aspects of procurement, from planning to completion. In terms of how these policies were applied in practice, the six councils were mostly compliant with legislative requirements and their own policies and procedures, but we found some gaps in compliance in some councils and made specific recommendations on closing these gaps.

There were also opportunities for councils to improve procurement management to mitigate risks to transparency, accountability and value for money. Common gaps in the councils’ procurement management approaches included not requiring procurement needs to be documented at the planning stage, not providing adequate staff training on procurement, not requiring procurement outcomes to be evaluated, and having discrepancies in contract values between contract registers and annual reports. These gaps expose risks to councils’ ability to demonstrate their procurements are justified, well managed, delivering to expectations, and achieving value for money. Chapter three of this report provides insights for the audited councils and the Local Government sector on ways to address these risks

Recommendations

  1. By June 2022, the Department of Planning, Industry and Environment should:
    1. publish comprehensive and updated guidance on effective procurement practices – including electronic tender submissions and procurements below the tender threshold
    2. review and update the Local Government (General) Regulation 2005 to reflect the increasing use of electronic tender submissions rather than paper copies.
  2. By December 2021, the six audited councils should consider the opportunities to improve procurement management in line with the improvement areas outlined in chapter three of this report.
  3. Cumberland City Council should immediately:
    1. ensure contract values are consistent between the contract register and the annual report
    2. introduce procedures to ensure supplier performance reviews are conducted as per the council’s policy
  4. Georges River Council should immediately:
    1. ensure contract values are consistent between the contract register and the annual report
    2. introduce procedures to ensure all the steps up to the awarding of a contract are documented as per the council’s policy
    3. introduce procedures to ensure outcome evaluations are conducted as per the council’s policy.
  5. Lockhart Shire Council should immediately:
    1. include additional information in the council’s contract register to ensure compliance with Section 29(b), (f), (g), (h) and (i) of the GIPA Act
    2. ensure contract values are consistent between the contract register and the annual report.
  6. Waverley Council should immediately ensure contracts are disclosed in the annual report as per Section 217(1)(a2) of the Regulation.

(1) The relevant ICAC publications include: Corruption Risks in NSW Government Procurement – The Management Challenge (2011), Corruption Risks in NSW Government Procurement – Suppliers’ Perception of Corruption (2011) and Corruption Risks in NSW Government Procurement – Recommendations to Government (2011).

While all six councils had procurement policies in place and were generally compliant with legislative requirements, this report has identified common gaps in processes and practices that expose risks to transparency, accountability and value for money.

This section discusses how councils can mitigate risks and ensure the best outcomes are achieved from their procurements.

Documented justification of procurement needs

The ICAC notes that determining what goods and services an agency requires is the first step of procurement, and the scope for corruption in how need is determined is significant. Without documenting how procurement needs have been justified, councils cannot demonstrate that they fulfill business needs, nor how the procurements may link to the councils’ strategic plans to deliver to the community.

This audit found that none of the six councils’ policies required them to document justification of procurement needs, and none did so consistently in practice. Councils can address this gap by building into their procurement planning process a requirement for staff to document the justification of procurement needs. For higher value procurements, this could be extended to include analysis of options, an assessment of risks and defining intended outcomes. Similarly, clearly establishing and documenting how relevant procurements relate to a council’s community strategic plans or operational plans helps ensure transparency.

Although a formal business case may not be required for many procurements (for example, low-value procurements or routine replacements), some form of documented justification for the expenditure should still be kept on record to demonstrate that the procurement relates to business purposes and is needed.

Segregation of duties

Segregation of duties is an effective control for reducing risks of error, fraud and corruption in procurement. It works on the principle that one person should not have end-to-end control of a procurement. Effective segregation of duties also often involves managerial or independent oversight that is built into the process. Four of the audited councils (Cumberland City Council, Georges River Council, Lockhart Shire Council and Wollongong City Council) appropriately addressed segregation of duties in their procurement frameworks. For example:

  • All procurements in Cumberland City Council required a delegated officer’s approval before commencing, and the requisitioning department is responsible for ensuring the completion of the goods, works or services associated with each contract. For contracts over $50,000, a specific ‘Authority to Procure’ form had to be completed by the requesting staff, signed by an approver and then forwarded to the procurement team.

  • Reflecting its small size, all procurements in Lockhart Shire Council were managed by one senior staff member. Nevertheless, this staff member had to bring contract management plans to the rest of the Executive Leadership Team for review and discussion, with large contracts such as those above the tender threshold referred to Council for approval.

The ICAC notes that segregation of duties helps to control discretion, which has particular risk implications for some types of procurement.This includes those involving low-value and high-volume transactions, restricted tenders, long-standing procurements and ‘pet projects’ (projects advocated by individual staff members). In cases where corruption risks are low, ICAC notes that monitoring staff’s involvement in procurement may be a cost-effective alternative to total segregation of duties.

Assessment of supplier performance

Councils need to monitor and assess supplier performance to ensure suppliers deliver the goods and services as agreed. The audit found that all six councils consistently monitored progress in capital works and for externally funded projects. Contract monitoring in these cases included ensuring timelines, funding, and legislative requirements were met. This is positive, as capital works made up the bulk of procurements (in terms of volume) in all of the audited councils.

That said, in all six councils, the level of scrutiny was lower for other types of procurements, and there is scope for improvement. For instance, the approach to monitoring capital works or externally funded projects could be replicated across other procurements of a similar nature and value. Conducting assessments and keeping records of supplier performance on all procurements does not need to be onerous, but instead provides useful information to inform future decision-making—including by helping ensure supplier pricing remains competitive, and avoiding re-engaging underperforming suppliers.

The NSW Government Procurement Policy Framework requires that NSW Government agencies establish systems and processes jointly with the suppliers to ensure compliance with contract terms and performance requirements. It also advises that agencies should drive continuous improvement and encourage innovation in coordination with suppliers and key stakeholders.

Centralised contract register

Centrally registering a contract provides improved transparency of procurement activities and facilitates monitoring and compliance checks. While councils are already required to maintain a contract register for all contracts above the reporting threshold (as per the GIPA Act), given the threshold is set at a relatively high benchmark ($150,000), there is merit in councils extending the practice to procurements below the reporting threshold. A central and comprehensive register of contracts helps avoid duplication of procurements and re-contracting of underperforming suppliers.

Three of the audited councils (Georges River Council, Tweed Shire Council and Wollongong City Council) had contract register policies that applied to procurements below the reporting threshold during the audited period. For example, Georges River Council required contracts valued at $10,000 or above to be registered with the procurement team, and Tweed Shire Council had a threshold of $50,000.

Evaluation of community outcomes and value for money

Councils may be progressing procurements to fulfill their strategic and business plans, or using them to fulfill commitments to the community. In these instances, outcomes evaluation is an important way to demonstrate to the community that the intended benefits and value for money have been delivered.

Five of the six audited councils did not require evaluations of community outcomes and value for money. While Georges River Council required contracts valued at $50,000 or more to be monitored, evaluated and reported on at least annually throughout the contract and also at its conclusion, in the procurements we examined the only ‘outcome evaluations’ that the council had conducted were community surveys that did not refer to individual procurements. Councils can miss opportunities to understand the impact of their work on the local community if evaluations of procurement outcomes are not completed. Evaluation findings are also valuable in guiding future resource allocation decisions.

Value for money in the procurement of goods and services is more than just having the specified goods delivered or services carried out. The NSW Government Procurement Policy Framework requires that state government agencies track and report benefits to demonstrate how value for money is being delivered. The framework notes that value for money is not necessarily the lowest price, nor the highest quality good or service, but requires a balanced assessment of a range of financial and non-financial factors, such as: quality, cost, fitness for purpose, capability, capacity, risk, total cost of ownership or other relevant factors.

Procurement training

Effective procurement management relies on the capability of staff involved in various stages of the process. Guidance can be provided through training, which is an important element of any procurement management framework. It ensures that staff members are aware of the councils' policies and procedures. If structured appropriately and provided in a timely manner, training can help to standardise practices, ensure compliance, reduce chances of error, and mitigate risks of fraud or corruption.

The ICAC notes that effective procurement management depends on the competence of staff undertaking procurements and the competence of those who oversee procurement activities. As the public sector is characterised by varying levels of procurement expertise, the ICAC notes that the sector would benefit from a structured approach to training and the application of minimum standards.3

At the time of this audit, only Wollongong City Council addressed staff training requirements in its procurement management framework. Exhibit 8 details its approach.

Exhibit 8: Wollongong City Council's approach to training
  • Wollongong City Council has a suite of procurement training available for staff, administered by a dedicated staff member who also monitors attendance and training needs
  • Staff must complete training before they can take part in a procurement or be a member of a tender assessment panel, and the council keeps a list of all accredited staff members.
  • Staff cannot access procurement files on the council's electronic records management system until they have received training and have been approved for access by the trainer.
  • Staff must be trained before they can receive a financial delegation.

Source: Audit Office of New South Wales analysis of Wollongong City Council's procurement policies and procedures 2020.
 

Two of the audited councils have now also introduced procurement training:

  • Georges River Council implemented online training, which is mandatory for new staff and serves as refresher training for existing staff. The council also provides in-person training for selected staff (covering contract management, contract specification writing and contractor relationship management) and has developed quick reference cards for all staff to increase awareness of the council's procurement processes.
  • Tweed Shire Council implemented mandatory online training for all staff members. The training covers the council's procurement policy and protocol as well as relevant legislation. It is linked to relevant council documents such as the Procurement Toolkit on the council's intranet, and includes a quiz for which training participants must score at least 80 per cent to have the training marked as completed.
(2) ICAC (2011) Corruption Risks in NSW Government Procurement – The Management Challenge.
(3) ICAC (2011) Corruption Risks in NSW Government Procurement – Recommendations to Government.

Appendix one – Responses from councils and the Department of Planning, Industry and Environment

Appendix two – Councils’ procurement contracts

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #345 - released 17 December 2020

Published

Actions for Governance and internal controls over local infrastructure contributions

Governance and internal controls over local infrastructure contributions

Local Government
Planning
Environment
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today on how well four councils managed their local infrastructure contributions during the 2017-18 and 2018-19 financial years. 

Local infrastructure contributions, also known as developer contributions, are collected from developers to pay for local infrastructure such as drainage, local roads, open space and community facilities. Controls over local infrastructure contributions help to ensure that all contributions owed are collected, funds are spent as intended, and any contributions paid in the form of works-in-kind or dedicated land are correctly valued.

The audit found that Blacktown City Council and City of Sydney Council provided effective governance over their local infrastructure contributions whereas Central Coast and Liverpool City Councils’ governance arrangements require improvement.

The audit found that three councils had spent local infrastructure contributions in accordance with approved contributions plans. Central Coast Council and the former Gosford City Council had spent $13.2 million on administration costs in breach of the Environmental Planning and Assessment Act 1979. These funds were repaid into the council’s local infrastructure fund during the course of the audit.

The Auditor-General made a number of recommendations for each council relating to improving controls over contributions and increasing transparency. 

Read full report (PDF)
 

This audit examined the effectiveness of governance and internal controls over local infrastructure contributions, also known as developer contributions, held by four councils during the 2017–18 and 2018–19 financial years.

This performance audit was conducted with reference to the legislative and regulatory planning framework that was in place during that period.

Our work for this performance audit was completed at the end of March 2020 when we issued the final report to the four audited councils and the Department of Planning, Industry and Environment. We received their respective formal responses to the report’s recommendations during April and May 2020.

Concurrently to this audit, we sought Crown Solicitor’s advice (the ‘Advice’) regarding the use of local infrastructure contributions collected by local councils under the Environmental Planning and Assessment Act 1979 (‘the EPA Act’) for our financial audit work. The Advice clarified the applicable legislative requirements with reference to the application, investment and pooling of local infrastructure contributions. The Advice is included in Appendix 2 of this report. The Advice has not impacted on the findings and recommendations of this report.

Councils collect Local Infrastructure Contributions (LICs) from developers under the Environmental Planning and Assessment Act (1979), the Local Government Act (1993) and the City of Sydney Act (2000) (EP&A Act, LG Act and City of Sydney Act) to fund infrastructure required to service and support new development. At 30 June 2018, councils across NSW collectively held more than $3.0 billion in LICs collected from developers. Just over $1.37 billion in total was held by ten councils. Councils collecting LICs must prepare a contributions plan, which outlines how LICs will be calculated and apportioned across different types of infrastructure. Councils that deliver water and sewer services prepare a development servicing plan (DSP) which allows them to collect contributions for water and sewer infrastructure.

Development timeframes are such that there is often several years between when LICs are collected and the infrastructure is required. Good governance and internal controls are needed over these funds to ensure they are available when needed and spent appropriately.

This audit assessed the effectiveness of governance and internal controls over LICs collected by four councils during the 2017–18 and 2018–19 financial years: Blacktown City Council, Central Coast Council, City of Sydney Council and Liverpool City Council. As at June 2018 these councils held the four highest LIC balances, each in excess of $140 million.

Audit Conclusion

Three of the four councils audited were currently compliant with legislation, regulations and Ministerial Directions regarding LICs. All had gaps in governance and controls over LICs which limited effective oversight.

Three of the councils included in the audit complied with legislation, regulations and Ministerial Directions relating to LICs. Central Coast Council breached the EP&A Act between 2001 and 2019 when it used LICs for administration costs. These funds were repaid in late 2019.

While controls over the receipt and expenditure of contributions funds were largely in place at all councils, there were some exceptions relating to valuing work and land delivered in lieu of cash. Three councils do not provide probity guidance in policies relating to LICs delivered through works-in-kind. Three of the councils had contributions plans that were more than five years old.

Staff at all four councils are knowledgeable about LICs but not all councils keep procedures up to date. Three councils' governance frameworks operate effectively with senior officers from across the council involved in decisions about spending LICs, entering into voluntary planning agreements (VPAs) and reviewing contributions plans.

Transparency over key information relating to LICs is important for senior management so they can make informed decisions, and for the community who pay LICs and expect infrastructure to be provided. During the period of the audit, none of the councils included in the audit provided sufficient information to senior management or their councillors about the projected financial status of contributions plans. This information would be valuable when making broader strategic and financial decisions. Information about LIC levies and intended infrastructure is available to the community but not always easy to find.

A strong governance framework is important at each council to ensure that the funds are managed well, available when needed and spent as intended. The audit examined the following features of each council's governance framework as they apply to LICs:

  • decision-making by councillors and council officers relating to LICs
  • monitoring delivery of contributions plans and DSPs including:
    • reviewing assumptions underlying the plans
    • monitoring projected status of plans.

Internal controls over LICs are important to promote accountability, prevent fraud and deliver infrastructure to the required standard at the best possible price. If financial controls are weak or are not implemented well, there is a risk that LICs are misspent or that councils pay too much for infrastructure.

Not all councils' internal controls adequately addressed risks associated with the administration of LICs

The audit examined a number of internal controls that manage risks related to LICs. These included:

  • financial controls over receipt and expenditure of LIC funds
  • management of conflicts-of-interest when dealing with developers
  • independent valuations of works-in-kind and dedicated land
  • ensuring delivery and quality of works-in-kind, and obtaining security from developers in the event of non-delivery or poor quality work
  • management of variations to VPAs and works-in-kind agreements.

We reviewed controls included in policies and procedures and then checked samples of work to ensure that controls were implemented. We found variation in the controls that councils implemented, and some weaknesses in controls. It is a matter for each council to assess their financial risk and develop internal controls that support the collection, management, and expenditure of LICs. However, councils must be able to assure their communities and developers that they are doing everything possible to collect all LICs owing and that work conducted by developers in lieu of cash payments is properly valued and carried out to the required standard.

Further information about audit findings in relation to internal controls for each council are included in chapters five to eight. The exhibit below demonstrates variation in several controls implemented in the audited councils.

In a 2018 report, the Independent Commission Against Corruption noted that 'the appetite for transparency is expanding in both the public and private sectors'.

The Practice Note and S64 Guidance refer to transparency, including the importance of transparency over:

  • calculation and apportionment of LICs
  • funding of infrastructure, including where and when infrastructure is delivered
  • arrangements made with developers through VPAs.

The LIC system is largely transparent for community members who know where to look

Contributions plans and DSPs are public documents, exhibited to the public before being adopted by council. Councils included in the audit publish their contributions plans and DSPs on their websites and meet statutory requirements with regard to reporting and accessibility of information.

However, other public information relating to the LIC system is fragmented across different websites and reports and varies in detail across councils.

Exhibit 10: Published information about LICs at the four audited councils
  Blacktown City Council Central Coast Council City of Sydney Council Liverpool City Council
Financial details about contributions collected and spent Financial statements Financial statements Financial statements Financial statements
Implementation plans for spending LICs Contribution plans S64 implementation plans in DSPs. S7.11 & S7.12 implementation plans developed annually within capital works plan Contribution plans Developed annually within capital works plan
Capital works underway or completed, funded by LICs Capital works plan and annual report Not published Not published Capital works plan
Source: Audit Office analysis.

The Practice Note states that councils are accountable for providing the infrastructure for which contributions are collected. Demonstrating that infrastructure has been provided is difficult with fragmented information. As an example of transparent reporting, Blacktown City Council's 2018–19 annual report includes information about infrastructure that has been delivered for every contributions plan, providing transparency over how LICs have been spent.

Use of LICs collected under VPAs is not always transparent

Contributions collected under VPAs are not required to demonstrate the same relationship to a development as LICs collected under section 7.11 of the EP&A Act. VPAs are often negotiated because a developer requests a change to a planning instrument, and it is important that these arrangements, and their outcomes, are transparent to the community.

The EP&A Regulation includes mechanisms to ensure that VPAs are partially transparent. VPAs are exhibited to the public and approved by the elected council. Councils must maintain a VPA Register and make the VPA Deeds of Agreement available on request. However, there is no obligation on council to report on the outcomes or delivery of developers' obligations under VPAs. The four audited councils vary in transparency and accessibility of information available about VPAs.

Exhibit 11: Published information about VPAs at the four audited councils
  Blacktown City Council Central Coast Council City of Sydney Council Liverpool City Council
VPA Register Council website and annual report Annual report Annual report Council website and annual report
VPA Deeds of Agreement Council website Available on request Available on request Council website
Intended use of LICs collected under VPAs In Deeds of Agreement In Deeds of Agreement In VPA Register and most Deeds of Agreement In VPA Register and most Deeds of Agreement
Completion of work funded by cash collected under VPAs Not published Not published Not published Not published
Delivery of works-in-kind or land negotiated under VPAs Not published Not published In VPA Register Not published
Source: Audit Office analysis.

The Practice Note suggests that councils incorporate the intended use of LICs collected under VPAs in the Deed of Agreement, but there is no guidance relating to transparency over where and when funds have actually been spent. There is merit in councils providing greater transparency over public benefits delivered through VPAs to give communities confidence in VPAs as a planning tool.

Credit arrangements with developers are not always well documented or monitored

When levying LICs, section 7.11(6) of the EP&A Act requires councils to take into account land, money, or works-in-kind that the developer has contributed on other development sites over and above their LIC obligations. This section of the EP&A Act allows a developer to offset a LIC owed on one site against land or works contributed on another. This leads to some developers carrying 'credits' for work delivered to councils, to be paid back by reduced LICs on a future development. Blacktown City Council and Central Coast Council allow developers to carry credits. Liverpool City Council and City of Sydney Council do not permit credits and instead pay the developers for any additional work undertaken.

Councils should formally document credit arrangements and have a robust process to validate and keep track of credit balances and report on them. Central Coast Council does not keep good track of credit arrangements and neither Blacktown City Council or Central Coast Council aggregate or report on outstanding credit balances.

Blacktown City Council manages the largest LIC fund in NSW and negotiates more VPAs than any other council. Overall, Blacktown City Council demonstrates effective governance over the LIC funds but there is scope for improved oversight of the projected financial status of contributions plans and credit arrangements with developers. Blacktown City Council also needs to update its operating procedures relating to LICs and improve security over key information.

Blacktown City Council is managing areas with high growth. There is a risk that Blacktown City Council will be unable to collect sufficient LICs to fund the infrastructure required to support that growth. However, Blacktown City Council does not assess and report to senior management or its Audit, Risk and Improvement Committee about the projected financial status of contributions plans.

Blacktown City Council has policies in place to guide the management of LICs although management of credit arrangements with developers requires greater oversight. Policies relating to works-in-kind agreements provide no guidance about probity in negotiations with developers and valuations of works-in-kind are not independent as they are paid for by the developer. Blacktown City Council's S7.11 committee structure could act as a model for other councils. Blacktown City Council is spending LICs according to its contributions plans. Staff managing LICs demonstrate good knowledge of the regulatory environment. However, a number of administrative processes need attention such as outdated procedures, lack of security over key spreadsheets, and inappropriate retention of sensitive personal data.

Recommendations

By December 2020, Blacktown City Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. update council's works-in-kind policy to address probity risks during negotiations with developers
  3. mitigate risks associated with lack of independence in valuations of works-in-kind
  4. improve public reporting about expenditure of cash collected under VPAs
  5. improve management oversight of credit arrangements with developers
  6. update procedures for managing LICs
  7. implement security measures over critical or personal information and spreadsheets. 

Central Coast Council's governance and internal controls over LICs were not fully effective. Between 2001 and 2019, more than $13.0 million in LICs was misspent on administration costs in breach of the EP&A Act. There is scope for improved oversight of the projected financial status of contributions plans and credit arrangements with developers. Policies and procedures from the two former councils are not aligned.

In May 2016, the newly amalgamated Central Coast Council inherited 53 contributions plans from the former Gosford City and Wyong Shire Councils. Managing this number of contributions plans fragments the available funds and increases complexity. Central Coast Council is currently working on consolidating these plans. Between June 2016 and June 2019, its LIC balance doubled from $90.0 million to $196 million. Central Coast Council does not assess and report to senior management or its Audit, Risk and Improvement Committee about the projected financial status of contributions plans. Central Coast Council has a LIC committee but it has no formal charter and senior officers do not regularly attend meetings. This limits the committee's effectiveness as a decision-making body. A draft policy relating to works-in-kind agreements provide no guidance about probity in negotiations with developers. Valuations of works-in-kind and land dedications are not independent as they are paid for by the developer.

Central Coast Council has adjusted its accounts in 2018–19 by $13.2 million to repay the LIC fund for administration expenses that were not provided for in 40 contributions plans.

Recommendations

By June 2020, Central Coast Council should:

1. obtain independent validation of the adjustment made to the restricted asset accounts and general fund to repay LICs spent on administration, and adjustments made to each infrastructure category within the contributions plans

2. publish current contributions plans from the former Gosford City Council on the Central Coast Council website.

By December 2020, Central Coast Council should:

3. regularly report to senior management on the projected financial status of contributions plans

4. increase transparency of information available to the public about LIC works planned and underway, including intended use of contributions collected under VPAs

5. consolidate existing plans, ensuring the new contributions plans includes a regular review cycle

6. develop a formal charter for the developer contributions committee and increase the seniority of membership

7. complete and adopt council's works-in-kind policy currently under development, ensuring it addresses probity risks during negotiations with developers

8. mitigate risks associated with lack of independence in valuations of works-in-kind and dedicated land

9. improve public reporting about expenditure of cash collected under VPAs

10. improve management oversight of credit arrangements with developers

11. implement security measures to ensure the integrity of key spreadsheets used to manage LICs

12. align policies and procedures relating to LICs across the amalgamated council including developing policies and procedures for the management of S64 LICs

13. update council's VPA policy to address increased or indexed bank guarantees to accommodate cost increases.

City of Sydney Council manages a complex development environment across the Sydney CBD and inner suburbs. Overall, governance and internal controls over LICs are effective although there is scope for improved oversight of the projected financial status of contributions plans.

City of Sydney Council maintains a large balance of LICs, although not excessive relative to the annual level of LIC expenditure. Unspent contributions are largely associated with open space infrastructure that cannot be delivered until suitable land is available. Thirty per cent of cash contributions are collected under VPAs and there is limited transparency over how these funds are spent. City of Sydney Council does not assess and report to management or its Audit, Risk and Compliance Committee about the projected financial status of contributions plans.

In 2017–18 and 2018–19, LICs were spent in accordance with the corresponding contributions plans. City of Sydney Council staff are knowledgeable about the regulatory environment and are supported by up-to-date policies and procedures.

Recommendations

By December 2020, City of Sydney Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. improve public reporting about expenditure of cash collected under VPAs
  3. periodically review the risk of unpaid LICs associated with complying development certificates and assess whether additional controls are required
  4. implement security measures to ensure the integrity of key spreadsheets used to manage LICs. 

During the audit period 2017–18 and 2018–19, Liverpool City Council did not have effective governance and internal controls over LICs. Liverpool City Council is addressing deficiencies and risks identified through an internal audit published in December 2018 although further work is required. There is scope for improved oversight of the projected financial status of contributions plans.

In the two years to 30 June 2019, the balance of unspent LICs increased by more than 60 per cent against a relatively low pattern of expenditure. Prior to an internal audit completed in late 2018, there was no regular reporting on the status of LICs and a lack of transparency when prioritising the expenditure of LIC funds. During 2019, and following the internal audit, Liverpool City Council engaged additional skilled resources to improve focus and accountability for LICs. A LIC committee has been established to manage contributions plans and support business units to initiate relevant infrastructure projects, although it is too early to assess whether this committee is operating effectively. From February 2019, Liverpool City Council commenced monthly reporting to its Chief Executive Officer (CEO) about the point-in-time status of LIC funds, and to its Audit, Risk and Improvement Committee about risks associated with LICs and the implementation of internal audit recommendations. There is limited reporting to senior management about the projected financial status of some contributions plans. Our audit found no evidence of misuse of funds during the audited period. Methods for valuing work and land are not aligned with policies and procedures and are implemented inconsistently. In addition, valuations of works-in-kind and land dedications are not independent as they are paid for by the developer. The policy relating to works-in-kind provides no guidance about managing probity risks when negotiating with developers.

Recommendations

By December 2020, Liverpool City Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. update council's policies and procedures to provide consistent guidance about how works and land offered by developers should be valued
  3. update council's Works-in-Kind and Land Acquisition Policy to address probity risks during negotiations with developers
  4. improve public reporting about expenditure of cash collected under VPAs
  5. mitigate risks associated with lack of independence in valuations of works-in-kind and dedicated land
  6. implement security measures over critical or private information. 

Appendix one – Responses from councils and the Department of Planning, Industry and Environment

Appendix two – Advice from the Crown Solicitor

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #339 - released 17 August 2020

Published

Actions for Report on Local Government 2019

Report on Local Government 2019

Local Government
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery
Shared services and collaboration
Workforce and capability

I am pleased to present my third report to the Parliament on the 2019 audits of local government councils in New South Wales.

This report notes that unqualified audit opinions were issued on the 2018–19 financial statements of 134 councils and 11 joint organisations. The opinion for one council was disclaimed and three audits are yet to complete.

The report also highlights improvements I have seen in financial reporting and governance arrangements across councils. Fewer errors were identified. More councils have audit, risk and improvement committees and internal audit functions. Risk management practices, including fraud control systems, have also improved.

These are very pleasing indicators of the gradual strengthening of governance and financial oversight of the sector. I want to acknowledge the investment councils have made in working with the Audit Office to improve consistency of practice and accountability generally.

Of course there is more work to do, particularly to prepare for new accounting standards and to strengthen controls over information technology and cyber security management. Asset management practices can also be improved. This report provides some guidance to council on these matters and we will continue to partner with the Office of Local Government in the Department of Planning, Industry and Environment to support good practice.

Margaret Crawford

Auditor-General
5 March 2020

This report focuses on key observations and findings from the 2018–19 financial audits of councils and joint organisations.

Unqualified audit opinions were issued on the financial statements for 134 councils and 11 joint organisations. The audit opinion for Bayside’s 2017–18 and 2018–19 financial statements were disclaimed. Three audits are still in progress and will be included in next year’s report.

The report highlights a number of areas where there has been improvement. There was a reduction in errors identified in council financial statements and high risk issues reported in audit management letters. More councils have audit, risk and improvement committees and internal audit functions. Risk management practices and fraud control systems have also improved.

The report also found that councils could do more to be better prepared for the new accounting standards, asset management practices could be strengthened, and information technology controls and cyber security management could be improved.

The Auditor-General recommended that the Office of Local Government within the Department of Planning, Industry and Environment develop a cyber security policy by 30 June 2021 to ensure a consistent response to cyber security risks across councils.

Read the PDF Report

Financial reporting is an important element of good governance. Confidence in and transparency of public sector decision making is enhanced when financial reporting is accurate and timely. Strong financial performance provides the platform for councils to deliver services and respond to community needs.

This chapter outlines our audit observations on the financial reporting and performance of councils and joint organisations.

Section highlights
  • There was a reduction in the number and dollar value of errors identified in councils' financial statements.
  • We continue to identify prior period errors, which are predominantly asset-related.
  • Unqualified audit opinions were issued for 99 per cent of completed audits for councils and joint organisations.
  • Three audits remain outstanding, with the outcomes to be reported in next year's Report to Parliament.
  • Seventy-nine per cent of councils and joint organisations lodged their financial reports by 31 October 2019.
  • Councils that performed some early reporting procedures achieved better outcomes in terms of the quality and timeliness of financial reporting.
  • Councils are at various levels of preparedness to implement the new accounting standards for the 2019–20 financial year. Some have made the necessary modifications to systems and processes, but others are still assessing impacts.
  • Most councils met the prescribed benchmarks for the liquidity and working capital performance measures over the past three years.
  • More councils reported negative operating performance compared with the prior year, meaning their operating expenditure exceeded their operating revenue.

Strong governance systems and internal controls help councils to operate effectively and efficiently, produce reliable financial reports, comply with laws and regulations and support ethical government.

This chapter outlines the overall trends related to governance and internal control issues across councils and joint organisations for 2018–19.

Section highlights
  • While the total number of issues reported in our management letters increased compared with the prior year, the total number of high risk issues have decreased. Of the high-risk issues, 41 per cent were deficiencies in information technology controls.
  • More councils have established audit, risk and improvement committees and internal audit functions.
  • Councils have improved risk management practices, with over 75 per cent of councils now having a risk management policy and register.
  • While most councils have policies and processes to manage gifts and benefits, we identified some instances of non-compliance with the Model Code of Conduct.
  • Most councils have policies and processes to manage the use of credit cards.
  • Councils can strengthen policies and practices for managing fraud controls and legislative compliance.
  • There are further opportunities for councils to improve internal controls over revenue, purchasing, payroll, cash, financial accounting and governance processes.

Councils rely on information technology (IT) to deliver services and manage information. While IT delivers considerable benefits, it also presents risks that council needs to address.

In prior years, we reported that councils need to improve IT governance and controls to manage key financial systems. This chapter outlines the progress made by councils in the management of key IT risks and controls, with an added focus on cyber security.

Section highlights
  • We continue to report deficiencies in information technology controls, particularly around user access management. These controls are key to ensuring IT systems are protected from inappropriate access and misuse.
  • Many councils do not have IT policies and procedures and others do not identify, monitor or report on IT risks.
  • Cyber security management requires improvement, with some basic elements of governance not yet in place for many councils.

Councils are responsible for managing a significant range of assets to deliver services on behalf of the community.

This chapter outlines our asset management observations across councils and joint organisations.

Section highlights
  • There was an increase in the total number of issues reported in our management letters for asset management processes.
  • There were less high-risk issues reported compared to the previous year.
  • We continue to identify discrepancies between the council's Crown land asset records and the Crown Land Information Database (CLID) managed by the former Department of Industry (DOI).
  • Inconsistent practices remain across the Local Government sector in accounting for landfill sites.

Appendix one – Response from the Office of Local Government within the Department of Planning, Industry and Environment

Appendix two – Status of 2018 recommendations

Appendix three – Status of audits 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.