Reports

Published

Actions for Supporting the District Criminal Court

Supporting the District Criminal Court

Justice
Community Services
Information technology
Internal controls and governance
Project management

The Auditor-General for New South Wales, Margaret Crawford, released a report today on whether the Department of Communities and Justice (the department) effectively supports the efficient operation of the District Criminal Court system.

The audit found that in the provision of data and technology services, the department is not effectively supporting the efficient operation of the District Criminal Court system. The department has insufficient controls in place to ensure that data in the system is always accurate.

The department is also using outdated technology and could improve its delivery of technical support to courts.

The audit also assessed the implementation of the Early Appropriate Guilty Pleas reform. This reform aims to improve court efficiency by having more cases resolved earlier with a guilty plea in the Local Court. The audit found that the department effectively governed the implementation of the reform but is not measuring achievement of expected benefits, placing the objectives of the reform at risk.

The Auditor-General made seven recommendations to the department, aimed at improving the controls around courts data, reporting on key performance indicators, improving regional technical support and measuring the success of the Early Appropriate Guilty Pleas reform. 

The District Court is the intermediate court in the New South Wales court system. It hears most serious criminal matters, except murder, treason and piracy. The Department of Communities and Justice (the Department) provides support to the District Court in a variety of ways. For example, it provides security services, library services and front-desk services. This audit examined three forms of support that the Department provides to the District Court:

  • data collection, reporting and analysis - the Department collects data from cases in its case management system, JusticeLink, based on the orders Judges make in court and court papers
  • technology - the Department provides technology to courts across New South Wales, as well as technical support for this technology
  • policy - the Department is responsible for proposing and implementing policy reforms.

Recent years have seen a worsening of District Court efficiency, as measured in the Productivity Commission's Report on Government Services (RoGS). Efficiency in the court system is typically measured through timeliness of case completion. There is evidence that timeliness has worsened. For example, the median time from arrest to finalisation of a case in the District Court increased from 420 days in 2012–13 to 541 days in 2017–18.

As a result, the government has announced a range of measures to improve court performance, particularly in the District Court. These measures included the Early Appropriate Guilty Pleas (EAGP) reform. One of the objectives of EAGP is to improve court efficiency, which would be achieved by having more cases resolve with a guilty plea in the Local Court.

This audit assessed whether the Department of Communities and Justice effectively supports the efficient operation of the District Criminal Court system. We assessed this with the following lines of inquiry:

  • Does the Department effectively collect, analyse and report performance information relevant to court efficiency?
  • Does the Department effectively provide technology to support the efficient working of the courts?
  • Does the Department have effective plans, governance and monitoring for the Early Appropriate Guilty Pleas reform?

The audit did not consider other support functions provided by the Department. Further information on the audit, including detailed audit criteria, may be found in Appendix two.

Conclusion
In the provision of data and technology services, the Department is not effectively supporting the efficient operation of the District Criminal Court system. The Department has insufficient controls in place to ensure accurate data in the District Criminal Court system. The Department is also using outdated technology in significant numbers and could improve its delivery of technical support to meet agreed targets.
The Department effectively governed the implementation of the Early Appropriate Guilty Pleas reform. However, it is not ensuring that the benefits stated in the business case are being achieved, placing its objectives at risk.
The impact of inaccurate court data can be severe, and the Department does not have sufficient controls in place to ensure that its court data is accurate. Recent Bureau of Crime Statistics and Research reviews have identified data inaccuracies, and this demonstrates the Department needs strong controls in place to ensure that its court data is accurate.
The Department does not have a policy for data quality and has not formally assigned responsibility for data quality to any individual or branch. The Department also does not have a data dictionary outlining all the fields in its case management system. While the Department validates the highest risk items, such as warrants, to ensure that they are accurate, most data is not validated. The Department has recently commenced setting up a data unit for the Courts, Tribunals and Service Delivery branch. It is proposed that this unit will address most of the identified shortcomings.
The Department did not provide timely technical support to the court system in 2017 and is using outdated technology in significant numbers. The Digital and Technology Services branch of the Department had agreed a Service Level Agreement with the rest of the Department, outlining the expected speed of technical support responses. The branch did not meet response times in 2017. Performance improved in 2018, though DTS fell short of its targets for critical and moderate priority incidents. Critical incidents are particularly important to deal with in a timely manner as they include incidents which may delay a court sitting.
Requests for technical support rose significantly in 2018 compared to 2017, which may be related to the number of outdated pieces of technology. As at April 2019, the whole court system had 2,389 laptops or desktop computers outside their warranty period. The Department was also using other outdated technology. Outdated technology is more prone to failure and continuing to use it poses a risk of court delays.
The Department is not measuring all the expected benefits from the Early Appropriate Guilty Pleas reform, placing the objectives of the program at risk. The Early Appropriate Guilty Pleas business case outlined nine expected benefits from the reform. The Department is not measuring one of these benefits and is not measuring the economic benefits of a further five business case benefits. Not measuring the impact of the reform means that the Department does not know if it is achieving its objectives and if the reform had the desired impact.

The Department is responsible for providing technology to the courts, which can improve the efficiency of court operations by making them faster and cheaper. The Department is also responsible for providing technical support to courtrooms and registries. It is important that technical support is provided in a timely manner because some technical incidents can delay court sittings and thus impact on court efficiency. A 2013 Organisation for Economic Co‑operation and Development report emphasised the importance of technology and digitisation for reducing trial length.

While the Department may provide technology to the courts, they are not responsible for deciding when, how or if the technology is used in the courtroom.

The Department is using a significant amount of outdated technology, risking court delays

As of April 2019, the whole court system had 2,389 laptops or desktop computers out of warranty, 56.0 per cent of the court system's fleet. The court system also had 786 printing devices out of their normal warranty period, 75.1 per cent of all printers in use. The Department also advised that many of its court audio transcription machines are out of date. These machines must be running for the court to sit and thus it is critical that they are maintained to a high degree. The then Department of Justice estimated the cost of aligning its hardware across the whole Department with desired levels at $14.0 million per year for three years. Figures for the court system were not calculated but they are likely to be a significant portion of this figure.

Using outdated technology poses a risk to the court system as older equipment may be more likely to break down, potentially delaying courts or slowing down court services. In the court system throughout 2018, hardware made up 30.8 per cent of all critical incidents reported to technical support and 41.9 per cent of all high priority incidents. In addition, 16.2 per cent of all reported issues related to printing devices or printing.

From 2017 to 2018, technical support incidents from courts or court services increased. There were 4,379 technical support incidents in 2017, which increased significantly to 9,186 in 2018. The Department advised that some outside factors may have contributed to this increase. The Department was rolling out its new incident recording system throughout 2017, meaning that there would be an under‑reporting of incidents in that year. The Department also advised that throughout 2018 there was a greater focus on ensuring that every issue was logged, which had not previously been the case. Despite these factors, the use of outdated technology has likely increased the risk of technology breakages and may have contributed to the increase in requests for technical support.

Refreshing technology on a regular basis would reduce the risk of hardware failures and ensure that equipment is covered by warranty.

The Department did not meet all court technical support targets in 2017 and 2018

The Digital and Technology Services branch (DTS) was responsible for providing technical support to the courts and the Courts and Tribunal Services branch prior to July 2019. DTS provided technical support in line with a Service Level Agreement (SLA) with the Department. In 2017, DTS did not provide this support in a timely manner. Performance improved in 2018, though DTS fell short of its targets for critical and moderate priority incidents. Exhibit 7 outlines DTS' targets under the SLA.

Exhibit 7: Digital and Technology Services' Service Level Agreement
Priority Target resolution time Target percentage in time (%)
1. Critical 4 hours 80
2. High 1 day 80
3. Moderate 3 days 85
4. Low 5 days 85
Source: Department of Communities and Justice, 2019.

Critical incidents are particularly important for the Department to deal with in a timely manner because these include incidents which may delay a court sitting until resolved or incidents which impact on large numbers of staff. Some of the critical incidents raised with DTS specifically stated that they were delaying a court sitting, often due to transcription machines not working. High priority incidents include those where there is some impact on the functions of the business, which may in turn affect the efficiency of the court system. High priority incidents also include those directly impacting on members of the Judiciary. 

This audit examined DTS' performance against its SLA in the 2017 and 2018 calendar years across the whole court system, not just the District Court. The total number of incidents, as well as critical and high priority incidents, can be seen in Exhibit 8.

Exhibit 8: Number of incidents in 2017 and 2018
Priority 2017 2018
All 4,379 9,186
1. Critical 48 91
2. High 128 315
Source: Audit Office of NSW analysis of Department of Communities and Justice data, 2019.

The Department's results against its SLA in 2017 and 2018 are shown in Exhibit 9.

The Early Appropriate Guilty Pleas (EAGP) reform consists of five main elements:

  • early disclosure of evidence from NSW Police Force to the prosecution and defence
  • early certification of what the accused is going to be charged with to minimise changes
  • mandatory criminal case conferencing between the prosecutor and accused's representation
  • changes to Local Court case management
  • more structured sentence discounts.

More detailed descriptions of each of these changes can be found in the Introduction. These reform elements are anticipated to have three key effects:

  • accelerate the timing of guilty pleas
  • increase the overall proportion of guilty pleas
  • decrease the average length of contested trials.

Improving District Court efficiency is one of the stated aims of EAGP, which would be achieved by having more cases resolve in the Local Court and having fewer defendants plead guilty on the day of their trial in the District Court. The reform commenced in April 2018 and it is too early to state the impact of this reform on District Court efficiency.

The Department is responsible for delivering EAGP in conjunction with other justice sector agencies. They participated in the Steering Committee and the Working Groups, as well as providing the Project Management Office (PMO).

The Department is not measuring the economic benefits stated in the EAGP business case

The business case for EAGP listed nine quantifiable benefits which were expected to be derived from the achievement of the three key effects listed above. The Department is not measuring one of these benefits and is not measuring the economic benefits for five more, as shown in Exhibit 12.

Benefit Economic benefit (over ten years) Being measured?
Accelerated timing of guilty pleas $54.6m yellow circle with minus in the center
Increased guilty plea rate $90.7m yellow circle with minus in the center
Decreased average trial length $27.5m yellow circle with minus in the center
A reduction in the delay of indictable matters proceeding to trial N/A check circle mauve
Increase the number of finalised matters per annum N/A check circle mauve
Reduction of the current backlog of criminal trials in the District Court N/A check circle mauve
Reduction in bed pressure on the correction system due to reduced
average time in custody
$13.7m Exclamation circle red
Productivity improvements due to reduction in wasted effort $53.3m yellow circle with minus in the center
Bankable cost savings due to jury empanelment avoided $2.5m yellow circle with minus in the center

 

Exhibit 12: The Department's measurement of quantifiable benefits
Key check circle mauve Measuring yellow circle with minus in the center Not measuring economic benefit Exclamation circle red Not measuring
Source: Audit Office of NSW analysis.

While it is too early to comment on the overall impact of EAGP, better practice in benefits realisation involves an ongoing effort to monitor benefits to ensure that the reform is on target and determine whether any corrective action is needed.

The Department is measuring the number of finalised matters per annum and while the Department is not measuring the reduction in the backlog as part of this program, this measure is reported as part of the Department's internal reporting framework. The Department is not monitoring the reduction in delay of indictable matters proceeding to trial directly as part of this reform, but this does form part of the monthly Operational Performance Report which the Department sends to the EAGP Steering Committee.

The Department is not monitoring any of the economic benefits stated in the business case. These economic benefits are a mixture of bankable savings and productivity improvements. This amounts to a total of $242.3 million over ten years which was listed in the business case as potential economic benefits from the implementation of this reform against the total cost of $206.9 million over ten years. The Department is collecting proxy indicators which would assist in these calculations for several indicators, but it is not actively monitoring these savings. For example, the Department is monitoring average trial length, but is not using this information to calculate economic benefits derived from changes in trial length.

The Department is also not collecting information related to the average length of custody as part of this program. This means that it is unable to determine if EAGP is putting less pressure on the correctives system and it is not possible for the Department to calculate the savings from this particular benefit.

While stakeholders are optimistic about the impact of EAGP, not measuring the expected benefits stated in the business case means that the Department does not know if the reform is achieving what it was designed to achieve. Further, the Department does not know if it must take corrective action to ensure that the program achieves the stated benefits. These two things put the overall program benefits at risk.

The Department has not assigned responsibility for the realisation of each benefit, potentially risking the success of the program

The Department has not assigned responsibility for the realisation of each benefit stated in the business case. The Department holds the Steering Committee responsible for the realisation of all benefits. Benefits realisation is the process which ensures that the agency reaches benefits as stated in the business case. Assigning responsibility for benefits realisation to the Steering Committee rather than individuals is not in line with good practice.

Good practice benefits realisation involves assigning responsibility for the realisation of each benefit to an individual at the business unit level. This ensures there is a single point of accountability for each part of the program with knowledge of the benefit and the ability to take corrective action if it looks like that benefit will not be realised. This responsibility should sit at the operational level where detailed action can most easily be undertaken. The role of a Steering Committee in benefits realisation is to ensure that responsible parties are monitoring their benefits and taking appropriate corrective action.

The Department advised that it believes the Steering Committee should have responsibility for the realisation of benefits due to the difficulty of attributing the achievement of each benefit to one part of the reform alone. Given the Steering Committee meets only quarterly, it is not well placed to take action in response to variances in performance.

A BOCSAR evaluation is planned, however data errors make some of the information unreliable

BOCSAR are planning to undertake an overall evaluation of EAGP which is planned for release in 2021. Undertaking this evaluation will require high quality data to gain an understanding of the drivers of the reform. However, data captured throughout the first year of EAGP has proven unreliable, which may reduce the usefulness of BOCSAR's evaluation. These data issues were discussed in Exhibit 5 in Chapter 2, above. Access to accurate data is vital for conducting any program evaluation and inaccurate data raises the risk that the BOCSAR evaluation will not be able to provide an accurate evaluation of the impact of EAGP.

In addition to the BOCSAR evaluation, the Department had plans for a series of 'snapshot' evaluations for some of the key elements of the reform to ensure that they were operating effectively. These were initially delayed due to an efficiency dividend which affected EAGP. In August 2019, the Department commissioned a review of the implementation of several key success factors for EAGP.

There was clear governance throughout the implementation of EAGP

The implementation stage of EAGP had clear governance, lines of authority and communication. The Steering Committee, each Working Group and each agency had clear roles and responsibilities, and these were organised through a Project Management Office (PMO) provided by the former Department of Justice. The governance structure throughout the implementation phase can be seen at Exhibit 13.

The Steering Committee was established in December 2016 and met regularly from March 2017. It comprised senior members of key government agencies, as well as the Chief Judge and the Chief Magistrate for most of the duration of the implementation period. The Steering Committee met at least monthly throughout the life of the program. The Steering Committee was responsible for overseeing the delivery of EAGP and making key decisions relating to implementation, including spending decisions. The Chief Judge and the Chief Magistrate abstained from financial decisions. The Steering Committee updated the governance and membership of the Steering Committee as appropriate throughout the life of the reform.

Appendix one – Response from agency
 
Appendix two – About the audit 

Appendix three – Performance auditing 

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary Reference: Report number #329 - released 18 December 2019

Published

Actions for Managing growth in the NSW prison population

Managing growth in the NSW prison population

Justice
Infrastructure
Management and administration
Project management
Service delivery
Workforce and capability

The Department of Justice has relied heavily on temporary responses to accommodate growing prisoner numbers according to a report released today by the Acting Auditor-General for New South Wales, Ian Goodwin.

At the time of this audit, the NSW Department of Justice (DOJ) was responsible for delivering custodial corrections services in New South Wales through its Corrective Services NSW division (Corrective Services NSW). From 1 July 2019, the Department of Family and Community Services and Justice will be responsible for these functions. 

Within DOJ, Corrective Services NSW is responsible for administering sentences and legal orders through custodial and community-based management of adult offenders. Its key priorities are:

  • providing safe, secure and humane management of prisoners
  • reducing reoffending
  • improving community safety and confidence in the justice system. 

The prison population in New South Wales grew by around 40 per cent between 2012 to 2018, from 9,602 to 13,630 inmates. This rate of growth was higher than experienced prior to 2012. DOJ forecasts growth to continue over the short and longer-term. 

DOJ has responded to inmate population growth by doubling-up and tripling-up the number of prison beds in cells, reactivating previously closed prisons, and a $3.8 billion program of new prison capacity. DOJ has also developed a long-term prison infrastructure strategy that projects long-term needs and recommended investments to meet these needs. 

This audit assessed how efficiently and effectively DOJ is responding to growth in the NSW prison population. In this report, we have not analysed the sources of demand or recommended ways that custody may be avoided. These are largely government policy issues. 

Conclusion
The DOJ has relied heavily on temporary responses to accommodate growth in the NSW prison population. Sustained reliance on these responses is inefficient and creates risks to safety, and timely access to prisoner support services.
DOJ has experienced significant growth in the prison population since 2012. To meet demand, it has relied on temporary responses that are not designed to be sustained, including doubling-up or tripling-up the number of beds in cells, reopening previously closed facilities and using obsolete facilities. DOJ has also regularly moved inmates between its facilities to accommodate the increasing need for beds in metropolitan Sydney. 
Relying on temporary approaches over a long period contributes to prison crowding and has affected DOJ's ability to manage inmates in line with its correctional principles. It has increased risks to staff and prisoner safety, and timely inmate access to prisoner support services and programs. In addition, the cost per prisoner per day increased over the past two years.
DOJ is progressively delivering new capacity to address the growing prison population.
In response to continuing and projected growth in the prison population, the NSW Government announced a one-off $3.8 billion program to deliver around 6,100 beds by May 2021. Under the program, DOJ developed and delivered two rapid build dormitory style prisons within 18 months. DOJ’s capability to deliver the program, including implementation of new beds and new prisons, governance, project management, risk assessment and commissioning has improved over time. Most new capacity will be delivered on existing DOJ sites, mainly in regional New South Wales. 
DOJ has developed a strategy to respond to long-term projected growth in the prison population, but it has yet to be funded. 
The Corrective Services NSW Infrastructure Strategy (CSIS) sets out challenges, strategic priorities, and planned actions to respond to projected growth over the next 20 years and improve overall system efficiency and effectiveness. But, proposed actions are subject to individual business cases and funding decisions. Three versions of the CSIS have been provided to, and endorsed by, the NSW Government. The key challenge identified in the CSIS is to overcome demand for prison beds in the Sydney metropolitan region. DOJ advised that it is developing a final business case to address metropolitan capacity needs, but this is subject to government approval and funding. DOJ should continue to highlight the urgency of this issue until it is addressed, as it prevents planned actions to improve system efficiency and effectiveness.
 

The Productivity Commission’s Report on Government Services outlines the performance indicator framework for corrective services in Australia (Appendix three). We have used measures from this framework to assess the efficiency and effectiveness of DOJ’s responses to prison bed capacity needs. 

In this section, we analyse system-wide indicators as DOJ has not consistently published or reported data for individual correctional centres over the period of review.
 

Published

Actions for Transport Access Program

Transport Access Program

Transport
Infrastructure
Project management
Service delivery

The following report is available in an Easy English version that is intended to meet the needs of some people with lower literacy skills, some people with an intellectual disability and some people from different cultural backgrounds.

View the Easy English version of the Transport Access Program report

Transport for NSW’s process for selecting and prioritising projects for the third stage of its Transport Access Program balanced compliance with national disability standards with broader customer outcomes. Demographics, deliverability and value for money were also considered. However, Transport for NSW does not know the complete scope of work required for full compliance, limiting its ability to demonstrate that its approach is effective, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.

Access to transport is critical to ensuring that people can engage in all aspects of community life, including education, employment and recreation. People with disability can encounter barriers when accessing public transport services. In 2015, there were 1.37 million people living with disability in New South Wales.

Accessible public transport is about more than physical accessibility. It also means barrier-free access for people who have vision, hearing or cognitive impairments. All users, not just people with disability, benefit from improvements to the accessibility and inclusiveness of transport services. 

Transport for NSW has an obligation under Australian Government legislation to provide accessible services to people with disabilities in a manner which is not discriminatory. Under the Disability Standards for Accessible Public Transport 2002 (the DSAPT - an instrument of the Disability Discrimination Act 1992 (the Act) (Commonwealth)), there is a requirement to modify and develop new infrastructure, means of transport and services to provide access for people with disabilities. All public transport operators are required to ensure that at least 90 per cent of their networks met DSAPT by December 2017 and the networks will need to be 100 per cent compliant with all parts of the standards by 31 December 2022. Trains are not required to be fully compliant with DSAPT until December 2032. 

The Transport Access Program (TAP) is Transport for NSW's largest program with a specific focus on improving access to public transport for people with disability. The TAP is a series of projects to upgrade existing public transport infrastructure across four networks: Sydney Trains, Intercity Trains, Regional Trains and Sydney Ferries. Transport for NSW established the TAP as a rolling program and, to date, it has delivered the first tranche of TAP (TAP 1) and is completing the final projects for the second tranche (TAP 2). NSW budget papers estimate that by 30 June 2018, Transport for NSW had spent $1.2 billion in the TAP since its commencement in 2011-12.

After the completion of TAP 1 and TAP 2 (as well as through other transport infrastructure programs), Transport for NSW estimates that 58.5 per cent of the Sydney Trains, Regional Trains and Intercity Trains networks, and 66 per cent of the Sydney Ferries network, will be accessible. To close the significant gap in compliance with the DSAPT target, the objective for TAP 3 is ‘to contribute to Disability Discrimination Act 1992 related targets through DSAPT compliance upgrades’. 

The audit assessed whether Transport for NSW has an effective process to select and prioritise projects as part of the TAP, with a specific focus on the third tranche of TAP funding.

In August 2018, at the commencement of this audit, Transport for NSW intended to complete the selection of projects for the TAP 3 final business case in December 2018. Transport for NSW advise that it now intends to complete the development stage and final business case in the first quarter of 2019, prior to the final investment decision of the TAP program. This report is based on the TAP 3 strategic business case and information provided by Transport for NSW up to December 2018.

Conclusion
Transport for NSW’s process for selecting and prioritising projects for TAP 3 balanced DSAPT compliance goals with broader customer outcomes. It also considered demographics, deliverability and value for money. However, Transport for NSW does not know the complete scope of work required for full DSAPT compliance, and this limits its ability to demonstrate that its approach is effective. 
Transport for NSW has applied most of the external review recommendations from previous funding rounds to the implementation of the third round of TAP funding (TAP3), with positive results. Changes made include a clear objective for TAP 3 to focus on improving compliance, improved governance arrangements, and better consideration of deliverability and design during project planning. 
Through TAP 3, Transport for NSW is also trying to better address disability access in a way that balances DSAPT compliance with other considerations - such as population demographics, access to services and value for money. Transport for NSW developed an objective prioritisation and selection methodology to assess projects for TAP 3 funding. 
Transport for NSW cannot quantify the work needed to meet DSAPT compliance targets across the rail and ferry networks as it has not completed a comprehensive audit of compliance. This information is needed to ensure the effective targeting of funding, and to measure the contribution of TAP 3 work to meeting the DSAPT compliance targets. Instead, Transport for NSW has undertaken a phased approach to completing a comprehensive audit of compliance across the networks, with a focus on first assessing compliance at locations that are not wheelchair accessible. This creates two problems. First, Transport for NSW does not know the complete scope of work required to achieve DSAPT compliance. Second, not all wheelchair accessible locations fully meet DSAPT standards.
Transport for NSW's proposed communication plan for the schedule of TAP 3 funded works does not align with its Disability Inclusion Action Plan 2018-2022. The Disability Inclusion Action Plan commits Transport for NSW to providing a full list of stations and wharves to be upgraded with their estimated time of construction when the next round of funding, TAP 3, is announced. Given the long timeframes associated with improving transport infrastructure, this information is important as it allows people to make informed decisions about where they live, work or study. Instead, Transport for NSW plans to communicate information to customers on a project by project basis.

In 2015, there were 1.37 million people living with disability in New South Wales. Access to transport is critical to ensuring that people can engage in all aspects of community life, including education, employment and recreation. People with disability can encounter barriers when accessing public transport services. 

The social model of disability, outlined in the United Nations Convention on the Rights of Persons with Disabilities, views people with disability as not disabled by their impairment but by the barriers in the community and environment that restrict their full and effective participation in society on an equal basis with others. 

Accessible public transport is more than the provision of physical access to premises and conveyances, it provides barrier-free access for people who have vision, hearing or cognitive impairments. All users, not just people with disability, benefit from improvements to the accessibility and inclusiveness of transport services.

According to the Australian Bureau of Statistics, the main types of difficulties experienced by people with disability when using public transport relate to steps (39.9 per cent), difficulty getting to stops and stations (25 per cent), fear and anxiety (23.3 per cent) and lack of seating or difficulty standing (20.7 per cent).

Transport for NSW has a Disability Inclusion Action Plan (the Action Plan) 2018-2022 that sets an overall framework for planning, delivering and reporting on initiatives to increase accessibility of the transport network. It covers all elements of the journey experienced when using public transport, including journey planning, staff training, customer services and interaction between the physical environment and modes of transport. Appendix five outlines the guiding principles of the Action Plan.

Transport for NSW's Transport Social Policy branch developed the Action Plan in consultation with internal and external stakeholders. The director of the Transport Social Policy branch is a member of the TAP executive steering committee, which supports alignment between the Action Plan and TAP.

Transport for NSW's Disability Inclusion Action Plan describes a customer focussed approach to accessibility

One of the guiding principles of the Action Plan is ‘intelligent compliance’. Transport for NSW describes this as compliance that prioritises customer-focused outcomes over a narrow focus on legal compliance with accessibility standards. As well as being compliant, infrastructure should be practical, usable, fit for purpose and convenient. 

The TAP prioritisation and selection methodology reflects Transport for NSW’s focus on intelligent compliance. We consider this a reasonable approach as had Transport for NSW focussed exclusively on achieving compliance with the DSAPT targets by upgrading the most affordable infrastructure, some locations, that are used by more customers, would remain inaccessible to people with disability. However, this approach should not be seen as an alternative to Transport for NSW meeting its DSAPT compliance obligations.

TAP program staff consult with the Accessible Transport Advisory Committee

The Accessible Transport Advisory Committee (ATAC) has representatives from disability and ageing organisations, who provide expert guidance to Transport for NSW on access and inclusion. The ATAC provide guidance and feedback on projects and project solutions, including user testing where appropriate. TAP program staff provide regular updates at ATAC meetings, which include briefings on progress. The ATAC also provides feedback and suggestions to TAP program staff, which is considered and sometimes included in current and future projects.For example, in March 2017 the TAP program team briefed the ATAC on the challenges with respect to a number of ferry wharves and sought support for DSAPT exemptions proposed in the TAP 3 strategic business case.

Case study: Feedback on Braille lettering for lift buttons
In June 2018, the Program team sought feedback on a variety of lift button options to improve accessibility on future TAP projects. In September 2018, during the ATAC meeting attended by the Audit Office, the program team sought feedback on the standard designs for TAP 3. Some ATAC members noted that the standard design included Braille lettering on the lift buttons, and that this was not good practice because people can accidently press the button while reading it. As a result, Transport for NSW are incorporating this feedback into design requirements for the lifts for TAP 3, which will consider larger buttons, clearer Braille and Braille signage adjacent to the button.

Transport for NSW has not briefed the Advisory Committee on the outcome of the prioritisation and selection process

TAP program staff briefed the Advisory Committee about the prioritisation and selection methodology, after the Minister approved it in 2016. However, Transport for NSW have not briefed or consulted the Advisory Committee on the outcome of the prioritisation process. Infrastructure NSW noted this issue during its review of the strategic business case. 

Transport for NSW advised us that it established the ATAC as an advisory group, and that Transport for NSW does not disclose sensitive information to it. Transport for NSW intends to share the outcome of the prioritisation process following the completion of the TAP 3 development stage and final investment decision.

The TAP communication plan does not fully meet the requirements of the Disability Inclusion Action Plan

The Disability Inclusion Action Plan includes an action item to ‘provide a listing of stations and wharves to be upgraded with estimated time of construction as each new tranche of the Transport Access Program is announced’ The TAP Communication Plan that we reviewed does not include this provision instead focussing on communication on a per project basis. Given the long timeframes associated with improving transport infrastructure, this information is important as it allows people to make informed decisions about where they live, work or study.

Published

Actions for Liverpool to Parramatta Bus Transitway

Liverpool to Parramatta Bus Transitway

Transport
Treasury
Infrastructure
Management and administration
Project management
Service delivery

Several of my recent audits have identified a need to improve our public transport system – both for the benefit of travellers and to assist in achieving better air quality.

Bus Transitways can provide a good public transport solution for lower density population areas, potentially at a relatively low capital cost. This audit examines the transitway running between Liverpool and Parramatta, the first of several planned for Sydney. This audit should contribute to a better understanding of the lessons learnt from this first project, and so to future transitways providing better value for money.

But this audit also raises broader issues.

It highlights the importance of accurately projecting the total cost of major infrastructure projects before governments lock in their decisions. It also highlights the need for sound decision-making processes when government agencies compete with the private sector. The principles and recommendations flowing from these issues are ones I would draw to the attention of all agencies, and to the Government.

 

Parliamentary reference - Report number #146 - released 5 December 2005

Published

Actions for Implementing Asset Management Reforms

Implementing Asset Management Reforms

Justice
Planning
Finance
Treasury
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Project management

Hospitals, schools, public housing, roads, bridges, buses and trains are just some of the assets used by government in providing services to citizens.

The NSW Government’s asset base is impressive in size - with a value of around $167 billion and with government plans to spend around $8 billion acquiring or replacing assets in the current year. Another $2 billion is spent each year on maintenance.

Good asset management is very important to government; even a small efficiency gain in this area can provide significant returns. Good practice by those responsible for managing assets can improve reliability, extend asset life, save on maintenance costs and aid in identifying and disposing of unnecessary or non-performing assets.

Improving the NSW public sector’s approach to asset management has been on the reform agenda for at least a decade. Changes in practice have been accelerated more recently by integrating asset management policy with the budget process.

In this audit we examined NSW Treasury’s efforts to improve asset management practices in the public sector and the progress made by 3 agencies - the Department of Corrective Services, NSW Fire Brigades and the Powerhouse Museum - towards better managing their asset portfolios.

This report informs Parliament and the community on progress to date and what more needs to be done to ensure that agencies manage assets effectively and achieve best value.

 

Parliamentary reference - Report number #143 - released 12 October 2005

Published

Actions for Managing and Measuring Success: Department of Juvenile Justice

Managing and Measuring Success: Department of Juvenile Justice

Justice
Compliance
Internal controls and governance
Management and administration
Service delivery

Criminal or anti-social juvenile behaviour affects us all. Some of us may be victims of juvenile crime, some may be apprehensive about their personal safety, while others may know of young people who have been in trouble with the law. And, as taxpayers, all of us contribute to the costs of juvenile justice.

Currently about one in every 200 young people in NSW is convicted of a crime each year. The Department of Juvenile Justice works with these young offenders to help them fit back into society and lead a life free of crime.

This is not an easy task. Young offenders are often difficult to help. Many come from disadvantaged backgrounds and may have had poor parental supervision. They may have achieved little at school, have poor work prospects and psychological problems, and be part of an anti-social peer group.

While the Department of Juvenile Justice has prime responsibility, agencies in the justice and welfare systems need to work closely together to tackle these complex and diverse issues. They ultimately desire the same result for young offenders – progression to a well-adjusted, crime-free adulthood.

The report highlights the challenges facing all those who work with young offenders - youth workers, police officers, magistrates, health workers and teachers. Achieving the best possible outcome for these young people will help bring about safer and more harmonious communities for us all.

This is the first of two audits in our current performance audit program that deals with young offenders. We examined how the Department of Juvenile Justice measures performance, and whether staff have adequate information to make sound planning decisions and recommend appropriate interventions for young offenders.

Our next audit, starting later in 2005, will review whether relevant government agencies effectively coordinate the management of young offenders.

 

Parliamentary reference - Report number #142 - released 14 September 2005

Published

Actions for Coordination of Rescue Services

Coordination of Rescue Services

Justice
Internal controls and governance
Management and administration
Regulation
Service delivery
Workforce and capability

Nearly 11,000 rescues are carried out each year in New South Wales, the majority involving motor vehicle accidents.

In metropolitan areas we have three emergency services providing general land rescue - NSW Police, the Ambulance Service and the NSW Fire Brigades. The two volunteer services, the State Emergency Service and the Volunteer Rescue Association, generally cover the remainder of the State.

Rescue arrangements in NSW are different to all other mainland states. Elsewhere, the trend in metropolitan areas has been towards consolidation with only one provider of rescue services.

The State Rescue Board of NSW was set up in 1989. Its primary role is to ensure efficient and effective rescue services are maintained throughout the State.

In this audit we examined how well placed the Board was to provide assurance to Parliament and the community that the organisation of rescue services in NSW best serves those in need of rescuing.

NSW deserves a clear and unequivocal answer on such an important issue. However, the issues are complex, often strongly argued, and generally there is insufficient relevant information upon which to make judgements about performance and value. This report outlines a way forward.

 

Parliamentary reference - Report number #140 - released 20 July 2005

Published

Actions for Managing Disruptions to Cityrail Passenger Services

Managing Disruptions to Cityrail Passenger Services

Transport
Management and administration
Service delivery
Workforce and capability

About one in every twelve Sydney people travels by train each weekday.

Unplanned disruptions to services are inevitable, even on the best-run railways.

Because of the complexities of Sydney’s rail network, a single event can disrupt many services.

From a passenger’s perspective, three issues are important –

  • how quickly the disruption is fixed (“When will my train arrive?”)
  • the accuracy of information provided about the disruption (“Should I change my travel/meeting/other arrangements?”)
  • how often the disruptions occur (“Should I give up on rail travel?”).

In this audit, we looked at how well RailCorp responds when there are routine disruptions to its CityRail passenger services. We focused on how RailCorp manages passenger journeys and informs passengers.

This report informs Parliament and the community about the limitations of the current system, and what more needs to be done in order to minimise the impact of disruptions on passengers.

It should also help passengers judge the extent to which they can rely on the information they receive, and to better understand some of the obstacles faced by staff.

 

Parliamentary reference - Report number #139 - released 22 June 2005

Published

Actions for Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Project management
Service delivery
Workforce and capability

Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits.

This gives Parliament and the public an update on the extent of progress made.

In this follow-up audit, we examine changes following our May 2002 report on how well the:

  • State Transit Authority maintained its buses
  • Ministry of Transport administered contracts for the provision of regular passenger bus services.

 

Parliamentary reference - Report number #138 - released 14 June 2005

Published

Actions for Planning for Sydney's Water Needs

Planning for Sydney's Water Needs

Planning
Environment
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

Reliably supplying water to our State’s principal city, Sydney, is a major responsibility for the Government.

The community has been made keenly aware in recent years that inflows have been decreasing, and that Sydney has been using more water than is available. In April 2005 the water in Sydney’s storages dropped to 41.5 per cent of their capacity – the lowest level since the construction of Warragamba dam in 1960.

As Sydney continues to develop, it is expected that the demand for water will increase. The way that we use it will need to be sustainable, as it has a direct impact on our economy, our lifestyle and our environment.

In planning for the future the State’s water agencies face a range of uncertainties. But the task is vital.

This report informs Parliament and the community on the progress made - and what remains to be done - to ensure a reliable water supply for Sydney.

 

Parliamentary reference - Report number #135 - released 4 May 2005