Actions for CBD and South East Light Rail Project

CBD and South East Light Rail Project

Transport
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford.

Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case.

 

Parliamentary reference - Report number #278 - released 30 November 2016

Published

Actions for Red tape reduction

Red tape reduction

Premier and Cabinet
Finance
Financial reporting
Internal controls and governance
Management and administration
Project management
Regulation
Shared services and collaboration

Overall, NSW Government initiatives and processes to prevent and reduce red tape were not effective, according to a report released today by the NSW Auditor-General.

In 2015, the Government reported that its red tape reduction initiatives, implemented between 2011 and 2015, had resulted in $896 million in savings. While these initiatives resulted in some savings, the total value of savings is unknown because estimates for some initiatives were based on unverified assumptions, cost transfers or unrealised projections.

 

Parliamentary reference - Report number #272 - released 25 August 2016

Published

Actions for Early childhood education

Early childhood education

Education
Compliance
Information technology
Management and administration
Project management
Regulation
Risk
Service delivery
Workforce and capability

Enrolments in quality early childhood education programs in New South Wales are increasing but are below the national benchmark, according to a report released today by the NSW Auditor-General, Margaret Crawford.

Ninety-five per cent of children should be enrolled in at least 600 hours in the year before school, but according to the latest NSW figures 77 per cent of children were enrolled in quality early childhood education programs. This 2015 figure is below the benchmark, but is a significant improvement on 2013 when 59 per cent were enrolled.

 

Parliamentary reference - Report number #271 - released 26 May 2016

Published

Actions for Realising the benefits of the Service NSW initiative

Realising the benefits of the Service NSW initiative

Whole of Government
Information technology
Internal controls and governance
Management and administration
Project management
Service delivery
Shared services and collaboration

The current benefits realisation approach for Service NSW needs to improve so benefits and savings can be effectively measured, reported and realised, according to a report released today by the NSW Acting Auditor-General, Tony Whitfield.

Customers are finding that Service NSW provides a convenient and practical way to access all government transaction services.

 

Parliamentary reference - Report number #266 - released 17 February 2016

Published

Actions for Lease to Fox Studios Australia

Lease to Fox Studios Australia

Premier and Cabinet
Asset valuation
Infrastructure
Management and administration
Procurement
Project management

The audit found that the process for the lease and development of the Showground site commenced on the basis that no Government moneys would be provided and no theme park activities would be allowed. However despite this a State Government subsidy of between $84.8m and $106.8m (in net present value terms) is to be provided for the development and the area of the Showground to be leased to Fox was extended to comprise 24.3 hectares of the 28.8 hectare site to allow Fox also to develop a family entertainment park.

The audit also found that the process commenced under the former Government were intended to ensure that no one party was placed above another however, the actual processes employed up to the General Election in March 1995 were so flawed as not to be relied upon to select a preferred proponent or to justify dispensing with a tender process.

 

Parliamentary reference - Report number #44 - released 8 December 1997

Published

Actions for Review of Eastern Distributor

Review of Eastern Distributor

Transport
Infrastructure
Procurement
Project management

Following a resolution of the Legislative Council, the Audit Office has undertaken a performance audit of the Eastern Distributor. For a number of reasons, The Audit Office is not in the position to determine “whether the proposed toll and concession period represents the best deal”. In part this is the result of time constraints which do not allow a careful analysis of many toll and concession options. Similarly, the audit does not answer “whether the current proposal represents the best environmental outcome”. But each of these issues (toll and concession and environmental consequences) is discussed in the audit report.

The Audit Office recommends that the Roads and Traffic Authority (RTA), for any further major project of this type, ensures that it establishes a process which allows all decision makers to have a thorough understanding of the reasonableness of the proponents’ offers and their implications for the State and for the public. The Audit Office also recommends that the RTA should at the outset consult with TCorp in respect of each major project put to tender.

 

Parliamentary reference - Report number #42 - released 31 July 1997

Published

Actions for Review of NSW Agriculture

Review of NSW Agriculture

Industry
Asset valuation
Infrastructure
Internal controls and governance
Management and administration
Workforce and capability

Following a request from the NSW Legislative Council in September 1996, a performance audit into various matters affecting the operation of the New South Wales Department of Agriculture was undertaken by The Audit Office.

Among the recommendations from this report, the Audit Office found that:

  • An economic appraisal should be undertaken before all major developments, including rationalisation plans, are implemented. It should include details of anticipated benefits from the changes planned, so that their achievement can be evaluated after implementation.

  • Government policies should be made explicit or else established by directives in writing. Planning Infrastructure and human resources should be planned to maximise efficiency and effectiveness. If Government chooses alternatives that have higher costs or lower benefits for the Department, then these should be explicitly funded.

  • The Department should strengthen its system of internal control by strengthening the role of the Board of Management as a means of management control, directing an overhaul of the Charter of the Internal Audit Committee and using it to drive the Department’s internal audit function and ensuring implementation of an effective financial management information system.

 

Parliamentary reference - Report number #36 - released 27 March 1997