Refine search Expand filter

Reports

Published

Actions for Planning, Industry and Environment 2019

Planning, Industry and Environment 2019

Planning
Industry
Environment
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Service delivery
Workforce and capability

This report outlines the results of audits of the financial statements of agencies now grouped in the NSW Planning, Industry and Environment cluster.

Unqualified audit opinions were issued for 56 of the 66 cluster agencies’ 30 June 2019 financial statements. Ten audits remain incomplete. The cluster agencies need to improve the timeliness of financial reporting. 

The Audit Office continued to identify issues regarding unprocessed Aboriginal land claims and the recognition of Crown land. ‘Auditor-General’s reports to parliament have recommended action to reduce the level of unprocessed land claims since 2007. However, the number of unprocessed claims continued to increase’, Margaret Crawford said.

One in five internal control findings were repeat issues. Key themes included information technology, asset management and improvements required to expense and payroll controls.

The report makes several recommendations including:

  • Property NSW should urgently address the deficiencies in the lease data used to calculate the impact of the new leasing standard effective from 1 July 2019
  • the Department of Planning, Industry and Environment should prioritise action to reduce unprocessed Aboriginal land claims
  • the Department of Planning, Industry and Environment should ensure the Crown land database is complete and accurate so state agencies and local government councils are better informed about the Crown land they control.

This report analyses the results of our audits of financial statements of the Planning, Industry and Environment cluster agencies for the year ended 30 June 2019. The table below summarises our key observations.

1. Machinery of Government changes

Creation of the Planning, Industry and Environment cluster

The Machinery of Government (MoG) changes abolished the former Planning and Environment cluster and former Industry cluster, and created the Planning, Industry and Environment cluster on 1 July 2019.

The Department of Planning and Environment (DPE), the Department of Industry (DOI), the Office of Environment and Heritage, and the Office of Local Government were abolished and the majority of their functions were transferred to the new Department of Planning, Industry and Environment (DPIE).

The Department of Planning, Industry and Environment is still in the process of implementing changes

The MoG changes bring risks and challenges to the cluster. A MoG Steering Committee, with the support of various project control groups and working groups, identified and developed responses to key risks arising from the changes.

However, the DPIE will take some time to fully integrate the policies, systems and processes of the abolished Departments and agencies.

2. Financial reporting

Audit opinions Unqualified audit opinions were issued for 56 of the 66 cluster agencies' 30 June 2019 financial statements audits. Ten financial statements audits are still ongoing.
Timeliness of financial reporting

Fifty-five of the 57 agencies subject to statutory deadlines submitted their financial statements on time.

Due to issues identified during the audit, 13 financial statements audits were not completed and audit opinions issued by the statutory deadline.

Agencies prepared and submitted their early close procedures in accordance with the mandatory timeframe set by NSW Treasury. However, 17 of the 49 agencies where we reviewed early close procedures were assessed as either partially addressing or not addressing one or more of the mandatory requirements. The cluster agencies could benefit from an increased focus on early close procedures.

Introduction of AASB 16 'Leases'

We noted errors in the lease data used in Property NSW's AASB 16 impact calculations, which affect both Property NSW and other government agencies. These errors were significant enough to present a risk of material misstatements to the financial statements of Property NSW and other government agencies in future reporting periods.

We had similar findings in our recent performance audit on 'Property Asset Utilisation', which highlighted issues with the quality of Property NSW's records.

Recommendation: Property NSW should urgently address the deficiencies in the lease data used to calculate the impact of the new leasing standard effective from 1 July 2019.

Unprocessed Aboriginal land claims have continued to increase

Despite an increase in the number of claims resolved, the number of unprocessed Aboriginal land claims increased by 7.2 per cent from the prior year to 35,855 at 30 June 2019. Claims can be made over Crown land assets of the DPIE or other government agencies. Until claims are resolved, there is an uncertainty over who is entitled to the land and the uses and activities that can be carried out on the land. We first recommended action to address unprocessed claims in 2007.

Recommendation (repeat issue): The DPIE should prioritise action to reduce unprocessed Aboriginal land claims.

3. Audit observations

Internal controls

One in five internal control issues identified and reported to management in 2018–19 were repeat issues.

The lack of user access review was the most common IT general control issue in the cluster.

Drought relief

The NSW Government announced an emergency drought relief package of $500 million in 2018, in addition to other financial assistance measures already in place.

Limited documentation and written agreements between relevant delivery agencies resulted in a $31.0 million misstatement relating to grant revenue.

Recognition of Crown land

Crown land is an important asset of the state. Management and recognition of Crown land assets is weakened when there is confusion over who is responsible for a particular Crown land parcel. Last year we recommended the DOI should ensure the database of Crown land is complete and accurate. While the DOI has commenced actions to improve the database, this continued to be an issue in 2018–19.

Recommendation (repeat issue): The DPIE should ensure the Crown land database is complete and accurate so state agencies and local government councils are better informed about the Crown land they control.

Developer contributions The former DPE continued to accumulate more developer contributions revenues than it spent on infrastructure projects. Total unspent funds increased to $274 million at 30 June 2019.

 

This report provides parliament and other users of the Planning, Industry and Environment cluster agencies financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

This cluster was created by the Machinery of Government changes on 1 July 2019. This report is focused on agencies in the Planning, Industry and Environment cluster from 1 July 2019. However, these agencies were all in other clusters during 2018–19. Please refer to the section on Machinery of Government changes for more details.

Machinery of Government (MoG) refers to how the government organises the structures and functions of the public service. MoG changes are where the government reorganises these structures and functions that are given effect by Administrative orders.

The MoG changes, announced following the NSW State election on 23 March 2019, created the Planning, Industry and Environment (PIE) cluster. The Administrative Changes Orders issued on 2 April 2019, 1 May 2019 and 28 June 2019 gave effect to these changes. These orders became effective on 1 July 2019.

Section highlights

The 2019 MoG changes significantly impacted the former Planning and Environment, and Industry clusters and agencies.

  • The PIE cluster combines most of the functions and agencies of the former Planning and Environment and Industry clusters from 1 July 2019.
  • The Department of Planning, Industry and Environment is the principal agency in the PIE cluster.
  • The MoG changes bring risks and challenges to the PIE cluster.
  • A MoG Steering Committee was established to oversee the transitional processes.
  • The full integration of the systems and processes will not be completed in the near future.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Planning, Industry and Environment (PIE) cluster for 2019. In this chapter, the Department of Planning, Industry and Environment is referred to as DPIE, the former Department of Planning and Environment as DPE, and the former Department of Industry as DOI.

Section highlights

  • Unqualified audit opinions were issued for all completed 30 June 2019 financial statements audits. However, some cluster agencies can further enhance the quality of financial reporting.
  • Timeliness of financial reporting remains an issue for 13 agencies.
  • Deficiencies were identified in the data used to calculate the impact of AASB 16 ‘Leases’ effective from 1 July 2019. Property NSW should urgently address these deficiencies.
  • Unprocessed Aboriginal land claims continue to increase. DPIE should prioritise action to reduce unprocessed Aboriginal land claims.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our audit observations and insights from our financial statement audits of agencies in the Planning, Industry and Environment (PIE) cluster for 2019. In this chapter, the Department of Planning, Industry and Environment is referred to as DPIE, the former Department of Planning and Environment as DPE, and the former Department of Industry as DOI.

Section highlights

  • One in five issues identified and reported to management in 2018–19 were repeat issues.
  • The lack of user access review was the most common IT general control issue in the PIE cluster.
  • The PIE cluster provided significant financial assistance for drought relief.
  • There continues to be significant deficiencies in Crown land records. The DPIE should ensure the Crown land database is complete and accurate.
  • Unspent developer contributions funds continued to build up in 2018–19. 

Appendix one – List of 2019 recommendations

Appendix two – Status of 2018 recommendations

Appendix three – Cluster agencies

Appendix four – Financial data

Appendix five – Management letter findings

Appendix six – Timeliness of financial reporting

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Development assessment: pre-lodgement and lodgement in Camden Council and Randwick City Council

Development assessment: pre-lodgement and lodgement in Camden Council and Randwick City Council

Local Government
Management and administration
Service delivery

The report found that both councils could do more to monitor and assess the effectiveness of their pre-lodgement and lodgement stages. The audit highlighted that Randwick City Council closely follows guidance designed to encourage good practice in these initial stages of its development assessments. It also demonstrated it was timely when processing lodgements. Camden Council is partially following the guidance and could not demonstrate that its lodgement stage was timely.

A development application is a formal application for development that requires consent under the NSW Environmental Planning and Assessment Act 1979. It is usually lodged with the local council for processing and determination, and consists of standard application forms, supporting technical reports and plans. 

In March 2017, the NSW Department of Planning and Environment (DPE)1 released the ‘Development Assessment Best Practice Guide' designed to help councils assess development applications in a timely manner and provide a better experience for applicants. 

DPE's guide describes the development assessment process in five stages. 

According to the Guidance, councils should systematically measure, monitor and review development assessment outcomes and timeframes against performance targets to ensure the process is transparent, accountable and outcome-focused.

Appendix one – Response from agencies

Appendix two – Council's alignment with the guidance

Appendix three – About the audit

Appendix four – Performance auditing

 

Parliamentary Reference: Report number #322 - released 20 June 2019

Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Domestic waste management in Campbelltown City Council and Fairfield City Council

Domestic waste management in Campbelltown City Council and Fairfield City Council

Local Government
Management and administration
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, today released a report on Domestic waste management in Campbelltown City Council and Fairfield City Council.The report found that both Councils collect and transport domestic kerbside waste effectively and process it at a low cost. The Councils also effectively process waste placed in green-lid and yellow-lid bins, but neither Council has been able to enforce their contracts for processing red-lid bin waste. As a result, almost all such waste goes straight to landfill. 

Local councils provide waste management services to their residents. They collect domestic waste primarily through kerbside services, but also at council drop off facilities. Waste management is one of the major services local councils deliver. Each year, councils collectively manage an estimated 3.5 million tonnes of waste generated by New South Wales residents.

Waste disposed of in landfills attracts a NSW Government waste levy. Councils’ kerbside services help residents to separate recyclable and non recyclable waste. This reduces the cost of waste disposed to landfill. These services typically provide yellow-lid bins for dry recyclables, green-lid bins for garden organics and red-lid bins for residual waste. To increase the level of recycling, some councils deliver residual waste to alternative waste treatment facilities for processing. This can involve composting and the recovery of resources, including plastics and metals, which can be recycled.

Appendix one - Responses from local councils

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary Reference: Report number #320 - released 5 June 2019

Published

Actions for Implementation of the NSW Government’s program evaluation initiative

Implementation of the NSW Government’s program evaluation initiative

Industry
Justice
Planning
Premier and Cabinet
Treasury
Environment
Financial reporting
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

The NSW Government’s ‘program evaluation initiative’, introduced to assess whether service delivery programs achieve expected outcomes and value for money, is largely ineffective according to a report released today by NSW Auditor-General, Margaret Crawford.

Government services, in areas such as public order and safety, health and education, are delivered by agencies through a variety of programs. In 2016–17, the NSW Government estimates that it will spend over $73 billion on programs to deliver services.

 

Parliamentary reference - Report number #277 - released 3 November 2016

Published

Actions for Monitoring food safety practices in retail food businesses

Monitoring food safety practices in retail food businesses

Health
Local Government
Compliance
Internal controls and governance
Management and administration
Risk
Shared services and collaboration

New South Wales has a lower rate of foodborne illness than the national average. This reflects some good practices in the NSW Food Authority’s approach to monitoring food safety standards. It also is a factor of the long-standing commitment by local councils’ to ensuring retail food businesses meet these standards.

To ensure foodborne illness remains low, the Authority needs to better monitor its arrangements with councils which inspect retail food businesses on its behalf, and receive additional and more timely information from councils on compliance with food safety standards.

 

Parliamentary reference - Report number #274 - released 15 September 2016

Published

Actions for Red tape reduction

Red tape reduction

Premier and Cabinet
Finance
Financial reporting
Internal controls and governance
Management and administration
Project management
Regulation
Shared services and collaboration

Overall, NSW Government initiatives and processes to prevent and reduce red tape were not effective, according to a report released today by the NSW Auditor-General.

In 2015, the Government reported that its red tape reduction initiatives, implemented between 2011 and 2015, had resulted in $896 million in savings. While these initiatives resulted in some savings, the total value of savings is unknown because estimates for some initiatives were based on unverified assumptions, cost transfers or unrealised projections.

 

Parliamentary reference - Report number #272 - released 25 August 2016

Published

Actions for Follow-up audits: Police response to calls for assistance, The levying and collection of Land Tax and Coordination of bushfire fighting activities

Follow-up audits: Police response to calls for assistance, The levying and collection of Land Tax and Coordination of bushfire fighting activities

Justice
Finance
Management and administration
Service delivery

The acceptance of audit recommendations by agencies in the current review was high and represented 96 per cent of the recommendations made. In addition, half of the recommendations in the 1998 audits have been adequately addressed and for over 70 per cent of recommendations there has been some measurable change in practices or performance.

But overall, most of these improvements have been incremental. And, for nearly one third of the recommendations, changes have not yet taken effect and there is a risk that the issue or problem contained in the original reports may persist. There is also a danger that current reporting arrangements may not provide Parliament sufficient assurance as to the extent accepted recommendations have been implemented and improvements have been achieved. 

To provide greater transparency and accountability, agencies, following a performance audit, should establish arrangements, such as an audit committee, to follow up on the progress of implementation of the recommendations and report on the progress of the implementation of recommendations in their annual report to Parliament.

 

Parliamentary reference - Report number #84 - released 21 June 2001