Actions for Liverpool to Parramatta Bus Transitway

Liverpool to Parramatta Bus Transitway

Transport
Treasury
Infrastructure
Management and administration
Project management
Service delivery

Several of my recent audits have identified a need to improve our public transport system – both for the benefit of travellers and to assist in achieving better air quality.

Bus Transitways can provide a good public transport solution for lower density population areas, potentially at a relatively low capital cost. This audit examines the transitway running between Liverpool and Parramatta, the first of several planned for Sydney. This audit should contribute to a better understanding of the lessons learnt from this first project, and so to future transitways providing better value for money.

But this audit also raises broader issues.

It highlights the importance of accurately projecting the total cost of major infrastructure projects before governments lock in their decisions. It also highlights the need for sound decision-making processes when government agencies compete with the private sector. The principles and recommendations flowing from these issues are ones I would draw to the attention of all agencies, and to the Government.

 

Parliamentary reference - Report number #146 - released 5 December 2005

Published

Actions for Implementing Asset Management Reforms

Implementing Asset Management Reforms

Justice
Planning
Finance
Treasury
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Project management

Hospitals, schools, public housing, roads, bridges, buses and trains are just some of the assets used by government in providing services to citizens.

The NSW Government’s asset base is impressive in size - with a value of around $167 billion and with government plans to spend around $8 billion acquiring or replacing assets in the current year. Another $2 billion is spent each year on maintenance.

Good asset management is very important to government; even a small efficiency gain in this area can provide significant returns. Good practice by those responsible for managing assets can improve reliability, extend asset life, save on maintenance costs and aid in identifying and disposing of unnecessary or non-performing assets.

Improving the NSW public sector’s approach to asset management has been on the reform agenda for at least a decade. Changes in practice have been accelerated more recently by integrating asset management policy with the budget process.

In this audit we examined NSW Treasury’s efforts to improve asset management practices in the public sector and the progress made by 3 agencies - the Department of Corrective Services, NSW Fire Brigades and the Powerhouse Museum - towards better managing their asset portfolios.

This report informs Parliament and the community on progress to date and what more needs to be done to ensure that agencies manage assets effectively and achieve best value.

 

Parliamentary reference - Report number #143 - released 12 October 2005

Published

Actions for Follow-up of Performance Audit: Management of Intellectual Property

Follow-up of Performance Audit: Management of Intellectual Property

Whole of Government
Compliance
Internal controls and governance
Management and administration
Regulation

Periodically we review the extent to which agencies have implemented the recommendations they accept from our earlier audits. This gives Parliament
and the public an update on the extent of progress made.

Intellectual property (IP) can have value to the agency concerned and may have the potential for wider commercial use. Poor management of IP can impose risks, including the risk of lost opportunities. Because it is not ‘tangible’ like a building or plant and equipment, the need for properly managing IP may be overlooked.

In this follow-up audit, we examine changes following our October 2001 report on how well public sector agencies were managing intellectual property.

 

Parliamentary reference - Report number #133 - released 30 March 2005

Published

Actions for Using computers in schools for teaching and learning

Using computers in schools for teaching and learning

Education
Information technology
Infrastructure
Management and administration
Workforce and capability

Realisation of the Government’s objectives for integrating computers into the school environment is a major change that will take some time to achieve. The logistics of equipping schools with computers and making them operational have been approached energetically by the Department. Four years into the Computers in Schools Program, student and teacher access to computer hardware, software and the Internet is now substantially greater and teachers are now better placed to integrate computers into teaching and learning. But while much has been achieved there are significant challenges that still remain.

 

Parliamentary reference - Report number #73 - released 7 June 2000