Refine search Expand filter

Reports

Published

Actions for Managing Disruptions to Cityrail Passenger Services

Managing Disruptions to Cityrail Passenger Services

Transport
Management and administration
Service delivery
Workforce and capability

About one in every twelve Sydney people travels by train each weekday.

Unplanned disruptions to services are inevitable, even on the best-run railways.

Because of the complexities of Sydney’s rail network, a single event can disrupt many services.

From a passenger’s perspective, three issues are important –

  • how quickly the disruption is fixed (“When will my train arrive?”)
  • the accuracy of information provided about the disruption (“Should I change my travel/meeting/other arrangements?”)
  • how often the disruptions occur (“Should I give up on rail travel?”).

In this audit, we looked at how well RailCorp responds when there are routine disruptions to its CityRail passenger services. We focused on how RailCorp manages passenger journeys and informs passengers.

This report informs Parliament and the community about the limitations of the current system, and what more needs to be done in order to minimise the impact of disruptions on passengers.

It should also help passengers judge the extent to which they can rely on the information they receive, and to better understand some of the obstacles faced by staff.

 

Parliamentary reference - Report number #139 - released 22 June 2005

Published

Actions for Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Project management
Service delivery
Workforce and capability

Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits.

This gives Parliament and the public an update on the extent of progress made.

In this follow-up audit, we examine changes following our May 2002 report on how well the:

  • State Transit Authority maintained its buses
  • Ministry of Transport administered contracts for the provision of regular passenger bus services.

 

Parliamentary reference - Report number #138 - released 14 June 2005

Published

Actions for Emergency Mental Health Services

Emergency Mental Health Services

Health
Management and administration
Service delivery
Shared services and collaboration
Workforce and capability

It is estimated that one in five people will be affected at some stage by a mental health problem or illness. The increasing prevalence of mental illness means that at some point in time most of us will either be affected or we will know of someone who is.

Although most people with mental illness can be treated in the community, at times some may require emergency treatment or admission to hospital for shortterm intensive therapy.

Not only are more mental health patients presenting to an emergency department for treatment than ever before, they are reportedly sicker and a greater number require admission to a hospital bed for further treatment. And, because of its very nature, those suffering from acute mental illness may not understand what is wrong or be able to communicate their problems clearly.

This makes access to emergency mental health services a significant issue for government that requires continuing attention.

The focus of this report is on the provision of 24-hour crisis services to adults. Emergency mental health services play a vital role in providing timely and appropriate care. Without proper treatment the severity of the illness may escalate, increasing the risk of self-harm or harm to others.

There have been many changes to mental health services over the last decade to deal with increasing demand. Much has been done to improve access to, and the quality of emergency services through significant increases in funding, the opening of new beds and the employment of more mental health staff.

Yet recent reviews have highlighted problems with accessing mental health beds and inadequate levels of psychiatric support in rural areas.

I believe that our report will provide valuable assistance to area health services on alternative models of emergency mental health care that better manage patient risk and further improve service quality.

 

Parliamentary reference - Report number #136 - released 26 May 2005

Published

Actions for Planning for Sydney's Water Needs

Planning for Sydney's Water Needs

Planning
Environment
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

Reliably supplying water to our State’s principal city, Sydney, is a major responsibility for the Government.

The community has been made keenly aware in recent years that inflows have been decreasing, and that Sydney has been using more water than is available. In April 2005 the water in Sydney’s storages dropped to 41.5 per cent of their capacity – the lowest level since the construction of Warragamba dam in 1960.

As Sydney continues to develop, it is expected that the demand for water will increase. The way that we use it will need to be sustainable, as it has a direct impact on our economy, our lifestyle and our environment.

In planning for the future the State’s water agencies face a range of uncertainties. But the task is vital.

This report informs Parliament and the community on the progress made - and what remains to be done - to ensure a reliable water supply for Sydney.

 

Parliamentary reference - Report number #135 - released 4 May 2005

Published

Actions for Follow-up of Performance Audit: Collecting Outstanding Fines and Penalties

Follow-up of Performance Audit: Collecting Outstanding Fines and Penalties

Finance
Internal controls and governance
Management and administration
Service delivery

Periodically we review the extent to which agencies have implemented the recommendations they accept from our earlier audits. This gives Parliament and the public an update on the extent of progress made.

In this follow-up audit, we examine changes following our April 2002 report on how well the State Debt Recovery Office (under the Office of State Revenue) was collecting outstanding fines and penalties.

 

Parliamentary reference - Report number #132 - released 17 March 2005

Published

Actions for Fraud Control: Current Progress and Future Directions

Fraud Control: Current Progress and Future Directions

Whole of Government
Compliance
Fraud
Management and administration
Regulation
Risk

Periodically we review the extent to which agencies have implemented the recommendations they accept from our earlier audits. This gives Parliament and the public an update on the extent of progress made.

Given the size of the NSW public sector, the potential for fraud could run into billions of dollars if not properly managed. It is an area of risk that warrants close and ongoing attention. Over the last decade, we have responded by issuing three performance audits and a comprehensive guide to better practice on this topic.

In conducting my financial audits, there is now an Auditing Standard that requires me to seek annual assurances from every agency concerning the adequacy of their arrangements for fraud control. This latest performance audit provides a further report card on the extent to which the NSW public sector is managing its fraud risks.

This Report also provides updated guidance on improving arrangements for fraud control both at a whole-of-government level and at the agency level.

I commend the Report for close and careful attention by every agency.

 

Parliamentary reference - Report number #130 - released 9 February 2005

Published

Actions for Follow-up of Performance Audit: Environmental Impact Assessment of Major Projects

Follow-up of Performance Audit: Environmental Impact Assessment of Major Projects

Environment
Compliance
Management and administration
Service delivery
Shared services and collaboration

Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits. This gives Parliament and the public an update on the extent of progress made.

Major development and infrastructure projects may have significant environmental, social and quality-of-life impacts. The purpose of environmental impact assessment is to ensure that major projects are environmentally and socially sustainable and integrated with State, regional and local planning.

The Department of Infrastructure, Planning and Natural Resources (DIPNR) manages the assessment of major infrastructure proposals and coordinates whole of Government involvement. In November 2001 we audited this process, then undertaken by the Department of Urban and Regional Planning. (In July 2003 the new Department of Infrastructure, Planning and Natural Resources assumed responsibility.)

In this follow-up audit, we examine DIPNR’s implementation of the recommendations of the 2001 audit.

 

Parliamentary reference - Report number #129 - released 1 February 2005