Published

Actions for Volume Eleven 2012 focusing on Health

Volume Eleven 2012 focusing on Health

Health
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

One in three ambulance crews were delayed for longer than 30 minutes at hospital. Over the year these delays totalled 84,680 hours of lost time, up from 78,224 last year and 58,399 the year before. The longer ambulance crews are at hospitals the less time they are available to respond to the next emergency.

Published

Actions for Volume Eight 2012 focusing on Transport and Ports

Volume Eight 2012 focusing on Transport and Ports

Transport
Industry
Compliance
Financial reporting
Fraud
Information technology
Infrastructure
Management and administration
Procurement
Project management
Regulation
Risk
Workforce and capability

We issued unqualified audit opinions on the transport entities’ 30 June 2012 financial statements. Some of the findings of the report include: government funding to the public transport operators totalled $4.4 billion in 2011-12 ($3.7 billion in 2010-11) passenger services revenue only covered 20 per cent of RailCorp's operating costs Transport for NSW has formalised a protocol to mitigate the risk of potential conflicts of interests A

Published

Actions for Volume Seven 2012 focusing on Law, Order and Emergency Services

Volume Seven 2012 focusing on Law, Order and Emergency Services

Justice
Compliance
Fraud
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

Since the Victims’ Compensation Scheme started in 1989, $1.6 billion has been paid to victims of crime, but only $57.4 million or nearly four per cent has been recovered from convicted offenders. The remaining 96 per cent has been funded by the taxpayer.

Published

Actions for Volume Two 2012 focusing on Universities

Volume Two 2012 focusing on Universities

Universities
Financial reporting
Fraud
Management and administration
Regulation
Workforce and capability

The Members tested substantially complied with the requirements of the Parliamentary Remuneration Tribunal’s (PRT) Determination for the year ended 30 June 2011. Findings note that the Department of Parliamentary Services should remind Members that they should not approve additional temporary staff claim forms before staff have worked the hours.

Published

Actions for Volume One 2012 focusing on themes from 2011

Volume One 2012 focusing on themes from 2011

Health
Industry
Premier and Cabinet
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Shared services and collaboration

The following overview of audits from 2011 found agency restructures significantly impacted agency financial reporting processes, agencies are having difficulty establishing and enforcing compliance with their own policies and procedures, agencies experienced problems complying with regulations and providing adequate documentation to support their financial statements, the poor quality of some financial statements with 1,256 misstatements identified, 540

Published

Actions for Liverpool to Parramatta Bus Transitway

Liverpool to Parramatta Bus Transitway

Transport
Treasury
Infrastructure
Management and administration
Project management
Service delivery

Several of my recent audits have identified a need to improve our public transport system – both for the benefit of travellers and to assist in achieving better air quality. Bus Transitways can provide a good public transport solution for lower density population areas, potentially at a relatively low capital cost. This audit examines the transitway running between Liverpool and Parramatta, the first of several planned for Sydney. This audit should cont

Published

Actions for Implementing Asset Management Reforms

Implementing Asset Management Reforms

Justice
Planning
Finance
Treasury
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Project management

Hospitals, schools, public housing, roads, bridges, buses and trains are just some of the assets used by government in providing services to citizens. The NSW Government’s asset base is impressive in size - with a value of around $167 billion and with government plans to spend around $8 billion acquiring or replacing assets in the current year. Another $2 billion is spent each year on maintenance. Good asset management is very important to government;

Published

Actions for Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Project management
Service delivery
Workforce and capability

Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits. This gives Parliament and the public an update on the extent of progress made. In this follow-up audit, we examine changes following our May 2002 report on how well the: State Transit Authority maintained its buses Ministry of Transport administered contracts for the provision of regular passenger bus services.   Parliament

Published

Actions for Planning for Sydney's Water Needs

Planning for Sydney's Water Needs

Planning
Environment
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

Reliably supplying water to our State’s principal city, Sydney, is a major responsibility for the Government. The community has been made keenly aware in recent years that inflows have been decreasing, and that Sydney has been using more water than is available. In April 2005 the water in Sydney’s storages dropped to 41.5 per cent of their capacity – the lowest level since the construction of Warragamba dam in 1960. As Sydney continues to develop, it i

Published

Actions for Fraud Control: Current Progress and Future Directions

Fraud Control: Current Progress and Future Directions

Whole of Government
Compliance
Fraud
Management and administration
Regulation
Risk

Periodically we review the extent to which agencies have implemented the recommendations they accept from our earlier audits. This gives Parliament and the public an update on the extent of progress made. Given the size of the NSW public sector, the potential for fraud could run into billions of dollars if not properly managed. It is an area of risk that warrants close and ongoing attention. Over the last decade, we have responded by issuing three perfo