Refine search Expand filter

Reports

Published

Actions for Planning and Environment 2018

Planning and Environment 2018

Planning
Environment
Asset valuation
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released her report today on the NSW Planning and Environment cluster. The report focuses on key observations and findings from the most recent financial audits of these agencies. Unqualified audit opinions were issued for all agencies' financial statements. However, some cultural institutions had challenges valuing collection assets in 2017–18. These issues were resolved before the financial statements were finalised.

This report analyses the results of our audits of financial statements of the Planning and Environment cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides parliament and other users of the Planning and Environment cluster agencies' financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • service delivery.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making is enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Planning and Environment cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all agencies' financial statements. The quality of financial reporting remains high across the cluster.
2.2 Key accounting issues
There were errors in some cultural institutions' collection asset valuations. Recommendation: Collection asset valuations could be improved by:
  • early engagement with key stakeholders regarding the valuation method and approach
  • completing revaluations, including quality review processes earlier 
  • improving the quality of asset data by registering all items in an electronic database. 
2.3 Timeliness of financial reporting
Except for two agencies, the audits of cluster agencies’ financial statements were completed within the statutory timeframe.  Issues with asset revaluations delayed the finalisation of two environment and heritage agencies' financial statement audits. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Planning and Environment cluster for 2018
  • the areas of focus identified in the Audit Office work program.

The Audit Office annual work program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.

Observation Conclusions and recommendations
3.1 Internal controls
One in five internal control weaknesses reported in 2017–18 were repeat issues. Delays in implementing audit recommendations can prolong the risk of fraud and error.
Recommendation (repeat issue): Management letter recommendations to address internal control weaknesses should be actioned promptly, with a focus on addressing repeat issues.
One extreme risk was identified relating to the National Art School. The School does not have an occupancy agreement for the Darlinghurst campus. Lack of formal agreement creates uncertainty over the School's continued occupancy of the Darlinghurst site.

The School should continue to liaise with stakeholders to formalise the occupancy arrangement. 
 
3.2 Information technology controls
The controls and governance arrangements when migrating payroll data from the Aurion system to SAP HR system were effective. Data migration from the Aurion system to SAP HR system had no significant issues.
The Department can improve controls over user access to SAP system. The Department needs to ensure the SAP user access controls are appropriate, including investigation of excess access rights and resolving segregation of duties issues. 
3.3 Annual work program
Agencies used different benchmarks to monitor their maintenance expenditure. The cluster agencies under review operate in different industries. As a result, they do not use the same benchmarks to assess the adequacy of their maintenance spend. 

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited. 

We report this information on service delivery to provide additional context to understand the operations of the Planning and Environment cluster, and to collate and present service information for different segments of the cluster in one report. 

In our recent performance audit, ‘Progress and measurement of Premier's Priorities’, we identified 12 limitations of performance measurement and performance data. We recommended the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all relevant agency data sources.

Published

Actions for Newcastle Urban Transformation and Transport Program

Newcastle Urban Transformation and Transport Program

Transport
Planning
Compliance
Infrastructure
Management and administration
Procurement
Project management

The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.

The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.

This audit had two objectives:

  1. To assess the economy of the approach chosen to achieve the objectives of the Program.
  2. To assess the effectiveness of the consultation and oversight of the Program.

We addressed the audit objectives by answering the following questions:

a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?

Conclusion
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.

The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.

Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.

The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.

Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
The light rail is not justified by conventional cost-benefit analysis and there is insufficient evidence that the indirect contribution of light rail to achieving the economic development objectives of the Program will justify the cost.
Analysis presented in Program business cases and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The business case analysis of the benefits and costs of light rail was prepared after the decision to build light rail had been made and announced. Our previous reports, and recent reports by others, have emphasised the importance of completing thorough analysis before announcing infrastructure projects. Some advice provided after the initial light rail decision was announced was overly optimistic. It included benefits that cannot reasonably be attributed to light rail and underestimated the scope and cost of the project.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the high cost of the light rail, we believe agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
  • providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
  • providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
  • making business cases available to the public.​​​​​​
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government.

The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.

The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.

Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
  • work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations about the urban renewal activities followed good practice standards, but consultation on transport decisions for the Program did not.

Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received. 

There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.

There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public. 

Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations. 

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.

Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.

The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.

Recommendations
For future infrastructure programs, NSW Government agencies should: 

  • develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
  • establish whole-of-government oversight early in the program to guide major decisions. This should include:
    • agreeing on objectives and ensuring all agencies understand these
    • clearly defining roles and responsibilities for all agencies
    • establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.

By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:

  • setting measurable targets for the desired benefits
  • clearly allocating ownership for achieving the desired benefits
  • monitoring progress toward achieving the desired benefits and reporting publicly on the results.

Appendix one - Response from agencies    

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #310 - released 12 December 2018

Published

Actions for Internal Controls and Governance 2018

Internal Controls and Governance 2018

Education
Community Services
Finance
Health
Industry
Justice
Planning
Premier and Cabinet
Transport
Treasury
Whole of Government
Environment
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management

The Auditor-General for New South Wales Margaret Crawford found that as NSW state government agencies’ digital footprint increases they need to do more to address new and emerging information technology (IT) risks. This is one of the key findings to emerge from the second stand-alone report on internal controls and governance of the 40 largest NSW state government agencies.

This report analyses the internal controls and governance of the 40 largest agencies in the NSW public sector for the year ended 30 June 2018.

This report covers the findings and recommendations from our 2017–18 financial audits that relate to internal controls and governance at the 40 largest agencies (refer to Appendix three) in the NSW public sector.

This report offers insights into internal controls and governance in the NSW public sector

This is our second report dedicated to internal controls and governance at NSW State Government agencies. The report provides insights into the effectiveness of controls and governance processes in the NSW public sector by:

  • highlighting the potential risks posed by weaknesses in controls and governance processes
  • helping agencies benchmark the adequacy of their processes against their peers
  • focusing on new and emerging risks, and the internal controls and governance processes that might address those risks.

Without strong governance systems and internal controls, agencies increase the risks associated with effectively managing their finances and delivering services to citizens. The way agencies deliver services increasingly relies on contracts and partnerships with the private sector. Many of these arrangements deliver front line services, but others provide less visible back office support. For example, an agency may rely on an IT service provider to manage a key system used to provide services to the community. The contract and service level agreements are only truly effective where they are actively managed to reduce risks to continuous quality service delivery, such as interruptions caused by system outages, cyber security attacks and data security breaches.

Our audits do not review all aspects of internal controls and governance every year. We select a range of measures, and report on those that present heightened risks for agencies to mitigate. This report divides these into the following five areas:

  1. Internal control trends
  2. Information technology (IT), including IT vendor management
  3. Transparency and performance reporting
  4. Management of purchasing cards and taxis
  5. Fraud and corruption control.

The findings in this report should not be used to draw conclusions on the effectiveness of individual agency control environments and governance arrangements. Specific financial reporting, controls and service delivery comments are included in the individual 2018 cluster financial audit reports, which will be tabled in Parliament from November to December 2018.

The focus of the report has changed since last year

Last year's report topics included asset management, ethics and conduct, and risk management. We are reporting on new topics this year. We plan to introduce new topics and re-visit our previous topics in subsequent reports on a cyclical basis. This will provide a baseline against which to measure the NSW public sectors’ progress in implementing appropriate internal controls and governance processes to mitigate existing, new and emerging risks in the public sector.

Agencies selected for the volume account for 95 per cent of the state's expenditure

While we have covered only 40 agencies in this report, those selected are a large enough group to identify common issues and insights. They represent about 95 per cent of total expenditure for all NSW public sector agencies.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of findings, level of risk and the most common deficiencies we found across agencies. The rest of this volume presents this year’s controls and governance findings in more detail.

Observation Conclusions and recommendations
2.1 High risk findings
We found six high risk findings (seven in 2016–17), one of which was repeated from both last year and 2015–16. Recommendation: Agencies should reduce risk by addressing high risk internal control deficiencies as a priority.
2.2 Common findings
We found several internal controls and governance findings common to multiple agencies. Conclusion: Central agencies or the lead agency in a cluster can play a lead role in helping ensure agency responses to common findings are consistent, timely, efficient and effective.
2.3 New and repeat findings
Although internal control deficiencies decreased over the last four years, this year has seen a 42 per cent increase in internal control deficiencies. The increase in new IT control deficiencies and repeat IT control deficiencies signifies an emerging risk for agencies.
IT control deficiencies feature in this increase, having risen by 63 per cent since last year. The number of repeat IT control deficiencies has doubled and is driven by the increasing digital footprint left by agencies as government prioritises on-line interfaces with citizens, and the number of transactions conducted through digital channels increases

Recommendation: Agencies should reduce IT risks by:

  • assigning ownership of recommendations to address IT control deficiencies, with timeframes and actions plans for implementation
  • ensuring audit and risk committees and agency management regularly monitor the implementation status of recommendations.

 

Government agencies’ financial reporting is now heavily reliant on information technology (IT). IT is also increasingly important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our audits reviewed whether agencies have effective controls in place to manage both key financial systems and IT service contracts.

Observation Conclusions and recommendations
3.1 Management of IT vendors
Contract management framework 
Although 87 per cent of agencies have a contract management policy to manage IT vendors, one fifth require review.
 

Conclusion: Agencies can more effectively manage IT vendor contracts by developing policies and procedures to ensure vendor management frameworks are kept up to date, plans are in place to manage vendor performance and risk, and compliance with the framework is monitored by:

  • internal audit focusing on key contracting activities
  • experienced officers who are independent of contract administration performing spot checks or peer reviews
  • targeted analysis of data in contract registers.
Contract risk management
Forty-one per cent of agencies are not using contract management plans and do not assess contract risks. Half of the agencies that did assess contract risks, had not updated the risk assessments since the commencement of the contract.
 
Conclusion: Instead of applying a 'set and forget' approach in relation to management of contract risks, agencies should assess risk regularly and develop a plan to actively manage identified risks throughout the contract lifecycle - from negotiation and commencement, to termination.

Performance management
Eighty-six per cent of agencies meet with vendors to discuss performance. 

Only 24 per cent of agencies sought assurance about the accuracy of vendor reporting against KPIs, yet sixty-seven per cent of the IT contracts allow agencies to determine performance based payments and/or penalise underperformance.

Conclusion: Agencies are monitoring IT vendor performance, but could improve outcomes and more effectively manage under-performance by:

  • a more active, rigorous approach to both risk and performance management
  • checking the accuracy of vendor reporting against those KPIs and where appropriate seeking assurance over their accuracy
  • invoking performance based payments clauses in contracts when performance falls below agreed standards.

Transitioning services
Forty-three per cent of the IT vendor contracts did not contain transitioning-out provisions.

Where IT vendor contracts do make provision for transitioning-out, only 28 per cent of agencies have developed a transitioning-out plan with their IT vendor.

Conclusion: Contract transition/phase out clauses and plans can mitigate risks to service disruption, ensure internal controls remain in place, avoid unnecessary costs and reduce the risk of 'vendor lock-in'.
Contract Registers
Eleven out of forty agencies did not have a contract register, or have registers that are not accurate and/or complete.

Conclusion: A contract register helps to manage an agency’s compliance obligations under the Government Information (Public Access) Act 2009 (the GIPA Act). However, it also helps agencies more effectively manage IT vendors by:

  • monitoring contract end dates and contract extensions, and commence new procurements through their central procurement teams in a timely manner
  • managing their contractual commitments, budgeting and cash flow requirements.

Recommendation: Agencies should ensure their contract registers are complete and accurate so they can more effectively govern contracts and manage compliance obligations.

3.2 IT general controls
Governance
Ninety-five per cent of agencies have established policies to manage key IT processes and functions within the agency, with ten per cent of those due for review.
 
Conclusion: Regular review of IT policies ensures risks are considered and appropriate strategies and procedures are implemented to manage these risks on a consistent basis. An absence of policies can lead to ad-hoc responses to risks, and failure to consider emerging IT risks and changes to agency IT environments. 

User access administration
Seventy-two deficiencies were identified related to user access administration, including:

  • thirty issues related to granting user access across 43 per cent of agencies
  • sixteen issues related to removing user access across 30 per cent of agencies
  • twenty-six issues related to periodic reviews of user access across 50 per cent of agencies.
Recommendation: Agencies should strengthen the administration of user access to prevent inappropriate access to key systems.
Privileged access
Forty per cent of agencies do not periodically review logs of the activities of privileged users to identify suspicious or unauthorised activities.

Recommendation: Agencies should:

  • review the number of, and access granted to privileged users, and assess and document the risks associated with their activities
  • monitor user access to address risks from unauthorised activity.
Password controls
Twenty-three per cent of agencies did not comply with their own policy on password parameters.
Recommendation: Agencies should ensure IT password settings comply with their password policies.
Program changes
Fifteen per cent of agencies had deficient IT program change controls mainly related to segregation of duties and authorisation and testing of IT program changes prior to deployment.
Recommendation: Agencies should maintain appropriate segregation of duties in their IT functions and test system changes before they are deployed.

 

This chapter outlines our audit observations, conclusions and recommendations from our review of how agencies reported their performance in their 2016–17 annual reports. The Annual Reports (Statutory Bodies) Regulation 2015 and Annual Reports (Departments) Regulation 2015 (annual reports regulation) currently prescribes the minimum requirements for agency annual reports.

Observation Conclusion or recommendation
4.1 Reporting on performance

Only 57 per cent of agencies linked reporting on performance to their strategic objectives.

The use of targets and reporting performance over time was limited and applied inconsistently.

Conclusion: There is significant disparity in the quality and consistency of how agencies report on their performance in their annual reports. This limits the reliability and transparency of reported performance information.

Agencies could improve performance reporting by clearly linking strategic objectives to reported outcomes, and reporting on performance against targets over time. NSW Treasury may need to provide more guidance to agencies to support consistent and high-quality performance reporting in annual reports.

There is no independent assurance that the performance metrics agencies report in their annual reports are accurate.

Prior performance audits have noted issues related to the collection of performance information. For example, our 2016 Report on Red Tape Reduction highlighted inaccuracies in how the dollar-value of red tape reduction had been reported.

Conclusion: The ability of Parliament and the public to rely on reported information as a relevant and accurate reflection of an agency's performance is limited.

The relevance and accuracy of performance information is enhanced when:

  • policies and guidance support the consistent and accurate collection of data
  • internal review processes and management oversight are effective
  • independent review processes are established to provide effective challenge to the assumptions, judgements and methodology used to collect the reported performance information.
4.2 Reporting on reports

Agency reporting on major projects does not meet the requirements of the annual reports regulation.

Forty-seven per cent of agencies did not report on costs to date and estimated completion dates for major works in progress. Of the 47 per cent of agencies that reported on major works, only one agency reported detail about significant cost overruns, delays, amendments, deferments or cancellations.

NSW Treasury produce an annual report checklist to help agencies comply with their annual report obligations.

Recommendation: Agencies should comply with the annual reports regulation and report on all mandatory fields, including significant cost overruns and delays, for their major works in progress.

The information the annual reports regulation requires agencies to report deals only with major works in progress. There is no requirement to report on completed works.

Sixteen of 30 agencies reported some information on completed major works.

Conclusion: Agencies could improve their transparency if they reported, or were required to report:

  • on both works in progress and projects completed during the year
  • actual costs and completion dates, and forecast completion dates for major works, against original and revised budgets and original expected completion dates
  • explanations for significant cost overruns, delays and key project performance metrics.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency preventative and detective controls over purchasing card and taxi use for 2017–18.

Observation Conclusion or recommendation
5.1 Management of purchasing cards
Volume of credit card spend
Purchasing card expenditure has increased by 76 per cent over the last four years in response to a government review into the cost savings possible from using purchasing cards for low value, high volume procurement.
 
Conclusion: The increasing use of purchasing cards highlights the importance of an effective framework for the use and management of purchasing cards.
Policy framework
We found all agencies that held purchasing cards had a policy in place, but 26 per cent of agencies have not reviewed their purchasing card policy by the scheduled date, or do not have a scheduled revision date stated within their policy.
Recommendation: Agencies should mitigate the risks associated with increased purchasing card use by ensuring policies and purchasing card frameworks remain current and compliant with the core requirements of TPP 17–09 'Use and Management of NSW Government Purchasing Cards'.
Preventative controls
We found that:
  • all agencies maintained purchasing card registers
  • seventy-six per cent provided training to cardholders prior to being issued with a card
  • eighty-nine per cent appointed a program administrator, but only half of these had clearly defined roles and responsibilities
  • thirty-two per cent of agencies place merchant blocks on purchasing cards
  • forty-seven per cent of agencies place geographic restrictions on purchasing cards.

Agencies have designed and implemented preventative controls aimed at deterring the potential misuse of purchasing cards.

Conclusion: Further opportunities exist for agencies to better control the use of purchasing cards, such as:

  • updating purchasing card registers to contain all mandatory fields required by TPP17–09
  • appointing a program administrator for the agency's purchasing card framework and defining their role and responsibility for the function
  • strengthening preventive controls to prevent misuse.

Detective controls
Ninety-two per cent of agencies have designed and implemented at least one control to monitor purchasing card activity.

Major reviews, such as data analytics (29 per cent of agencies) and independent spot checks (49 per cent of agencies) are not widely used.

Agencies have designed and implemented detective controls aimed at identifying potential misuse of purchasing cards.

Conclusion: More effective monitoring using purchasing card data can provide better visibility over spending activity and can be used to:

  • detect misuse and investigate exceptions
  • analyse trends to highlight cost saving opportunities.
5.2 Management of taxis
Policy framework
Thirteen per cent of agencies have not developed and implemented a policy to manage taxi use. In addition:
  • a further 41 per cent of agencies have not reviewed their policies by the scheduled revision date, or do not have a scheduled revision date
  • more than half of all agencies’ policies do not offer alternative travel options. For example, only 36 per cent of policies promoted the use of general Opal cards.
Conclusion: Agencies can promote savings and provide more options to staff where their taxi use policies:
  • limit the circumstances where taxi use is appropriate
  • offer alternate, lower cost options to using taxis, such as general Opal cards and rideshare.
Detective controls
All agencies approve taxi expenditure by expense reimbursement, purchasing card and Cabcharge, and have implemented controls around this approval process. However, beyond this there is minimal monitoring and review activity, such as data monitoring, independent spot checks or internal audit reviews.
Conclusion: Taxi spend at agencies is not significant in terms of its dollar value, but it is significant from a probity perspective. Agencies can better address the probity risk by incorporating taxi use into a broader purchasing card or fraud monitoring program.

 

Fraud and corruption control is one of the 17 key elements of our governance lighthouse. Recent reports from ICAC into state agencies and local government councils highlight the need for effective fraud control and ethical frameworks. Effective frameworks can help protect an agency from events that risk serious reputational damage and financial loss.

Our 2016 Fraud Survey found the NSW Government agencies we surveyed reported 1,077 frauds over the three year period to 30 June 2015. For those frauds where an estimate of losses was made, the reported value exceeded $10.0 million. The report also highlighted that the full extent of fraud in the NSW public sector could be higher than reported because:

  • unreported frauds in organisations can be almost three times the number of reported frauds
  • our 2015 survey did not include all NSW public sector agencies, nor did it include any NSW universities or local councils
  • fraud committed by citizens such as fare evasion and fraudulent state tax self-assessments was not within the scope of our 2015 survey
  • agencies did not estimate a value for 599 of the 1,077 (56 per cent) reported frauds.

Commissioning and outsourcing of services to the private sector and the advancement of digital technology are changing the fraud and corruption risks agencies face. Fraud risk assessments should be updated regularly and in particular where there are changes in agency business models. NSW Treasury Circular TC18-02 NSW Fraud and Corruption Control Policy now requires agencies develop, implement and maintain a fraud and corruption control framework, effective from 1 July 2018. 

Our Fraud Control Improvement Kit provides guidance and practical advice to help organisations implement an effective fraud control framework. The kit is divided into ten attributes. Three key attributes have been assessed below; prevention, detection and notification systems.

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency fraud and corruption controls for 2017–18.

Observation Conclusion or recommendation
6.1 Prevention systems

Prevention systems
Ninety-two per cent of agencies have a fraud control plan in place, 81 per cent maintain a fraud database and 79 per cent report fraud and corruption matters as a standing item on audit and risk committee agendas.

Only 54 per cent of agencies have an employment screening policy and all agencies have IT security policies, but gaps in IT security controls could undermine their policies.

Conclusion: Most agencies have implemented fraud prevention systems to reduce the risk of fraud. However poor IT security along with other gaps in agency prevention systems, such as employment screening practices heightens the risk of fraud and inappropriate use of data.

Agencies can improve their fraud prevention systems by:

  • completing regular fraud risk assessments, embedding fraud risk assessment into their enterprise risk management process and reporting the results of the assessment to the audit and risk committee
  • maintaining a fraud database and reviewing it regularly for systemic issues and reporting a redacted version of the database on the agency's website to inform corruption prevention networks
  • developing policies and procedures for employee screening and benchmarking their current processes against ICAC's publication ‘Strengthening Employment Screening Practices in the NSW Public Sector’
  • developing and maintaining up to date IT security policies and monitoring compliance with the policy.
Twenty-three per cent of agencies were not performing fraud risk assessments and some agency fraud risk assessments may not be as robust as they could be.  Conclusion: Agencies' systems of internal controls may be less effective where new and emerging fraud risks have been overlooked, or known weaknesses have not been rectified.
6.2 Detection systems
Detection systems
Several agencies reported they were developing a data monitoring program, but only 38 per cent of agencies had already implemented a program.
 

Studies have shown data monitoring, whereby entire populations of transactional data are analysed for indicators of fraudulent activity, is one of the most effective methods of early detection. Early detection decreases the duration a fraud remains undetected thereby limiting the extent of losses.

Conclusion: Data monitoring is an effective tool for early detection of fraud and is more effective when informed by a comprehensive fraud risk assessment.

6.3 Notification systems
Notification system
All agencies have notification systems for reporting actual or suspected fraud and corruption. Most agencies provide multiple reporting lines, provide training and publicise options for staff to report actual or suspected fraud and corruption.
Conclusion: Training staff about their obligations and the use of fraud notification systems promotes a fraud-aware culture

 

Published

Actions for Council reporting on service delivery

Council reporting on service delivery

Local Government
Compliance
Internal controls and governance
Management and administration
Service delivery

New South Wales local government councils’ could do more to demonstrate how well they are delivering services in their reports to the public, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. Many councils report activity, but do not report on outcomes in a way that would help their communities assess how well they are performing. Most councils also did not report on the cost of services, making it difficult for communities to see how efficiently they are being delivered. And councils are not consistently publishing targets to demonstrate what they are striving for.

I am pleased to present my first local government performance audit pursuant to section 421D of the Local Government Act 1993.

My new mandate supports the Parliament’s objectives to:

  • strengthen governance and financial oversight in the local government sector
  • improve financial management, fiscal responsibility and public accountability for how councils use citizens’ funds.

Performance audits aim to help councils improve their efficiency and effectiveness. They will also provide communities with independent information on the performance of their councils.

For this inaugural audit in the local government sector, I have chosen to examine how well councils report to their constituents about the services they provide.

In this way, the report will enable benchmarking and provide improvement guidance to all councils across New South Wales.

Specific recommendations to drive improved reporting are directed to the Office of Local Government, which is the regulator of councils in New South Wales.

Councils provide a range of services which have a direct impact on the amenity, safety and health of their communities. These services need to meet the needs and expectations of their communities, as well as relevant regulatory requirements set by state and federal governments. Councils have a high level of autonomy in decisions about how and to whom they provide services, so it is important that local communities have access to information about how well they are being delivered and meeting community needs. Ultimately councils should aim to ensure that reporting performance is subject to quality controls designed to provide independent assurance.

Conclusion
While councils report on outputs, reporting on outcomes and performance over time can be improved. Improved reporting would include objectives with targets that better demonstrate performance over time. This would help communities understand what services are being delivered, how efficiently and effectively they are being delivered, and what improvements are being made.
To ensure greater transparency on service effectiveness and efficiency, the Office of Local Government (OLG) should work with councils to develop guidance principles to improve reporting on service delivery to local communities. This audit identified an interest amongst councils in improving their reporting and broad agreement with the good practice principles developed as part of the audit.
The Integrated Planning and Reporting Framework (the Framework), which councils are required to use to report on service delivery, is intended to promote better practice. However, the Framework is silent on efficiency reporting and provides limited guidance on how long-term strategic documents link with annual reports produced as part of the Framework. OLG's review of the Framework, currently underway, needs to address these issues.
OLG should also work with state agencies to reduce the overall reporting burden on councils by consolidating state agency reporting requirements. 

Councils report extensively on the things they have done, but minimally on the outcomes from that effort, efficiency and performance over time.

Councils could improve reporting on service delivery by more clearly relating the resources needed with the outputs produced, and by reporting against clear targets. This would enable communities to understand how efficiently services are being delivered and how well councils are tracking against their goals and priorities.

Across the sector, a greater focus is also needed on reporting performance over time so that communities can track changes in performance and councils can demonstrate whether they are on target to meet any agreed timeframes for service improvements.

The degree to which councils demonstrate good practice in reporting on service delivery varies greatly between councils. Metropolitan and regional town and city councils generally produce better quality reporting than rural councils. This variation indicates that, at least in the near-term, OLG's efforts in building capability in reporting would be best directed toward rural councils.

Recommendation

By mid-2018, OLG should:

  • assist rural councils to develop their reporting capability.

The Framework which councils are required to use to report on service delivery, is intended to drive good practice in reporting. Despite this, the Framework is silent on a number of aspects of reporting that should be considered fundamental to transparent reporting on service delivery. It does not provide guidance on reporting efficiency or cost effectiveness in service delivery and provides limited guidance on how annual reports link with other plans produced as part of the Framework. OLG's review of the Framework, currently underway, needs to address these issues.

Recommendation

By mid-2018, OLG should:

  • issue additional guidance on good practice in council reporting, with specific information on:
    • reporting on performance against targets
    • reporting on performance against outcome
    • assessing and reporting on efficiency and cost effectiveness
    • reporting performance over time
    • clearer integration of all reports and plans that are required by the Framework, particularly the role of End of Term Reporting
    • defining reporting terms to encourage consistency.

The Framework is silent on inclusion of efficiency or cost effectiveness indicators in reports

The guidelines produced by OLG in 2013 to assist councils to implement their Framework requirements advise that performance measures should be included in all plans. However, the Framework does not specifically state that efficiency or cost effectiveness indicators should be included as part of this process. This has been identified as a weakness in the 2012 performance audit report and the Local Government Reform Panel review of reporting by councils on service delivery.

The Framework and supporting documents provide limited guidance on reporting

Councils' annual reports provide a consolidated summary of their efforts and achievements in service delivery and financial management. However, OLG provides limited guidance on:

  • good practice in reporting to the community
  • how the annual report links with other plans and reports required by the Framework.

Further, the Framework includes both Annual and End of Term Reports. However, End of Term reports are published prior to council elections and are mainly a consolidation of annual reports produced during a council’s term. The relationship between Annual reports and End of Term reports is not clear.

OLG is reviewing the Framework and guidance

OLG commenced work on reviewing of the Framework in 2013 but this was deferred with work re‑starting in 2017. The revised guidelines and manual were expected to be released late in 2017.

OLG should build on the Framework to improve guidance on reporting on service delivery, including in annual reports

The Framework provides limited guidance on how best to report on service delivery, including in annual reports. It is silent on inclusion of efficiency or cost effectiveness indicators in reporting, which are fundamental aspects of performance reporting. Councils we consulted would welcome more guidance from OLG on these aspects of reporting.

Our consultation with councils highlighted that many council staff would welcome a set of reporting principles that provide guidance to councils, without being prescriptive. This would allow councils to tailor their approach to the individual characteristics, needs and priorities of their local communities.

Consolidating what councils are required to report to state agencies would reduce the reporting burden and enable councils to better report on performance. Comparative performance indicators are also needed to provide councils and the public with a clear understanding of councils' performance relative to each other.

Recommendations

By mid-2018, OLG should:

  • commence work to consolidate the information reported by individual councils to NSW Government agencies as part of their compliance requirements.
  • progress work on the development of a Performance Measurement Framework, and associated performance indicators, that can be used by councils and the NSW Government in sector-wide performance reporting.

Streamlining the reporting burden would help councils improve reporting

The NSW Government does not have a central view of all local government reporting, planning and compliance obligations. A 2016 draft IPART ‘Review of reporting and compliance burdens on Local Government’ noted that councils provide a wide range of services under 67 different Acts, administered by 27 different NSW Government agencies. Consolidating and coordinating reporting requirements would assist with better reporting over time and comparative reporting. It would also provide an opportunity for NSW Government agencies to reduce the reporting burden on councils by identifying and removing duplication.

Enabling rural councils to perform tailored surveys of their communities may be more beneficial than a state-wide survey in defining outcome indicators

Some councils use community satisfaction survey data to develop outcome indicators for reporting. The results from these are used by councils to set service delivery targets and report on outcomes. This helps to drive service delivery in line with community expectations. While some regional councils do conduct satisfaction surveys, surveys are mainly used by metropolitan councils which generally have the resources needed to run them.

OLG and the Department of Premier and Cabinet have explored the potential to conduct state-wide resident satisfaction surveys with a view to establishing measures to improve service delivery. This work has drawn from a similar approach adopted in Victoria. Our consultation with stakeholders in Victoria indicated that the state level survey is not sufficiently detailed or specific enough to be used as a tool in setting targets that respond to local circumstances, expectations and priorities. Our analysis of reports and consultation with stakeholders suggest that better use of resident survey data in rural and regional areas may support improvements in performance reporting in these areas. Rural councils may benefit more from tailored surveys of groups of councils with similar challenges, priorities and circumstances than from a standard state-wide survey. These could potentially be achieved through regional cooperation between groups of similar councils or regional groups.

Comparative reporting indicators are needed to enable councils to respond to service delivery priorities of their communities

The Local Government Reform Panel in 2012 identified the need for ‘more consistent data collection and benchmarking to enable councils and the public to gain a clear understanding of how a council is performing relative to their peers’.

OLG commenced work in 2012 to build a new performance measurement Framework for councils which aimed to move away from compliance reporting. This work was also strongly influenced by the approach used in Victoria that requires councils to report on a set of 79 indicators which are reported on the Victorian 'Know your council' website. OLG’s work did not fully progress at the time and several other local government representative bodies have since commenced work to establish performance measurement frameworks. OLG advised us it has recently recommenced its work on this project.

Our consultation identified some desire amongst councils to be able to compare their performance to support improvement in the delivery of services. We also identified a level of frustration that more progress has not been made toward establishment of a set of indicators that councils can use to measure performance and drive improvement in service delivery.

Several councils we spoke with were concerned that the current approaches to comparative reporting did not adequately acknowledge that councils need to tailor their service types, level and mix to the needs of their community. Comparative reporting approaches tend to focus on output measures such as number of applications processed, library loans annually and opening hours for sporting facilities, rather than outcome measures. These approaches risk unjustified and adverse interpretations of performance where councils have made a decision based on community consultation, local priorities and available resources. To mitigate this, it is important to

  • adopt a partnership approach to the development of indicators
  • ensure indicators measure performance, not just level of activity
  • compare performance between councils that are similar in terms of size and location.

It may be more feasible, at least in the short term, for OLG to support small groups of like councils to develop indicators suited to their situation.

Based on our consultations, key lessons from implementing a sector-wide performance indicator framework in Victoria included the benefits of:

  • consolidation of the various compliance data currently being reported by councils to provide an initial platform for comparative performance reporting
  • adopting a partnership approach to development of common indicators with groups of like councils.

Published

Actions for Fraud Survey

Fraud Survey

Education
Community Services
Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Transport
Treasury
Universities
Whole of Government
Environment
Fraud
Information technology
Internal controls and governance
Procurement
Risk

In a report released today, the NSW Auditor-General, Margaret Crawford provides a snapshot of reported fraud in the NSW public sector and an analysis of NSW Government agencies’ fraud controls based on a survey of 102 agencies.

Published

Actions for Implementation of the NSW Government’s program evaluation initiative

Implementation of the NSW Government’s program evaluation initiative

Industry
Justice
Planning
Premier and Cabinet
Treasury
Environment
Financial reporting
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

The NSW Government’s ‘program evaluation initiative’, introduced to assess whether service delivery programs achieve expected outcomes and value for money, is largely ineffective according to a report released today by NSW Auditor-General, Margaret Crawford.

Government services, in areas such as public order and safety, health and education, are delivered by agencies through a variety of programs. In 2016–17, the NSW Government estimates that it will spend over $73 billion on programs to deliver services.

 

Parliamentary reference - Report number #277 - released 3 November 2016

Published

Actions for Administering Domestic Waterfront Tenancies

Administering Domestic Waterfront Tenancies

Planning
Transport
Management and administration
Service delivery
Shared services and collaboration

The audit’s overall conclusion is that Lands and Maritime are broadly achieving outcomes consistent with the IPART report on administering domestic waterfront tenancies. But a lack of collaboration between the agencies is contributing to poor customer service. Inconsistencies with the IPART report recommendations and operational differences between the two agencies result in different rents and conditions for tenants in the two agencies. The differences are having a significant impact on customer service.

 

Parliamentary reference - Report number #191 - released 23 September 2009

Published

Actions for Environmental Grants Administration

Environmental Grants Administration

Planning
Environment
Internal controls and governance
Management and administration
Procurement
Shared services and collaboration

We found many aspects of good grants management, particularly in the Trust. All of the programs we looked at are clearly aligned to the Government’s objective to improve environmental outcomes. The Trust also has good practices for allocating grants. Performance in respect of results was mixed although many grants delivered tangible benefits - homes were protected from floods, degraded waterways restored and endangered habitats protected.

Generally we found that while both Department of Environment, Climate Change and Water and the NSW Environmental Trust had a range of strategies to monitor grants these were not always applied consistently or effectively. Grant programs need to be regularly evaluated to see what is working and what can be done better.

 

Parliamentary reference - Report number #190 - released 26 August 2009

Published

Actions for Grants Administration

Grants Administration

Premier and Cabinet
Treasury
Health
Community Services
Planning
Compliance
Internal controls and governance
Management and administration
Procurement
Risk

We found no significant difference in the funding of government and opposition electorates. However, more money was given to electorates that were safely held by the major parties. These seats received $1.29 for every dollar given to marginal and independent seats with government marginals getting the least. Electorates also receive different levels of funding according to which region they are in. Such variations may reflect valid agency objectives such as meeting State Plan targets or addressing socio-economic disadvantage.

But while agencies publish who gets what, they do not adequately evaluate or explain what grant programs have achieved. As a result, there is a risk that New South Wales may not get the best value for its spending. We recommend that agencies regularly evaluate their grant programs and publish the results.

 

Parliamentary reference - Report number #186 - released 6 May 2009

Published

Actions for Planning for Sydney's Water Needs

Planning for Sydney's Water Needs

Planning
Environment
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

Reliably supplying water to our State’s principal city, Sydney, is a major responsibility for the Government.

The community has been made keenly aware in recent years that inflows have been decreasing, and that Sydney has been using more water than is available. In April 2005 the water in Sydney’s storages dropped to 41.5 per cent of their capacity – the lowest level since the construction of Warragamba dam in 1960.

As Sydney continues to develop, it is expected that the demand for water will increase. The way that we use it will need to be sustainable, as it has a direct impact on our economy, our lifestyle and our environment.

In planning for the future the State’s water agencies face a range of uncertainties. But the task is vital.

This report informs Parliament and the community on the progress made - and what remains to be done - to ensure a reliable water supply for Sydney.

 

Parliamentary reference - Report number #135 - released 4 May 2005