Actions for Managing Grants

Managing Grants

Community Services
Industry
Planning
Management and administration
Service delivery

In our view, the agencies we studied cannot be sure that the grants they allocate align with their corporate objectives, and that program outcomes are achieved. This is mainly due to problems with grant selection and the evaluation of results. It was good to see that most of the grants programs had funding objectives which were fairly clear. But we found problems across most programs which could affect the fair and equitable selection of grants, such as, often no procedures for assessing applications, no assessment guidelines for advisory committees, often no clear rationale for assessments and poor documentation of the reasons for decisions.

 

Parliamentary reference - Report number #104 - released 4 December 2002

Published

Actions for Bus Maintenance and Bus Contracts

Bus Maintenance and Bus Contracts

Transport
Management and administration
Procurement
Service delivery

State Transit has developed fleet management plans and maintenance standards that meet its regulatory and contractual obligations as a bus operator and are consistent with vehicle manufacturers’ standards and best practice. However, assumptions used in fleet management plans to forecast fleet growth may not result in the most efficient and effective outcome for State Transit. Forecasts fail to take account of opportunities to redesign or reduce services where they exceed contract requirements and are difficult to justify on a commercial basis. Of greater concern are the consequences arising from bus maintenance practices not meeting State Transit’s own standards.

 

Parliamentary reference - Report number #97 - released 29 May 2002

Published

Actions for Government Property Register

Government Property Register

Finance
Asset valuation
Management and administration
Shared services and collaboration

Despite the issue being on the agenda for many years (formally, at least since 1988), at present there is not a comprehensive record of all government property assets in NSW. Whilst initiatives currently underway are promising, they will require continued priority to achieve tangible results. And careful coordination will be required to avoid duplication and waste.

 

Parliamentary reference - Report number #93 - released 31 January 2002

Published

Actions for Review of Walsh Bay

Review of Walsh Bay

Finance
Infrastructure
Management and administration
Procurement
Project management

The decision to seek development of Walsh Bay without a Master Plan and/or detailed study as to the state of the precinct presented significant problems throughout the life of the project. Now, four years later, negotiations still continue on the details of the final scheme. Based on the latest estimates, it will not provide a financial return as was originally expected. The audit found no evidence to indicate why the former Government wished to expedite Walsh Bay, but it is aware that there was an election due. Many of the problems which have been encountered could have been avoided with more careful and more extensive consideration at the start, particularly in the light of Property Services Group's recommendations.

 

Parliamentary reference - Report number #58 - released 17 December 1998

Published

Actions for The levying and collection of Land Tax

The levying and collection of Land Tax

Treasury
Information technology
Management and administration
Service delivery

Land tax has a significantly higher cost to collection ratio than other State taxes. In part this is because of its design. But there are opportunities to reduce collection costs within current policy constraints. The Office of State Revenue (OSR) has been actively pursuing better practice initiatives for some time and a substantial range of improvements has been made. OSR is continuing these efforts. However, inadequate systems and continued difficulties with the quality of land information remains as an impediment to efforts to increase efficiency and effectiveness and reduce collection costs.

Improvements canvassed in this Report (a number of which OSR had already been addressing before the audit commenced) would provide reduced collection costs (through greater efficiency) and improved collection results (through better education of taxpayers and better use of penalties and incentives). Notwithstanding these improvements, the long standing issues of land information standards and land ownership data compatibility between NSW agencies (largely outside OSR’s control) remain to be satisfactorily resolved.

 

Parliamentary reference - Report number #51 - released 5 August 1998

Published

Actions for Redevelopment proposal for East Fairfield (Villawood) Estate

Redevelopment proposal for East Fairfield (Villawood) Estate

Community Services
Infrastructure
Management and administration
Procurement
Project management
Service delivery

This audit examines the processes which led to the Government’s decision to demolish and sell the East Fairfield (Villawood) housing estate at a cost of nearly $32m gross ($17m net). In doing so, the audit focuses on whether the decision process demonstrates that it is an efficient and effective use of government funds.

The audit raises a number of concerns about the decision-making process. Although demolition and redevelopment may have been the most efficient and effective outcome, The Audit Office is not able to confirm this from the evidence presented. Audit found that the process used to arrive at this decision was not transparent, nor was it adequately justified by available evidence.

 

Parliamentary reference - Report number #46 - released 29 January 1998