Actions for Handback of the M4 Tollway

Handback of the M4 Tollway

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams.

To ensure that future private sector partnerships (PPP) deal adequately with handback, we recommend that the Roads and Traffic Authority (RTA):

  • ensure deeds spell out an appropriate inspection and testing program to determine repairs required to bring roads up to a satisfactory condition at handback (p.11)
  • ensure deeds link condition standards and maintenance approaches to changing industry standards and approaches over the life of the PPP (p.11)
  • consider including in deeds a requirement that operators provide a performance bond or similar security over the cost of handback repairs (p.11)
  • review the lessons learnt from the M4 tollway handback and determine whether it should seek to negotiate changes to existing tollway deeds to better deal with handback, by June 2010 (p.11)

 

Parliamentary reference - Report number #193 - released 27 October 2009

Published

Actions for Government Licensing Project

Government Licensing Project

Finance
Information technology
Internal controls and governance
Management and administration
Project management
Shared services and collaboration

The Government Licensing Project (GLP) is standardising and simplifying processes of agencies which issue licences. However, it is currently running over the original anticipated completion date, exceeding the original budget and expected to produce savings less than originally planned.

 

Parliamentary reference - Report number #192 - released 7 October 2009

Published

Actions for Administering Domestic Waterfront Tenancies

Administering Domestic Waterfront Tenancies

Planning
Transport
Management and administration
Service delivery
Shared services and collaboration

The audit’s overall conclusion is that Lands and Maritime are broadly achieving outcomes consistent with the IPART report on administering domestic waterfront tenancies. But a lack of collaboration between the agencies is contributing to poor customer service. Inconsistencies with the IPART report recommendations and operational differences between the two agencies result in different rents and conditions for tenants in the two agencies. The differences are having a significant impact on customer service.

 

Parliamentary reference - Report number #191 - released 23 September 2009

Published

Actions for Helping Aboriginal Defendants through MERIT

Helping Aboriginal Defendants through MERIT

Justice
Health
Management and administration
Service delivery

The Magistrates Early Referral into Treatment program (MERIT) diverts adult defendants with drug problems from the local court into a drug treatment program. Recent studies of MERIT outcomes indicate that MERIT is a highly appropriate intervention program for Aboriginal defendants. It has improved the health of participants, including significant reduction in drug use and significant improvement in mental health. Better justice outcomes include lower rates of imprisonment and reduced rates of reoffending.

Overall, the ability to identify MERIT clients, the eligibility criteria, the location and the ability of MERIT teams to engage with Aboriginal defendants are key factors that limit MERIT’s capacity to treat Aboriginal defendants. MERIT needs to overcome these barriers. If MERIT is to be a truly mainstream program, it must adapt to meet the needs of all who should participate.

 

Parliamentary reference - Report number #189 - released 5 August 2009

Published

Actions for Tackling Cancer with Radiotherapy

Tackling Cancer with Radiotherapy

Health
Internal controls and governance
Management and administration
Procurement
Service delivery
Workforce and capability

Overall radiotherapy services are managed in a reasonably efficient and effective manner. Much is being done to further improve efficiency and effectiveness, and more can be done. While New South Wales has a number of well-established radiotherapy treatment centres, the high capital cost limits their availability in all hospitals. Some patients need to travel long distances and be away from their homes for up to seven weeks. The projected growth in demand for radiotherapy services will further challenge NSW Health and it needs to more clearly demonstrate how it will have the right facilities in the right place at the right time.

 

Parliamentary reference - Report number #188 - released 23 June 2009

Published

Actions for Improving Road Safety: Heavy Vehicles

Improving Road Safety: Heavy Vehicles

Transport
Compliance
Internal controls and governance
Management and administration
Regulation
Risk

The RTA (Roads and Traffic Authority) approach to detecting and enforcing heavy vehicle safety has produced mixed results. There have been overall decreases in the number of crashes and people killed and injured in crashes involving heavy vehicles between 2002 and 2007. However, the number of crashes and the number of people injured have increased between 2006 and 2007.

We recognise that the RTA is unable to prevent all crashes. However, we consider that the RTA could do more to improve its ability to detect and respond to high risk heavy vehicles travelling on our roads.

 

Parliamentary reference - Report number #187 - released 13 May 2009

Published

Actions for Grants Administration

Grants Administration

Premier and Cabinet
Treasury
Health
Community Services
Planning
Compliance
Internal controls and governance
Management and administration
Procurement
Risk

We found no significant difference in the funding of government and opposition electorates. However, more money was given to electorates that were safely held by the major parties. These seats received $1.29 for every dollar given to marginal and independent seats with government marginals getting the least. Electorates also receive different levels of funding according to which region they are in. Such variations may reflect valid agency objectives such as meeting State Plan targets or addressing socio-economic disadvantage.

But while agencies publish who gets what, they do not adequately evaluate or explain what grant programs have achieved. As a result, there is a risk that New South Wales may not get the best value for its spending. We recommend that agencies regularly evaluate their grant programs and publish the results.

 

Parliamentary reference - Report number #186 - released 6 May 2009

Published

Actions for Sustaining Native Forest Operations

Sustaining Native Forest Operations

Industry
Management and administration
Procurement
Risk

We found that Forests NSW has adequate estimates of how much timber is available from native forests, now and into the future. It uses an industry accepted process to develop estimates, but more could be done to improve reliability. For instance, yield estimates for the South coast, Eden and Tumut are well overdue for review.

We also found that Forests NSW should have sufficient timber to meet its wood supply commitments which are fixed for periods up to 2023 using both native and plantation hardwood. However, the cost and difficulty of harvesting and hauling this timber is likely to increase over time. This presents a significant challenge for Forests NSW to manage.

 

Parliamentary reference - Report number #185 - released 29 April 2009

Published

Actions for Police Rostering

Police Rostering

Justice
Internal controls and governance
Management and administration
Risk
Service delivery
Workforce and capability

Overall, the NSW Police Force (the Force) is not meeting its target for responding to urgent calls for assistance. Today, one in four complaints is about customer service. Victims of crime report issues including difficulties in contacting an officer and frustration at having to wait for an officer to return to duty to find out about their case. The timeliness of investigations is also at risk when follow-up is delayed. Seventy per cent of commanders surveyed indicated that rosters did not support continuity of investigations or victims’ needs.

We are also concerned that the current roster pattern may not be in the best interest of the health and safety of officers. Sick and injury leave is higher in NSW than other states and the Force is yet to assess the extent to which rosters may contribute to this. The Force also needs to do more to protect its general duties officers from fatigue in line with contemporary practice for managing shiftwork.

 

Parliamentary reference - Report number #173 - released 5 December 2007

Published

Actions for Improving efficiency of irrigation water use on farms

Improving efficiency of irrigation water use on farms

Industry
Management and administration
Procurement
Service delivery
Shared services and collaboration

The Department of Primary Industries (DPI) has a crucial role in assisting the irrigation industry to respond to the conflicting demands placed upon the state’s water resources. The State Plan emphasises the importance of water to agriculture, and gives DPI responsibility to use its training programs to help farmers continue to increase water use efficiency. DPI needs to work closely with agencies with which it shares responsibilities in the State Plan to ensure that its water use efficiency activities contribute to the State Plan goals. It needs to work closely with Treasury to document the services it will require to do this, the resources which will be needed, and how its success will be measured. This will ensure that DPI is well placed to continue to assist the NSW farming industry to adapt and survive periods of reduced water availability. 

 