Actions for Industry, Skills, Electricity and Water 2016

Industry, Skills, Electricity and Water 2016

Industry
Asset valuation
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management

The Auditor-General, Margaret Crawford released a report today highlighting a decline in net profits of electricity agencies and the distributions the government received from these agencies. The report also details continuing issues in the management of Crown Land and TAFE NSW's student administration system.

Published

Actions for Planning and Environment 2016

Planning and Environment 2016

Planning
Environment
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Project management

Auditor-General, Margaret Crawford released a report on the planning and environment cluster today, concluding that the quality of financial reporting is improving. However, the cluster can improve its financial controls and governance framework.

Published

Actions for Finance, Services and Innovation 2016

Finance, Services and Innovation 2016

Finance
Asset valuation
Financial reporting
Information technology
Internal controls and governance
Project management
Risk

This report analyses the results of the financial statement audits of the Finance, Services and Innovation cluster entities for the year ended 30 June 2016.

Published

Actions for Red tape reduction

Red tape reduction

Premier and Cabinet
Finance
Financial reporting
Internal controls and governance
Management and administration
Project management
Regulation
Shared services and collaboration

Overall, NSW Government initiatives and processes to prevent and reduce red tape were not effective, according to a report released today by the NSW Auditor-General.

In 2015, the Government reported that its red tape reduction initiatives, implemented between 2011 and 2015, had resulted in $896 million in savings. While these initiatives resulted in some savings, the total value of savings is unknown because estimates for some initiatives were based on unverified assumptions, cost transfers or unrealised projections.

 

Parliamentary reference - Report number #272 - released 25 August 2016

Published

Actions for Government assistance to industry

Government assistance to industry

Industry
Management and administration
Project management

Governments provide assistance to industry for a number of reasons, including facilitating economic growth, increase employment, support regional development, or grow priority industries.
 
This audit examined seven programs administered by the former Department of Trade and Investment, Regional Infrastructure and Services that provide at least $2 million per year in grants and subsidies to industry. This included the State Investment Attraction Scheme and Regional Industries Investment Fund.

 

Parliamentary reference - Report number #262 - released 17 December 2015

Published

Actions for Volume Thirteen 2015 Electricity

Volume Thirteen 2015 Electricity

Planning
Information technology
Internal controls and governance
Project management
Risk

The NSW Government continues to divest its interest in electricity businesses.
 
In 2014-15, Macquarie Generation and Delta Electricity’s Colongra power stations were sold, collectively raising over $1.7 billion in gross proceeds.
 
In November 2015, the NSW Government announced the lease of TransGrid for 99 years to a private sector consortium for $10.3 billion and the sale of Delta Electricity’s Vales Point power station for $1.0 million. It expects to lease 50.4 percent of Ausgrid and Endeavour Energy during 2016, but retain 100 percent ownership of Essential Energy.
 
Its net investment in the electricity businesses at 30 June 2015 was $10.8 billion ($11.4 billion at 30 June 2014). This comprised $14.0 million in the electricity generators, $2.1 billion in TransGrid and $8.7 billion in the distributors.

Published

Actions for Volume Twelve 2015 Part One Trade & Investment and TAFE

Volume Twelve 2015 Part One Trade & Investment and TAFE

Planning
Education
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Project management
Risk

Serious system limitations prevented TAFE NSW from providing sufficient and appropriate evidence to support recorded student revenue of $477 million, student receivables and accrued income of $47.6 million and unearned revenue of $398 million.
 
These limitations resulted in: 

  • a qualified audit opinion being issued for TAFE NSW;
  • delays in enrolling students;
  • inability to fully reconcile cash balances;
  • difficulties in reconciling student enrolments with revenues recorded in the financial statements;
  • large volumes of manual processing.

Published

Actions for Volume Twelve 2015 Part Two Water

Volume Twelve 2015 Part Two Water

Planning
Environment
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Project management
Risk

The distributions to the NSW Government increased from $690 million in 2013-14 to $1.0 billion in 2014-15. The increase was largely due to a higher dividend from Sydney Water Corporation.

Published

Actions for Volume Nine 2015 Planning and Environment

Volume Nine 2015 Planning and Environment

Planning
Environment
Information technology
Internal controls and governance
Project management
Risk

The NSW Environment Protection Authority has reduced the average time to assess contaminated sites from 203 days in 2013-14 to 73 days in 2014-15. It is also improving transparency by making more information on its performance publicly available.
 
In 2014-15, the Department of Planning and Environment increased new housing approvals across New South Wales by 12 per cent to 58,252, exceeding the State priority target of 50,000. It also reduced the time taken to assess major projects from about three years in 2013-14 to four months in 2014-15.

Published

Actions for Government advertising 2015

Government advertising 2015

Premier and Cabinet
Environment
Whole of Government
Compliance
Internal controls and governance
Procurement
Project management

The Government Advertising Act 2011 requires the Auditor-General to conduct an annual performance audit to check NSW Government agency compliance with the Act.

This audit focused on the Department of Premier and Cabinet’s (DPC) role in monitoring government agencies compliance with government advertising requirements, and examined advertising campaigns run by Destination NSW and the Sydney Opera House.

 

Parliamentary reference - Report number #253 - released 22 June 2015