Actions for Passenger Rail Punctuality

Passenger Rail Punctuality

Transport
Information technology
Infrastructure
Service delivery

Rail agencies are well placed to manage the forecast increase in passengers up to 2019, including joining the Sydney Metro Northwest to the network at Chatswood. Their plans and strategies are evidence-based, and mechanisms to assure effective implementation are sound.

Based on forecast patronage increases, the rail agencies will find it hard to maintain punctuality after 2019 unless the capacity of the network to carry trains and people is increased significantly. If recent higher than forecast patronage growth continues, the network may struggle to maintain punctuality before 2019.

A NSW Government priority is to ‘maintain or improve reliability of public transport services over the next four years’. Punctuality is a key element of reliability, and the level of patronage is a critical factor in the ability to maintain punctuality. Increasing patronage places pressure on the length of time trains need to wait at stations to load and offload passengers which can lead to delays. The NSW Long Term Transport Master Plan forecasts that rail patronage could increase by 26 per cent between 2012 and 2031.  

Passenger rail services in NSW are provided under a purchaser-provider model. Transport for NSW enters contracts with:

  • Sydney Trains for Sydney suburban passenger rail services
  • NSW Trains for services that commence or terminate outside Sydney, including intercity services that operate between Central station and the South Coast, Southern Highlands, Blue Mountains and Central Coast and Newcastle.

Transport for NSW sets performance targets and standards for these services, develops the timetables, procures trains for the service providers, and is responsible for long term planning.

This audit assessed whether these rail agencies have plans and strategies to maintain or improve performance in getting the growing number of suburban and intercity rail passengers to their destinations on time.

Conclusion:

Rail agencies are well placed to manage the forecast increase in passengers up to 2019, including joining the Sydney Metro Northwest to the network at Chatswood. Their plans and strategies are evidence-based, and mechanisms to assure effective implementation are sound.

Based on forecast patronage increases, the rail agencies will find it hard to maintain punctuality after 2019 unless the capacity of the network to carry trains and people is increased significantly. If recent higher than forecast patronage growth continues, the network may struggle to maintain punctuality before 2019.

Transport for NSW has undertaken considerable work on developing strategies to increase capacity and maintain punctuality after 2019, but remains some way from putting a costed plan to the government. There is a significant risk that investments will not be made soon enough to handle future patronage levels. Ideally, planning and investment decisions should have been made already.

Punctuality measurement is satisfactory, but agencies could publish more information

Passenger rail punctuality indicators adopted in NSW are good practice. The key train punctuality indicator is better than indicators used by many other rail operators. It is also better than the on-time-running indicator that it replaced. Unlike the on-time-running indicator, the punctuality indicator classifies trains that have been cancelled or skipped stations as late and results are not adjusted to take account of delays caused by factors such as extreme weather or police operations.

NSW also has a customer delay measure which represents good practice. Work has started on refining and embedding customer delay as a key performance measure for the planned new Rail Operations Centre.

As train frequency approaches a ‘turn up and go’ level of service, rather than running to a timetable, more emphasis will need to be placed on excess waiting time and customer delay when assessing performance.

Measurement of punctuality is reasonably precise. There are some measurement inaccuracies which should be addressed, such as the estimated arrival time of a train being incorrect at some destination stations, but these do not affect punctuality results materially.  

Train punctuality is reported publicly, but not to the detail of the indicators in the contracts between Transport for NSW and Sydney Trains and NSW Trains. There is very limited public reporting of customer delay.

Overall punctuality is good, but some services are relatively poor

System-wide train punctuality has usually exceeded target since 2005, but some services suffer from poor punctuality compared to the rest of the network.  

The part of the network around North Sydney is creating problems for the punctuality of afternoon peak services heading through it and out to Western Sydney and to Hornsby via Strathfield. Transport for NSW and Sydney Trains are well advanced with strategies to address this up to 2019.  

The East Hills express trains in the afternoon peak also performed well below target. The rail agencies recently analysed this issue and believe it relates to the train timetable and signalling which restricts how close trains can run behind each other into Campbelltown. It further advises that this will be corrected over the next three years.  

Intercity train punctuality is below that of suburban trains and there was an extended period of declining punctuality between 2011 and 2014. Transport for NSW suggested that the old age of trains is a factor, and the recently announced intercity fleet acquisition may help address this. Apart from ensuring that train crew and station staff are available and perform their duties adequately, NSW Trains can do little to impact the punctuality of its intercity services directly. Train maintenance, track and signal maintenance, and management of trains on the rail network are performed by Sydney Trains. NSW Trains’ ability to influence improvement is hampered by key indicators in some contracts being undefined. Transport for NSW, Sydney Trains and NSW Trains are now working collaboratively to make improvements to the contracts.

Initiatives are in place or are planned to deliver good punctuality until 2019

Patronage increases, which can lead to overcrowding and trains having to wait longer at stations, are likely to present a significant challenge to maintaining punctuality into the future.

Based on patronage projections, the rail agencies have strategies to maintain punctuality up to and including joining the Sydney Metro Northwest to the network at Chatswood in 2019. These include improving infrastructure at particular parts of the network, increasing staff training, reducing the number of speed restrictions, and a new Rail Operations Centre. The projects are being managed by experienced staff, with good governance arrangements, quality assurance processes and planning systems in place. New timetables should provide more services and cater for more passengers, including off peak. They should increase network efficiency through better utilisation of capacity, but some passengers may face longer journey times and more may need to change trains mid-journey.  

The planned Rail Operations Centre has the potential to make operational decision-making more customer-focussed, by placing more emphasis on minimising customer delay during disruptions. If implemented well, it will also generate information to help agencies better identify the root cause of incidents that delay trains and improve communication with passengers so they can make better real-time travel decisions.

Predicted passenger growth presents a risk to punctuality after 2019

The rail system will struggle to maintain punctuality much beyond 2019 based on current patronage forecasts and system limitations.

From 2024, the Sydney Metro City and Southwest will help by extending the metro network from Chatswood under Sydney Harbour, through the city and out to Bankstown. Announced fleet upgrades will also help. Transport for NSW advises that it is also working with the Greater Sydney Commission to ensure network capacity constraints are considered in future urban planning.

In addition to investment in new metro networks, sustained and substantial investment needs to be made into the existing heavy rail network to meet demand and ensure its ongoing reliability. Transport for NSW has been developing strategies for this purpose, including an Advanced Train Control system. Its aim is to put a costed plan to the government by the third quarter of this (2017) calendar year. Given the likely lead times involved with major infrastructure projects, there remains a significant risk of poor punctuality after 2019.

Punctuality could be at risk sooner if recent patronage growth continues

If patronage continues to increase at a faster rate than forecast, particularly during the morning peak, the network will struggle to cope before 2019. Transport for NSW forecast that between 2011 and 2026 morning peak rail patronage would increase each year by approximately 3.3 per cent. Between 2011 and 2016 the number of passengers travelling to the city during the morning peak grew by an average of 4.4 per cent each year, including annual growth of 6.6 per cent since May 2014.

A good understanding of patronage levels, trends and drivers is critical to effective planning. The audit identified some shortcomings in measurement of peak passenger loads. Transport for NSW advised that measurement approaches have been improved recently, and this will soon flow into improved data quality.  

Given the increasing flexibility in work practices available to many city workers, the relatively new field of behavioural insights may offer opportunities to ‘nudge’ some passengers away from travelling at the height of the peak with benefits for them and the network.

  1. Transport for NSW should ensure that programs to address rail patronage growth over the next five to ten years are provided to the government for Cabinet consideration as soon as possible.
     
  2. Sydney Trains and Transport for NSW should:
    a) maintain effective oversight and resourcing for all strategies designed to address rail patronage growth
    b) adjust strategies for any patronage growth above projection.
     
  3. Sydney Trains, NSW Trains and Transport for NSW should publish Customer Delay results by June 2018.
     
  4. Transport for NSW, Sydney Trains and NSW Trains should agree by December 2017:
    a) specific performance requirements for intercity train, track and signal availability and reliability
    b) guidelines for train priorities during disruptions and indicators of control centre performance in implementing these guidelines.
     
  5. Sydney Trains, NSW Trains and Transport for NSW should by June 2018:
    a) improve the accuracy of patronage measurement and develop a better understanding of patronage growth trends
    b) address small errors in the adjustment factors used for determining a train’s punctuality status
    c) improve their understanding of the factors impacting on intercity punctuality.
     
  6. Transport for NSW should, commencing June 2017, explore the potential to use behavioural insights to encourage more passengers to travel outside the height of the morning peak (8 am to 9 am).

Published

Actions for Assessing major development applications

Assessing major development applications

Planning
Compliance
Internal controls and governance
Management and administration
Risk
Shared services and collaboration

The Planning Assessment Commission (the Commission) has improved its decision-making processes for major development applications in recent years. The Commission has improved how it consults the public and manages conflicts of interest, and now also publishes records of its meetings with applicants and stakeholders.

The Planning Assessment Commission (the Commission) is an independent body established in 2008 under the Environmental Planning and Assessment Act 1979 (the EP&A Act). It makes decisions on major development applications in New South Wales. Along with the Department of Planning and Environment (the Department) and the Land and Environment Court, it is one of three bodies that have a role in making decisions on these applications.

The Department refers development applications to the Commission where 25 or more objections have been received from the community, a local council objects to the proposal, or the applicant has donated to a political party.

These applications are often complex and controversial, and can attract a high level of public interest. This may mean that, regardless of the process, not all stakeholders are satisfied with the outcome.

The Commission is required to take into account section 79C of the EP&A Act when making decisions. Section 79C includes consideration of the likely environmental, social and economic impacts of the development.

This audit assessed the extent to which the Commission’s decisions on major development applications are made in a consistent and transparent manner. To assist us in making this assessment, we asked whether the Commission:

  • has sound processes in place to help it make decisions on major development applications that are informed and made in a consistent manner
  • ensures its decisions are free from bias and transparent to stakeholders and the public.

Conclusion

Over the last two years, the Commission has improved its decision-making process. It has improved how it consults the public and manages conflicts of interest, and now also publishes records of its meetings with applicants and stakeholders.

However, there are still some vital issues to be addressed to ensure it makes decisions in a consistent and transparent manner. Most importantly, the Commission was not able to show in every decision we reviewed how it met its statutory obligation to consider the matters in section 79C of the EP&A Act.

Despite improved probity measures put in place by the Commission, there is a perception among some stakeholders that it is not independent of the Department. The reasons for some of these concerns are outside of the Commission’s control. For example, the Commission becomes involved after the Department has prepared an assessment report which recommends whether a development should proceed. This creates the perception that the Commission is acting on the recommendation of the Department. The Department’s assessment report should state whether an application meets relevant legislative and policy requirements, but not recommend whether a development should be approved or not.

More can also be done to improve transparency in decision-making and the public’s perception of the independence of Commissioners. The Commission should continue to improve how it communicates the reasons for its decisions and also publish on its website a summary of Commissioners’ conflict of interest declarations for each development application.

Decision-making processes have improved but some key aspects need to be addressed

Although not articulated in one document, there is a framework in place to assist Commissioners make decisions on major development applications. This includes setting out the information to be considered, who to consult, and that a report is to be prepared. The Commission has recently improved how it conducts public meetings and the level of support provided to Commissioners to ensure they understand the decision-making process. The Commissioners we interviewed all showed a good understanding of their role.

As a consent authority, the Commission is required to consider the matters in section 79C of the EP&A Act when making a decision. However, it was not able to show how it met this requirement in every decision we reviewed. We found some evidence of these considerations in six of the nine cases we reviewed, for example in meeting notes or in its report on a decision. Of these six cases, the degree to which the Commission considered all matters under section 79C varied considerably. The larger, more complex applications were more likely to address these considerations. To demonstrate compliance with the EP&A Act, the Commission must be able to show how it considers all matters in section 79C for each decision it makes.

We found that the Commission has access to relevant information to make a decision and consults stakeholders for their views of the development. The level of consultation depends on the size and complexity of an application. If Commissioners decide they need more information to make a decision, they consult local councils, the community, other government agencies and experts as needed.

The Commission’s public meetings are a valuable part of the decision-making process, where new perspectives or issues are often raised. However, some aspects could be improved. For example, many stakeholders thought the five minutes allowed for individual speakers was insufficient. The Commission could be more flexible with this timeframe. Identifying new ways to notify the public of its meetings, other than advertisements on its website and in newspapers, would also ensure it reaches as many interested parties as possible.

Improved transparency and probity but the Commission is not seen by some as impartial

The Commission has sound processes in place to ensure that its decisions are impartial and transparent to the community. It has improved its probity measures over the last two years, following a review by the NSW Ombudsman in 2014. We found that the Commission:

  • has probity policies and procedures which are available on its website
  • has improved its record keeping of some processes, such as meetings with applicants and stakeholders
  • publishes its decision and supporting documentation, such as meeting notes, on its website.

Conflicts of interest are a significant risk for the Commission because they could lead to corruption, abuse of public office, and affect the public’s view of its independence. The Commission manages this risk well. It has a policy in place to address potential, perceived or actual conflicts. Commissioners update their conflicts of interest records annually, and declare any conflicts when the Commission assigns them to a development application. Unlike the Commission’s probity polices, Commissioners’ conflict of interest declarations are not available on its website. Providing a summary of this information on its website when Commissioners are allocated to a development application would further improve transparency around conflicts of interest.

The Commission has been improving how it communicates its decisions to the public. It now produces fact sheets for its decisions on matters that attract a high level of public interest. Its reports on decisions for complex applications also discuss issues raised by the community. However, the level of detail varied in the decisions we reviewed, and it was not always clear how conditions placed on a development would resolve identified issues. Similarly, the reports did not clearly address the matters under section 79C of the EP&A Act. Reporting this would further improve the transparency of its decisions, and clearly demonstrate compliance with the EP&A Act.

While we did not find any issues that would make us question the integrity or independence of Commissioners, there remains a perception among some stakeholders that the Commission is not impartial. Some of these concerns are within the Commission’s control to fix, such as allowing individual speakers at public meetings extra time to discuss their issues, therefore avoiding perceptions of bias.

Other perceptions, such as the Commission being part of the Department and not an independent decision making authority, are outside the Commission’s immediate control. For example, the Commission receives applications at the end of the assessment process, after the Department has prepared an assessment report recommending whether the application should be approved. This means there are effectively two reports on an application; the Department’s assessment report and the Commission’s report on its decision. However, there is only one decision-maker: the Commission. This may cause community confusion about the roles of the Department and the Commission in the decision-making process. Clearer separation of their roles in assessing applications and preparing reports is needed.

To minimise the perception that the Commission is simply ‘rubber stamping’ the Department’s recommendations, assessment reports should not recommend whether or not a project be approved. Instead, they should provide the Department’s views on whether a project meets relevant legislative and policy requirements. The Commission should also be involved earlier in the process, so it can establish key facts and identify relevant issues sooner. It should request that the Department’s assessment report covers matters Commissioners consider particularly important when assessing projects under section 79C. Earlier referral of applications should also help the Commission to plan its work in assessing applications, and may reduce the time taken to reach a decision.

Unless these issues are addressed, stakeholders will continue to believe the Commission does not act in a transparent and impartial manner, which could erode public confidence in the Commission.

The Planning Assessment Commission

The Planning Assessment Commission (the Commission) is a planning authority established in 2008 under the Environmental Planning and Assessment Act 1979 (the EP&A Act). One of its functions is to make decisions on major development applications.

The Commission is independent of the Department of Planning and Environment (the Department) and the Minister for Planning. This means its decisions are not subject to the direction or control of the Department or the Minister.

The Department refers applications for major development to the Commission, including state significant development and infrastructure applications. These projects are generally initiated by the private sector. Applications are referred to the Commission when one or more of the following criteria are met:

  • more than 25 objections are received about the proposal
  • the local council objects to the proposal
  • the applicant has donated $1,000 or more to a political party or member of parliament.

These applications are often controversial and may attract a high level of public interest. Of the 29 development applications the Commission received in 2015–16, almost 40 per cent were in the mining and energy sectors, and another 40 per cent related to urban development.

Section 79C of the EP&A Act outlines the matters the Commission must consider when making decisions about major development applications. These include:

  • any relevant environmental and planning instruments
  • likely environmental, social and economic impacts of the development
  • suitability of the site for the development
  • submissions received about the application
  • the public interest.

In addition to making decisions about major development applications, the Commission also reviews major developments as part of the planning process, and provides independent expert advice to the government on planning and development matters. Since the Commission’s inception, it has provided advice on 76 matters, conducted 39 reviews, and made 444 decisions on development applications.

Process for approving major development applications

The Commission is one of three bodies that have a role in the planning and approval process for major development applications in New South Wales, as seen in Exhibit 1. The other two bodies are the Department of Planning and Environment, and the Land and Environment Court.

The Department determines the outcomes of major development applications. When an application meets one of the criteria listed above, it refers these to the Commission to make the decision. In certain circumstances, the Land and Environment Court hears appeals against decisions made by either the Department or the Commission.

A Memorandum of Understanding between the Commission and the Department sets out timeframes the Commission must meet when making a decision, specifically:

  • two weeks where no stakeholder meetings are required
  • three weeks where stakeholder meetings are required
  • six weeks when a public meeting is required.

The Planning Assessment Commission should:

By July 2017:

  1. improve transparency by publishing on its website a summary of the Commissioners’ conflict of interest declarations for each development application referred to the Commission for determination, and how any conflicts were handled
     
  2. keep better records of how it considers each matter under section 79C of the EP&A Act for all decisions it makes on major development applications
     
  3. improve the public’s involvement in public meetings by:
    1. identifying and implementing additional mechanisms to notify the community of public meetings to ensure as many interested parties are advised as possible
    2. allowing the chair of decision-making panels discretion to extend the time allowed for individual speakers beyond five minutes
  1. continue to improve how it communicates the reasons for its decisions to the public by:
    1. including a summary in its reports of the issues raised during the consultation process and how they were considered by the Commission
    2. clearly outlining in its reports how any conditions placed on a development will address the issues raised
    3. detailing in its reports how section 79C of the EP&A Act has been addressed
    4. issuing fact sheets to accompany its reports for all decisions where public meetings were held
  1. work with the Department of Planning and Environment to:
    1. develop an agreed approach to presenting the Department’s views in its assessment reports on whether the project meets relevant legislative and policy requirements, reflecting the Commission’s status as an independent decision-maker
    2. refer applications to the Commission earlier in the process to ensure the Department’s assessment report covers matters that Commissioners consider important when assessing projects under section 79C of the EP&A Act.

Published

Actions for Implementation of the NSW Government’s program evaluation initiative

Implementation of the NSW Government’s program evaluation initiative

Industry
Justice
Planning
Premier and Cabinet
Treasury
Environment
Financial reporting
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

The NSW Government’s ‘program evaluation initiative’, introduced to assess whether service delivery programs achieve expected outcomes and value for money, is largely ineffective according to a report released today by NSW Auditor-General, Margaret Crawford.

Government services, in areas such as public order and safety, health and education, are delivered by agencies through a variety of programs. In 2016–17, the NSW Government estimates that it will spend over $73 billion on programs to deliver services.

 

Parliamentary reference - Report number #277 - released 3 November 2016

Published

Actions for Franchising of Sydney Ferries Network services

Franchising of Sydney Ferries Network services

Transport
Procurement
Service delivery

Franchising services on the Sydney Ferries Network was justified, and Transport for NSW’s management of the franchise has been largely effective according to a report released today by the NSW Acting Auditor-General, Tony Whitfield.

'Franchising has resulted in cost savings, good service performance, and effective risk transfer from government to the private sector operator', said Mr Whitfield.

 

Parliamentary reference - Report number #265 - released 4 February 2016