Actions for CBD and South East Light Rail Project

CBD and South East Light Rail Project

Transport
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford.

Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case.

 

Parliamentary reference - Report number #278 - released 30 November 2016

Published

Actions for Red tape reduction

Red tape reduction

Premier and Cabinet
Finance
Financial reporting
Internal controls and governance
Management and administration
Project management
Regulation
Shared services and collaboration

Overall, NSW Government initiatives and processes to prevent and reduce red tape were not effective, according to a report released today by the NSW Auditor-General.

In 2015, the Government reported that its red tape reduction initiatives, implemented between 2011 and 2015, had resulted in $896 million in savings. While these initiatives resulted in some savings, the total value of savings is unknown because estimates for some initiatives were based on unverified assumptions, cost transfers or unrealised projections.

 

Parliamentary reference - Report number #272 - released 25 August 2016

Published

Actions for Early childhood education

Early childhood education

Education
Compliance
Information technology
Management and administration
Project management
Regulation
Risk
Service delivery
Workforce and capability

Enrolments in quality early childhood education programs in New South Wales are increasing but are below the national benchmark, according to a report released today by the NSW Auditor-General, Margaret Crawford.

Ninety-five per cent of children should be enrolled in at least 600 hours in the year before school, but according to the latest NSW figures 77 per cent of children were enrolled in quality early childhood education programs. This 2015 figure is below the benchmark, but is a significant improvement on 2013 when 59 per cent were enrolled.

 

Parliamentary reference - Report number #271 - released 26 May 2016

Published

Actions for Dealing with Unlicensed and Unregistered Driving

Dealing with Unlicensed and Unregistered Driving

Justice
Transport
Information technology
Regulation
Shared services and collaboration

In our opinion there are inadequacies in the current arrangements for detecting unauthorised driving. For example better information is needed on the extent of unlicensed driving. This may require giving the NSW Police power to conduct random licence and registration checks. In addition, there are technological and legal constraints to the efficient and effective detection of unauthorised driving.

 

Parliamentary reference - Report number #115 - released 4 September 2003

Published

Actions for Freedom of Information

Freedom of Information

Transport
Premier and Cabinet
Education
Management and administration
Regulation
Service delivery

Freedom of Information (FOI) Coordinators and their staff were supportive of the legislation. However, the agencies examined can do considerably more to fully achieve the intentions of the Act. On the positive side, all three agencies had processes in place to handle requests and had made a number of changes to improve the effectiveness of the FOI process. Fees and charges had also been kept to a minimum. No processing fees were requested in the majority of cases, and if charged, were not unreasonable.

 

Parliamentary reference - Report number #114 - released 28 August 2003

Published

Actions for Northside Storage Tunnel Project

Northside Storage Tunnel Project

Planning
Environment
Infrastructure
Internal controls and governance
Procurement
Project management
Service delivery

The Northside Storage Tunnel was the first major public sector construction project using an alliance approach. In our opinion, the outcome of the project suggests that an alliance approach, when applied to a suitable project and managed appropriately, can support positive project outcomes. And in many respects the Alliance worked well. There are, however, a number of issues that we believe need to be addressed for future alliances.

 

Parliamentary reference - Report number #113 - released 24 July 2003

Published

Actions for The Millennium Train Project

The Millennium Train Project

Transport
Infrastructure
Procurement
Project management
Service delivery

State Rail has made significant improvements since the purchase of the Tangara. It improved measures necessary for handling contracts dealing with technically complex and innovative projects, although some other problems have been encountered, with new lessons to learn. The design and manufacture of new trains requires a significant investment in both time and cost. The Millennium Train has come at a considerably higher price than originally expected. And it is very late compared to the Government’s original announcements, as the development/design took longer than planned.

 

Parliamentary reference - Report number #112 - released 17 June 2003

Published

Actions for Protecting Our Rivers

Protecting Our Rivers

Environment
Internal controls and governance
Regulation
Shared services and collaboration

The Audit Office is of the opinion that responsibility for protecting the quality of river water is not clearly delineated. The current arrangements lack the structure to ensure success. There is no lead entity to co-ordinate efforts to protect river water. New South Wales has no overarching water quality or river health strategy and no water quality management plans to ensure clear outcomes and responsibilities for protecting river water quality and integrated decision-making to protect areas of greatest risk to water quality.

 

Parliamentary reference - Report number #108 - released 7 May 2003

Published

Actions for Implementing the Ovine Johne's Disease Program

Implementing the Ovine Johne's Disease Program

Industry
Internal controls and governance
Regulation
Service delivery
Shared services and collaboration

The implementation of the Ovine Johne's Disease (OJD) program in New South Wales has been prolonged and difficult. In our view, the OJD Program in New South Wales has experienced two major difficulties with its implementation: the lack of a strategic approach to program management, and an ill-defined governance structure. Both the NSW Government and industry need to be better organised and improve the planning, direction and co-ordination of the OJD Program and future programs.

 

Parliamentary reference - Report number #107 - released 26 February 2003

Published

Actions for Environmental impact assessment of major projects in NSW

Environmental impact assessment of major projects in NSW

Environment
Management and administration
Regulation
Service delivery

The Audit Office is of the opinion that the basis for environmental impact assessment of major projects in NSW is sound. The key concept of 'environmental significance' is well defined. The system is closely specified. The Department of Urban Affairs and Planning (DUAP) leads a whole-of-government approach to environmental impact assessment and its assessments are comprehensive. However, the Audit Office considers that there are opportunities for improvement by more actively managing the participants and the performance of the environmental impact assessment system. DUAP needs to strengthen its internal documentation and must ensure the public have greater involvement.

 

Parliamentary reference - Report number #92 - released 28 November 2001