Actions for CBD and South East Light Rail Project
CBD and South East Light Rail Project
Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford.
Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case.
Parliamentary reference - Report number #278 - released 30 November 2016
Actions for Implementation of the NSW Government’s program evaluation initiative
Implementation of the NSW Government’s program evaluation initiative
The NSW Government’s ‘program evaluation initiative’, introduced to assess whether service delivery programs achieve expected outcomes and value for money, is largely ineffective according to a report released today by NSW Auditor-General, Margaret Crawford.
Government services, in areas such as public order and safety, health and education, are delivered by agencies through a variety of programs. In 2016–17, the NSW Government estimates that it will spend over $73 billion on programs to deliver services.
Parliamentary reference - Report number #277 - released 3 November 2016
Actions for Early childhood education
Early childhood education
Enrolments in quality early childhood education programs in New South Wales are increasing but are below the national benchmark, according to a report released today by the NSW Auditor-General, Margaret Crawford.
Ninety-five per cent of children should be enrolled in at least 600 hours in the year before school, but according to the latest NSW figures 77 per cent of children were enrolled in quality early childhood education programs. This 2015 figure is below the benchmark, but is a significant improvement on 2013 when 59 per cent were enrolled.
Parliamentary reference - Report number #271 - released 26 May 2016
Actions for Supporting students with disability in NSW public schools
Supporting students with disability in NSW public schools
The Department of Education is doing a reasonable job in managing how well students with disability transition to a new school and supporting teachers to improve these students’ educational outcomes, according to a report released today by the NSW Auditor-General, Margaret Crawford.
The level of support provided to students with disability can vary between schools. This is partly due to cultural resistance in some schools and teachers not always having the necessary skills to support children with disability.
Parliamentary reference - Report number #270 - released 12 May 2016
Actions for Franchising of Sydney Ferries Network services
Franchising of Sydney Ferries Network services
Franchising services on the Sydney Ferries Network was justified, and Transport for NSW’s management of the franchise has been largely effective according to a report released today by the NSW Acting Auditor-General, Tony Whitfield.
'Franchising has resulted in cost savings, good service performance, and effective risk transfer from government to the private sector operator', said Mr Whitfield.
Parliamentary reference - Report number #265 - released 4 February 2016
Actions for Public sector management reforms
Public sector management reforms
The Public Service Commission is making good progress with leading the implementation of public sector management reforms, according to a report released today by the Acting New South Wales Auditor-General, Tony Whitfield.
'The Commission developed a sound evidence base for the reforms and gained wide public sector support by engaging with agency heads and using public sector working groups to develop options', said the Acting Auditor-General. 'They developed good guidance for government agencies and have improved the senior executive structure in the NSW public sector', he added.
Parliamentary reference - Report number #264 - released 28 January 2016
Actions for Sydney metropolitan bus contracts
Sydney metropolitan bus contracts
On 9 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on Sydney Metropolitan Bus Service Contracts.
All scheduled bus services in the Sydney metropolitan area are provided under contracts with the public and private operators. The contracts allow Transport for NSW (TfNSW) to determine what bus services are provided and to whom. This audit assessed the effectiveness of TfNSW’s design and management of these contracts.
Bus services provided under the Sydney Metropolitan Bus Service Contracts have largely been effective and efficient. Operators are mostly meeting their key performance indicators. Customer satisfaction is better than under the previous contracts and improving, patronage is increasing, and the unit costs of providing services are now lower than under the previous contracts.
However, punctuality remains a problem. Private operators are mostly starting their trips on time, but rarely meeting their mid and end-of-trip targets. State Transit Authority’s (STA) punctuality is improving but is worse than private operators, and other areas of performance are generally below private operators.
The current situation is a substantial improvement over what we found in our 2010 audit on the previous contracts.
Parliamentary reference - Report number #258 - released 9 September 2015
Actions for Identifying productivity in the public sector
Identifying productivity in the public sector
This report examines selected areas of government activity to see if sufficient information was available to identify and assess changes in productivity. The areas examined were primary and secondary school public education, acute inpatient care in NSW public hospitals, CityRail, the NSW Police Force, and the NSW Local Court.
Productivity is commonly defined as the amount of output per unit of input.
Parliamentary reference - Report number #256 - released 16 July 2015
Actions for Implementing performance audit recommendations
Implementing performance audit recommendations
NSW Government agencies have sound processes for implementing performance audit recommendations in Auditor-General’s Reports to Parliament. There are many cases of good practice. For example, some agencies formed a steering committee and developed a detailed plan to implement recommendations. Another incorporated the implementation of recommendations into both its business plan and the work plans of individual officers who were managing projects. Most agencies also used their Audit and Risk Committees to monitor recommendations.
We found some cases where agencies can improve how they coordinate actions to address recommendations. Most agencies were not revisiting these actions to determine whether they remain appropriate.
Parliamentary reference - Report number #254 - released 24 June 2015
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.
Parliamentary reference - Report number #252 - released 7 May 2015