Reports

Published

Actions for Stronger Communities 2020

Stronger Communities 2020

Justice
Community Services
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Management and administration
Service delivery

This report analyses the results of our audits of financial statements of the agencies comprising the Stronger Communities cluster for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Quality of financial reporting Unqualified audit opinions were issued for all agencies' 30 June 2020 financial statements.
Compliance with financial reporting requirements

The Treasury extended the statutory deadline for the submission of the 2019–20 financial statements. For agencies subject to Treasurer's Directions, Treasury required agencies to submit their 30 June 2020 financial statements by 5 August 2020. For other agencies, the deadline was extended to 31 October 2020. All agencies in the cluster met the revised statutory deadlines.

Cluster agencies substantially completed the mandatory early close procedures set by NSW Treasury. However, nine agencies including the Department of Communities and Justice (the department) did not complete one or more mandatory requirements, such as assessing the impact of new and updated accounting standards.

Financial implications of recent emergencies

Emergency events significantly impacted cluster agencies in 2019–20. Our review of seven cluster agencies most affected highlighted some had incurred additional expenditure because of the bushfires and floods. Others lost revenue due to the COVID-19 pandemic.

During the year these agencies collectively received additional funding of $1.1 billion from the State to respond to:

  • increased demand for homeless people seeking temporary accommodation
  • additional cleaning requirements
  • bushfire recovery efforts
  • emergency support for eligible small businesses.

The Sydney Cricket Ground Trust, Venues NSW and Office of Sport lodged insurance claims of $51.3 million with the Treasury Managed Fund with respect to lost revenues from the pandemic. The losses were mainly due to event cancellations and covered various periods ranging from mid-March to 31 December 2020.

The change in economic conditions caused by the COVID-19 pandemic resulted in the NSW Government cancelling the refurbishment of Stadium Australia it had previously approved in August 2019. Venues NSW wrote off $16.8 million of redevelopment costs during 2019–20.

Restatement of the Sydney Cricket Ground valuation The valuation of the Sydney Cricket Ground (the Stadium) included costs of $28.6 million which were not eligible for capitalisation. The financial statements were restated to reflect the reduction in the value of the Stadium and the asset revaluation reserve.
Unresolved data quality issues in the VS Connect system

The department continues to address significant data quality issues resulting from its implementation of the VS Connect system (the System) in 2019. The issues relate to the completeness and accuracy of the data transferred from the legacy system. The System is used by the department to manage its Victims Support Services (VSS) and for financial reporting purposes.

An independent actuary helps the department estimate its liability for VSS claims. The actuary's valuation at 30 June 2020 was again impacted by the data quality issues. Consequently, the actuary adopted a revised valuation methodology compared to previous years.

Recommendation (repeat issue):

The department should resolve the data quality issues in the VS Connect System before 31 March 2021.

AASB 16 'Leases' resulted in significant changes to agencies' financial position

Cluster agencies implemented three new accounting standards for the first time in 2019–20. Adoption of AASB 16 'Leases' resulted in cluster agencies collectively recognising right-of-use assets and lease liabilities of $1.7 billion and $1.1 billion respectively on 1 July 2019.

Significant misstatements in how lease related balances had been calculated were found in 17 of the 29 cluster agencies. The cluster outsources the management of most of its owned and leased property portfolio to Property NSW, but cluster agencies remain responsible for any deliverables under that arrangement. The misstatements were mainly caused by late revisions of key assumptions and issues with the accuracy and completeness of Property NSW's lease information.

2. Audit observations

Internal control deficiencies

Our 2019–20 financial audits identified 191 internal control issues. Of these, two were high risk and almost one-third were repeat findings from previous audits. While repeat findings reduced by 5.7 percentage points in 2019–20, the number remains high.

Recommendation (repeat issue):

Cluster agencies should action recommendations to address internal control weaknesses promptly. Focus should be given to addressing high risk and repeat issues.

Agencies response to recent emergencies

The severity of the recent bushfires and floods meant natural disaster expenses incurred by emergency services agencies rose from $67.4 million in 2018–19 to $497 million in 2019–20.

The COVID-19 pandemic presented unprecedented challenges for the cluster. Social distancing and other infection control measures disrupted the traditional means of delivering services. Agencies established committees or response teams to respond to these challenges.

The department introduced measures to minimise the risk of the spread of COVID-19 amongst inmates in custodial settings.

Managing excess annual leave

Managing excess annual leave was a challenge for cluster agencies directly involved in the government's response to the emergency events. Employees in frontline cluster agencies deferred leave plans and many have taken little or no annual leave during the reporting period.

Annual leave liabilities rose at the department, NSW Police Force, Fire and Rescue NSW, Office of the NSW Rural Fire Service, the Legal Aid Commission of New South Wales and the Office of the Director of Public Prosecutions. The combined liabilities increased from $620 million to $692 million or 11.6 per cent between 30 June 2019 and 30 June 2020.

Implementation of Machinery of Government (MoG) changes

Administrative Arrangement Orders effective from 1 July 2019, created the department of Communities and Justice and transferred functions and staff, together with associated assets and liabilities into the department from the former departments of Justice and Family and Community Services.

The department continues to establish its governance arrangements following the MoG changes.

Recommendation:

The department should finalise appropriate governance arrangements for its new organisational structure as soon as possible. This includes:

  • harmonising policies and procedures to ensure a unified approach across the department
  • finalising risk management and monitoring processes across the department
  • updating its delegation instruments to reflect the current organisational structure, delegation limits and roles and responsibilities.
Delivery of the Prison Bed Capacity Program

The department continued to expand prison system capacity through the NSW Government's $3.8 billion Prison Bed Capacity Program. The department reported it spent $480 million on the Program in 2019–20. Six prison expansion projects were completed during the year, which added 1,660 new and 395 refurbished beds to the NSW prison system.

Data from the department shows the number of adult inmates in the NSW prison system reached a maximum of 14,165 during the year. Operational capacity was 16,096 beds on 19 August 2020.

 

This report provides parliament and other users of the financial statements of agencies in the Stronger Communities cluster with the results of our audits, our observations, analysis, conclusions and recommendations.

Agencies in the Stronger Communities cluster were significantly impacted by the bushfires, floods and the COVID-19 pandemic in 2019–20. Our 2019–20 financial audits of the seven cluster agencies most significantly impacted by the recent emergency events considered:

  • the financial implications of the emergency events
  • changes to agencies' operating models and control environments
  • delivery of new or expanded projects, programs or services at short notice.

Our findings on these seven agencies' responses to the recent emergencies are included throughout this report. These agencies are:

  • Department of Communities and Justice
  • Fire and Rescue NSW
  • NSW Police Force
  • Office of the NSW Rural Fire Service
  • Office of the NSW State Emergency Service
  • Sydney Cricket and Sports Ground Trust
  • Venues NSW.

The Department of Communities and Justice is the principal agency of the cluster. The names of all agencies in the Stronger Communities cluster are included in Appendix one.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Stronger Communities cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Unqualified audit opinions were issued for all agencies' 30 June 2020 financial statements. All agencies met the revised statutory deadlines for completing early close procedures and submitting their financial statements.
  • Emergency events significantly impacted cluster agencies in 2019–20. Agencies received additional funding of $1.1 billion to respond to the emergencies.
  • Cluster agencies implemented three new accounting standards in 2019–20. Adoption of AASB 16 'Leases' resulted in significant changes to agencies' financial statements.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Stronger Communities cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies
  • review of how the cluster agencies managed the increased risks associated with new programs aimed at stemming the spread of COVID-19 and stimulating the economy.

Section highlights

  • Almost one-third of internal control issues reported were repeat findings. Cluster agencies should address these issues more promptly.
  • The severity of the recent bushfires and floods meant natural disaster expenses incurred by emergency services agencies increased by $430 million in 2019–20.
  • The department continues to establish its governance arrangements following Machinery of Government changes effective 1 July 2019.

 

Appendix one – Timeliness of financial reporting by agency

Appendix two – Management letter findings by agency

Appendix three – List of 2020 recommendations 

Appendix four – Status of 2019 recommendations 

Appendix five – Selected agencies for review of response to emergency events 

Appendix six – Financial data 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Waste levy and grants for waste infrastructure

Waste levy and grants for waste infrastructure

Planning
Environment
Management and administration
Regulation
Risk
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today that examined the effectiveness of the waste levy and grants for waste infrastructure in minimising the amount of waste sent to landfill and increasing recycling rates.  

The audit found that the waste levy has a positive impact on diverting waste from landfill. However, while the levy rates increase each year in line with the consumer price index, the EPA has not conducted a review since 2009 to confirm whether they are set at the optimal level. The audit also found that there were no objective and transparent criteria for which local government areas should pay the levy, and the list of levied local government areas has not been reviewed since 2014. 

Grant funding programs for waste infrastructure administered by the EPA and the Environmental Trust have supported increases in recycling capacity. However, these grant programs are not guided by a clear strategy for investment in waste infrastructure. 

The Auditor-General made six recommendations aimed at ensuring the waste levy is as effective as possible at meeting its objectives and ensuring funding for waste infrastructure is contributing effectively to recycling and waste diversion targets.

 

Overall, waste generation in New South Wales (NSW) is increasing. This leads to an increasing need to manage waste in ways that reduce the environmental impact of waste and promote the efficient use of resources. In 2014, the NSW Government set targets relating to recycling rates and diversion of waste from landfill, to be achieved by 2021–22. The NSW Waste and Resource Recovery (WARR) Strategy 2014–21 identifies the waste levy, a strong compliance regime, and investment in recycling infrastructure as key tools for achieving these waste targets.

This audit assessed the effectiveness of the NSW Government in minimising waste sent to landfill and increasing recycling rates. The audit focused on the waste levy, which is paid by waste facility operators when waste is sent to landfill, and grant programs that fund infrastructure for waste reuse and recycling.

The waste levy is regulated by the Environment Protection Authority (EPA) and is generally paid when waste is disposed in landfill. The waste levy rates are set by the NSW Government and prescribed in the Protection of Environment Operations (Waste) Regulation 2014. As part of its broader role in reviewing the regulatory framework for managing waste and recycling, the EPA can provide advice to the government on the operation of the waste levy.

The purpose of the waste levy is to act as an incentive for waste generators to reduce, re-use or recycle waste by increasing the cost of sending waste to landfill. In 2019–20, around $750 million was collected through the waste levy in NSW. The government spends approximately one third of the revenue raised through the waste levy on waste and environmental programs.

One of the waste programs funded through the one third allocation of the waste levy is Waste Less, Recycle More (WLRM). This initiative funds smaller grant programs that focus on specific aspects of waste management. This audit focused on five grant programs that fund projects that provide new or enhanced waste infrastructure such as recycling facilities. Four of these programs were administered by the Environmental Trust and one by the EPA.

Conclusion

The waste levy has a positive impact on diverting waste from landfill. However, aspects of the EPA's administration of the waste levy could be improved, including the frequency of its modelling of the waste levy impact and coverage, and the timeliness of reporting. Grant funding programs have supported increases in recycling capacity but are not guided by a clear strategy for investment in waste infrastructure which would help effectively target them to where waste infrastructure is most needed. Data published by the EPA indicates that the NSW Government is on track to meet the recycling target for construction and demolition waste, but recycling targets for municipal solid waste and commercial and industrial waste are unlikely to be met.

Waste levy

The waste levy rate, including a schedule of annual increases to 2016, was set by the NSW Government in 2009. Since 2016, the waste levy rate has increased in line with the consumer price index (CPI). The EPA has not conducted recent modelling to test whether the waste levy is set at the optimal level to achieve its objectives. The waste levy operation was last reviewed in 2012, although some specific aspects of the waste levy have been reviewed more recently, including reviews of waste levy rates for two types of waste. The waste levy is applied at different rates across the state. Decisions about which local government areas (LGAs) are subject to the levy, and which rate each LGA pays, were made in 2009 and potential changes were considered but not implemented in 2014. Currently, there are no objective and transparent criteria for determining which LGAs pay the levy. The EPA collects waste data from waste operators. This data has improved since 2015, but published data is at least one year out of date which limits its usefulness to stakeholders when making decisions relating to waste management.

Grants for waste infrastructure

All state funding for new and enhanced waste infrastructure in NSW is administered through grants to councils and commercial waste operators. The government's Waste and Resource Recovery (WARR) Strategy 2014–21 includes few priorities for waste infrastructure and there is no other waste infrastructure strategy in place to guide investment. The absence of a formal strategy to guide infrastructure investment in NSW limits the ability of the State Government to develop a shared understanding between planners, councils and the waste industry about waste infrastructure requirements and priorities. The Department of Planning, Industry and Environment is currently developing a 20-year waste strategy and there is an opportunity for the government to take a more direct role in planning the type, location and timing of waste infrastructure needed in NSW.

The grants administration procedures used for the grant programs reviewed in this audit were well designed. However, we identified some gaps in risk management, record-keeping and consistency of information provided to applicants and assessment teams. In four of the five programs we examined, there was no direct alignment between program objectives and the NSW Government's overall waste targets.

Achievement of the 2014–21 state targets for waste and resource recovery (WARR targets) is reliant in part on the availability of infrastructure that supports waste diversion and recycling. The state WARR targets dependent on waste infrastructure are:

  • Increase recycling rates to 70 per cent for municipal solid waste and commercial and industrial waste, and 80 per cent for construction and demolition waste.
  • Increase waste diverted from landfill to 75 per cent.

A further target — manage problem waste better by establishing or upgrading 86 drop-off facilities or services for managing household problem wastes state-wide — is dependent on accessible community waste drop-off facilities across NSW.

Exhibit 7 identifies the five grant programs that provide funding for new or enhanced waste infrastructure to increase capacity for reuse or recycling of waste. All five of these programs were examined in the audit.
In addition to the grant programs shown in Exhibit 7, other programs provide funding for infrastructure, but at a smaller scale. Examples of these include:

  • Bin Trim which provides rebates to small businesses for small scale recycling equipment such as cardboard and soft plastic balers.
  • Litter grants which provide funding for litter bins.
  • Weighbridges grants for installation of a weighbridge at waste facilities.
  • Landfill consolidation and environmental improvement grants for rural councils to replace old landfills with transfer stations or to improve the infrastructure at landfill sites.

Appendix one – Responses from audited agencies

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #343 - released 26 November 2020

Published

Actions for Governance and internal controls over local infrastructure contributions

Governance and internal controls over local infrastructure contributions

Local Government
Planning
Environment
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today on how well four councils managed their local infrastructure contributions during the 2017-18 and 2018-19 financial years. 

Local infrastructure contributions, also known as developer contributions, are collected from developers to pay for local infrastructure such as drainage, local roads, open space and community facilities. Controls over local infrastructure contributions help to ensure that all contributions owed are collected, funds are spent as intended, and any contributions paid in the form of works-in-kind or dedicated land are correctly valued.

The audit found that Blacktown City Council and City of Sydney Council provided effective governance over their local infrastructure contributions whereas Central Coast and Liverpool City Councils’ governance arrangements require improvement.

The audit found that three councils had spent local infrastructure contributions in accordance with approved contributions plans. Central Coast Council and the former Gosford City Council had spent $13.2 million on administration costs in breach of the Environmental Planning and Assessment Act 1979. These funds were repaid into the council’s local infrastructure fund during the course of the audit.

The Auditor-General made a number of recommendations for each council relating to improving controls over contributions and increasing transparency. 

Read full report (PDF)
 

This audit examined the effectiveness of governance and internal controls over local infrastructure contributions, also known as developer contributions, held by four councils during the 2017–18 and 2018–19 financial years.

This performance audit was conducted with reference to the legislative and regulatory planning framework that was in place during that period.

Our work for this performance audit was completed at the end of March 2020 when we issued the final report to the four audited councils and the Department of Planning, Industry and Environment. We received their respective formal responses to the report’s recommendations during April and May 2020.

Concurrently to this audit, we sought Crown Solicitor’s advice (the ‘Advice’) regarding the use of local infrastructure contributions collected by local councils under the Environmental Planning and Assessment Act 1979 (‘the EPA Act’) for our financial audit work. The Advice clarified the applicable legislative requirements with reference to the application, investment and pooling of local infrastructure contributions. The Advice is included in Appendix 2 of this report. The Advice has not impacted on the findings and recommendations of this report.

Councils collect Local Infrastructure Contributions (LICs) from developers under the Environmental Planning and Assessment Act (1979), the Local Government Act (1993) and the City of Sydney Act (2000) (EP&A Act, LG Act and City of Sydney Act) to fund infrastructure required to service and support new development. At 30 June 2018, councils across NSW collectively held more than $3.0 billion in LICs collected from developers. Just over $1.37 billion in total was held by ten councils. Councils collecting LICs must prepare a contributions plan, which outlines how LICs will be calculated and apportioned across different types of infrastructure. Councils that deliver water and sewer services prepare a development servicing plan (DSP) which allows them to collect contributions for water and sewer infrastructure.

Development timeframes are such that there is often several years between when LICs are collected and the infrastructure is required. Good governance and internal controls are needed over these funds to ensure they are available when needed and spent appropriately.

This audit assessed the effectiveness of governance and internal controls over LICs collected by four councils during the 2017–18 and 2018–19 financial years: Blacktown City Council, Central Coast Council, City of Sydney Council and Liverpool City Council. As at June 2018 these councils held the four highest LIC balances, each in excess of $140 million.

Audit Conclusion

Three of the four councils audited were currently compliant with legislation, regulations and Ministerial Directions regarding LICs. All had gaps in governance and controls over LICs which limited effective oversight.

Three of the councils included in the audit complied with legislation, regulations and Ministerial Directions relating to LICs. Central Coast Council breached the EP&A Act between 2001 and 2019 when it used LICs for administration costs. These funds were repaid in late 2019.

While controls over the receipt and expenditure of contributions funds were largely in place at all councils, there were some exceptions relating to valuing work and land delivered in lieu of cash. Three councils do not provide probity guidance in policies relating to LICs delivered through works-in-kind. Three of the councils had contributions plans that were more than five years old.

Staff at all four councils are knowledgeable about LICs but not all councils keep procedures up to date. Three councils' governance frameworks operate effectively with senior officers from across the council involved in decisions about spending LICs, entering into voluntary planning agreements (VPAs) and reviewing contributions plans.

Transparency over key information relating to LICs is important for senior management so they can make informed decisions, and for the community who pay LICs and expect infrastructure to be provided. During the period of the audit, none of the councils included in the audit provided sufficient information to senior management or their councillors about the projected financial status of contributions plans. This information would be valuable when making broader strategic and financial decisions. Information about LIC levies and intended infrastructure is available to the community but not always easy to find.

A strong governance framework is important at each council to ensure that the funds are managed well, available when needed and spent as intended. The audit examined the following features of each council's governance framework as they apply to LICs:

  • decision-making by councillors and council officers relating to LICs
  • monitoring delivery of contributions plans and DSPs including:
    • reviewing assumptions underlying the plans
    • monitoring projected status of plans.

Internal controls over LICs are important to promote accountability, prevent fraud and deliver infrastructure to the required standard at the best possible price. If financial controls are weak or are not implemented well, there is a risk that LICs are misspent or that councils pay too much for infrastructure.

Not all councils' internal controls adequately addressed risks associated with the administration of LICs

The audit examined a number of internal controls that manage risks related to LICs. These included:

  • financial controls over receipt and expenditure of LIC funds
  • management of conflicts-of-interest when dealing with developers
  • independent valuations of works-in-kind and dedicated land
  • ensuring delivery and quality of works-in-kind, and obtaining security from developers in the event of non-delivery or poor quality work
  • management of variations to VPAs and works-in-kind agreements.

We reviewed controls included in policies and procedures and then checked samples of work to ensure that controls were implemented. We found variation in the controls that councils implemented, and some weaknesses in controls. It is a matter for each council to assess their financial risk and develop internal controls that support the collection, management, and expenditure of LICs. However, councils must be able to assure their communities and developers that they are doing everything possible to collect all LICs owing and that work conducted by developers in lieu of cash payments is properly valued and carried out to the required standard.

Further information about audit findings in relation to internal controls for each council are included in chapters five to eight. The exhibit below demonstrates variation in several controls implemented in the audited councils.

In a 2018 report, the Independent Commission Against Corruption noted that 'the appetite for transparency is expanding in both the public and private sectors'.

The Practice Note and S64 Guidance refer to transparency, including the importance of transparency over:

  • calculation and apportionment of LICs
  • funding of infrastructure, including where and when infrastructure is delivered
  • arrangements made with developers through VPAs.

The LIC system is largely transparent for community members who know where to look

Contributions plans and DSPs are public documents, exhibited to the public before being adopted by council. Councils included in the audit publish their contributions plans and DSPs on their websites and meet statutory requirements with regard to reporting and accessibility of information.

However, other public information relating to the LIC system is fragmented across different websites and reports and varies in detail across councils.

Exhibit 10: Published information about LICs at the four audited councils
  Blacktown City Council Central Coast Council City of Sydney Council Liverpool City Council
Financial details about contributions collected and spent Financial statements Financial statements Financial statements Financial statements
Implementation plans for spending LICs Contribution plans S64 implementation plans in DSPs. S7.11 & S7.12 implementation plans developed annually within capital works plan Contribution plans Developed annually within capital works plan
Capital works underway or completed, funded by LICs Capital works plan and annual report Not published Not published Capital works plan
Source: Audit Office analysis.

The Practice Note states that councils are accountable for providing the infrastructure for which contributions are collected. Demonstrating that infrastructure has been provided is difficult with fragmented information. As an example of transparent reporting, Blacktown City Council's 2018–19 annual report includes information about infrastructure that has been delivered for every contributions plan, providing transparency over how LICs have been spent.

Use of LICs collected under VPAs is not always transparent

Contributions collected under VPAs are not required to demonstrate the same relationship to a development as LICs collected under section 7.11 of the EP&A Act. VPAs are often negotiated because a developer requests a change to a planning instrument, and it is important that these arrangements, and their outcomes, are transparent to the community.

The EP&A Regulation includes mechanisms to ensure that VPAs are partially transparent. VPAs are exhibited to the public and approved by the elected council. Councils must maintain a VPA Register and make the VPA Deeds of Agreement available on request. However, there is no obligation on council to report on the outcomes or delivery of developers' obligations under VPAs. The four audited councils vary in transparency and accessibility of information available about VPAs.

Exhibit 11: Published information about VPAs at the four audited councils
  Blacktown City Council Central Coast Council City of Sydney Council Liverpool City Council
VPA Register Council website and annual report Annual report Annual report Council website and annual report
VPA Deeds of Agreement Council website Available on request Available on request Council website
Intended use of LICs collected under VPAs In Deeds of Agreement In Deeds of Agreement In VPA Register and most Deeds of Agreement In VPA Register and most Deeds of Agreement
Completion of work funded by cash collected under VPAs Not published Not published Not published Not published
Delivery of works-in-kind or land negotiated under VPAs Not published Not published In VPA Register Not published
Source: Audit Office analysis.

The Practice Note suggests that councils incorporate the intended use of LICs collected under VPAs in the Deed of Agreement, but there is no guidance relating to transparency over where and when funds have actually been spent. There is merit in councils providing greater transparency over public benefits delivered through VPAs to give communities confidence in VPAs as a planning tool.

Credit arrangements with developers are not always well documented or monitored

When levying LICs, section 7.11(6) of the EP&A Act requires councils to take into account land, money, or works-in-kind that the developer has contributed on other development sites over and above their LIC obligations. This section of the EP&A Act allows a developer to offset a LIC owed on one site against land or works contributed on another. This leads to some developers carrying 'credits' for work delivered to councils, to be paid back by reduced LICs on a future development. Blacktown City Council and Central Coast Council allow developers to carry credits. Liverpool City Council and City of Sydney Council do not permit credits and instead pay the developers for any additional work undertaken.

Councils should formally document credit arrangements and have a robust process to validate and keep track of credit balances and report on them. Central Coast Council does not keep good track of credit arrangements and neither Blacktown City Council or Central Coast Council aggregate or report on outstanding credit balances.

Blacktown City Council manages the largest LIC fund in NSW and negotiates more VPAs than any other council. Overall, Blacktown City Council demonstrates effective governance over the LIC funds but there is scope for improved oversight of the projected financial status of contributions plans and credit arrangements with developers. Blacktown City Council also needs to update its operating procedures relating to LICs and improve security over key information.

Blacktown City Council is managing areas with high growth. There is a risk that Blacktown City Council will be unable to collect sufficient LICs to fund the infrastructure required to support that growth. However, Blacktown City Council does not assess and report to senior management or its Audit, Risk and Improvement Committee about the projected financial status of contributions plans.

Blacktown City Council has policies in place to guide the management of LICs although management of credit arrangements with developers requires greater oversight. Policies relating to works-in-kind agreements provide no guidance about probity in negotiations with developers and valuations of works-in-kind are not independent as they are paid for by the developer. Blacktown City Council's S7.11 committee structure could act as a model for other councils. Blacktown City Council is spending LICs according to its contributions plans. Staff managing LICs demonstrate good knowledge of the regulatory environment. However, a number of administrative processes need attention such as outdated procedures, lack of security over key spreadsheets, and inappropriate retention of sensitive personal data.

Recommendations

By December 2020, Blacktown City Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. update council's works-in-kind policy to address probity risks during negotiations with developers
  3. mitigate risks associated with lack of independence in valuations of works-in-kind
  4. improve public reporting about expenditure of cash collected under VPAs
  5. improve management oversight of credit arrangements with developers
  6. update procedures for managing LICs
  7. implement security measures over critical or personal information and spreadsheets. 

Central Coast Council's governance and internal controls over LICs were not fully effective. Between 2001 and 2019, more than $13.0 million in LICs was misspent on administration costs in breach of the EP&A Act. There is scope for improved oversight of the projected financial status of contributions plans and credit arrangements with developers. Policies and procedures from the two former councils are not aligned.

In May 2016, the newly amalgamated Central Coast Council inherited 53 contributions plans from the former Gosford City and Wyong Shire Councils. Managing this number of contributions plans fragments the available funds and increases complexity. Central Coast Council is currently working on consolidating these plans. Between June 2016 and June 2019, its LIC balance doubled from $90.0 million to $196 million. Central Coast Council does not assess and report to senior management or its Audit, Risk and Improvement Committee about the projected financial status of contributions plans. Central Coast Council has a LIC committee but it has no formal charter and senior officers do not regularly attend meetings. This limits the committee's effectiveness as a decision-making body. A draft policy relating to works-in-kind agreements provide no guidance about probity in negotiations with developers. Valuations of works-in-kind and land dedications are not independent as they are paid for by the developer.

Central Coast Council has adjusted its accounts in 2018–19 by $13.2 million to repay the LIC fund for administration expenses that were not provided for in 40 contributions plans.

Recommendations

By June 2020, Central Coast Council should:

1. obtain independent validation of the adjustment made to the restricted asset accounts and general fund to repay LICs spent on administration, and adjustments made to each infrastructure category within the contributions plans

2. publish current contributions plans from the former Gosford City Council on the Central Coast Council website.

By December 2020, Central Coast Council should:

3. regularly report to senior management on the projected financial status of contributions plans

4. increase transparency of information available to the public about LIC works planned and underway, including intended use of contributions collected under VPAs

5. consolidate existing plans, ensuring the new contributions plans includes a regular review cycle

6. develop a formal charter for the developer contributions committee and increase the seniority of membership

7. complete and adopt council's works-in-kind policy currently under development, ensuring it addresses probity risks during negotiations with developers

8. mitigate risks associated with lack of independence in valuations of works-in-kind and dedicated land

9. improve public reporting about expenditure of cash collected under VPAs

10. improve management oversight of credit arrangements with developers

11. implement security measures to ensure the integrity of key spreadsheets used to manage LICs

12. align policies and procedures relating to LICs across the amalgamated council including developing policies and procedures for the management of S64 LICs

13. update council's VPA policy to address increased or indexed bank guarantees to accommodate cost increases.

City of Sydney Council manages a complex development environment across the Sydney CBD and inner suburbs. Overall, governance and internal controls over LICs are effective although there is scope for improved oversight of the projected financial status of contributions plans.

City of Sydney Council maintains a large balance of LICs, although not excessive relative to the annual level of LIC expenditure. Unspent contributions are largely associated with open space infrastructure that cannot be delivered until suitable land is available. Thirty per cent of cash contributions are collected under VPAs and there is limited transparency over how these funds are spent. City of Sydney Council does not assess and report to management or its Audit, Risk and Compliance Committee about the projected financial status of contributions plans.

In 2017–18 and 2018–19, LICs were spent in accordance with the corresponding contributions plans. City of Sydney Council staff are knowledgeable about the regulatory environment and are supported by up-to-date policies and procedures.

Recommendations

By December 2020, City of Sydney Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. improve public reporting about expenditure of cash collected under VPAs
  3. periodically review the risk of unpaid LICs associated with complying development certificates and assess whether additional controls are required
  4. implement security measures to ensure the integrity of key spreadsheets used to manage LICs. 

During the audit period 2017–18 and 2018–19, Liverpool City Council did not have effective governance and internal controls over LICs. Liverpool City Council is addressing deficiencies and risks identified through an internal audit published in December 2018 although further work is required. There is scope for improved oversight of the projected financial status of contributions plans.

In the two years to 30 June 2019, the balance of unspent LICs increased by more than 60 per cent against a relatively low pattern of expenditure. Prior to an internal audit completed in late 2018, there was no regular reporting on the status of LICs and a lack of transparency when prioritising the expenditure of LIC funds. During 2019, and following the internal audit, Liverpool City Council engaged additional skilled resources to improve focus and accountability for LICs. A LIC committee has been established to manage contributions plans and support business units to initiate relevant infrastructure projects, although it is too early to assess whether this committee is operating effectively. From February 2019, Liverpool City Council commenced monthly reporting to its Chief Executive Officer (CEO) about the point-in-time status of LIC funds, and to its Audit, Risk and Improvement Committee about risks associated with LICs and the implementation of internal audit recommendations. There is limited reporting to senior management about the projected financial status of some contributions plans. Our audit found no evidence of misuse of funds during the audited period. Methods for valuing work and land are not aligned with policies and procedures and are implemented inconsistently. In addition, valuations of works-in-kind and land dedications are not independent as they are paid for by the developer. The policy relating to works-in-kind provides no guidance about managing probity risks when negotiating with developers.

Recommendations

By December 2020, Liverpool City Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. update council's policies and procedures to provide consistent guidance about how works and land offered by developers should be valued
  3. update council's Works-in-Kind and Land Acquisition Policy to address probity risks during negotiations with developers
  4. improve public reporting about expenditure of cash collected under VPAs
  5. mitigate risks associated with lack of independence in valuations of works-in-kind and dedicated land
  6. implement security measures over critical or private information. 

Appendix one – Responses from councils and the Department of Planning, Industry and Environment

Appendix two – Advice from the Crown Solicitor

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #339 - released 17 August 2020

Published

Actions for Planning, Industry and Environment 2019

Planning, Industry and Environment 2019

Planning
Industry
Environment
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Service delivery
Workforce and capability

This report outlines the results of audits of the financial statements of agencies now grouped in the NSW Planning, Industry and Environment cluster.

Unqualified audit opinions were issued for 56 of the 66 cluster agencies’ 30 June 2019 financial statements. Ten audits remain incomplete. The cluster agencies need to improve the timeliness of financial reporting. 

The Audit Office continued to identify issues regarding unprocessed Aboriginal land claims and the recognition of Crown land. ‘Auditor-General’s reports to parliament have recommended action to reduce the level of unprocessed land claims since 2007. However, the number of unprocessed claims continued to increase’, Margaret Crawford said.

One in five internal control findings were repeat issues. Key themes included information technology, asset management and improvements required to expense and payroll controls.

The report makes several recommendations including:

  • Property NSW should urgently address the deficiencies in the lease data used to calculate the impact of the new leasing standard effective from 1 July 2019
  • the Department of Planning, Industry and Environment should prioritise action to reduce unprocessed Aboriginal land claims
  • the Department of Planning, Industry and Environment should ensure the Crown land database is complete and accurate so state agencies and local government councils are better informed about the Crown land they control.

This report analyses the results of our audits of financial statements of the Planning, Industry and Environment cluster agencies for the year ended 30 June 2019. The table below summarises our key observations.

1. Machinery of Government changes

Creation of the Planning, Industry and Environment cluster

The Machinery of Government (MoG) changes abolished the former Planning and Environment cluster and former Industry cluster, and created the Planning, Industry and Environment cluster on 1 July 2019.

The Department of Planning and Environment (DPE), the Department of Industry (DOI), the Office of Environment and Heritage, and the Office of Local Government were abolished and the majority of their functions were transferred to the new Department of Planning, Industry and Environment (DPIE).

The Department of Planning, Industry and Environment is still in the process of implementing changes

The MoG changes bring risks and challenges to the cluster. A MoG Steering Committee, with the support of various project control groups and working groups, identified and developed responses to key risks arising from the changes.

However, the DPIE will take some time to fully integrate the policies, systems and processes of the abolished Departments and agencies.

2. Financial reporting

Audit opinions Unqualified audit opinions were issued for 56 of the 66 cluster agencies' 30 June 2019 financial statements audits. Ten financial statements audits are still ongoing.
Timeliness of financial reporting

Fifty-five of the 57 agencies subject to statutory deadlines submitted their financial statements on time.

Due to issues identified during the audit, 13 financial statements audits were not completed and audit opinions issued by the statutory deadline.

Agencies prepared and submitted their early close procedures in accordance with the mandatory timeframe set by NSW Treasury. However, 17 of the 49 agencies where we reviewed early close procedures were assessed as either partially addressing or not addressing one or more of the mandatory requirements. The cluster agencies could benefit from an increased focus on early close procedures.

Introduction of AASB 16 'Leases'

We noted errors in the lease data used in Property NSW's AASB 16 impact calculations, which affect both Property NSW and other government agencies. These errors were significant enough to present a risk of material misstatements to the financial statements of Property NSW and other government agencies in future reporting periods.

We had similar findings in our recent performance audit on 'Property Asset Utilisation', which highlighted issues with the quality of Property NSW's records.

Recommendation: Property NSW should urgently address the deficiencies in the lease data used to calculate the impact of the new leasing standard effective from 1 July 2019.

Unprocessed Aboriginal land claims have continued to increase

Despite an increase in the number of claims resolved, the number of unprocessed Aboriginal land claims increased by 7.2 per cent from the prior year to 35,855 at 30 June 2019. Claims can be made over Crown land assets of the DPIE or other government agencies. Until claims are resolved, there is an uncertainty over who is entitled to the land and the uses and activities that can be carried out on the land. We first recommended action to address unprocessed claims in 2007.

Recommendation (repeat issue): The DPIE should prioritise action to reduce unprocessed Aboriginal land claims.

3. Audit observations

Internal controls

One in five internal control issues identified and reported to management in 2018–19 were repeat issues.

The lack of user access review was the most common IT general control issue in the cluster.

Drought relief

The NSW Government announced an emergency drought relief package of $500 million in 2018, in addition to other financial assistance measures already in place.

Limited documentation and written agreements between relevant delivery agencies resulted in a $31.0 million misstatement relating to grant revenue.

Recognition of Crown land

Crown land is an important asset of the state. Management and recognition of Crown land assets is weakened when there is confusion over who is responsible for a particular Crown land parcel. Last year we recommended the DOI should ensure the database of Crown land is complete and accurate. While the DOI has commenced actions to improve the database, this continued to be an issue in 2018–19.

Recommendation (repeat issue): The DPIE should ensure the Crown land database is complete and accurate so state agencies and local government councils are better informed about the Crown land they control.

Developer contributions The former DPE continued to accumulate more developer contributions revenues than it spent on infrastructure projects. Total unspent funds increased to $274 million at 30 June 2019.

 

This report provides parliament and other users of the Planning, Industry and Environment cluster agencies financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

This cluster was created by the Machinery of Government changes on 1 July 2019. This report is focused on agencies in the Planning, Industry and Environment cluster from 1 July 2019. However, these agencies were all in other clusters during 2018–19. Please refer to the section on Machinery of Government changes for more details.

Machinery of Government (MoG) refers to how the government organises the structures and functions of the public service. MoG changes are where the government reorganises these structures and functions that are given effect by Administrative orders.

The MoG changes, announced following the NSW State election on 23 March 2019, created the Planning, Industry and Environment (PIE) cluster. The Administrative Changes Orders issued on 2 April 2019, 1 May 2019 and 28 June 2019 gave effect to these changes. These orders became effective on 1 July 2019.

Section highlights

The 2019 MoG changes significantly impacted the former Planning and Environment, and Industry clusters and agencies.

  • The PIE cluster combines most of the functions and agencies of the former Planning and Environment and Industry clusters from 1 July 2019.
  • The Department of Planning, Industry and Environment is the principal agency in the PIE cluster.
  • The MoG changes bring risks and challenges to the PIE cluster.
  • A MoG Steering Committee was established to oversee the transitional processes.
  • The full integration of the systems and processes will not be completed in the near future.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Planning, Industry and Environment (PIE) cluster for 2019. In this chapter, the Department of Planning, Industry and Environment is referred to as DPIE, the former Department of Planning and Environment as DPE, and the former Department of Industry as DOI.

Section highlights

  • Unqualified audit opinions were issued for all completed 30 June 2019 financial statements audits. However, some cluster agencies can further enhance the quality of financial reporting.
  • Timeliness of financial reporting remains an issue for 13 agencies.
  • Deficiencies were identified in the data used to calculate the impact of AASB 16 ‘Leases’ effective from 1 July 2019. Property NSW should urgently address these deficiencies.
  • Unprocessed Aboriginal land claims continue to increase. DPIE should prioritise action to reduce unprocessed Aboriginal land claims.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our audit observations and insights from our financial statement audits of agencies in the Planning, Industry and Environment (PIE) cluster for 2019. In this chapter, the Department of Planning, Industry and Environment is referred to as DPIE, the former Department of Planning and Environment as DPE, and the former Department of Industry as DOI.

Section highlights

  • One in five issues identified and reported to management in 2018–19 were repeat issues.
  • The lack of user access review was the most common IT general control issue in the PIE cluster.
  • The PIE cluster provided significant financial assistance for drought relief.
  • There continues to be significant deficiencies in Crown land records. The DPIE should ensure the Crown land database is complete and accurate.
  • Unspent developer contributions funds continued to build up in 2018–19. 

Appendix one – List of 2019 recommendations

Appendix two – Status of 2018 recommendations

Appendix three – Cluster agencies

Appendix four – Financial data

Appendix five – Management letter findings

Appendix six – Timeliness of financial reporting

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Stronger Communities 2019

Stronger Communities 2019

Justice
Community Services
Compliance
Financial reporting
Internal controls and governance
Management and administration
Project management
Service delivery
Shared services and collaboration
Workforce and capability

A report has been released on the NSW Stronger Communities cluster.

From 1 July 2019, the functions of the former Department of Justice, the former Department of Family and Community Services and many of the cluster agencies moved to the new Stronger Communities cluster. The Department of Communities and Justice is the principal agency in the new Stronger Communities cluster.

The report focuses on key observations and findings from the most recent financial audits of agencies in the Stronger Communities cluster.

Unqualified audit opinions were issued on the financial statements for all agencies in the cluster.  

There were 157 audit findings on internal controls. Two of these were high risk and 59 were repeat findings from previous financial audits. ‘Cluster agencies should prioritise actions to address internal control weaknesses promptly with particular focus given to issues that are assessed as high risk’, the Auditor-General said.

The report notes that the NSW Government’s new workers' compensation legislation, which gave eligible firefighters presumptive rights to workers' compensation, cost emergency services agencies $180 million in 2018–19, mostly in increased premiums.

Download the PDF version of report

This report analyses the results of our audits of financial statements of the agencies comprising the Stronger Communities cluster for the year ended 30 June 2019. The table below summarises our key observations.

This report provides parliament and other users of the financial statements of agencies in the Stronger Communities cluster with the results of our audits, our observations, analyses, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

This cluster was significantly impacted by the Machinery of Government (MoG) changes on 1 July 2019. This report focuses on the agencies that from 1 July 2019, comprised the Stronger Communities cluster. The MoG changes moved some agencies from the clusters to which they belonged in 2018–19 to the Stronger Communities cluster. Conversely, the MoG also moved some agencies formerly in the Family and Community Services cluster and Justice cluster elsewhere. Please refer to the section on Machinery of Government changes for more details.

The Department of Communities and Justice is the principal agency of the cluster. The newly created department combines functions of the former Department of Justice and the Department of Family and Community Services.

Machinery of Government (MoG) refers to how the government organises the structures and functions of the public service. MoG changes occur when the government reorganises these structures and functions and those changes are given effect by Administrative Orders.

The MoG changes announced following the NSW State election on 23 March 2019 significantly impacted the Stronger Communities cluster through Administrative Changes Orders issued on 2 April 2019 and 1 May 2019. These orders took effect on 1 July 2019.

Section highlights

The 2019 MoG changes significantly impacted the former Justice and Family and Community Services (FACS) departments and clusters.

  • The Stronger Communities cluster combines most of the functions and agencies of the former Justice and FACS clusters from 1 July 2019.
  • The Department of Communities and Justice is now the principal agency in the new cluster.
  • The MoG changes bring new responsibilities, risks and challenges to the cluster.
  • A temporary office has been established by the Department of Communities and Justice to support the cluster in the planning, delivery and reporting associated with implementing the changes.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations relating to the financial reporting of agencies in the Stronger Communities cluster for 2019.

Section highlights
  • Unqualified audit opinions were issued for all agencies' 30 June 2019 financial statements. However, further actions can be taken by some cluster agencies to enhance the quality of their financial reporting.
  • In November 2018, the Department of Justice implemented a new Victims Support Services system called VS Connect. Significant data quality issues arising from the VS Connect system implementation impacted the Department's ability to reliably estimate its Victims Support Scheme claims liabilities at 30 June 2019.
    We recommend the Department of Communities and Justice resolves the data quality issues in the new VS Connect System before 30 June 2020 and capture and apply lessons learned from recent project implementations, including LifeLink, Justice SAP and VS Connect, in any relevant future implementations.
  • Our audits found some cluster agencies needed to do more work on their impact assessments and preparedness to implement the new accounting standards, to minimise the risk of errors in their 2019–20 financial statements.
  • Cluster agencies with annual leave balances exceeding the State's target should further review their approach to managing leave balances.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Stronger Communities cluster.

Section highlights

  • Cluster agencies should action recommendations to address internal control weaknesses promptly. Particular focus should be given to prioritising high risk issues. The 2018–19 financial audits of cluster agencies identified 157 internal control issues. Of these, two were high risk and 37.6 per cent were repeat findings from previous audits.
  • Data from the Department of Justice shows the inmate population reached a maximum of 13,798, compared to an operational capacity of 14,626 beds on 31 August 2019. This equates to an operational vacancy rate of 5.7 per cent, which is more than the recommended 5.0 per cent buffer. This is the first time the vacancy rate has exceeded the target over the last five years. Growth in the NSW prison population is being managed through the NSW Government's $3.8 billion Prison Bed Capacity Program.
  • In September 2018, the NSW Government introduced new workers' compensation legislation, which gives eligible firefighters presumptive rights to workers' compensation when diagnosed with one of 12 prescribed cancers. The new legislation cost emergency services agencies $180 million in 2018–19, mainly through additional workers' compensation premiums.

Appendix one – Timeliness of financial reporting by agency

Appendix two – Management letter findings by agency

Appendix three – List of 2019 recommendations 

Appendix four – Status of 2018 recommendations 

Appendix five – Cluster agencies 

Appendix six – Financial data 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Contracting non-government organisations

Contracting non-government organisations

Community Services
Compliance
Fraud
Management and administration
Procurement
Regulation
Service delivery

This report found the Department of Family and Community Services (FACS) needs to do more to demonstrate it is effectively and efficiently contracting NGOs to deliver community services in the Permanency Support Program (a component of out-of-home-care services) and Specialist Homelessness Services. It notes that FACS is moving to an outcomes-based commissioning model and recommends this be escalated consistent with government policy.

Government agencies, such as the Department of Family and Community Services (FACS), are increasingly contracting non-government organisations (NGOs) to deliver human services in New South Wales. In doing so, agencies are responsible for ensuring these services are achieving expected outcomes. Since the introduction of the Commissioning and Contestability Policy in 2016, all NSW Government agencies are expected to include plans for customer and community outcomes and look for ways to use contestability to raise standards.

Two of the areas receiving the greatest funding from FACS are the Permanency Support Program and Specialist Homelessness Services. In the financial year 2017–18, nearly 500 organisations received $784 million for out-of-home care programs, including the Permanency Support Program. Across New South Wales, specialist homelessness providers assist more than 54,000 people each year and in the financial year 2017–18, 145 organisations received $243 million for providing short term accommodation and homelessness support, including Specialist Homelessness Services.

In the financial year 2017–18, FACS entered into 230 contracts for out-of-home care, of which 49 were for the Permanency Support Program, representing $322 million. FACS also entered into 157 contracts for the provision of Specialist Homelessness Services which totalled $170 million. We reviewed the Permanency Support Program and Specialist Homelessness Services for this audit.

This audit assessed how effectively and efficiently FACS contracts NGOs to deliver community services. The audit could not assess how NGOs used the funds they received from FACS as the Audit Office does not have a mandate that could provide direct assurance that NGOs are using government funds effectively.

Conclusion
FACS cannot demonstrate it is effectively and efficiently contracting NGOs to deliver community services because it does not always use open tenders to test the market when contracting NGOs, and does not collect adequate performance data to ensure safe and quality services are being provided. While there are some valid reasons for using restricted tenders, it means that new service providers are excluded from consideration - limiting contestability. In the service delivery areas we assessed, FACS does not measure client outcomes as it has not yet moved to outcomes-based contracts. 
FACS' procurement approach sometimes restricts the selection of NGOs for the Permanency Support Program and Specialist Homelessness Services
FACS has a procurement policy and plan which it follows when contracting NGOs for the provision of human services. This includes the option to use restricted tenders, which FACS sometimes uses rather than opening the process to the market. The use of restricted tenders is consistent with its procurement plan where there is a limited number of possible providers and the services are highly specialised. However, this approach perpetuates existing arrangements and makes it very difficult for new service providers to enter the market. The recontracting of existing providers means FACS may miss the opportunity to benchmark existing providers against the whole market. 
FACS does not effectively use client data to monitor the performance of NGOs funded under the Permanency Support Program and Specialist Homelessness Services
FACS' contract management staff monitor individual NGO performance including safety, quality of services and compliance with contract requirements. Although FACS does provide training materials on its intranet, FACS does not provide these staff with sufficient training, support or guidance to monitor NGO performance efficiently or effectively. FACS also requires NGOs to self-report their financial performance and contract compliance annually. FACS verifies the accuracy of the financial data but conducts limited validation of client data reported by NGOs to verify its accuracy. Instead, FACS relies on contract management staff to identify errors or inaccurate reporting by NGOs.
FACS' ongoing monitoring of the performance of providers under the Permanency Support Program is particularly limited due to problems with timely data collection at the program level. This reduces FACS' ability to monitor and analyse NGO performance at the program level as it does not have access to ongoing performance data for monitoring service quality.
In the Specialist Homelessness Services program, FACS and NGOs both provide the data required for the National Minimum Data Set on homelessness and provide it to the Australian Institute of Health and Welfare, as they are required to do. However, this data is not used for NGO performance monitoring or management.
FACS does not yet track outcomes for clients of NGOs
FACS began to develop an approach to outcomes-based contracting in 2015. Despite this, none of the contracts we reviewed are using outcomes as a measure of success. Currently, NGOs are required to demonstrate their performance is consistent with the measures stipulated in their contracts as part of an annual check of their contract compliance and financial accounts. NGOs report against activity-based measures (Key Performance Indicators) and not outcomes.
FACS advises that the transition to outcomes-based contracting will be made with the new rounds of funding which will take place in 2020–2021 for Specialist Homelessness Services and 2023 for the Permanency Support Program. Once these contracts are in place, FACS can transition NGOs to outcomes based reporting.
Incomplete data limits FACS' effectiveness in continuous improvement for the Permanency Support Program and Specialist Homelessness Services
FACS has policies and procedures in place to learn from past experiences and use this to inform future contracting decisions. However, FACS has limited client data related to the Permanency Support Program which restricts the amount of continuous improvement it can undertake. In the Specialist Homelessness Support Program data is collected to inform routine contract management discussions with service providers but FACS is not using this data for continuous improvement. 

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

Parliamentary Reference: Report number #323 - released 26 June 2019

Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Implementation of the NSW Government’s program evaluation initiative

Implementation of the NSW Government’s program evaluation initiative

Industry
Justice
Planning
Premier and Cabinet
Treasury
Environment
Financial reporting
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

The NSW Government’s ‘program evaluation initiative’, introduced to assess whether service delivery programs achieve expected outcomes and value for money, is largely ineffective according to a report released today by NSW Auditor-General, Margaret Crawford.

Government services, in areas such as public order and safety, health and education, are delivered by agencies through a variety of programs. In 2016–17, the NSW Government estimates that it will spend over $73 billion on programs to deliver services.

 

Parliamentary reference - Report number #277 - released 3 November 2016