Actions for Volume Six 2013 focusing on Law, Order and Emergency Services

Volume Six 2013 focusing on Law, Order and Emergency Services

Justice
Compliance
Fraud
Project management
Workforce and capability

We issued unqualified audit opinions on the above agencies’ 30 June 2013 financial statements. During the year, The Treasury issued TC 13/01 ‘Mandatory early close procedures for 2013’. As a result, the law and order services agencies were required to perform early close procedures. All law and order service agencies were broadly successful in performing the procedures, which helped them submit financial statements by an earlier due date. This in turn enabled the financial statement audits to be finalised within an earlier timeframe of eight weeks (nine weeks in 2011-12).

As previously recommended, the Department of Attorney General and Justice should continue integrating policies, operations and systems between its divisions and, once complete, analyse the costs and benefits. The Department of Attorney-General and Justice should also ensure it has the necessary processes in place to enable it to regularly monitor and measure the performance and success of the Victims Support Scheme in providing a more accessible, streamlined and targeted service to victims of violent crime in New South Wales.

Published

Actions for Management of Historic Heritage in National Parks and Reserves

Management of Historic Heritage in National Parks and Reserves

Planning
Environment
Infrastructure
Management and administration

The National Parks and Wildlife Service is spreading its resources too thinly, running the risk that the heritage significance of important assets will eventually be lost.

 

Parliamentary reference - Report number #230 - released 29 May 2013

Published

Actions for Implementing Asset Management Reforms

Implementing Asset Management Reforms

Justice
Planning
Finance
Treasury
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Project management

Hospitals, schools, public housing, roads, bridges, buses and trains are just some of the assets used by government in providing services to citizens.

The NSW Government’s asset base is impressive in size - with a value of around $167 billion and with government plans to spend around $8 billion acquiring or replacing assets in the current year. Another $2 billion is spent each year on maintenance.

Good asset management is very important to government; even a small efficiency gain in this area can provide significant returns. Good practice by those responsible for managing assets can improve reliability, extend asset life, save on maintenance costs and aid in identifying and disposing of unnecessary or non-performing assets.

Improving the NSW public sector’s approach to asset management has been on the reform agenda for at least a decade. Changes in practice have been accelerated more recently by integrating asset management policy with the budget process.

In this audit we examined NSW Treasury’s efforts to improve asset management practices in the public sector and the progress made by 3 agencies - the Department of Corrective Services, NSW Fire Brigades and the Powerhouse Museum - towards better managing their asset portfolios.

This report informs Parliament and the community on progress to date and what more needs to be done to ensure that agencies manage assets effectively and achieve best value.

 

Parliamentary reference - Report number #143 - released 12 October 2005

Published

Actions for Planning for Sydney's Water Needs

Planning for Sydney's Water Needs

Planning
Environment
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

Reliably supplying water to our State’s principal city, Sydney, is a major responsibility for the Government.

The community has been made keenly aware in recent years that inflows have been decreasing, and that Sydney has been using more water than is available. In April 2005 the water in Sydney’s storages dropped to 41.5 per cent of their capacity – the lowest level since the construction of Warragamba dam in 1960.

As Sydney continues to develop, it is expected that the demand for water will increase. The way that we use it will need to be sustainable, as it has a direct impact on our economy, our lifestyle and our environment.

In planning for the future the State’s water agencies face a range of uncertainties. But the task is vital.

This report informs Parliament and the community on the progress made - and what remains to be done - to ensure a reliable water supply for Sydney.

 

Parliamentary reference - Report number #135 - released 4 May 2005