The following report focuses on key observations and findings from the most recent financial statement audits of agencies in the Transport cluster. Unqualified audit opinions were issued for all agencies' financial statements. However, the report notes the agencies can improve their asset revaluation processes. 1. Financial reporting and controls Audit opinions Unq
Actions for Sydney Road Maintenance Contracts
Sydney Road Maintenance Contracts
In November 2013, Roads and Maritime Services (RMS) outsourced the maintenance of State roads in the Sydney region south and west zones using an innovative contracting approach called the Stewardship Maintenance Contract (SMC). The SMC links risk to reward, and uses a performance framework where outcomes should drive improved performance over time. RMS’ SMC contract management includes most elements of good practice, including governance and dispute re
Actions for NorthConnex
NorthConnex
The processes used to assess NorthConnex adequately considered value for money for taxpayers.This report also found that the impact of tolling concessions on road users and the motorway network was consistent with policy objectives described in the 2012 NSW Long Term Transport Master Plan. NorthConnex is a nine-kilometre tolled motorway tunnel be
Actions for Passenger Rail Punctuality
Passenger Rail Punctuality
Rail agencies are well placed to manage the forecast increase in passengers up to 2019, including joining the Sydney Metro Northwest to the network at Chatswood. Their plans and strategies are evidence-based, and mechanisms to assure effective implementation are sound. Based on forecast patronage increases, the rail agencies will find it hard to maintain punctuality after 2019 unless the capacity of the network to carry trains and people is increased s
Actions for 2016 - An overview
2016 - An overview
This report focuses on key observations and findings from 2016 audits and highlights key areas of focus for financial and performance audits in 2017. The quality and timeliness of financial reporting continued to improve across the NSW public sector in 2016. Only one qualified audit opinion was issued and most agencies signed their financial statements on time. We found the Government’s cluster governance arrangements were unclear and inconsisten
Actions for Transport 2016
Transport 2016
Financial reporting within the Transport Cluster continues to improve with reported misstatements down 96 per cent since 2011-12 to just three in 2015-16, according to a report released today by the NSW Auditor-General, Margaret Crawford.
Actions for CBD and South East Light Rail Project
CBD and South East Light Rail Project
Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford. Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case. Parliamentary reference - Report number #278 - released 30 November 2016
Actions for Handback of the M4 Tollway
Handback of the M4 Tollway
This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams. To ensure that future private sector partnerships (PPP) deal adequately with handb
Actions for Liverpool to Parramatta Bus Transitway
Liverpool to Parramatta Bus Transitway
Several of my recent audits have identified a need to improve our public transport system – both for the benefit of travellers and to assist in achieving better air quality. Bus Transitways can provide a good public transport solution for lower density population areas, potentially at a relatively low capital cost. This audit examines the transitway running between Liverpool and Parramatta, the first of several planned for Sydney. This audit should cont
Actions for Follow-up of Performance Audit: Bus Maintenance and Bus Contracts
Follow-up of Performance Audit: Bus Maintenance and Bus Contracts
Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits. This gives Parliament and the public an update on the extent of progress made. In this follow-up audit, we examine changes following our May 2002 report on how well the: State Transit Authority maintained its buses Ministry of Transport administered contracts for the provision of regular passenger bus services. P