The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the management of the One TAFE NSW modernisation program.
In 2016, the Government released 'A Vision for TAFE NSW' which stated that TAFE NSW needed to become more flexible, efficient and competitive. It set out the need to progressively reduce significant cost inefficiencies, including by moving away from separate institutes to a single institute model. TAFE NSW established the One TAFE NSW modernisation program to deliver on that vision.
The Auditor General found that the One TAFE NSW modernisation program did not deliver against its key objectives within planned timeframes. The modernisation program originally aimed to realise $250 million in annual savings from 2018–19. Because of project delays and higher than expected transition costs, TAFE NSW did not meet the original savings target. TAFE NSW has made progress on key elements of the program and anticipates that savings will be realised in coming years.
The report makes two recommendations to improve governance arrangements for delivering on commercial objectives and increasing transparency of non commercial activities.
The report also identifies a series of lessons for future government transformation programs.
TAFE NSW is the public provider of Vocational Education and Training (VET) in New South Wales. In 2018, TAFE NSW enrolled 436,000 students in more than 1,200 courses at around 130 locations across the State.
There have been major policy changes impacting TAFE NSW over the past decade. Under the Smart and Skilled reform, TAFE NSW started to compete with other Registered Training Organisations (RTOs) for a share of the student market.
In 2016, the NSW Government released 'A Vision for TAFE NSW'. The Vision stated that a failure to adapt to market circumstances had left TAFE NSW with unsustainable costs and inefficiencies. To address this, TAFE NSW needed to become more flexible, efficient and competitive. It set out that TAFE NSW must progressively reduce significant cost inefficiencies, including by moving away from a model of separate institutes to a One TAFE NSW model. The NSW Government set TAFE NSW a target to achieve savings through implementing the Vision.
TAFE NSW established the One TAFE NSW modernisation program to deliver on that vision. The program initially aimed to deliver savings of $250 million per year from 2018–19, but this target was reviewed and updated as the program was being delivered.
This audit assessed whether TAFE NSW effectively managed the One TAFE NSW modernisation program to deliver on the NSW Government's vision for TAFE NSW. In making this assessment, the audit examined whether:
- delivery of the program was well planned
- the program was driven by sound governance arrangements
- TAFE NSW is making progress against the intended outcomes of the program.
The audit focused on the effectiveness of planning, governance and reporting arrangements. It examined five projects within the overall modernisation program as case studies.
Conclusion
The One TAFE NSW modernisation program was an ambitious plan to deliver on the NSW Government’s vision for TAFE NSW, while achieving ongoing savings. Several factors contributed to TAFE NSW not effectively managing the program to deliver on planned timeframes and objectives. These factors include unclear expectations of the primary role of TAFE NSW, unrealistic timeframes, undertaking a large number of complex projects concurrently, governance arrangements that were not fit-for-purpose and poor-quality data.
Planning for the modernisation program and its projects was driven by top-down savings targets and pre-determined timeframes. This led to TAFE NSW attempting to deliver a large number of programs concurrently within tight timeframes. Program management capability was underdeveloped at the commencement of the program and this affected the quality of planning for delivery.
There was a lack of clarity around TAFE NSW's primary purpose. Part of the NSW Government's vision for TAFE NSW was for it to be more commercial, competitive and efficient. These objectives were not fully supported by existing legislation. The commercial objectives of the modernisation program conflicted with legislated social objectives for TAFE NSW. TAFE NSW did not have the autonomy to operate like a government-owned business in a market environment. And while TAFE NSW received separate funding to support students facing disadvantage this did not cover the costs of other non-commercial activities undertaken for social purposes, such as delivering uneconomic courses. The role of the TAFE Commission Board was ambiguous during the initial years of the program, which increased reporting requirements and blurred accountabilities for decision-making.
TAFE NSW's Strategic Plan 2016-22 nominated ten key milestones for delivery by January 2019. TAFE NSW has made progress against several important milestones, including that TAFE ‘is a single TAFE NSW brand’ and has 'industry specific TAFE NSW SkillsPoints'. Other key elements have yet to be delivered, including that TAFE NSW achieves 'integrated enterprise-wide business systems'. Because of delays to projects and higher than expected transition costs, TAFE NSW reported that it did not meet the originally targeted $250 million in annual savings for 2018–19 (which was reviewed and updated as the program was being delivered).
Appendix one – Response from agency
Appendix two – About the audit
Appendix three – Performance auditing
© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.
Parliamentary reference - Report number #346 - released 17 December 2020
Actions for Internal controls and governance 2020
Internal controls and governance 2020
The Auditor-General for New South Wales, Margaret Crawford today released her report on the findings and recommendations from the 2019–20 financial audits that relate to internal controls and governance at 40 of the largest agencies in the NSW public sector.
The bushfire and flood emergencies and the COVID‑19 pandemic continue to have a significant impact on the people and public sector of New South Wales. The scale of the government response to these events has been significant. The report focuses on the effectiveness of internal controls and governance processes, including relevant agencies’ response to the emergencies. In particular, the report focuses on:
- financial and information technology controls
- business continuity and disaster recovery planning arrangements
- procurement, including emergency procurement
- delegations that support timely and effective decision-making.
Due to the ongoing impact of COVID‑19 agencies have not yet returned to a business‑as‑usual environment. ‘Agencies will need to assess their response to the recent emergencies and update their business continuity, disaster recovery and other business resilience frameworks to reflect the lessons learnt from these events’ the Auditor-General said.
The report noted that special procurement provisions were put in place to allow agencies to better respond to the COVID-19 pandemic. The Auditor-General recommended agencies update their procurement policies to reflect the current requirements of the NSW Procurement Framework and the emergency procurement requirements.
This report analyses the internal controls and governance of 40 of the largest agencies in the NSW public sector for the year ended 30 June 2020. These 40 agencies constitute an estimated 85 per cent of total expenditure for all NSW public sector agencies.
1. Internal control trends
New, repeat and high risk findings |
Internal control deficiencies increased by 13 per cent compared to last year. This is predominately due to a seven per cent increase in new internal control deficiencies and 24 per cent increase in repeat internal control deficiencies. There were ten high risk findings compared to four last year. The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies. Agencies should:
|
Common findings |
A number of findings remain common across multiple agencies over the last four years, including:
|
2. Information technology controls
IT general controls |
We found deficiencies in information security controls over key financial systems including:
The deficiencies above increase the risk of non-compliance with the NSW Cyber Security Policy, which requires agencies to have processes in place to manage user access, including privileged user access to sensitive information or systems and remove that access once it is not required or employment is terminated. |
3. Business continuity and disaster recovery planning
Assessing risks to business continuity and Scenario testing |
The response to the recent emergencies and the COVID-19 pandemic has encompassed a wide range of activities, including policy setting, on-going service delivery, safety and availability of staff, availability of IT and other systems and financial management. Agencies were required to activate their business continuity plans in response, and with the continued impact of COVID-19 have not yet returned to a business-as-usual environment. Our audits focused on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic. We identified deficiencies in agency business continuity and disaster recovery planning arrangements. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities. Agencies can also improve the content of their BIA. For example, ten per cent of agencies' BIAs did not include recovery time objectives and six per cent of agencies did not identify key IT systems that support critical business functions. Scenario testing improves the effectiveness with which a live crisis is handled, but 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. There were also opportunities to improve the effectiveness of scenario testing exercises by:
Agencies have responded to the recent emergencies but addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required. During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'. |
Responding to disruptions |
We found agencies' governance functions could have been better informed about responses to disruptive incidents that had activated a business continuity or disaster recovery response between 1 January 2019 to 31 December 2019. For instance: in 89 per cent of instances where a business continuity response was activated, a post-incident review had been performed. In 82 per cent of these instances, the outcomes were reported to a relevant governance or executive management committee in 95 per cent of instances where a disaster recovery response was activated, a post incident review had been performed. In 86 per cent of these instances, the outcomes were reported to a relevant governance committee or executive management committee. Examples of recorded incidents included extensive air quality issues and power outages due to bushfires, system and network outages, and infected and hijacked servers. Agencies should assess their response to the recent emergencies and the COVID-19 pandemic and update business continuity, disaster recovery and other business resilience frameworks to incorporate lessons learned. Agencies should report to those charged with governance on the results and planned actions. |
Management review and oversight | Eighty-two per cent and 86 per cent of agencies report to their audit and risk committees (ARC) on their business continuity and disaster recovery planning arrangements, respectively. Only 18 per cent and five per cent of ARCs are briefed on the results of respective scenario testing. Briefing ARCs on the results of scenario testing exercises helps inform their decisions about whether sound and effective business continuity and disaster recovery arrangements have been established. |
4. Procurement, including emergency procurement
Policy framework |
Agency procurement policies did not capture the requirements of several key NSW Procurement Board Directions (the Directions), increasing the risk of non-compliance with the Directions. We noted:
Recommendation: Agencies should review their procurement policies and guidelines to ensure they capture the key requirements of the NSW Government Procurement Policy Framework, including NSW Procurement Board Directions. |
Managing contracts |
Eighty-eight per cent of agencies maintain a central contract register to record all details of contracts above $150,000, which is a requirement of GIPA legislation. Of the agencies that maintained registers, 13 per cent did not capture all contracts and eight per cent did not include all relevant contract details. Sixteen per cent of agencies did not periodically review their contract register. Timely review increases compliance with GIPA legislation, and enhances the effectiveness with which procurement business units monitor contract end dates, contract extensions and commence new procurement. |
Training and support |
Ninety-three per cent of agencies provide training to staff involved in procurement processes, and a further 77 per cent of agencies provide this training on an on-going basis. Of the seven per cent of agencies that had not provided training to staff, we noted gaps in aspects of their procurement activity, including:
Training on procurement activities ensures there is effective management of procurement processes to support operational requirements, and compliance with procurement directions. |
Procurement activities | While agencies had implemented controls for tender activities above $650,000, 43 per cent of unaccredited agencies did not comply with the NSW Procurement Policy Framework because they had not had their procurement endorsed by an accredited agency within the cluster or by NSW Procurement. This endorsement aims to ensure the procurement is properly planned to deliver a value for money outcome before it commences. |
Emergency procurement |
As at 30 June 2020, agencies within the scope of this report reported conducting 32,239 emergency procurements with a total contract value of $316,908,485. Emergency procurement activities included the purchase of COVID-19 cleaning and hygiene supplies. The government, through NSW Procurement released the 'COVID-19 Emergency procurement procedure', which relaxed procurement requirements to allow agencies to make COVID-19 emergency procurements. Our review against the emergency procurement measures found most agencies complied with requirements. For example:
Complying with the procedure helps to ensure government resources are being efficiently, effectively, economically and in accordance with the law. Recommendation: Agency procurement frameworks should be reviewed and updated so they can respond effectively to emergency situations that may arise in the future. This includes:
|
5. Delegations
Instruments of delegation |
We found that agencies have established financial and human resources delegations, but some had not revisited their delegation manuals following the legislative and machinery of government changes. For those agencies impacted by machinery of government changes we noted:
Delegations manuals are not always complete; 16 per cent of agencies had no delegation for writing off bad debts and 26 per cent of agencies had no delegation for writing off capital assets. Recommendation: Agencies should ensure their financial and human resources delegation manuals contain regular set review dates and are updated to reflect the Government Sector Finance Act 2018, machinery of government changes and their current organisational structure and roles and responsibilities. |
Compliance with delegations |
Agencies did not understand or correctly apply the requirements of the Government Sector Finance Act 2018 (GSF Act), resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act. Further detail on this issue will be included in our Auditor-General's Reports to Parliament on Central Agencies, Education, Health and Stronger Communities, which will be tabled throughout December 2020. Recommendation: Agencies should review financial and human resources delegations to ensure they capture all key functions of laws and regulations, and clearly specify the relevant power or function being conferred on the officer. |
6. Status of 2019 recommendations
Progress implementing last year's recommendations |
Recommendations were made last year to improve transparency over reporting on gifts and benefits and improve the visibility management and those charged with governance had over actions taken to address conflicts of interest that may arise. This year, we continue to note:
While we acknowledge the significance of the recent emergencies, which have consumed agency time and resources, we note limited progress has been made implementing these recommendations. Further detail on the status of implementing all recommendations is in Appendix 2. Recommendation: Agencies should re-visit the recommendations made in last year's report on internal controls and governance and action these recommendations. |
Internal controls are processes, policies and procedures that help agencies to:
- operate effectively and efficiently
- produce reliable financial reports
- comply with laws and regulations
- support ethical government.
This chapter outlines the overall trends for agency controls and governance issues, including the number of audit findings, the degree of risk those deficiencies pose to the agency, and a summary of the most common deficiencies we found across agencies. The rest of this report presents this year’s controls and governance findings in more detail.
Section highlights We identified ten high risk findings, compared to four last year with two findings repeated from the previous year. There was an overall increase of 13 per cent in the number of internal control deficiencies compared to last year due to a seven per cent increase in new internal control deficiencies, and a 24 per cent increase in repeat internal control deficiencies. The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies. We identified a number of findings that remain common across multiple agencies over the last four years. Some of these findings related to areas that are fundamental to good internal control environments and effective organisational governance. Examples include:
Policies, procedures and internal controls should be properly designed, be appropriate for the current organisational structure and its business activities, and work effectively. |
This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency controls to manage key financial systems.
Section highlights Government agencies’ financial reporting is heavily reliant on information technology (IT). We continue to see a high number of deficiencies related to IT general controls, particularly those related to user access administration. These controls are key in adequately protecting IT systems from inappropriate access and misuse. IT is also important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our financial audits do not review all agency IT systems. For example, IT systems used to support agency service delivery are generally outside the scope of our financial audit. However, agencies should also consider the relevance of our findings to these systems. Agencies need to continue to focus on assessing the risks of inappropriate access and misuse and the implementation of controls to adequately protect their systems, focussing on the processes in place to grant, remove and monitor user access, particularly privileged user access. |
This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency business continuity and disaster recovery planning arrangements.
Section highlights We identified deficiencies in agency business continuity and disaster recovery planning arrangements and opportunities for agencies to enhance their business continuity management and disaster recovery planning arrangements. This will better prepare them to respond to a disruption to their critical functions, resulting from an emergency or other serious event. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities and 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. Scenario testing improves the effectiveness with which a live crisis is handled. This section focusses on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic. While agencies have responded to the recent emergencies, proactively addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required. During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'. |
This chapter outlines our audit observations, conclusions and recommendations, arising from our review of procurement agency procurement policies and procurement activity.
Section highlights We found agencies have procurement policies in place to manage procurement activity, but the content of these policies was not sufficiently detailed to ensure compliance with NSW Procurement Board Directions (the Directions). The Directions aim to ensure procurement activity achieves value for money and meets the principles of probity and fairness. Agencies have generally implemented controls over their procurement process. In relation to emergency procurement activity, agencies reported conducting 32,239 emergency procurements with a total contract value of $316,908,485 up to 30 June 2020. Our review of emergency procurement activity conducted during 2019–20 identified areas where some agencies did not fully comply with the 'COVID-19 Emergency procurement procedure'. We also found not all agencies are maintaining complete and accurate contract registers. This not only increases the risk of non-compliance with GIPA legislation, but also limits the effectiveness of procurement business units to monitor contract end dates, contract extensions and commence new procurement in a timely manner. We noted instances where agencies renewed or extended contracts without going through a competitive tender process during the year. |
This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency compliance with financial and human resources delegations.
Appendix one – List of 2020 recommendations
Appendix two – Status of 2019 recommendations
Appendix three – Cluster agencies
Copyright notice
© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.
Actions for Integrity of data in the Births, Deaths and Marriages Register
Integrity of data in the Births, Deaths and Marriages Register
This report outlines whether the Department of Customer Service (the department) has effective controls in place to ensure the integrity of data in the Births, Deaths and Marriages Register (the register), and to prevent unauthorised access and misuse.
The audit found that the department has processes in place to ensure that the information entered in the register is accurate and that any changes to it are validated. Although there are controls in place to prevent and detect unauthorised access to, and activity in the register, there were significant gaps in these controls. Addressing these gaps is necessary to ensure the integrity of information in the register.
The Auditor-General made nine recommendations to the department, aimed at strengthening controls to prevent and detect unauthorised access to, and activity in the register. These included increased monitoring of individuals who have access to the register and strengthening security controls around the databases that contain the information in the register.
The NSW Registry of Births Deaths and Marriages is responsible for maintaining registers of births, deaths and marriages in New South Wales as well as registering adoptions, changes of names, changes of sex and relationships. Maintaining the integrity of this information is important as it is used to confirm people’s identity and unauthorised access to it can lead to fraud or identity theft.
The NSW Registry of Births Deaths and Marriages (BD&M) is responsible for maintaining registers of births, deaths and marriages in New South Wales. BD&M is also responsible for registering adoptions, changes of name, changes of sex and relationships. These records are collectively referred to as 'the Register'. The Births, Deaths and Marriages Registration Act 1995 (the BD&M Act) makes the Registrar (the head of BD&M) responsible for maintaining the integrity of the Register and preventing fraud associated with the Register. Maintaining the integrity of the information held in the Register is important as it is used to confirm people's identity. Unauthorised access to, or misuse of the information in the Register can lead to fraud or identity theft. For these reasons it is important that there are sufficient controls in place to protect the information.
BD&M staff access, add to and amend the Register through the LifeLink application. While BD&M is part of the Department of Customer Service, the Department of Communities and Justice (DCJ) manages the databases that contain the Register and sit behind LifeLink and is responsible for the security of these databases.
This audit assessed whether BD&M has effective controls in place to ensure the integrity of data in the Births, Deaths and Marriages Register, and to prevent unauthorised access and misuse. It addressed the following:
- Are relevant process and IT controls in place and effective to ensure the integrity of data in the Register and the authenticity of records and documents?
- Are security controls in place and effective to prevent unauthorised access to, and modification of, data in the Register?
ConclusionBD&M has processes and controls in place to ensure that the information entered in the Register is accurate and that amendments to the Register are validated. BD&M also has controls in place to prevent and detect unauthorised access to, and activity in the Register. However, there are significant gaps in these controls. Addressing these gaps is necessary to ensure the integrity of the information in the Register. BD&M has detailed procedures for all registrations and amendments to the Register, which include processes for entering, assessing and checking the validity and adequacy of source documents. Where BD&M staff have directly input all the data and for amendments to the Register, a second person is required to check all information that has been input before an event can be registered or an amendment can be made. BD&M carries out regular internal audits of all registration processes to check whether procedures are being followed and to address non-compliance where required. BD&M authorises access to the Register and carries out regular access reviews to ensure that users are current and have the appropriate level of access. There are audit trails of all user activity, but BD&M does not routinely monitor these. At the time of the audit, BD&M also did not monitor activity by privileged users who could make unauthorised changes to the Register. Not monitoring this activity created a risk that unauthorised activity in the Register would not be detected. BD&M has no direct oversight of the database environment which houses the Register and relies on DCJ's management of a third-party vendor to provide the assurance it needs over database security. The vendor operates an Information Security Management System that complies with international standards, but neither BD&M nor DCJ has undertaken independent assurance of the effectiveness of the vendor's IT controls. |
Appendix one – Response from agency
Appendix two – About the audit
Appendix three – Performance auditing
Copyright notice
© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.
Parliamentary reference - Report number #330 - released 7 April 2020.
Actions for Internal Controls and Governance 2019
Internal Controls and Governance 2019
This report covers the findings and recommendations from the 2018–19 financial audits that relate to internal controls and governance at 40 of the largest agencies in the NSW public sector. The 40 agencies selected for this report constitute around 84 per cent of total expenditure for all NSW public sector agencies.
The report provides insights into the effectiveness of controls and governance processes across the NSW public sector. It evaluates how agencies identify, mitigate and manage risks related to:
- financial controls
- information technology controls
- gifts and benefits
- internal audit
- contingent labour
- sensitive data.
The Auditor-General recommended that agencies do more to prioritise and address vulnerabilities in their internal controls and governance. The Auditor-General also recommended agencies increase the transparency of their management of gifts and benefits by publishing their registers on their websites.
This report analyses the internal controls and governance of 40 of the largest agencies in the NSW public sector for the year ended 30 June 2019.
1. Internal control trends
New, repeat and high risk findings |
There was an increase in internal control deficiencies of 12 per cent compared to last year. The increase is predominately due to a 100 per cent increase in repeat financial and IT control deficiencies. Some agencies attributed the delay in actioning repeat findings to the diversion of staff from their regular activities to implement and operationalise the recent Machinery of Government changes. As a result, actions to address audit recommendations have been deferred or re prioritised, as the changes are implemented. Agencies need to ensure they are actively managing the risks associated with having these vulnerabilities in internal control systems unaddressed for extended periods of time. |
Common findings |
A number of findings were common to multiple agencies. These findings often related to areas that are fundamental to good internal control environments and effective organisational governance, such as:
|
2. Information technology controls
IT general controls |
We examined information security controls over key financial systems that support the preparation of agency financial statements. We found:
We also found 20 per cent of agencies had deficient IT program change controls, mainly related to segregation of duties in approval and authorisation processes, and user acceptance testing of program changes prior to deployment into production environments. User acceptance testing helps identify potential issues with software incompatibility, operational workflows, absent controls and software issues, as well as areas where training or user support may be required. |
3. Gifts and benefits
Gifts and benefits registers |
All agencies had a gifts and benefits policy and 90 per cent of agencies maintain a gifts and benefits register. However, 51 per cent of the gifts and benefits registers we examined contained incomplete declarations, such as missing details for the approving officer, value of the gift and/or benefit offered and reasons supporting the decision. In some cases, gaps in recorded information meant the basis for decisions around gifts and benefits was not always clear, making it difficult to determine whether decisions in those instances were appropriate, compliant with policy and were not direct or indirect inducements to the recipients to favour suppliers or service providers. Agencies should ensure their gifts and benefits register includes all key fields specified in the Public Service Commission's minimum standards for gifts and benefits. Agencies should also perform regular reviews of the register to ensure completeness and ensure any gift or benefit accepted by a staff member meets the public's expectations for ethical behaviour. |
Managing gifts and benefits |
We found opportunities to improve gifts and benefits processes and enhance transparency. For example, only three per cent of agencies publish their gifts and benefits registers on their websites. Agencies can improve management of gifts and benefits by:
|
Reporting and monitoring |
Only 35 per cent of agencies reported trends in the number and nature of gifts and benefits recorded in their registers to the agency's senior executive management and/or a governance committee. Agencies should regularly report to the agency executive or other governance committee on trends in the offer and acceptance of gifts and benefits. |
4. Internal audit
Obtaining value from the internal audit function |
Agencies have established and maintained internal audit functions to provide assurance on the effectiveness of agency controls and governance systems. However, we identified areas where agencies' internal audit functions could improve their processes to add greater value. For example, only 73 per cent of CAEs regularly attend meetings of the agency board or executive management committee. Internal audit functions can add greater value by involving the CAE more extensively in executive forums as an observer. Internal audit functions should also consider producing an annual report on internal audit. An annual report allows the internal audit function to report on their performance and add value by drawing to the attention of audit and risk committees and senior management strategic issues, thematic trends and emerging risks. |
Role of the Chief Audit Executive |
Forty-five per cent of agencies assigned responsibilities to the Chief Audit Executive (CAE) that were broader than internal audit, but 17 per cent of these had not documented safeguards to protect the independence of the CAE. The reporting lines and status of the CAE at some agencies also needs review. At two agencies, the CAE reported to the CFO. Agencies should ensure:
|
Quality assurance and improvement program |
Thirty-five per cent of agencies did not have a documented quality assurance and improvement program for its internal audit function. The policy and the International Standards for the Professional Practice of Internal Auditing require agencies to have a documented quality assurance and improvement program. The results of this program should be reported annually. Agencies should ensure there is a documented and operational Quality Assurance and Improvement Program for the internal audit function that covers both internal and external assessments. |
5. Managing contingent labour
Obtaining value for money from contingent labour |
According to NSW Procurement data, spend on contingent labour has increased by 75 per cent over the last five years, to $1.5 billion in 2018–19. Improvements in internal processes and a renewed focus on agency monitoring and oversight of contingent labour can help ensure agencies get the best value for money from their contingent workforces. Agencies can improve their management of contingent labour by:
We also found 57 per cent of the 23 agencies we examined with contingent labour spend of more than $5 million in 2018–19 have implemented the government's vendor management system and service provider 'Contractor Central'. |
6. Managing sensitive data
Identifying and assessing sensitive data |
Sixty-eight per cent of agencies maintain an inventory of their sensitive data and where it resides. However, these inventories are not always complete and risks may be overlooked. Agencies can improve processes to manage sensitive data by:
|
Managing data breaches |
Eighty-eight per cent of agencies have established policies to respond to potential data breaches when they are identified and 70 per cent of agencies maintain a register to record key information in relation to identified data breach incidents. Agencies should maintain a data breach register to effectively manage the actions undertaken to contain, evaluate and remediate each data breach. |
This report covers the findings and recommendations from our 2018–19 financial audits that relate to internal controls and governance at 40 of the largest agencies (refer to Appendix three) in the NSW public sector. The 40 agencies selected for this volume constitute around 84 per cent of total expenditure for all NSW public sector agencies.
Although the report includes several agencies that have changed as a result of the Machinery of Government changes that were effective from 1 July 2019, its focus on sector wide issues and insights means that its findings remain relevant to NSW public sector agencies, including newly formed agencies that have assumed the functions of abolished agencies.
This report offers insights into internal controls and governance in the NSW public sector
This is the third report dedicated to internal controls and governance at NSW State Government agencies. The report provides insights into the effectiveness of controls and governance processes in the NSW public sector by:
- highlighting the potential risks posed by weaknesses in controls and governance processes
- helping agencies benchmark the adequacy of their processes against their peers
- focusing on new and emerging risks, and the internal controls and governance processes that might address those risks.
Without strong governance systems and internal controls, agencies increase the risks associated with effectively managing their finances and delivering services to citizens. For example, if they do not have strong information technology controls, sensitive information may be at risk of unauthorised access and misuse.
Areas of specific focus of the report have changed since last year
Last year's report topics included transparency and performance reporting, management of purchasing cards and taxi use, and fraud and corruption control. We are reporting on new topics this year and re-visiting agency management of gifts and benefits, which we first covered in our 2017 report. Re-visiting topics from prior years provides a baseline to show the NSW public sectors’ progress implementing appropriate internal controls and governance processes to mitigate existing, new and emerging risks in the public sector.
Our audits do not review all aspects of internal controls and governance every year. We select a range of measures and report on those that present heightened risks for agencies to mitigate. This year the report focusses on:
- internal control trends
- information technology controls, including access to agency systems
- protecting sensitive information held within agencies
- managing large and diverse workforces (controls around employing and managing contingent workers)
- maintaining an ethical culture (management of gifts and benefits)
- effectiveness of internal audit function and its oversight by Audit and Risk Committees.
The findings in this report should not be used to draw conclusions on the effectiveness of individual agency control environments and governance arrangements. Specific financial reporting, internal controls and audit observations are included in the individual 2019 cluster financial audit reports, which will be tabled in parliament from November to December 2019.
Internal controls are processes, policies and procedures that help agencies to:
- operate effectively and efficiently
- produce reliable financial reports
- comply with laws and regulations
- support ethical government.
This chapter outlines the overall trends for agency controls and governance issues, including the number of audit findings, the degree of risk those deficiencies pose to the agency, and a summary of the most common deficiencies we found across agencies. The rest of this report presents this year’s controls and governance findings in more detail.
Key conclusions and sector wide learnings
- out of date policies or an absence of policies to guide appropriate decisions
- poor record keeping and document retention
- incomplete or inaccurate centralised registers or gaps in these registers.
Policies, procedures and internal controls should be properly designed, be appropriate for the current organisational structure and its business activities, and work effectively.
This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency controls to manage key financial systems.
This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency controls to manage gifts and benefits.
Key conclusions and sector wide learnings
We found most agencies have implemented the Public Service Commission's minimum standards for gifts and benefits. All agencies had a gifts and benefits policy and 90 per cent of agencies maintained a gifts and benefits register and provided some form of training to employees on the treatment of gifts and benefits.
Based on our analysis of agency registers, we found some areas where opportunities existed to make processes more effective. In some cases, gaps in recorded information meant the basis for decisions around gifts and benefits was not always clear, making it difficult to determine whether decisions in those instances were appropriate and compliant with policy. Fifty-one per cent of the gifts and benefits registers reviewed contained declarations where not all fields of information had been completed. Seventy-seven per cent of agencies that maintained a gifts and benefits register did not include all key fields suggested by the minimum standards.
Areas where agencies can improve their management of gifts and benefits include:
- ensuring agency policies comprehensively cover the elements necessary to make it effective in an operational environment, such as identifying risks specific to the agency and actions that will be taken in the event of a policy breach
- establishing and publishing a statement of business ethics on the agency's website to clearly communicate expected behaviours to clients, customers,suppliers and contractors
- updating gifts and benefits registers to include all key fields suggested by the minimum standards, as well as performing regular reviews of the register to ensure completeness
- providing on-going training, awareness activities and support to employees, not just at induction
- regularly reporting gifts and benefits to executive management and/or a governance committee such as the audit and risk committee, focussing on trends in the number and types of gifts and benefits offered to and accepted by agency staff
- publishing their gifts and benefits registers on their websites to demonstrate a commitment to a transparently ethical environment.
This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency internal audit functions.
Key conclusions and sector wide learnings
We found agencies have established and maintained internal audit functions to provide assurance on the effectiveness of agency controls and governance systems as required by TPP15-03 'Internal Audit and Risk Management Policy for the NSW Public Sector'. However, we identified areas where agencies' internal audit functions could improve their processes to add greater value, including:
- documenting and implementing safeguards to address conflicting roles performed by the Chief Audit Executive (CAE)
- ensuring the reporting lines for the CAE comply with the NSW Treasury policy, and the CAE reports neither functionally or administratively to the finance function or other significant recipients of internal audit services
- involving the CAE more extensively in executive forums as an observer
- documenting a Quality Assurance and Improvement Program for the internal audit function and performing both internal and external performance assessments to identify opportunities for continuous improvement
- reporting against key performance indicators or a balanced scorecard and producing an annual report on internal audit to bring to the attention of the audit and risk committee and senior management strategic issues, thematic trends and emerging risks that may require further attention or resources.
This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency controls to on-board, manage and off-board contingent labour.
Key conclusions and sector wide learnings
Agencies have implemented controls to manage contingent labour and most agencies have some level of reporting and oversight of contingent labour at an executive level. However, the increasing trend in spend on contingent labour warrants a renewed focus on agency monitoring and oversight of their use of contingent labour. Over the last five years spend on contingent labour has increased by 75 per cent, to $1.5 billion in 2018–19.
There are also some key gaps that limit the ability of agencies to effectively manage contingent labour. Key areas where agencies can improve their management of contingent labour include:
- preparing workforce plans to inform their resourcing strategy, and confirm prior to engaging contingent labour, that this solution aligns with the strategy and best meets business needs
- involving agency human resources units in decisions about engaging contingent labour
- regularly reporting on contingent labour use to agency executive teams, particularly in terms of trends in agency spend, tenure and compliance with policies and procedures
- strengthening on-boarding and off-boarding processes, including establishing checklists to on-board and off-board contingent labour, making provisions for knowledge transfer, and assessing, documenting and capturing performance information.
This chapter outlines our audit observations, conclusions and recommendations, arising from our review of governance and processes in relation to the management of sensitive data.
Key conclusions and sector wide learnings
Information technology risks are rapidly increasing. More interfaces between agencies and greater connectivity means the amounts of data agencies generate, access, store and share continue to increase. Some of this information is sensitive information, which is protected by the Privacy Act 1988.
It is important that agencies understand what sensitive data they hold, the risks associated with the inadvertent release of this information and how they are mitigating those risks. We found that agencies need to continue to identify and record their sensitive data, as well as expand the methods they use to identify sensitive data. This includes data held in unstructured repositories, such as network shared drives and by agency service providers.
Eighty-eight per cent of agencies have established policies to respond to potential data breaches when they are identified and 70 per cent of agencies maintain a register to record key information in relation to identified data breach incidents.
Key areas where agencies can improve their management of sensitive data include:
- identifying sensitive data, based on a comprehensive and structured process and maintaining an inventory of the data
- assessing the criticality and sensitivity of the data so that the protection of high risk data can be prioritised
- developing comprehensive data breach management policies to ensure data breaches are appropriately managed
- maintaining a data breach incident register to record key information in relation to identified data breaches incidents, including the estimated cost of the breach
- providing on-going training and awareness activities to employees in relation to sensitive data and managing data breaches.
Appendix one – List of 2019 recommendations
Appendix two – Status of 2018 recommendations
Appendix three – In-scope agencies
© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.
Actions for Property Asset Utilisation
Property Asset Utilisation
Property NSW’s effectiveness in managing NSW Government owned and leased commercial office property is limited in three areas according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.
At 30 June 2018, the NSW Government owned $160 billion worth of land and buildings. The NSW Treasury predicts this figure will rise over the coming years. Property NSW manages more than 900 leased office properties across the state. Approximately 250 of these are owned by Property NSW. Other NSW Government agencies maintain ownership and control of properties considered essential for service provision, such as schools, prisons and hospitals. Between 2012–13 and 2017–18 sales of property assets across the whole of the NSW Government have raised $10 billion, of which Property NSW has sold property assets of approximately $2 billion.
In September 2012, the Property Asset Utilisation Taskforce (the Taskforce) released its report on ‘real property asset management across government’ and concluded that the government has accumulated, over time, ‘a real property asset portfolio it cannot afford to maintain or protect’. The Taskforce noted that ‘a lack of centralised information seriously inhibits any whole-of-government strategic asset planning’ and that maintaining under-utilised or unnecessary properties diverted funds from areas where they might be better used. The Taskforce’s key findings included:
- the NSW Government should own property only as a means to deliver or enhance services
- many government properties were under-utilised, poorly maintained and inappropriate to support service delivery.
The Taskforce recommended the creation of Property NSW, as a replacement for the State Property Authority, to improve property asset utilisation and to drive efficiencies in the government’s owned and leased property portfolio. Property NSW was to achieve these goals by:
- collating property information across the whole-of-government
- working with agencies on longer-term strategic real property asset planning to:
- provide services to agencies as customers
- bring a whole-of-government perspective to real property asset planning.
In response to the Taskforce report, in December 2012, the Premier's Memorandum M2012-20 (the Memorandum) established Property NSW to improve the management of the NSW Government's owned and leased real property portfolio.
Under the Memorandum, Property NSW is responsible for:
- management of all leased and owned commercial office accommodation
- acting as the central acquisition and disposal agency
- providing advice to the government on property matters and developing property policy
- conducting regular and ongoing reviews of agencies portfolios, working with agencies to identify efficiencies to improve service delivery, in relation to the review of capital planning1
- maintaining the register of all government owned property.
The Memorandum states that ownership of all commercial office property should be vested in Property NSW.
This audit assessed whether Property NSW is effective in the management of NSW Government owned and leased commercial office property. To do this we assessed whether NSW Government leased commercial office space is being effectively utilised and whether the Government Property Register, a register of all government owned property, is accurate and up-to-date.
In December 2017, Property NSW started working across the NSW Government to help agencies identify real property assets, including commercial office properties, that are under-utilised or surplus and that could be recycled, repurposed, or vested to Property NSW.
1 Capital Planning was previously referred to as Total Asset Management (TAM).
By December 2019, Property NSW should:
- combine the results of property portfolio reviews to produce a whole-of-government picture of the NSW Government property portfolio
- devise a strategy and plan to recycle or repurpose under-utilised properties using a whole-of-government picture of the NSW Government property portfolio
- develop and report on indicators for progress in reducing the number and value of under-utilised properties at the whole-of-government level, referencing progress against an accurate baseline stocktake.
By December 2019, Property NSW should:
4. improve the data held on government owned and leased properties by combining and automating data feeds to construct a single, consolidated and accurate whole-of-government property data set.
By December 2019, Property NSW should:
5. document and communicate to stakeholders how its assessment criteria inform key decisions including agency relocations, lease renewals and rectifying under-utilisation
6. include customer satisfaction measures in its annual reports and reviews, in accordance with the requirements set out in the Premier's Memorandum M2012-20
7. improve record-keeping and compliance with the State Records Act 1998 and the Department of Finance, Services and Innovation Records Management Policy.
Appendix one - Response from agency
Appendix two - Audit Office response
Appendix three - About the audit
Appendix four - Performance auditing
Parliamentary reference - Report number #312 - released 18 December 2018
Actions for Unsolicited proposal process for the lease of Ausgrid
Unsolicited proposal process for the lease of Ausgrid
In October 2016, the NSW Government accepted an unsolicited proposal from IFM Investors and AustralianSuper to lease 50.4 per cent of Ausgrid for 99 years. The deal followed the Federal Government’s rejection of two bids from foreign investors, for national security reasons.
A performance audit of the lease of Ausgrid has found shortcomings in the unsolicited proposal process. Releasing the audit findings today, the Auditor-General for New South Wales, Margaret Crawford said ‘this transaction involved a $20 billion asset owned by the people of New South Wales. As such, it warranted strict adherence to established guidelines’.
Ausgrid is a distributor of electricity to eastern parts of Sydney, the Central Coast, Newcastle and the Hunter Region.
In June 2014, the then government announced its commitment to lease components of the state's electricity network as part of the Rebuilding NSW plan. Implementation of the policy began after the government was re-elected in 2015. Between November 2015 and August 2016, the NSW Government held a competitive tender process to lease 50.4 per cent of Ausgrid for 99 years. The NSW Government abandoned the process on 19 August 2016 after the Australian Treasurer rejected two bids from foreign investors, for national security reasons. That day, the Premier and Treasurer released a media statement clarifying the government's objective to complete the transaction via a competitive process in time to include the proceeds in the 2017–18 budget.
On 31 August 2016, the state received an unsolicited proposal from IFM Investors and AustralianSuper to acquire an interest in Ausgrid under the same terms proposed by the state during the tender process. In October 2016, the government accepted the unsolicited proposal.
This audit examined whether the unsolicited proposal process for the partial long-term lease of Ausgrid was effectively conducted and in compliance with the government’s 2014 Unsolicited Proposals: Guide for Submission and Assessment (Unsolicited Proposals Guide or the Guide).
The audit focused on how the government-appointed Assessment Panel and Proposal Specific Steering Committee assessed key requirements in the Guide that unsolicited proposals must be demonstrably unique and represent value for money.
The evidence available does not conclusively demonstrate the unsolicited proposal was unique, and there were some shortcomings in the negotiation process, documentation and segregation of duties. That said, before the final commitment to proceed with the lease, the state obtained assurance that the proposal delivered value for money.
It is particularly important to demonstrate unsolicited proposals are unique, in order to justify the departure from other transaction processes that offer greater competition, transparency and certainty about value for money.
The Assessment Panel and the Proposal Specific Steering Committee determined the Ausgrid unsolicited proposal was unique, primarily on the basis that the proponent did not require foreign investment approval from the Australian Treasurer, and the lease transaction could be concluded earlier than through a second tender process. However, the evidence that persuaded the Panel and Committee did not demonstrate that no other proponent could conclude the transaction in time to meet the government’s deadline.
It is not appropriate to determine an unsolicited proposal is unique because it delivers an earlier outcome than possible through a tender process. The Panel and Committee did not contend, and it is not evident, that the unsolicited proposal was the only way to meet the government’s transaction deadline.
The evidence does not demonstrate that the proponent was the only party that would not have needed foreign investment approval to participate in the transaction. It also does not demonstrate that the requirement for foreign investment approval would have reduced the pool of foreign buyers to the degree that it would be reasonable to assume none would emerge.
The Panel, Committee and financial advisers determined that the final price represented value for money, and that retendering offered a material risk of a worse financial outcome. However, an acceptable price was revealed early in the negotiation process, and doing so made it highly unlikely that the proponent would offer a higher price than that disclosed. The Department of Premier and Cabinet (DPC) and NSW Treasury were not able to provide a documented reserve price, bargaining strategy or similar which put the negotiations in context. It is not evident that the Panel or Committee authorised, justified or endorsed negotiations in advance.
Key aspects of governance recommended by the Guide were in place. Some shortcomings relating to role segregation, record keeping and probity assurance weakened the effectiveness of the unsolicited proposal process adopted for Ausgrid.
The reasons for accepting that the proposal and proponent were unique are not compelling.
The Unsolicited Proposals Guide says the 'unique benefits of the proposal and the unique ability of the proponent to deliver the proposal' must be demonstrated.
The conclusion reached by the Panel and Committee that the proposal offered a ‘unique ability to deliver (a) strategic outcome’ was primarily based on the proponent not requiring foreign investment approval from the Australian Treasurer, and allowing the government to complete the lease transaction earlier than by going through a second tender process.
It is not appropriate to determine an unsolicited proposal is unique because it delivers an earlier outcome than possible through a tender process. The Panel and Committee did not contend, and it is not evident, that the unsolicited proposal was the only way to meet the government’s transaction deadline.
The evidence does not demonstrate that the proponent was the only party that would not have needed foreign investment approval to participate in the transaction. Nor does it demonstrate that the requirement for foreign investment approval would have reduced the pool of foreign buyers to the degree that it would be reasonable to assume none would emerge.
That said, the Australian Treasurer’s decision to reject the two bids from the previous tender process created uncertainty about the conditions under which he would approve international bids. The financial advisers engaged for the Ausgrid transaction informed the Panel and Committee that:
- it was not likely another viable proponent would emerge soon enough to meet the government’s transaction deadline
- the market would be unlikely to deliver a better result than offered by the proponent
- going to tender presented a material risk of a worse financial result.
The Unsolicited Proposals Guide says that a proposal to directly purchase or acquire a government-owned entity or property will generally not be unique. The Ausgrid unsolicited proposal fell into this category.
Recommendations:
DPC should ensure future Assessment Panels and Steering Committees considering a proposal to acquire a government business or asset:
- recognise that when considering uniqueness they should:
- require very strong evidence to decide that both the proponent and proposal are the only ones of their kind that could meet the government’s objectives
- give thorough consideration to any reasonable counter-arguments against uniqueness.
- rigorously consider all elements of the Unsolicited Proposals Guide when determining whether a proposal should be dealt with as an unsolicited proposal, and document these deliberations and all relevant evidence
- do not use speed of transaction compared to a market process as justification for uniqueness.
The Panel and Committee concluded the price represented value for money, based on peer-reviewed advice from their financial advisers and knowledge acquired from previous tenders. The financial advisers also told the Panel and Committee that there was a material risk the state would receive a lower price than offered by the unsolicited proposal if it immediately proceeded with a second market transaction.
The state commenced negotiations on price earlier than the Guide says they should have. Early disclosure of a price that the state would accept reduced the likelihood of achieving a price greater than this. DPC says the intent of this meeting was to quickly establish whether the proponents could meet the state’s benchmark rather than spending more time and resources on a proposal which had no prospect of proceeding.
DPC and NSW Treasury were not able to provide a documented reserve price, negotiation strategy or similar which put the negotiations and price achieved in context. It was not evident that the Panel or Committee authorised, justified or endorsed negotiations in advance. However, the Panel and Committee endorsed the outcomes of the negotiations.
The negotiations were informed by the range of prices achieved for similar assets and the specific bids for Ausgrid from the earlier market process.
Recommendations:
DPC should ensure any future Assessment Panels and Steering Committees considering a proposal to acquire a government business or asset:
- document a minimum acceptable price, and a negotiating strategy designed to maximise price, before commencing negotiations
- do not communicate an acceptable price to the proponent, before the negotiation stage of the process, and then only as part of a documented bargaining strategy.
The state established a governance structure in accordance with the Unsolicited Proposals Guide, including an Assessment Panel and Proposal Specific Steering Committee. The members of the Panel and Steering Committee were senior and experienced officers, as befitted the size and nature of the unsolicited proposal.
The separation of negotiation, assessment and review envisaged by the Guide was not maintained fully. The Chair of the Assessment Panel and a member of the Steering Committee were involved in negotiations with the proponent.
DPC could not provide comprehensive records of some key interactions with the proponent or a documented negotiation strategy. The absence of such records means the Department cannot demonstrate engagement and negotiation processes were authorised and rigorous.
The probity adviser reported there were no material probity issues with the transaction. The probity adviser also provided audit services. This is not good practice. The same party should not provide both advisory and audit services on the same transaction.
Recommendations:
DPC should ensure any future Assessment Panels and Steering Committees considering a proposal to acquire a government entity or asset:
• maintain separation between negotiation, assessment and review in line with the Unsolicited Proposals Guide
• keep an auditable trail of documentation relating to the negotiation process
• maintain separation between any probity audit services engaged and the probity advisory and reporting services recommended in the current Guide.
Appendix one - Response from agency
Appendix two - NSW Government’s summary of assessment of the Ausgrid unsolicited proposal
Appendix three - The definition and nature of unsolicited proposals
Appendix four - Ausgrid unsolicited proposal process
Appendix five - About the audit
Appendix six - Performance auditing
Parliamentary reference - Report number #309 - released 11 December 2018
Actions for Internal Controls and Governance 2018
Internal Controls and Governance 2018
The Auditor-General for New South Wales Margaret Crawford found that as NSW state government agencies’ digital footprint increases they need to do more to address new and emerging information technology (IT) risks. This is one of the key findings to emerge from the second stand-alone report on internal controls and governance of the 40 largest NSW state government agencies.
This report analyses the internal controls and governance of the 40 largest agencies in the NSW public sector for the year ended 30 June 2018.
This report covers the findings and recommendations from our 2017–18 financial audits that relate to internal controls and governance at the 40 largest agencies (refer to Appendix three) in the NSW public sector.
This report offers insights into internal controls and governance in the NSW public sector
This is our second report dedicated to internal controls and governance at NSW State Government agencies. The report provides insights into the effectiveness of controls and governance processes in the NSW public sector by:
- highlighting the potential risks posed by weaknesses in controls and governance processes
- helping agencies benchmark the adequacy of their processes against their peers
- focusing on new and emerging risks, and the internal controls and governance processes that might address those risks.
Without strong governance systems and internal controls, agencies increase the risks associated with effectively managing their finances and delivering services to citizens. The way agencies deliver services increasingly relies on contracts and partnerships with the private sector. Many of these arrangements deliver front line services, but others provide less visible back office support. For example, an agency may rely on an IT service provider to manage a key system used to provide services to the community. The contract and service level agreements are only truly effective where they are actively managed to reduce risks to continuous quality service delivery, such as interruptions caused by system outages, cyber security attacks and data security breaches.
Our audits do not review all aspects of internal controls and governance every year. We select a range of measures, and report on those that present heightened risks for agencies to mitigate. This report divides these into the following five areas:
- Internal control trends
- Information technology (IT), including IT vendor management
- Transparency and performance reporting
- Management of purchasing cards and taxis
- Fraud and corruption control.
The findings in this report should not be used to draw conclusions on the effectiveness of individual agency control environments and governance arrangements. Specific financial reporting, controls and service delivery comments are included in the individual 2018 cluster financial audit reports, which will be tabled in Parliament from November to December 2018.
The focus of the report has changed since last year
Last year's report topics included asset management, ethics and conduct, and risk management. We are reporting on new topics this year. We plan to introduce new topics and re-visit our previous topics in subsequent reports on a cyclical basis. This will provide a baseline against which to measure the NSW public sectors’ progress in implementing appropriate internal controls and governance processes to mitigate existing, new and emerging risks in the public sector.
Agencies selected for the volume account for 95 per cent of the state's expenditure
While we have covered only 40 agencies in this report, those selected are a large enough group to identify common issues and insights. They represent about 95 per cent of total expenditure for all NSW public sector agencies.
Internal controls are processes, policies and procedures that help agencies to:
- operate effectively and efficiently
- produce reliable financial reports
- comply with laws and regulations
- support ethical government.
This chapter outlines the overall trends for agency controls and governance issues, including the number of findings, level of risk and the most common deficiencies we found across agencies. The rest of this volume presents this year’s controls and governance findings in more detail.
Observation | Conclusions and recommendations |
---|---|
2.1 High risk findings | |
We found six high risk findings (seven in 2016–17), one of which was repeated from both last year and 2015–16. | Recommendation: Agencies should reduce risk by addressing high risk internal control deficiencies as a priority. |
2.2 Common findings | |
We found several internal controls and governance findings common to multiple agencies. | Conclusion: Central agencies or the lead agency in a cluster can play a lead role in helping ensure agency responses to common findings are consistent, timely, efficient and effective. |
2.3 New and repeat findings | |
Although internal control deficiencies decreased over the last four years, this year has seen a 42 per cent increase in internal control deficiencies. | The increase in new IT control deficiencies and repeat IT control deficiencies signifies an emerging risk for agencies. |
IT control deficiencies feature in this increase, having risen by 63 per cent since last year. The number of repeat IT control deficiencies has doubled and is driven by the increasing digital footprint left by agencies as government prioritises on-line interfaces with citizens, and the number of transactions conducted through digital channels increases |
Recommendation: Agencies should reduce IT risks by:
|
Government agencies’ financial reporting is now heavily reliant on information technology (IT). IT is also increasingly important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our audits reviewed whether agencies have effective controls in place to manage both key financial systems and IT service contracts.
Observation | Conclusions and recommendations |
---|---|
3.1 Management of IT vendors | |
Contract management framework Although 87 per cent of agencies have a contract management policy to manage IT vendors, one fifth require review. |
Conclusion: Agencies can more effectively manage IT vendor contracts by developing policies and procedures to ensure vendor management frameworks are kept up to date, plans are in place to manage vendor performance and risk, and compliance with the framework is monitored by:
|
Contract risk management Forty-one per cent of agencies are not using contract management plans and do not assess contract risks. Half of the agencies that did assess contract risks, had not updated the risk assessments since the commencement of the contract. |
Conclusion: Instead of applying a 'set and forget' approach in relation to management of contract risks, agencies should assess risk regularly and develop a plan to actively manage identified risks throughout the contract lifecycle - from negotiation and commencement, to termination. |
Performance management Only 24 per cent of agencies sought assurance about the accuracy of vendor reporting against KPIs, yet sixty-seven per cent of the IT contracts allow agencies to determine performance based payments and/or penalise underperformance. |
Conclusion: Agencies are monitoring IT vendor performance, but could improve outcomes and more effectively manage under-performance by:
|
Transitioning services Where IT vendor contracts do make provision for transitioning-out, only 28 per cent of agencies have developed a transitioning-out plan with their IT vendor. |
Conclusion: Contract transition/phase out clauses and plans can mitigate risks to service disruption, ensure internal controls remain in place, avoid unnecessary costs and reduce the risk of 'vendor lock-in'. |
Contract Registers Eleven out of forty agencies did not have a contract register, or have registers that are not accurate and/or complete. |
Conclusion: A contract register helps to manage an agency’s compliance obligations under the Government Information (Public Access) Act 2009 (the GIPA Act). However, it also helps agencies more effectively manage IT vendors by:
Recommendation: Agencies should ensure their contract registers are complete and accurate so they can more effectively govern contracts and manage compliance obligations. |
3.2 IT general controls | |
Governance Ninety-five per cent of agencies have established policies to manage key IT processes and functions within the agency, with ten per cent of those due for review. |
Conclusion: Regular review of IT policies ensures risks are considered and appropriate strategies and procedures are implemented to manage these risks on a consistent basis. An absence of policies can lead to ad-hoc responses to risks, and failure to consider emerging IT risks and changes to agency IT environments. |
User access administration
|
Recommendation: Agencies should strengthen the administration of user access to prevent inappropriate access to key systems. |
Privileged access Forty per cent of agencies do not periodically review logs of the activities of privileged users to identify suspicious or unauthorised activities. |
Recommendation: Agencies should:
|
Password controls Twenty-three per cent of agencies did not comply with their own policy on password parameters. |
Recommendation: Agencies should ensure IT password settings comply with their password policies. |
Program changes Fifteen per cent of agencies had deficient IT program change controls mainly related to segregation of duties and authorisation and testing of IT program changes prior to deployment. |
Recommendation: Agencies should maintain appropriate segregation of duties in their IT functions and test system changes before they are deployed. |
This chapter outlines our audit observations, conclusions and recommendations from our review of how agencies reported their performance in their 2016–17 annual reports. The Annual Reports (Statutory Bodies) Regulation 2015 and Annual Reports (Departments) Regulation 2015 (annual reports regulation) currently prescribes the minimum requirements for agency annual reports.
Observation | Conclusion or recommendation |
4.1 Reporting on performance | |
Only 57 per cent of agencies linked reporting on performance to their strategic objectives. The use of targets and reporting performance over time was limited and applied inconsistently. |
Conclusion: There is significant disparity in the quality and consistency of how agencies report on their performance in their annual reports. This limits the reliability and transparency of reported performance information. Agencies could improve performance reporting by clearly linking strategic objectives to reported outcomes, and reporting on performance against targets over time. NSW Treasury may need to provide more guidance to agencies to support consistent and high-quality performance reporting in annual reports. |
There is no independent assurance that the performance metrics agencies report in their annual reports are accurate. Prior performance audits have noted issues related to the collection of performance information. For example, our 2016 Report on Red Tape Reduction highlighted inaccuracies in how the dollar-value of red tape reduction had been reported. |
Conclusion: The ability of Parliament and the public to rely on reported information as a relevant and accurate reflection of an agency's performance is limited. The relevance and accuracy of performance information is enhanced when:
|
4.2 Reporting on reports | |
Agency reporting on major projects does not meet the requirements of the annual reports regulation. Forty-seven per cent of agencies did not report on costs to date and estimated completion dates for major works in progress. Of the 47 per cent of agencies that reported on major works, only one agency reported detail about significant cost overruns, delays, amendments, deferments or cancellations. |
NSW Treasury produce an annual report checklist to help agencies comply with their annual report obligations. Recommendation: Agencies should comply with the annual reports regulation and report on all mandatory fields, including significant cost overruns and delays, for their major works in progress. |
The information the annual reports regulation requires agencies to report deals only with major works in progress. There is no requirement to report on completed works. Sixteen of 30 agencies reported some information on completed major works. |
Conclusion: Agencies could improve their transparency if they reported, or were required to report:
|
This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency preventative and detective controls over purchasing card and taxi use for 2017–18.
Observation | Conclusion or recommendation |
5.1 Management of purchasing cards | |
Volume of credit card spend Purchasing card expenditure has increased by 76 per cent over the last four years in response to a government review into the cost savings possible from using purchasing cards for low value, high volume procurement. |
Conclusion: The increasing use of purchasing cards highlights the importance of an effective framework for the use and management of purchasing cards. |
Policy framework We found all agencies that held purchasing cards had a policy in place, but 26 per cent of agencies have not reviewed their purchasing card policy by the scheduled date, or do not have a scheduled revision date stated within their policy. |
Recommendation: Agencies should mitigate the risks associated with increased purchasing card use by ensuring policies and purchasing card frameworks remain current and compliant with the core requirements of TPP 17–09 'Use and Management of NSW Government Purchasing Cards'. |
Preventative controls We found that:
|
Agencies have designed and implemented preventative controls aimed at deterring the potential misuse of purchasing cards. Conclusion: Further opportunities exist for agencies to better control the use of purchasing cards, such as:
|
Detective controls Major reviews, such as data analytics (29 per cent of agencies) and independent spot checks (49 per cent of agencies) are not widely used. |
Agencies have designed and implemented detective controls aimed at identifying potential misuse of purchasing cards. Conclusion: More effective monitoring using purchasing card data can provide better visibility over spending activity and can be used to:
|
5.2 Management of taxis | |
Policy framework Thirteen per cent of agencies have not developed and implemented a policy to manage taxi use. In addition:
|
Conclusion: Agencies can promote savings and provide more options to staff where their taxi use policies:
|
Detective controls All agencies approve taxi expenditure by expense reimbursement, purchasing card and Cabcharge, and have implemented controls around this approval process. However, beyond this there is minimal monitoring and review activity, such as data monitoring, independent spot checks or internal audit reviews. |
Conclusion: Taxi spend at agencies is not significant in terms of its dollar value, but it is significant from a probity perspective. Agencies can better address the probity risk by incorporating taxi use into a broader purchasing card or fraud monitoring program. |
Fraud and corruption control is one of the 17 key elements of our governance lighthouse. Recent reports from ICAC into state agencies and local government councils highlight the need for effective fraud control and ethical frameworks. Effective frameworks can help protect an agency from events that risk serious reputational damage and financial loss.
Our 2016 Fraud Survey found the NSW Government agencies we surveyed reported 1,077 frauds over the three year period to 30 June 2015. For those frauds where an estimate of losses was made, the reported value exceeded $10.0 million. The report also highlighted that the full extent of fraud in the NSW public sector could be higher than reported because:
- unreported frauds in organisations can be almost three times the number of reported frauds
- our 2015 survey did not include all NSW public sector agencies, nor did it include any NSW universities or local councils
- fraud committed by citizens such as fare evasion and fraudulent state tax self-assessments was not within the scope of our 2015 survey
- agencies did not estimate a value for 599 of the 1,077 (56 per cent) reported frauds.
Commissioning and outsourcing of services to the private sector and the advancement of digital technology are changing the fraud and corruption risks agencies face. Fraud risk assessments should be updated regularly and in particular where there are changes in agency business models. NSW Treasury Circular TC18-02 NSW Fraud and Corruption Control Policy now requires agencies develop, implement and maintain a fraud and corruption control framework, effective from 1 July 2018.
Our Fraud Control Improvement Kit provides guidance and practical advice to help organisations implement an effective fraud control framework. The kit is divided into ten attributes. Three key attributes have been assessed below; prevention, detection and notification systems.
This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency fraud and corruption controls for 2017–18.
Observation | Conclusion or recommendation |
6.1 Prevention systems | |
Prevention systems Only 54 per cent of agencies have an employment screening policy and all agencies have IT security policies, but gaps in IT security controls could undermine their policies. |
Conclusion: Most agencies have implemented fraud prevention systems to reduce the risk of fraud. However poor IT security along with other gaps in agency prevention systems, such as employment screening practices heightens the risk of fraud and inappropriate use of data. Agencies can improve their fraud prevention systems by:
|
Twenty-three per cent of agencies were not performing fraud risk assessments and some agency fraud risk assessments may not be as robust as they could be. | Conclusion: Agencies' systems of internal controls may be less effective where new and emerging fraud risks have been overlooked, or known weaknesses have not been rectified. |
6.2 Detection systems | |
Detection systems Several agencies reported they were developing a data monitoring program, but only 38 per cent of agencies had already implemented a program. |
Studies have shown data monitoring, whereby entire populations of transactional data are analysed for indicators of fraudulent activity, is one of the most effective methods of early detection. Early detection decreases the duration a fraud remains undetected thereby limiting the extent of losses. Conclusion: Data monitoring is an effective tool for early detection of fraud and is more effective when informed by a comprehensive fraud risk assessment. |
6.3 Notification systems | |
Notification system All agencies have notification systems for reporting actual or suspected fraud and corruption. Most agencies provide multiple reporting lines, provide training and publicise options for staff to report actual or suspected fraud and corruption. |
Conclusion: Training staff about their obligations and the use of fraud notification systems promotes a fraud-aware culture |
Actions for Members' Additional Entitlements 2017
Members' Additional Entitlements 2017
Actions for Progress and measurement of the Premier's Priorities
Progress and measurement of the Premier's Priorities
The Premier’s Implementation Unit uses a systematic approach to measuring and reporting progress towards the Premier’s Priorities performance targets, but public reporting needed to improve, according to a report released today by the Auditor-General of NSW, Margaret Crawford.
The Premier of New South Wales has established 12 Premier’s Priorities. These are key performance targets for government.
The 12 Premier's Priorities | |
---|---|
|
|
|
|
|
|
|
|
|
|
|
|
Source: Department of Premier and Cabinet, Premier’s Priorities website.
Each Premier’s Priority has a lead agency and minister responsible for achieving the performance target.
The Premier’s Implementation Unit (PIU) was established within the Department of Premier and Cabinet (DPC) in 2015. The PIU is a delivery unit that supports agencies to measure and monitor performance, make progress toward the Premier’s Priorities targets, and report progress to the Premier, key ministers and the public.
This audit assessed how effectively the NSW Government is progressing and reporting on the Premier's Priorities.
The Premier’s Implementation Unit (PIU) is effective in assisting agencies to make progress against the Premier’s Priorities targets. Progress reporting is regular but transparency to the public is weakened by the lack of information about specific measurement limitations and lack of clarity about the relationship of the targets to broader government objectives.The PIU promotes a systematic approach to measuring performance and reporting progress towards the Premier’s Priorities’ performance targets. Public reporting would be improved with additional information about the rationale for choosing specific targets to report on broader government objectives.
The PIU provides a systematic approach to measuring performance and reporting progress towards the Premier's Priorities performance targets. Public reporting would be improved with additional information about the rationale for choosing specific targets to report on broader government objectives. The data used to measure the Premier’s Priorities comes from a variety of government and external datasets, some of which have known limitations. These limitations are not revealed in public reporting, and only some are revealed in progress reported to the Premier and ministers. This limits the transparency of reporting.
The PIU assists agencies to avoid unintended outcomes that can arise from prioritising particular performance measures over other areas of activity. The PIU has adopted a collaborative approach to assisting agencies to analyse performance using data, and helping them work across organisational silos to achieve the Premier’s Priorities targets.
Data used to measure progress for some of the Premier’s Priorities has limitations which are not made clear when progress is reported. This reduces transparency about the reported progress. Public reporting would also be improved with additional information about the relationship between specific performance measures and broader government objectives.
The PIU is responsible for reporting progress to the Premier, key ministers and the public. Agencies provide performance data and some play a role in preparing progress reports for the Premier and ministers. For 11 of the Premier's Priorities, progress is reported against measurable and time-related performance targets. For the infrastructure priority, progress is reported against project milestones.
Progress of some Priorities is measured using data that has known limitations, which should be noted wherever progress is reported. For example, the data used to report on housing completions does not take housing demolitions into account, and is therefore overstating the contribution of this performance measure to housing supply. This known limitation is not explained in progress reports or on the public website.
Data used to measure progress is sourced from a mix of government and external datasets. Updated progress data for most Premier’s Priorities is published on the Premier’s Priorities website annually, although reported to the Premier and key ministers more frequently. The PIU reviews the data and validates it through fieldwork with front line agencies. The PIU also assists agencies to avoid unintended outcomes that can arise from prioritising single performance measures. Most, but not all, agencies use additional indicators to check for misuse of data or perverse outcomes.
We examined the reporting processes and controls for five of the Premier’s Priorities. We found that there is insufficient assurance over the accuracy of the data on housing approvals.
The relationships between performance measures and broader government objectives is not always clearly explained on the Premier’s Priority website, which is the key source of public information about the Premier’s Priorities. For example, the Premier’s Priority to reduce litter volumes is communicated as “Keeping our Environment Clean.” While the website explains why reducing litter is important, it does not clearly explain why that particular target has been chosen to measure progress in keeping the environment clean.
By December 2018, the Department of Premier and Cabinet should:
- improve transparency of public reporting by:
- providing information about limitations of reported data and associated performance
- clarifying the relationship between the Premier’s Priorities performance targets and broader government objectives.
- ensure that processes to check and verify data are in place for all agency data sources
- encourage agencies to develop and implement additional supporting indicators for all Premier’s Priority performance measures to prevent and detect unintended consequences or misuse of data.
The Premier's Implementation Unit is effective in supporting agencies to deliver progress towards the Premier’s Priority targets.
The PIU promotes a systematic approach to monitoring and reporting progress against a target, based on a methodology used in delivery units elsewhere in the world. The PIU undertakes internal self-evaluation, and commissions regular reviews of methodology implementation from the consultancy that owns the methodology and helped to establish the PIU. However, the unit lacks periodic independent reviews of their overall effectiveness. The PIU has adopted a collaborative approach and assists agencies to analyse performance using data, and work across organisational silos to achieve the Premier’s Priorities targets.
Agency representatives recognise the benefits of being responsible for a Premier's Priority and speak of the value of being held to account and having the attention of the Premier and senior ministers.
By June 2019, the Department of Premier and Cabinet should:
- establish routine collection of feedback about PIU performance including:
- independent assurance of PIU performance
- opportunity for agencies to provide confidential feedback.
Appendix one: Response from agency
Appendix three: About the audit
Appendix four: Performance auditing
Parliamentary reference - Report number #307 - released 13 September 2018
Actions for Regional Assistance Programs
Regional Assistance Programs
Infrastructure NSW effectively manages how grant applications for regional assistance programs are assessed and recommended for funding. Its contract management processes are also effective. However, we are unable to conclude whether the objectives of these programs have been achieved as the relevant agencies have not yet measured their benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.
In 2011, the NSW Government established Restart NSW to fund new infrastructure with the proceeds from the sale and lease of government assets. From 2011 to 2017, the NSW Government allocated $1.7 billion from the fund for infrastructure in regional areas, with an additional commitment of $1.3 billion to be allocated by 2021. The NSW Government allocates these funds through regional assistance programs such as Resources for Regions and Fixing Country Roads. NSW councils are the primary recipients of funding provided under these programs.
The NSW Government announced the Resources for Regions program in 2012 with the aim of addressing infrastructure constraints in mining affected communities. Infrastructure NSW administers the program, with support from the Department of Premier and Cabinet.
The NSW Government announced the Fixing Country Roads program in 2014 with the aim of building more efficient road freight networks. Transport for NSW and Infrastructure NSW jointly administer this program, which funds local councils to deliver projects that help connect local and regional roads to state highways and freight hubs.
This audit assessed whether these two programs (Resources for Regions and Fixing Country Roads) were being effectively managed and achieved their objectives. In making this assessment, we answered the following questions:
- How well are the relevant agencies managing the assessment and recommendation process?
- How do the relevant agencies ensure that funded projects are being delivered?
- Do the funded projects meet program and project objectives?
The audit focussed on four rounds of Resources for Regions funding between 2013–14 to 2015–16, as well as the first two rounds of Fixing Country Roads funding in 2014–15 and 2015–16.
The project selection criteria are consistent with the program objectives set by the NSW Government, and the RIAP applied the criteria consistently. Probity and record keeping practices did not fully comply with the probity plans.
The assessment methodology designed by Infrastructure NSW is consistent with2 the program objectives and criteria. In the rounds that we reviewed, all funded projects met the assessment criteria.
Infrastructure NSW developed probity plans for both programs which provided guidance on the record keeping required to maintain an audit trail, including the use of conflict of interest registers. Infrastructure NSW and Transport for NSW did not fully comply with these requirements. The relevant agencies have taken steps to address this in the current funding rounds for both programs.
NSW Procurement Board Directions require agencies to ensure that they do not engage a probity advisor that is engaged elsewhere in the agency. Infrastructure NSW has not fully complied with this requirement. A conflict of interest arose when Infrastructure NSW engaged the same consultancy to act as its internal auditor and probity advisor.
While these infringements of probity arrangements are unlikely to have had a major impact on the assessment process, they weaken the transparency and accountability of the process.
Some councils have identified resourcing and capability issues which impact on their ability to participate in the application process. For both programs, the relevant agencies conducted briefings and webinars with applicants to provide advice on the objectives of the programs and how to improve the quality of their applications. Additionally, Transport for NSW and the Department of Premier and Cabinet have developed tools to assist councils to demonstrate the economic impact of their applications.
The relevant agencies provided feedback on unsuccessful applications to councils. Councils reported that the quality of this feedback has improved over time.
Recommendations
- By June 2018, Infrastructure NSW should:
- ensure probity reports address whether all elements of the probity plan have been effectively implemented.
- By June 2018, Infrastructure NSW and Transport for NSW should:
- maintain and store all documentation regarding assessment and probity matters according to the State Records Act 1998, the NSW Standard on Records Management and the relevant probity plans
Infrastructure NSW is responsible for overseeing and monitoring projects funded under Resources for Regions and Fixing Country Roads. Infrastructure NSW effectively manages projects to keep them on track, however it could do more to assure itself that all recipients have complied with funding deeds. Benefits and outcomes should also start to be measured and reported as soon as practicable after projects are completed to inform assessment of future projects.
Infrastructure NSW identifies projects experiencing unreasonable delays or higher than expected expenses as 'at‑risk'. After Infrastructure NSW identifies a project as 'at‑risk', it puts in place processes to resolve issues to bring them back on track. Infrastructure NSW, working with Public Works Advisory regional offices, employs a risk‑based approach to validate payment claims, however this process should be strengthened. Infrastructure NSW would get better assurance by also conducting annual audits of compliance with the funding deed for a random sample of projects.
Infrastructure NSW collects project completion reports for all Resources for Regions and Fixing Country Roads funded projects. It applies the Infrastructure Investor Assurance Framework to Resources for Regions and Fixing Country Roads at a program level. This means that each round of funding (under both programs) is treated as a distinct program for the purposes of benefits realisation. It plans to assess whether benefits have been realised once each project in a funding round is completed. As a result, no benefits realisation assessment has been done for any project funded under either Resources for Regions or Fixing Country Roads. Without project‑level benefits realisation, future decisions are not informed by the lessons from previous investments.
Recommendations
- By December 2018, Infrastructure NSW should:
- conduct annual audits of compliance with the funding deed for a random sample of projects funded under Resources for Regions and Fixing Country Roads
- publish the circumstances under which unspent funds can be allocated to changes in project scope
- measure benefits delivered by projects that were completed before December 2017
- implement an annual process to measure benefits for projects completed after December 2017
- By December 2018, Transport for NSW and Infrastructure NSW should:
- incorporate a benefits realisation framework as part of the detailed application.
Appendix one - Response from agencies
Appendix two - Maps of funded projects
Appendix three - About the audit
Appendix four - Performance auditing
Parliamentary reference - Report number #300 - released 17 May 2018