Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.

The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.

This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.

 

Parliamentary reference - Report number #247 - released 18 December 2014

Published

Actions for Learning Management and Business Reform Program

Learning Management and Business Reform Program

Education
Information technology
Internal controls and governance
Management and administration
Procurement
Project management
Risk

The Learning Management and Business Reform (LMBR) program was established in 2006 to improve service delivery to schools, corporate staff and TAFE NSW. Some parts of the three major components of the LMBR program have been delivered to different areas of the Department of Education and Communities. However, complete implementation is behind schedule and over budget, and the Department has yet to demonstrate that it will achieve the expected benefits.

 

Parliamentary reference - Report number #246 - released 16 December 2014

Published

Actions for Managing Contaminated Sites

Managing Contaminated Sites

Planning
Industry
Environment
Compliance
Internal controls and governance
Management and administration
Project management
Regulation
Risk

NSW Government agencies with large landholdings need to better manage their contaminated sites.

When contaminated sites are reported to the Environmental Protection Authority (EPA) there are long delays in assessing the extent of contamination. The EPA also lacks the management controls to ensure that all significantly contaminated sites are actively monitored and key milestones for remediation are met.

 

Parliamentary reference - Report number #245 - released 10 July 2014

Published

Actions for Making the Most of Government Purchasing Power - Telecommunications

Making the Most of Government Purchasing Power - Telecommunications

Whole of Government
Compliance
Information technology
Internal controls and governance
Management and administration
Procurement

The Auditor-General has found that agencies have consistently failed to negotiate the best price for their telecommunication contracts and are not getting value for money because of inadequate contract and expense management processes.

The audit examined six agencies to assess whether the government was getting value for money from its telecommunications contracts. It again raised problems with the way NSW government agencies manage contracts.

 

Parliamentary reference - Report number #244 - released 26 June 2014

Published

Actions for Effectiveness of the New Death and Disability Scheme

Effectiveness of the New Death and Disability Scheme

Justice
Internal controls and governance
Management and administration
Risk
Service delivery

More NSW Police officers are returning to work after being injured and there are fewer medical discharges as a result of the new NSW Police death and disability scheme. The new scheme is also costing less and if early trends continue, costs may fall sufficiently to meet the government’s target.

 

Parliamentary reference - Report number #242 - released 22 May 2014

Published

Actions for Regional Road Funding - Block Grant and REPAIR Programs

Regional Road Funding - Block Grant and REPAIR Programs

Transport
Internal controls and governance
Management and administration
Project management
Risk

In 2013–14, Roads and Maritime Services (RMS) provided over $170 million to local councils through the Block Grant and REPAIR programs to spend on Regional Roads. Regional Roads are the link between State Roads and Local Roads.

 

Parliamentary reference - Report number #241 - released 8 May 2014

Published

Actions for NSW State Emergency Service Management of Volunteers

NSW State Emergency Service Management of Volunteers

Justice
Internal controls and governance
Management and administration
Project management
Risk
Service delivery
Workforce and capability

The SES needs to better understand the location, availability and skills of its volunteers so it can properly plan for emergency events. It needs to improve how it selects and retains the right volunteers and provide more up-to-date and focused training.

The SES has improved volunteer safety with injury claims falling by 40 per cent to 70 in the four years to 30 June 2013. The average cost of claims has fallen by 58 per cent to $3,547. The SES attributes this reduction to better equipment and work practices. 

 

Parliamentary reference - Report number #240 - released 15 April 2014

Published

Actions for Improving Legal and Safe Driving Among Aboriginal People

Improving Legal and Safe Driving Among Aboriginal People

Transport
Finance
Justice
Whole of Government
Management and administration

Government responses to improve legal and safe driving among Aboriginal people have had limited success reducing Aboriginal peoples’ over-representation in road accident fatalities, traffic-related offending and imprisonments.

 

Parliamentary reference - Report number #238 - released 19 December 2013

Published

Actions for Volume Ten 2013 focusing on Health

Volume Ten 2013 focusing on Health

Health
Asset valuation
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Project management
Risk
Shared services and collaboration

Unqualified opinions were issued for all agencies audited in the following report.

Some of the reports findings include:

  • Most cultural bodies rely heavily on government grants to fund services

  • The Sydney Opera House Trust earns most of its revenue from commercial operations

  • Less than half of the 2014-16 service agreements between HealthShare NSW and its customers have been signed. HealthShare NSW and health entities should finalise their 2014-2016 service agreements by no later than 31 January 2014

  • Five service level agreements with NSW Health Pathology for 2012-13 were never signed. NSW Health Pathology and local health districts/speciality networks should finalise their 2013-14 service agreements by no later than 31 December 2013

  • HealthShare NSW is committed to sharing internal audit findings across NSW Health

  • The Ministry has started a long-term project to review its policy directives

  • A recent review concluded the health sector has mature risk management practices

  • When changes to the Aboriginal Land Rights Act 1983 occur, the Minister should identify and assess any risks from the changes and develop strategies to mitigate against them.

Published

Actions for Volume Eight 2013 focusing on Transport and Ports

Volume Eight 2013 focusing on Transport and Ports

Transport
Industry
Compliance
Financial reporting
Procurement
Project management
Regulation
Workforce and capability

Unqualified audit opinions were issued on the above corporations’ 30 June 2013 financial statements. During the year, Treasury issued TC 13/01 ‘Mandatory early close procedures for 2013’. This Circular aimed to improve the quality and timeliness of agencies’ annual financial statements. In 2012-13, application of the circular was made mandatory for State owned corporations. As a result, the port corporations were required to perform the early close procedures. All the port corporations were successful in performing the procedures, which helped them submit financial statements by an earlier due date. The early close procedures also resulted in general improvements to the quality of most financial statements.

The report recommends all transport entities should do more to reduce excessive annual leave balances to ensure they will comply with new targets set by the Premier, RailCorp, Sydney Trains and NSW Trains should minimise the amount of overtime bonuses paid to train drivers and that Transport for NSW should set targets to measure the overall satisfaction of train users.