Refine search Expand filter

Reports

Published

Actions for CBD and South East Light Rail Project

CBD and South East Light Rail Project

Transport
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford.

Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case.

 

Parliamentary reference - Report number #278 - released 30 November 2016

Published

Actions for Franchising of Sydney Ferries Network services

Franchising of Sydney Ferries Network services

Transport
Procurement
Service delivery

Franchising services on the Sydney Ferries Network was justified, and Transport for NSW’s management of the franchise has been largely effective according to a report released today by the NSW Acting Auditor-General, Tony Whitfield.

'Franchising has resulted in cost savings, good service performance, and effective risk transfer from government to the private sector operator', said Mr Whitfield.

 

Parliamentary reference - Report number #265 - released 4 February 2016

Published

Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.

The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.

This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.

 

Parliamentary reference - Report number #247 - released 18 December 2014

Published

Actions for Review of Eastern Distributor

Review of Eastern Distributor

Transport
Infrastructure
Procurement
Project management

Following a resolution of the Legislative Council, the Audit Office has undertaken a performance audit of the Eastern Distributor. For a number of reasons, The Audit Office is not in the position to determine “whether the proposed toll and concession period represents the best deal”. In part this is the result of time constraints which do not allow a careful analysis of many toll and concession options. Similarly, the audit does not answer “whether the current proposal represents the best environmental outcome”. But each of these issues (toll and concession and environmental consequences) is discussed in the audit report.

The Audit Office recommends that the Roads and Traffic Authority (RTA), for any further major project of this type, ensures that it establishes a process which allows all decision makers to have a thorough understanding of the reasonableness of the proponents’ offers and their implications for the State and for the public. The Audit Office also recommends that the RTA should at the outset consult with TCorp in respect of each major project put to tender.

 

Parliamentary reference - Report number #42 - released 31 July 1997