Actions for Volume Thirteen 2015 Electricity
Volume Thirteen 2015 Electricity
The NSW Government continues to divest its interest in electricity businesses.
In 2014-15, Macquarie Generation and Delta Electricity’s Colongra power stations were sold, collectively raising over $1.7 billion in gross proceeds.
In November 2015, the NSW Government announced the lease of TransGrid for 99 years to a private sector consortium for $10.3 billion and the sale of Delta Electricity’s Vales Point power station for $1.0 million. It expects to lease 50.4 percent of Ausgrid and Endeavour Energy during 2016, but retain 100 percent ownership of Essential Energy.
Its net investment in the electricity businesses at 30 June 2015 was $10.8 billion ($11.4 billion at 30 June 2014). This comprised $14.0 million in the electricity generators, $2.1 billion in TransGrid and $8.7 billion in the distributors.
Actions for Volume Twelve 2015 Part One Trade & Investment and TAFE
Volume Twelve 2015 Part One Trade & Investment and TAFE
Serious system limitations prevented TAFE NSW from providing sufficient and appropriate evidence to support recorded student revenue of $477 million, student receivables and accrued income of $47.6 million and unearned revenue of $398 million.
These limitations resulted in:
- a qualified audit opinion being issued for TAFE NSW;
- delays in enrolling students;
- inability to fully reconcile cash balances;
- difficulties in reconciling student enrolments with revenues recorded in the financial statements;
- large volumes of manual processing.
Actions for Volume Twelve 2015 Part Two Water
Volume Twelve 2015 Part Two Water
The distributions to the NSW Government increased from $690 million in 2013-14 to $1.0 billion in 2014-15. The increase was largely due to a higher dividend from Sydney Water Corporation.
Actions for Volume Nine 2015 Planning and Environment
Volume Nine 2015 Planning and Environment
The NSW Environment Protection Authority has reduced the average time to assess contaminated sites from 203 days in 2013-14 to 73 days in 2014-15. It is also improving transparency by making more information on its performance publicly available.
In 2014-15, the Department of Planning and Environment increased new housing approvals across New South Wales by 12 per cent to 58,252, exceeding the State priority target of 50,000. It also reduced the time taken to assess major projects from about three years in 2013-14 to four months in 2014-15.
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.
Parliamentary reference - Report number #252 - released 7 May 2015
Actions for Country towns water supply and sewerage program
Country towns water supply and sewerage program
The Country Towns Water Supply and Sewerage Program has effectively promoted adoption of better management practices by local water utilities, but will not achieve its objective of eliminating the water supply and sewerage infrastructure backlog in urban areas of country NSW.
The $1.2 billion Program aims to help local water utilities provide appropriate, affordable, cost effective and well-managed water supply and sewerage services in the urban areas of country NSW. It has two broad elements:
- promoting adoption of better practices
- providing financial assistance towards the capital cost of infrastructure backlog works.
Parliamentary reference - Report number #251 - released 4 May 2015
Actions for Areas of focus from 2014
Areas of focus from 2014
Actions for Security of critical IT infrastructure
Security of critical IT infrastructure
Roads and Maritime Services and Transport for NSW have deployed many controls to protect traffic management systems but these would have been only partially effective in detecting and preventing incidents and unlikely to support a timely response. There was a potential for unauthorised access to sensitive information and systems that could have disrupted traffic.
Until Roads and Maritime Services’ IT disaster recovery site is fully commissioned, a disaster involving the main data centre is likely to lead to higher congestion in the short-term as traffic controllers would be operating on a regional basis without the benefit of the Traffic Management Centre.
Parliamentary reference - Report number #248 - released 21 January 2015
Actions for Volume Nine 2010 focus on Transport, Planning and Industry
Volume Nine 2010 focus on Transport, Planning and Industry
The report includes comments on his financial audits of NSW Government transport, planning and industry agencies for 2009-10. A key recommendation from the report is that the New South Wales Government identify lessons learnt from the metro experience and ensure that future decision processes are developed to ensure the State never again expends such a large amount of scarce transport funding dollars and valuable time on a project that does not proceed.
Actions for Volume Seven 2010 focus on Environment, Climate Change and Water
Volume Seven 2010 focus on Environment, Climate Change and Water
The report includes comments on his financial audits of NSW Government environment, climate change and water agencies. The audits of these agencies’ financial reports for the year ended 30 June 2010 resulted in one qualified Independent Auditor’s Report. Sydney Water has not recognised assets and liabilities of the Build-Own-Operate schemes in their statement of financial position. The combined profit after tax of the four largest water utilities increased substantially from $300 million in 2008-09 to $584 million in 2009-10. Distributions to the Government were $379 million up 17 per cent or $55 million from last year.