Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project. The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money. This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and

Published

Actions for Volume Seven 2014 Focusing on Transport

Volume Seven 2014 Focusing on Transport

Transport
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Project management
Risk

All agencies in transport cluster received unqualified audit opinions for the year ended 30 June 2014. The quality of financial reporting continues to improve with the number of misstatements identified during audits falling for the fifth year in a row.

Published

Actions for Regional Road Funding - Block Grant and REPAIR Programs

Regional Road Funding - Block Grant and REPAIR Programs

Transport
Internal controls and governance
Management and administration
Project management
Risk

In 2013–14, Roads and Maritime Services (RMS) provided over $170 million to local councils through the Block Grant and REPAIR programs to spend on Regional Roads. Regional Roads are the link between State Roads and Local Roads.   Parliamentary reference - Report number #241 - released 8 May 2014

Published

Actions for Volume One 2014 - Areas of focus from 2013

Volume One 2014 - Areas of focus from 2013

Education
Community Services
Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Transport
Treasury
Universities
Whole of Government
Environment
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management
Risk

Today the Auditor-General of New South Wales, Grant Hehir, released his Volume One Report to Parliament for 2014. The observations included in this report are designed to inform readers of common findings from the 2013 financial and performance audits so agencies and audit committees can use them to identify issues that may be relevant to their organisations.

Published

Actions for Volume Eight 2013 focusing on Transport and Ports

Volume Eight 2013 focusing on Transport and Ports

Transport
Industry
Compliance
Financial reporting
Procurement
Project management
Regulation
Workforce and capability

Unqualified audit opinions were issued on the above corporations’ 30 June 2013 financial statements. During the year, Treasury issued TC 13/01 ‘Mandatory early close procedures for 2013’. This Circular aimed to improve the quality and timeliness of agencies’ annual financial statements. In 2012-13, application of the circular was made mandatory for State owned corporations. As a result, the port corporations were required to perform the early close proce

Published

Actions for Volume Eight 2012 focusing on Transport and Ports

Volume Eight 2012 focusing on Transport and Ports

Transport
Industry
Compliance
Financial reporting
Fraud
Information technology
Infrastructure
Management and administration
Procurement
Project management
Regulation
Risk
Workforce and capability

We issued unqualified audit opinions on the transport entities’ 30 June 2012 financial statements. Some of the findings of the report include: government funding to the public transport operators totalled $4.4 billion in 2011-12 ($3.7 billion in 2010-11) passenger services revenue only covered 20 per cent of RailCorp's operating costs Transport for NSW has formalised a protocol to mitigate the risk of potential conflicts of interests

Published

Actions for Volume Eight 2011 Focus on Transport and Ports

Volume Eight 2011 Focus on Transport and Ports

Transport
Industry
Asset valuation
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effect

Published

Actions for Improving road safety: Young drivers

Improving road safety: Young drivers

Transport
Finance
Project management
Regulation
Service delivery

The audit concluded that the RTA’s licence testing and regulation has been generally effective in ensuring the safety of young drivers. There has been a significant reduction in crash and fatality rates involving young drivers over the last decade, more so than for drivers 26 years and older. This has coincided with the introduction by the RTA of an enhanced GLS. International and national research has demonstrated graduated licensing systems to be effec

Published

Actions for Improving Road Safety: Speed Cameras

Improving Road Safety: Speed Cameras

Transport
Project management
Regulation

We found that fixed speed cameras were generally located in areas with high road safety risk. Likewise, safety cameras that enforced speed limits were initially placed at high risk sites. However as all safety cameras will now enforce speed, RTA no longer uses evidence of a speeding problem to select these sites. Overall, total crashes and injuries each fell 26 per cent, and fatalities fell by more than two-thirds, in the three years after the installati

Published

Actions for Government expenditure and transport planning in relation to implementing Barangaroo

Government expenditure and transport planning in relation to implementing Barangaroo

Industry
Treasury
Transport
Compliance
Internal controls and governance
Management and administration
Project management
Service delivery

Barangaroo is an ambitious and significant development on Government-owned Sydney Harbour foreshore. Construction on the 22 hectare CBD site is expected to take 12 years to 2023. Developer contributions to Government of $1 billion are to provide for public domain and other Government development costs, including a six hectare Headland Park. When completed the precinct is to service an anticipated 26,000 workers and residents and up to 33,000 visitors a d