The Auditor‑General for New South Wales, Margaret Crawford, released a report today examining procurement management in Local Government.

The audit assessed the effectiveness of procurement management practices in six councils. All six councils had procurement management policies that were consistent with legislative requirements, but the audit found compliance gaps in some councils. The audit also identified opportunities for councils to address risks to transparency and accountability, and to ensure value for money is achieved when undertaking procurement.

The Auditor‑General recommended that the Department of Planning, Industry and Environment review the Local Government (General) Regulation 2005 and publish updated and more comprehensive guidance on procurement management for the Local Government sector. The report also generated insights for the Local Government sector on opportunities to strengthen procurement practices.

Effective procurement is important in ensuring councils achieve their objectives, demonstrate value for money and deliver benefits to the community when purchasing goods and services. Procurement also comes with risks and challenges in ensuring the purchased goods and services deliver to expectations. The risks of fraud and conflicts of interest also need to be mitigated.

The legislative requirements related to procurement in the Local Government sector are focused on sourcing and assessing tender offers. These requirements are included in the Local Government Act 1993 (the Act), the Local Government Amendment Act 2019 (the Amendment), the Local Government (General) Regulation 2005 (the Regulation), the Tendering Guidelines for NSW Local Government 2009 (the Tendering Guidelines), the Government Information (Public Access) Act 2009 (the GIPA Act) and the State Records Act 1998.

General requirements and guidance relevant to councils are also available in the Model Code of Conduct for Local Councils in NSW 2018 (the Model Code), the NSW Government Procurement Policy Framework 2019 and in publications by the Independent Commission Against Corruption (ICAC).1

Individual councils have developed their own procurement policies and procedures to expand on the legislative requirements. Understandably, these vary to reflect each council’s location, size and procurement needs. Nevertheless, the general principles of effective procurement management (such as transparency and accountability) and risk-mitigating practices (such as segregation of duties and the provision of training) are relevant to all councils.

The Audit Office of New South Wales Report on Local Government 2018 provided a sector-wide summary of aspects of procurement management in Local Government (see Section 2.1 of this report). This audit builds on this state-wide view by examining in detail the effectiveness of procurement management practices in six councils. This report also provides insights on opportunities to strengthen procurement management in the sector.

The selected councils for this audit were Cumberland City Council, Georges River Council, Lockhart Shire Council, Tweed Shire Council, Waverley Council and Wollongong City Council. They were selected to provide a mix of councils of different geographical classifications, sizes, priorities and levels of resourcing.

Conclusion

All six councils had procurement management policies and procedures that were consistent with the legislative requirements for sourcing and assessing tender offers. Their policies and procedures also extended beyond the legislative requirements to cover key aspects of procurement, from planning to completion. In terms of how these policies were applied in practice, the six councils were mostly compliant with legislative requirements and their own policies and procedures, but we found some gaps in compliance in some councils and made specific recommendations on closing these gaps.

There were also opportunities for councils to improve procurement management to mitigate risks to transparency, accountability and value for money. Common gaps in the councils’ procurement management approaches included not requiring procurement needs to be documented at the planning stage, not providing adequate staff training on procurement, not requiring procurement outcomes to be evaluated, and having discrepancies in contract values between contract registers and annual reports. These gaps expose risks to councils’ ability to demonstrate their procurements are justified, well managed, delivering to expectations, and achieving value for money. Chapter three of this report provides insights for the audited councils and the Local Government sector on ways to address these risks

Recommendations

  1. By June 2022, the Department of Planning, Industry and Environment should:
    1. publish comprehensive and updated guidance on effective procurement practices – including electronic tender submissions and procurements below the tender threshold
    2. review and update the Local Government (General) Regulation 2005 to reflect the increasing use of electronic tender submissions rather than paper copies.
  2. By December 2021, the six audited councils should consider the opportunities to improve procurement management in line with the improvement areas outlined in chapter three of this report.
  3. Cumberland City Council should immediately:
    1. ensure contract values are consistent between the contract register and the annual report
    2. introduce procedures to ensure supplier performance reviews are conducted as per the council’s policy
  4. Georges River Council should immediately:
    1. ensure contract values are consistent between the contract register and the annual report
    2. introduce procedures to ensure all the steps up to the awarding of a contract are documented as per the council’s policy
    3. introduce procedures to ensure outcome evaluations are conducted as per the council’s policy.
  5. Lockhart Shire Council should immediately:
    1. include additional information in the council’s contract register to ensure compliance with Section 29(b), (f), (g), (h) and (i) of the GIPA Act
    2. ensure contract values are consistent between the contract register and the annual report.
  6. Waverley Council should immediately ensure contracts are disclosed in the annual report as per Section 217(1)(a2) of the Regulation.

(1) The relevant ICAC publications include: Corruption Risks in NSW Government Procurement – The Management Challenge (2011), Corruption Risks in NSW Government Procurement – Suppliers’ Perception of Corruption (2011) and Corruption Risks in NSW Government Procurement – Recommendations to Government (2011).

While all six councils had procurement policies in place and were generally compliant with legislative requirements, this report has identified common gaps in processes and practices that expose risks to transparency, accountability and value for money.

This section discusses how councils can mitigate risks and ensure the best outcomes are achieved from their procurements.

Documented justification of procurement needs

The ICAC notes that determining what goods and services an agency requires is the first step of procurement, and the scope for corruption in how need is determined is significant. Without documenting how procurement needs have been justified, councils cannot demonstrate that they fulfill business needs, nor how the procurements may link to the councils’ strategic plans to deliver to the community.

This audit found that none of the six councils’ policies required them to document justification of procurement needs, and none did so consistently in practice. Councils can address this gap by building into their procurement planning process a requirement for staff to document the justification of procurement needs. For higher value procurements, this could be extended to include analysis of options, an assessment of risks and defining intended outcomes. Similarly, clearly establishing and documenting how relevant procurements relate to a council’s community strategic plans or operational plans helps ensure transparency.

Although a formal business case may not be required for many procurements (for example, low-value procurements or routine replacements), some form of documented justification for the expenditure should still be kept on record to demonstrate that the procurement relates to business purposes and is needed.

Segregation of duties

Segregation of duties is an effective control for reducing risks of error, fraud and corruption in procurement. It works on the principle that one person should not have end-to-end control of a procurement. Effective segregation of duties also often involves managerial or independent oversight that is built into the process. Four of the audited councils (Cumberland City Council, Georges River Council, Lockhart Shire Council and Wollongong City Council) appropriately addressed segregation of duties in their procurement frameworks. For example:

  • All procurements in Cumberland City Council required a delegated officer’s approval before commencing, and the requisitioning department is responsible for ensuring the completion of the goods, works or services associated with each contract. For contracts over $50,000, a specific ‘Authority to Procure’ form had to be completed by the requesting staff, signed by an approver and then forwarded to the procurement team.

  • Reflecting its small size, all procurements in Lockhart Shire Council were managed by one senior staff member. Nevertheless, this staff member had to bring contract management plans to the rest of the Executive Leadership Team for review and discussion, with large contracts such as those above the tender threshold referred to Council for approval.

The ICAC notes that segregation of duties helps to control discretion, which has particular risk implications for some types of procurement.This includes those involving low-value and high-volume transactions, restricted tenders, long-standing procurements and ‘pet projects’ (projects advocated by individual staff members). In cases where corruption risks are low, ICAC notes that monitoring staff’s involvement in procurement may be a cost-effective alternative to total segregation of duties.

Assessment of supplier performance

Councils need to monitor and assess supplier performance to ensure suppliers deliver the goods and services as agreed. The audit found that all six councils consistently monitored progress in capital works and for externally funded projects. Contract monitoring in these cases included ensuring timelines, funding, and legislative requirements were met. This is positive, as capital works made up the bulk of procurements (in terms of volume) in all of the audited councils.

That said, in all six councils, the level of scrutiny was lower for other types of procurements, and there is scope for improvement. For instance, the approach to monitoring capital works or externally funded projects could be replicated across other procurements of a similar nature and value. Conducting assessments and keeping records of supplier performance on all procurements does not need to be onerous, but instead provides useful information to inform future decision-making—including by helping ensure supplier pricing remains competitive, and avoiding re-engaging underperforming suppliers.

The NSW Government Procurement Policy Framework requires that NSW Government agencies establish systems and processes jointly with the suppliers to ensure compliance with contract terms and performance requirements. It also advises that agencies should drive continuous improvement and encourage innovation in coordination with suppliers and key stakeholders.

Centralised contract register

Centrally registering a contract provides improved transparency of procurement activities and facilitates monitoring and compliance checks. While councils are already required to maintain a contract register for all contracts above the reporting threshold (as per the GIPA Act), given the threshold is set at a relatively high benchmark ($150,000), there is merit in councils extending the practice to procurements below the reporting threshold. A central and comprehensive register of contracts helps avoid duplication of procurements and re-contracting of underperforming suppliers.

Three of the audited councils (Georges River Council, Tweed Shire Council and Wollongong City Council) had contract register policies that applied to procurements below the reporting threshold during the audited period. For example, Georges River Council required contracts valued at $10,000 or above to be registered with the procurement team, and Tweed Shire Council had a threshold of $50,000.

Evaluation of community outcomes and value for money

Councils may be progressing procurements to fulfill their strategic and business plans, or using them to fulfill commitments to the community. In these instances, outcomes evaluation is an important way to demonstrate to the community that the intended benefits and value for money have been delivered.

Five of the six audited councils did not require evaluations of community outcomes and value for money. While Georges River Council required contracts valued at $50,000 or more to be monitored, evaluated and reported on at least annually throughout the contract and also at its conclusion, in the procurements we examined the only ‘outcome evaluations’ that the council had conducted were community surveys that did not refer to individual procurements. Councils can miss opportunities to understand the impact of their work on the local community if evaluations of procurement outcomes are not completed. Evaluation findings are also valuable in guiding future resource allocation decisions.

Value for money in the procurement of goods and services is more than just having the specified goods delivered or services carried out. The NSW Government Procurement Policy Framework requires that state government agencies track and report benefits to demonstrate how value for money is being delivered. The framework notes that value for money is not necessarily the lowest price, nor the highest quality good or service, but requires a balanced assessment of a range of financial and non-financial factors, such as: quality, cost, fitness for purpose, capability, capacity, risk, total cost of ownership or other relevant factors.

Procurement training

Effective procurement management relies on the capability of staff involved in various stages of the process. Guidance can be provided through training, which is an important element of any procurement management framework. It ensures that staff members are aware of the councils' policies and procedures. If structured appropriately and provided in a timely manner, training can help to standardise practices, ensure compliance, reduce chances of error, and mitigate risks of fraud or corruption.

The ICAC notes that effective procurement management depends on the competence of staff undertaking procurements and the competence of those who oversee procurement activities. As the public sector is characterised by varying levels of procurement expertise, the ICAC notes that the sector would benefit from a structured approach to training and the application of minimum standards.3

At the time of this audit, only Wollongong City Council addressed staff training requirements in its procurement management framework. Exhibit 8 details its approach.

Exhibit 8: Wollongong City Council's approach to training
  • Wollongong City Council has a suite of procurement training available for staff, administered by a dedicated staff member who also monitors attendance and training needs
  • Staff must complete training before they can take part in a procurement or be a member of a tender assessment panel, and the council keeps a list of all accredited staff members.
  • Staff cannot access procurement files on the council's electronic records management system until they have received training and have been approved for access by the trainer.
  • Staff must be trained before they can receive a financial delegation.

Source: Audit Office of New South Wales analysis of Wollongong City Council's procurement policies and procedures 2020.
 

Two of the audited councils have now also introduced procurement training:

  • Georges River Council implemented online training, which is mandatory for new staff and serves as refresher training for existing staff. The council also provides in-person training for selected staff (covering contract management, contract specification writing and contractor relationship management) and has developed quick reference cards for all staff to increase awareness of the council's procurement processes.
  • Tweed Shire Council implemented mandatory online training for all staff members. The training covers the council's procurement policy and protocol as well as relevant legislation. It is linked to relevant council documents such as the Procurement Toolkit on the council's intranet, and includes a quiz for which training participants must score at least 80 per cent to have the training marked as completed.
(2) ICAC (2011) Corruption Risks in NSW Government Procurement – The Management Challenge.
(3) ICAC (2011) Corruption Risks in NSW Government Procurement – Recommendations to Government.

Appendix one – Responses from councils and the Department of Planning, Industry and Environment

Appendix two – Councils’ procurement contracts

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #345 - released 17 December 2020

Published

Actions for Waste levy and grants for waste infrastructure

Waste levy and grants for waste infrastructure

Planning
Environment
Management and administration
Regulation
Risk
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today that examined the effectiveness of the waste levy and grants for waste infrastructure in minimising the amount of waste sent to landfill and increasing recycling rates.  

The audit found that the waste levy has a positive impact on diverting waste from landfill. However, while the levy rates increase each year in line with the consumer price index, the EPA has not conducted a review since 2009 to confirm whether they are set at the optimal level. The audit also found that there were no objective and transparent criteria for which local government areas should pay the levy, and the list of levied local government areas has not been reviewed since 2014. 

Grant funding programs for waste infrastructure administered by the EPA and the Environmental Trust have supported increases in recycling capacity. However, these grant programs are not guided by a clear strategy for investment in waste infrastructure. 

The Auditor-General made six recommendations aimed at ensuring the waste levy is as effective as possible at meeting its objectives and ensuring funding for waste infrastructure is contributing effectively to recycling and waste diversion targets.

 

Overall, waste generation in New South Wales (NSW) is increasing. This leads to an increasing need to manage waste in ways that reduce the environmental impact of waste and promote the efficient use of resources. In 2014, the NSW Government set targets relating to recycling rates and diversion of waste from landfill, to be achieved by 2021–22. The NSW Waste and Resource Recovery (WARR) Strategy 2014–21 identifies the waste levy, a strong compliance regime, and investment in recycling infrastructure as key tools for achieving these waste targets.

This audit assessed the effectiveness of the NSW Government in minimising waste sent to landfill and increasing recycling rates. The audit focused on the waste levy, which is paid by waste facility operators when waste is sent to landfill, and grant programs that fund infrastructure for waste reuse and recycling.

The waste levy is regulated by the Environment Protection Authority (EPA) and is generally paid when waste is disposed in landfill. The waste levy rates are set by the NSW Government and prescribed in the Protection of Environment Operations (Waste) Regulation 2014. As part of its broader role in reviewing the regulatory framework for managing waste and recycling, the EPA can provide advice to the government on the operation of the waste levy.

The purpose of the waste levy is to act as an incentive for waste generators to reduce, re-use or recycle waste by increasing the cost of sending waste to landfill. In 2019–20, around $750 million was collected through the waste levy in NSW. The government spends approximately one third of the revenue raised through the waste levy on waste and environmental programs.

One of the waste programs funded through the one third allocation of the waste levy is Waste Less, Recycle More (WLRM). This initiative funds smaller grant programs that focus on specific aspects of waste management. This audit focused on five grant programs that fund projects that provide new or enhanced waste infrastructure such as recycling facilities. Four of these programs were administered by the Environmental Trust and one by the EPA.

Conclusion

The waste levy has a positive impact on diverting waste from landfill. However, aspects of the EPA's administration of the waste levy could be improved, including the frequency of its modelling of the waste levy impact and coverage, and the timeliness of reporting. Grant funding programs have supported increases in recycling capacity but are not guided by a clear strategy for investment in waste infrastructure which would help effectively target them to where waste infrastructure is most needed. Data published by the EPA indicates that the NSW Government is on track to meet the recycling target for construction and demolition waste, but recycling targets for municipal solid waste and commercial and industrial waste are unlikely to be met.

Waste levy

The waste levy rate, including a schedule of annual increases to 2016, was set by the NSW Government in 2009. Since 2016, the waste levy rate has increased in line with the consumer price index (CPI). The EPA has not conducted recent modelling to test whether the waste levy is set at the optimal level to achieve its objectives. The waste levy operation was last reviewed in 2012, although some specific aspects of the waste levy have been reviewed more recently, including reviews of waste levy rates for two types of waste. The waste levy is applied at different rates across the state. Decisions about which local government areas (LGAs) are subject to the levy, and which rate each LGA pays, were made in 2009 and potential changes were considered but not implemented in 2014. Currently, there are no objective and transparent criteria for determining which LGAs pay the levy. The EPA collects waste data from waste operators. This data has improved since 2015, but published data is at least one year out of date which limits its usefulness to stakeholders when making decisions relating to waste management.

Grants for waste infrastructure

All state funding for new and enhanced waste infrastructure in NSW is administered through grants to councils and commercial waste operators. The government's Waste and Resource Recovery (WARR) Strategy 2014–21 includes few priorities for waste infrastructure and there is no other waste infrastructure strategy in place to guide investment. The absence of a formal strategy to guide infrastructure investment in NSW limits the ability of the State Government to develop a shared understanding between planners, councils and the waste industry about waste infrastructure requirements and priorities. The Department of Planning, Industry and Environment is currently developing a 20-year waste strategy and there is an opportunity for the government to take a more direct role in planning the type, location and timing of waste infrastructure needed in NSW.

The grants administration procedures used for the grant programs reviewed in this audit were well designed. However, we identified some gaps in risk management, record-keeping and consistency of information provided to applicants and assessment teams. In four of the five programs we examined, there was no direct alignment between program objectives and the NSW Government's overall waste targets.

Achievement of the 2014–21 state targets for waste and resource recovery (WARR targets) is reliant in part on the availability of infrastructure that supports waste diversion and recycling. The state WARR targets dependent on waste infrastructure are:

  • Increase recycling rates to 70 per cent for municipal solid waste and commercial and industrial waste, and 80 per cent for construction and demolition waste.
  • Increase waste diverted from landfill to 75 per cent.

A further target — manage problem waste better by establishing or upgrading 86 drop-off facilities or services for managing household problem wastes state-wide — is dependent on accessible community waste drop-off facilities across NSW.

Exhibit 7 identifies the five grant programs that provide funding for new or enhanced waste infrastructure to increase capacity for reuse or recycling of waste. All five of these programs were examined in the audit.
In addition to the grant programs shown in Exhibit 7, other programs provide funding for infrastructure, but at a smaller scale. Examples of these include:

  • Bin Trim which provides rebates to small businesses for small scale recycling equipment such as cardboard and soft plastic balers.
  • Litter grants which provide funding for litter bins.
  • Weighbridges grants for installation of a weighbridge at waste facilities.
  • Landfill consolidation and environmental improvement grants for rural councils to replace old landfills with transfer stations or to improve the infrastructure at landfill sites.

Appendix one – Responses from audited agencies

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #343 - released 26 November 2020

Published

Actions for Government advertising 2018-19 and 2019-20

Government advertising 2018-19 and 2019-20

Whole of Government
Finance
Community Services
Compliance
Management and administration
Procurement

A report released today by the Auditor-General for New South Wales, Margaret Crawford found that select advertising campaigns conducted by Service NSW and the NSW Rural Fire Service met most requirements of the Government Advertising Act, regulations, Guidelines and other laws. However, the audit found that Service NSW inappropriately used its post campaign evaluation to measure sentiment towards and confidence in the NSW Government.  

While agency analysis shows that the ‘Cost of Living’ (phases 2 and 3)  and ‘How Fireproof is Your Plan?’ campaigns achieved most of their objectives, the campaign objectives and targets set by both agencies were not sufficient to measure all aspects of campaign effectiveness. 

The report makes two recommendations to the Department of Customer Service. The first is to review its guidance to ensure agencies are not using post campaign evaluations to measure sentiment towards the government. The second, to review its guidance and the new process of peer review to ensure they support agencies to comply with the Act, the regulations and the Guidelines. 

The Government Advertising Act 2011 requires the Auditor General to conduct an annual performance audit of one or more government agencies to see whether their advertising activities were carried out in an effective, economical and efficient manner and in compliance with the Government Advertising Act 2011.
 

Read full report (PDF)

The Government Advertising Act 2011 (the Act) requires the Auditor-General to conduct a performance audit on the activities of one or more government agencies in relation to government advertising campaigns in each financial year. The performance audit assesses whether a government agency or agencies have carried out activities in relation to government advertising in an effective, economical and efficient manner and in compliance with the Act, the regulations, other laws and the Government Advertising Guidelines (the Guidelines). This audit examined two campaigns run during the 2018–19 and 2019–20 financial years respectively:

  • the 'Cost of Living' campaign run by Service NSW (phases 2 and 3 delivered in 2018–19)
  • the 'How Fireproof Is Your Plan?' (Fireproof) campaign run by NSW Rural Fire Service (year two of a three-year campaign delivered in 2019–20).

Section 6 of the Act prohibits political advertising. Under this section, material that is part of a government advertising campaign must not contain the name, voice or image of a minister, member of parliament or a candidate nominated for election to parliament or the name, logo or any slogan of a political party. Further, a campaign must not be designed to influence (directly or indirectly) support for a political party.

Conclusion

Neither campaign breached the prohibition on political advertising contained in section 6 of the Act. While both campaigns met most requirements of the Act, the regulations, other laws and the Guidelines, we identified some instances of non-compliance. Service NSW inappropriately used its post campaign evaluation to measure sentiment towards and confidence in the NSW Government.

Service NSW used its post-campaign evaluation to measure sentiment towards and confidence in the NSW Government. While neither campaign breached the prohibition on political advertising contained in section 6 of the Act, measuring sentiment towards and confidence in the NSW Government is not an appropriate use of the post-campaign evaluation and creates a risk that the results may be used for party political purposes. This risk is heightened as both phases 2 and 3 of the Cost of Living campaign were run immediately before the NSW state election. We have made this finding previously in our report 'Government advertising 2017–18'.

The campaign objectives and targets set by both agencies were not sufficient to fully measure campaign effectiveness. Service NSW advertised seven rebates in phase 2 of the campaign but only set targets for the awareness and uptake of three of these rebates. NSW Rural Fire Service set objectives and targets to be achieved over the life of the three-year campaign but did not set targets to be achieved for each year of the campaign. While the Fireproof campaign is a three-year campaign, each year of the campaign is subject to a separate approval and peer review process.

Agency analysis shows that both campaigns achieved most of their objectives. There was some overlap in the timing of phases 2 and 3 of the Cost of Living campaign and both phases had similar high-level objectives to increase awareness of rebates, making it difficult to evaluate the effectiveness of each distinct campaign phase. NSW Rural Fire Service conducted a post-campaign evaluation for year two of the Fireproof campaign (2019–20) but although this showed positive results against the overall objectives of the three-year campaign, NSW Rural Fire Service did not set specific targets for year two of the campaign, making it difficult to evaluate effectiveness for that year.

Service NSW was not able to demonstrate that its campaign was economical as it directly negotiated with a single supplier for the creative materials for phase 2. This is contrary to the NSW Government's procurement rules which require agencies to obtain three quotes when using suppliers on a prequalification scheme. Service NSW did not comply with its own procurement policy, which restricts Service NSW employees from entering into discussions with a supplier until the appropriate delegate approves a direct procurement. NSW Rural Fire Service achieved cost efficiencies by re-using creative material developed in the first year of the campaign. NSW Rural Fire Service also received $4 million worth of free advertising time and space.

The cost benefit analyses prepared by both agencies did not fully meet the requirements in the Guidelines. Both agencies identified an alternative to advertising but did not assess the costs and benefits of that alternative. We have made this finding previously in our report 'Government advertising 2017–18' and in our report 'Government advertising 2015–16 and 2016–17'.

In 2018–19, Service NSW delivered phases 2 and 3 of the 'Cost of Living' campaign. The Cost of Living advertising campaign aimed to build awareness of the help available to ease the cost of living for people under financial pressure including awareness of specific rebates that can be claimed. As part of the Cost of Living program, Service NSW developed a webpage designed as a single portal to access more than 40 NSW Government savings, rebates and initiatives (which originated from over 12 different agencies). It also launched the Cost of Living service which includes face to face meetings and phone interviews to help people claim rebates from the NSW Government. Phase 2 of the campaign ran from September 2018 to August 2019. Phase 3 of the campaign ran from January 2019 to July 2019. The budgets for phases 2 and 3 were $4.127 million and $934,800 respectively. See Appendix two for more details on this campaign.

Service NSW complied with most requirements of the Act, the Regulations and the Guidelines. Campaign materials that we reviewed did not breach the prohibition on political advertising contained in section 6 of the Act. However, Service NSW used its post-campaign evaluation to measure sentiment towards, and confidence in, the NSW Government. This is not an appropriate use of the post-campaign evaluation and creates a risk that the results may be used for party political purposes. This risk is heightened as both phases 2 and 3 of the Cost of Living campaign were run immediately before the NSW state election.
The post-campaign evaluation shows that the campaign was effective in achieving most of its objectives. However, in phase 2, Service NSW did not set targets for all of the rebates it advertised. There was some overlap in the timing of phases 2 and 3 of the Cost of Living campaign and both phases had similar high-level objectives to increase awareness of rebates, making it difficult to evaluate the effectiveness of each distinct campaign phase.
Service NSW was not able to demonstrate that its campaign was economical as it directly negotiated with a single supplier for the creative materials in phase 2 (total cost $731,480). This is contrary to the NSW Government's procurement rules which require agencies to obtain three quotes when using suppliers on a prequalification scheme where the estimated cost is more than $150,000. Service NSW did not comply with its own procurement policy, which restricts Service NSW employees from entering into discussions with a supplier until the appropriate delegate approves a direct procurement.
The cost benefit analysis for phase 2 did not accurately assess the benefits of the campaign as Service NSW did not know which rebates would be included in the advertisements at the time the cost benefit analysis was developed. The cost benefit analysis for phase 2 did not assess the costs and benefits of alternatives to advertising.

Campaign materials we reviewed did not breach section 6 of the Act

The audit team reviewed campaign materials developed as part of the paid advertising campaign including radio transcripts, digital videos and display. The audit team did not review the use of social media outside paid social media content as section four of the Act defines government advertising as the dissemination of information which is funded by or on behalf of a government agency. See Appendix two for examples of campaign materials for this campaign.

Section 6 of the Act prohibits political advertising as part of a government advertising campaign. A government advertising campaign must not:

  • be designed to influence (directly or indirectly) support for a political party
  • contain the name, voice or image of a minister, a member of parliament or a candidate nominated for election to parliament
  • contain the name, logo, slogan or any other reference to a political party.

The audit found no breaches of section 6 of the Act in the campaign material we reviewed. 

Post-campaign evaluations measured sentiment towards and confidence in the NSW Government

The post-campaign evaluation for phases 2 and 3 measured levels of confidence with the statement ‘the NSW Government has your best interests at heart’, despite the fact this was not a stated objective of the campaign. This is not an appropriate use of the post-campaign evaluation, which should measure the success of the campaign against its stated objectives. The post-campaign evaluation for phase 3 found that exposure to the campaign improved sentiment towards the government amongst those who did not have confidence in the NSW Government.

Service NSW advised that it was important to measure the sentiment of the advertising including the wording 'best interests' as it did not want the whole of government brand to be detrimental to customer engagement with applying for the rebates.

Following phase 2, Service NSW conducted analysis of media sentiment using the key words 'cost of living' and the names of the Premier, Treasurer and Minister for Customer Service. The analysis presented the level of positive, negative and neutral media sentiment. The Government Advertising Guidelines 2012 list the purposes that government advertising may serve which do not include improving the perception of the government. The inclusion of this analysis in Service NSW's post-campaign evaluation creates a risk that the results may be used for party political purposes.

Section 10 of the Act restricts agencies from carrying out a campaign after 26 January in the calendar year before the Legislative Assembly is due to expire and before the election for the Legislative Assembly in that year. Service NSW authorised a media agency to book media in line with the media plans for the campaign. The media plans for the campaign show that Service NSW did not authorise or plan to run any advertisements between 27 January 2019 and 23 March 2019.

Service NSW did not set targets for all rebates advertised in phase 2

Service NSW did not set targets for four of the seven rebates that were advertised as part of phase 2 of the campaign. These rebates were the Family Energy Rebate, Appliance Replacement Offer, National Parks Concession Offer and the Pensioner Travel Voucher. As a result, it was unable to evaluate whether the advertisements for these rebates were effective. Service NSW advised that at the time the campaign went to peer review, when campaign objectives are set, it did not know which rebates would be included in the advertisements.

Service NSW stated in its submission to the Department of Premier and Cabinet that it may change the creative content for phase 2 as it announced new initiatives and rebates. The peer review process should have ensured that Service NSW set targets for any additional rebates or savings it intended to advertise before that advertising commenced to ensure a strategic approach to the campaigns that clearly demonstrated anticipated benefits were in place.

The post-campaign evaluation for phase 2 shows that the advertising campaign met most of its objectives

Service NSW set overall campaign objectives and specific targets for some rebates advertised as part of phase 2 of the campaign. The objectives, targets and results for phase 2 are shown in Exhibit 5. In phase 2, Service NSW established baseline data on levels of awareness of government rebates during the peer review process. The baseline level of awareness for government rebates was 44 per cent. The level of awareness for specific rebates was 46 per cent for the Compulsory Third Party (CTP) green slip refund, and 21 per cent for both Active Kids and Toll Relief.

Post-campaign evaluation reports for phase 2 show that the campaign met its objective to raise awareness of NSW Government rebates, achieving a 16 per cent increase in awareness from 44 per cent to 51 per cent. The campaign did not meet its target to increase awareness of the CTP green slip refund by ten per cent.

Service NSW did not report the results of the uptake of the CTP green slip refund, Active Kids and Toll Relief in its post campaign effectiveness report submitted to the Department of Premier and Cabinet. However, other post-campaign evaluation documentation, which Service NSW advise was submitted to the Department of Premier and Cabinet, show that these targets were met.

Service NSW did not report to the Department of Premier and Cabinet on whether it achieved the target of a ten per cent increase of average monthly visits to the Cost of Living webpage. Service NSW reported that it had achieved an average of 11,753 visitors to the webpage per day during the campaign. These average daily results indicate that the target was met.

Exhibit 5: Phase 2 - campaign objectives, targets and results
Campaign objectives and targets Does the post-campaign evaluation show that the target was met?
1. a) Increase awareness of rebates from the NSW Government by ten per cent.
Image
mauve circle with tick inside

    b) Increase average monthly visits to the Cost of Living webpage by ten per cent.

Image
mauve circle with tick inside and asterisk to the right

2. Increase awareness of rebates and savings by ten per cent for:

 
  • CTP green slip refund
Image
gold circle with white minus symbol inside
  • Active Kids
Image
mauve circle with tick inside
  • Toll Relief.
Image
mauve circle with tick inside
3. Increase awareness that NSW Government initiatives relating to the cost of living are available via Service NSW by ten per cent.
Image
mauve circle with tick inside
4. Increase the uptake of rebates and savings for the CTP green slip refund, Active Kids and Toll Relief by ten per cent.
Image
mauve circle with tick inside and asterisk to the right
Key
Image
mauve circle with tick inside
Yes
Image
gold circle with white minus symbol inside
Not Fully

*  Some issues with reporting on target.
Source: Service NSW. Audit Office analysis.

The post-campaign evaluation for phase 3 shows that the advertising campaign met most of its objectives

Service NSW set overall campaign objectives and specific targets for the two rebates advertised as part of phase 3 of the campaign. The objectives, targets and results for phase 3 are shown in Exhibit 6.

In phase 3, Service NSW established baseline data on levels of awareness during the peer review process. The baseline level of awareness for government rebates was 44 per cent. This is the same baseline that was used to measure performance for phase 2 of the campaign. Service NSW did not set baselines for awareness and uptake of Energy Switch and Creative Kids as these were new services.

Post-campaign evaluation reports for phase 3 show that the campaign met its objective to raise awareness of NSW Government rebates by ten per cent, achieving a 30 per cent increase in awareness from 44 per cent to 57 per cent. The overall increase in message take-out was met with 43 per cent agreeing with the message that the NSW Government is taking steps to ease the cost of living. The campaign achieved awareness and uptake targets for the specific rebates included in phase 3, except for awareness of Creative Kids which achieved 28 per cent awareness, falling short of the 30 per cent awareness target.

Exhibit 6: Phase 3 - campaign objectives, targets and results
Campaign objectives and targets Does the post-campaign evaluation show that the target was met?
1. Increase message takeout that ‘The NSW Government is taking steps to help ease the cost of living in NSW’ by ten per cent for those who can recall the campaign.
2. Increase awareness that the NSW Government has a range of rebates and savings by ten per cent.
3. Generate awareness with NSW residents aged 18+ of:
 
 
  • Energy Switch (15 per cent awareness)
  • Creative Kids (30 per cent awareness).
4. Create uptake of Energy Switch and Creative Kids (8,356 clicks on the Energy Switch website and 107,938 Creative Kids vouchers downloaded with 70 per cent conversion).
Key
Yes
Not Fully

Source: Service NSW. Audit Office analysis.

The timing of campaign phases meant that it was difficult for Service NSW to evaluate each distinct campaign phase and reduced opportunities to incorporate learnings from previous phases

Service NSW commenced planning for phase 2 of the campaign while phase 1 was still underway. This limited the opportunity for Service NSW to incorporate learnings from phase 1 into phase 2. There was some overlap in the timing of phase 2 and the start of phase 3 of the campaign, making it difficult to evaluate the effectiveness of each distinct campaign phase. Both phases 2 and 3 had the same high-level outcome objective to raise awareness of rebates by ten per cent. The baseline measures that were used to evaluate performance for phase 3 were the same as those used to evaluate phase 2. As a result, Service NSW was not able to separately evaluate these two phases of the campaign. This is important given the budgets for phases 2 and 3 were $4.127million and $934,800 respectively.

Service NSW allocated 7.5 per cent of its media budget to communications with culturally and linguistically diverse (CALD) and Aboriginal audiences

The NSW Government CALD and Aboriginal Advertising Policy requires that agencies spend at least 7.5 per cent of an advertising campaign media budget on direct communications with CALD and Aboriginal audiences. Service NSW authorised a media company to book media in line with the media plans for the campaign. The media plans for phases 2 and 3 of the campaign indicate that Service NSW met this requirement, with 7.5 per cent of the budget allocated to these audiences in phase 2 and 10.4 per cent in phase 3.

The post campaign evaluation for phases 1 and 2 of the Cost of Living campaign contained a recommendation to look at other opportunities to reach CALD audiences. Effective communication with CALD audiences was particularly important in phase 3 of the campaign, where they made up 30 per cent of the target audience for the Creative Kids advertisement. The post-campaign analysis for phase 3 showed that the campaign performed well with some, but not all CALD audiences. The post-campaign analysis also showed low awareness and uptake with Aboriginal audiences. Pre-campaign focus groups in phase 3 found Aboriginal audiences had a negative reaction to the campaign tag line ‘NSW Government is helping with the cost of living’ however this tagline was still used in some advertisements in phase 3.

The cost-benefit analysis (CBA) for phase 2 did not accurately assess the benefits of the campaign and did not assess the costs and benefits of alternatives to advertising

Under the Government Advertising Act 2011, agencies are required to prepare a CBA when the cost of the campaign is likely to exceed $1 million. The CBA conducted by Service NSW for phase 2 includes $8 million in benefits attributed to the advertisements for the Energy Switch tool and $6.9 million in benefits attributed to the advertisements for Creative Kids vouchers. These benefits should not have been included in the CBA for phase 2 as they were not included in this phase of the campaign. The CBA did not estimate the benefits of some other rebates and savings advertised in phase 2 of the campaign. This means that the CBA did not accurately assess the benefits of the campaign. Service NSW advised that at the time the CBA was developed it had not selected the rebates to be included in the campaign.

The Government Advertising Guidelines require agencies to consider options other than advertising to achieve the desired objective including a comparison of costs and benefits. The CBA developed as part of phase 2 identified using existing NSW Government communication channels as an alternative to advertising but did not assess the costs and benefits of this alternative.

This is a repeat finding from two previous government advertising audits. The report ‘Government Advertising: 2015–16 and 2016–17’ found that both agencies subject to the audit did not meet the requirements in the guidelines to consider alternatives to advertising. The report made a recommendation to the Department of Premier and Cabinet to work with Treasury to ensure the requirements of the guidelines are fully reflected in the 'Cost-Benefit Analysis Framework for Government Advertising and Information Campaigns'. The report ‘Government advertising 2017–18’ found that one agency subject to the audit did not identify to what extent the benefits could be achieved without advertising, nor did it consider alternatives to advertising which could achieve the same impact as the advertising campaign.

Service NSW negotiated with a single creative agency in phase 2, making it difficult to demonstrate value for money

Agencies are required to obtain three quotes when procuring a creative agency on the prequalification scheme if the estimated cost of the creative content is greater than $150,000. In phase 2 of the campaign, Service NSW extended the contract with the creative agency used for phase 1 of the campaign and did not obtain three quotes despite the cost of the creative content for phase 2 being $731,480. The requirement to obtain three quotes was met in phase 1 when initially selecting this creative agency.

Service NSWs procurement policy details that direct negotiation may be appropriate where there is a compelling reason to renew or rollover a contract beyond temporal or convenience reasons or in the cases of a genuine emergency. In its briefing to the Chief Executive, Service NSW stated that this contract extension was sought due to the time-sensitive nature of the project and that if work was delayed by a tender process, Service NSW may not be able to meet marketing milestones and this could result in limited customer uptake. This reason is not a genuine emergency and is not compelling as it does not explain what consequences would occur if it did not meet the marketing milestones or if there was limited customer uptake.

Service NSW's procurement policy also states that under no circumstances must Service NSW employees enter into discussions with a supplier until the delegate has formally made their decision to enter into direct negotiation. Service NSW briefed the Chief Executive of Service NSW in relation to extending the contract on 5 September 2018. The briefing states that the creative agency had already begun developing creative content for phase 2 and Service NSW had already received quotes from the creative provider for the proposed work prior to 5 September 2018. Procurement sign-offs were not completed until 7 September 2018. The engagement of the creative provider prior to appropriate approvals was contrary to Service NSWs procurement policy.

The economy of the campaign may have been limited by not meeting the procurement requirements in phase 2. It is possible that the creative provider may have offered a more competitive rate if it was aware that Service NSW was seeking quotes from other creative providers. Additionally, it is possible that another creative provider could have provided better value for money.

In phase 3 of the campaign, the estimated cost of the creative exceeded $150,000 however Service NSW chose to contract two different creative agencies, and the cost for each agency fell below the threshold to obtain three quotes. Agencies are permitted to obtain one quote when using a creative provider on the prequalification scheme if the cost is between $50,000 to $150,000. Service NSW advised that it contracted two creative providers as two different project teams were responsible for the rebates, each with separate marketing budgets.

Service NSW allowed sufficient time for cost-efficient media placement

During the peer review process, the Department of Premier and Cabinet advised agencies about the time they should allow to ensure cost-efficient media placement. For example, the Department of Premier and Cabinet advised that agencies book television advertising six to 12 weeks in advance and that agencies book radio advertising two to eight weeks in advance.

Service NSW allowed sufficient time between the completion of the peer review process and the commencement of the first advertising. Service NSW signed the agreement with the approved Media Agency Services provider with sufficient time to achieve cost-efficient media placement for all types of media used in this campaign.

The campaign may have been misleading for some people who were not eligible for rebates

Advertisements we reviewed focused on the amount of savings that could be obtained from rebates, for example ‘Save up to $285’, and ended with a statement ‘To save, visit service.nsw.gov.au. This directed viewers to the Cost of Living website which contains eligibility information. However, the advertisements in phases 2 and 3 we reviewed did not contain any details on the eligibility for these rebates and not all advertisements stated that eligibility criteria apply. Service NSW advised that the eligibility criteria for each rebate is extensive and that it was not possible to include this in the creative material.

Post-campaign evaluations in phase 3 recommended that advertisements for Creative Kids should indicate eligibility (e.g. age criteria) as statements on savings have the potential to be misleading when not all viewers will be eligible for rebates. Social media analysis conducted following phase 2 showed ineligibility or inability to claim rebates or refunds caused anger for some respondents.

Some advertisements in phase 2 stated ‘we've got something for everyone’. However, as rebates were subject to eligibility criteria, it is possible that some residents in NSW would not be eligible for any rebates as part of the Cost of Living initiative. As such, this statement has the potential to be misleading.

The campaign included statements that underestimated the savings that some customers could obtain

The Guidelines require accuracy in the presentation of all facts, statistics, comparisons and other arguments. The Guidelines also require that all claims of fact included in government advertising campaigns must be able to be substantiated.

In phase 2, the possible savings customers could obtain for two rebates or savings exceeded the amounts stated in the advertising campaign. Exhibit 7 shows some advertisements in phase 2 which stated, ‘My Green Slip Saving Save up to $60’. However, the State Insurance Regulatory Authority website shows that savings for some types of motor vehicles under the 2017 CTP scheme exceed $60. The State Insurance Regulatory Authority website states that the average saving under this scheme has been $129. Service NSW advised that these advertisements were designed for regional markets and that it used different advertisements for metropolitan areas which contained different amounts of savings.

Some advertisements in phase 2 stated, ‘My Toll Relief save up to $700’. The Service NSW website states that drivers can obtain free vehicle registration if they have spent $1,352 or more in tolls in the previous financial year. The cost of registration for some vehicles exceeds $700. This means the savings detailed in the advertisement were lower than what some customers could actually save.

NSW Rural Fire Service conducted the 'How FireProof Is Your Plan?' (Fireproof) campaign. The Fireproof campaign is a three-year campaign which ran in 2018–19 (year one), 2019–20 (year two) and is planned for 2020–21 (year three). This audit examined year two of the campaign (2019–20).

The Fireproof campaign is a public safety campaign encouraging people to plan and prepare for bush fires across the summer period. The campaign aims to improve the quality of bush fire planning and preparation in the community and decrease the impact of fires on the community when they occur.

The Fireproof campaign (year two) complied with most requirements of the Act, the Regulations and the Guidelines. The campaign materials that we reviewed did not breach the prohibition on political advertising contained in section 6 of the Act. NSW Rural Fire Service set objectives and targets to be achieved over the life of the three-year Fireproof campaign. Post-campaign evaluation shows that the Fireproof campaign was effective in achieving increases against its three-year objectives during year two. However, NSW Rural Fire Service did not set targets to be achieved for each year of the campaign, making it difficult to evaluate the effectiveness of year two of the campaign. NSW Rural Fire Service achieved cost efficiencies by re-using creative material developed in the first year of the campaign. NSW Rural Fire Service received $4 million worth of free advertising time and space. The cost benefit analysis for the Fireproof campaign did not assess the costs and benefits of alternatives to advertising.

Campaign materials we reviewed did not breach section 6 of the Act

The audit team reviewed campaign materials developed as part of the paid advertising campaign for example radio advertisements, television commercials and digital displays. The audit team did not review the use of social media outside paid social media content as section four of the Act defines government advertising as the dissemination of information which is funded by or on behalf of a government agency. Examples of campaign materials are shown in Appendix two.

Section 6 of the Act prohibits political advertising as part of a government advertising campaign. A government advertising campaign must not:

  • be designed to influence (directly or indirectly) support for a political party
  • contain the name, voice or image of a minister, a member of parliament or a candidate nominated for election to parliament
  • contain the name, logo, slogan or any other reference to a political party.

The audit found no breaches of section 6 of the Act in the campaign material we reviewed. 

NSW Rural Fire Service did not set targets for the second year of the campaign

The second year of the Fireproof campaign (2019–20) had the same objectives as the first year of the campaign (2018–19), however no specific targets were set for the second year. The advertising submission for the first year of the campaign (2018–19) details the targets for each objective as an increase of ten per cent against the baseline data to be achieved by March 2021, at the end of the three-year campaign.

The second year of the Fireproof campaign (2019–20) was one of the first campaigns approved under the new budget and peer review processes introduced by the Department of Customer Service in 2019–20. The new process for peer review introduced a new template for campaign submissions. The former template for campaign submissions contained more prompts for agencies to ensure the submission contained sufficient detail of campaign objectives, baseline measures, targets, dates for measurement and detail on how they would measure objectives. Despite this, the peer review process should have identified that NSW Rural Fire Service did not set targets for the second year of the campaign.

The 2016 Guidelines for Implementing NSW Government Evaluation Framework for Advertising and Communications requires campaign objectives to be SMART (specific, measurable, achievable, realistic and timed). NSW Rural Fire Service did not meet this requirement for year two of the Fireproof campaign.

Post-campaign evaluations showed increases against four out of five objectives, however there were no specific targets

NSW Rural Fire Service set three campaign objectives at the time it submitted the second year of the campaign (2019–20) to the Department of Customer Service for peer review. However, the post-campaign effectiveness report submitted to the Department of Customer Service measured campaign effectiveness against five campaign objectives. The objectives in the post-campaign effectiveness report were the same objectives set for the first year of the campaign, which is appropriate as this was a repeat campaign.

NSW Rural Fire Service achieved increases against four of their five objectives. However, as noted above there were no specific targets (such as percentage increases) against which performance of the 2019–20 campaign could be measured. Despite this, at the end of the second year, the Fireproof campaign had already achieved some of the targets that NSW Rural Fire Service had set for the end of the third year of the campaign. The post-campaign research showed that both audience recall and exposure to the campaign increased significantly from the prior year. The campaign objectives and results are shown in Exhibit 8.

For those people who already have a bush fire plan, the campaign aimed to increase the number of those plans which have included two or more elements from the Guide to Making a Bush Fire Survival Plan. Elements from the Guide to Making A Bush Fire Survival Plan include actions such as deciding what to take with you if you leave, ensuring you have the right equipment for defending your home and allocating responsibilities to members of a household. The post-campaign evaluation showed that the campaign did not achieve an increase against this objective for people who planned to stay and defend their property rather than leave.

Exhibit 8: Campaign objectives and results
Campaign objectives Does the post-campaign evaluation show increases against the objective?
1. Continue to increase the number of people that have discussed and/or written a plan with regards to what they will do in the event of a fire.
2. Of those who indicate they have a plan, increase the number of people who have included two or more elements from the Guide to Making a Bush Fire Survival Plan:  
  • for those who plan to leave
  • for those who plan to stay and defend.
3. Increase the frequency in completing preparation activities around a person’s property.
4. Increase the number of people who correctly assess it is their responsibility to complete preparation activities and enact their plan without direct intervention from emergency services.
5. Visits to MyFirePlan website.
Key
Yes
No

Source: NSW Rural Fire Service. Audit Office analysis.

NSW Rural Fire Service achieved cost efficiencies by reusing creative content developed in the first year of the campaign

Total creative and production costs incurred in year one of the campaign were $1.08 million. Rather than commissioning new creative materials, NSW Rural Fire Service re-used the same creative content in year two of the campaign. NSW Rural Fire Service incurred $100,000 in creative and production costs in year two of the campaign and achieved cost-efficiencies by reusing the same creative developed in the prior year.

NSW Rural Fire Service allowed sufficient time for cost-efficient media placement and received free media placements

The Department of Customer Service advises agencies to work with media contacts to book media in advance to ensure a cost-efficient placement. Prior to 2019–20, the Department of Premier and Cabinet provided suggested timeframes for agencies to book media as part of the peer review process. For example, it advised agencies to book television six to 12 weeks in advance and book radio advertising two to eight weeks in advance. NSW Rural Fire Service allowed sufficient time for a cost-efficient media placement.

NSW Rural Fire Service received $4 million of free advertising time and space donated by media companies due to the extent and impact of the 2019–20 fire season.

The cost benefit analysis (CBA) did not assess the costs and benefits of alternatives to advertising

Under the Government Advertising Act 2011, agencies are required to prepare a CBA when the cost of the campaign is likely to exceed $1 million. As part of the CBA, the Government Advertising Guidelines require agencies to consider options other than advertising to achieve the desired objective including a comparison of costs and benefits.

The CBA for the Fireproof campaign (year two) notes that the proposed campaign is one component of a broader community engagement strategy which has been developed over time and is based on research and evaluation. The CBA considers two options to achieve the objectives of the campaign. The first option is community engagement activities without an advertising campaign and the second option is community engagement activities alongside an advertising campaign. The CBA does not identify and assess the costs and benefits of both of the options in order to assess the most cost-efficient option.

This is a repeat finding from two previous government advertising audits. The report ‘Government Advertising: 2015–16 and 2016–17’ found that both agencies subject to the audit did not meet the requirements in the guidelines to consider alternatives to advertising. The report made a recommendation to the Department of Premier and Cabinet to work with Treasury to ensure the requirements of the guidelines are fully reflected in the 'Cost-Benefit Analysis Framework for Government Advertising and Information Campaigns'. The report ‘Government advertising 2017–18’ found that one agency subject to the audit did not identify to what extent the benefits could be achieved without advertising, nor did it consider alternatives to advertising which could achieve the same impact as the advertising campaign.

Appendix one – Responses from agencies

Appendix two – About the campaigns

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #342 - released 19 November 2020

Published

Actions for Support for regional town water infrastructure

Support for regional town water infrastructure

Industry
Environment
Local Government
Infrastructure
Management and administration
Regulation
Risk

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Planning, Industry and Environment has effectively supported the planning for, and funding of, town water infrastructure in regional NSW.

The audit found that the department has not effectively supported or overseen town water infrastructure planning since at least 2014. It does not have a clear regulatory approach and lacks internal procedures and data to guide its support for local water utilities that service around 1.85 million people in regional NSW.

The audit also found that the department has not had a strategy in place to target investments in town water infrastructure to the areas of greatest priority. A state-wide plan is now in development.

The Auditor-General made seven recommendations to the department, aimed at improving the administration and transparency of its oversight, support and funding for town water infrastructure, and at strengthening its sector engagement and interagency coordination on town water planning issues and investments.

According to the Auditor-General, ‘A continued focus on coordinating town water planning, investments and sector engagement is needed for the department to more effectively support, plan for and fund town water infrastructure, and to work with local water utilities to help avoid future shortages of safe water in regional towns and cities.’ 

This report is part of a multi-volume series on the theme of water. Refer to ‘Water conservation in Greater Sydney’ and ‘Water management and regulation – undertaking in 2020-21’.

Read full report (PDF)

Safe and reliable water and sewer services are essential for community health and wellbeing, environmental protection, and economic productivity. In 2019, during intense drought, around ten regional New South Wales (NSW) cities or towns were close to ‘zero’ water and others had six to 12 months of supply. In some towns, water quality was declared unsafe.

Ensuring the right water and sewer infrastructure in regional NSW to deliver these services (known as 'town water infrastructure') involves a strategic, integrated approach to water management. The NSW Government committed to ‘secure long-term potable water supplies for towns and cities’ in 2011. In 2019, it reiterated a commitment to invest in water security by funding town water infrastructure projects.

The New South Wales’ Water Management Act 2000 (WM Act) aims to promote the sustainable, integrated and best practice management of the State’s water resources, and establishes the priority of town water for meeting critical human needs.

The Department of Planning, Industry and Environment (the department) is the lead agency for water resource policy, regulation and planning in NSW. It is also responsible for ensuring water management is consistent with the shared commitments of the Australian, State and Territory Governments under the National Water Initiative. This includes the provision of healthy, safe and reliable water supplies, and reporting on the performance of water utilities.

Ninety-two Local Water Utilities (LWUs) plan for, price and deliver town water services in regional NSW. Eighty-nine are operated by local councils under the New South Wales’ Local Government Act 1993, and other LWUs exercise their functions under the WM Act. The Minister for Water, Property and Housing is the responsible minister for water supply functions under both acts.

The department is the primary regulator of LWUs. NSW Health, the NSW Environment Protection Authority (EPA) and the Natural Access Resource Regulator (NRAR) also regulate aspects of LWUs' operations. The department’s legislative powers with respect to LWUs cover approving infrastructure developments and intervening where there are town water risks, or in emergencies. In this context, the department administers the Best Practice Management of Water Supply and Sewerage Guidelines (BPM Guidelines) to support its regulation and to assist LWUs to strategically plan and price their services, including their planning for town water infrastructure.

Under the BPM Guidelines, the department supports LWU’s town water infrastructure planning with the Integrated Water Cycle Management (IWCM) Checklist. The Checklist outlines steps for LWUs to prepare an IWCM strategy: a long-term planning document that sets out town water priorities, including infrastructure and non-infrastructure investments, water conservation and drought measures. The department's objective is to review and approve (i.e. give ‘concurrence to’) an IWCM strategy before the LWU implements it. In turn, these documents should provide the department with evidence of town water risks, issues and infrastructure priorities.

The department also assesses and co-funds LWU's town water infrastructure projects. In 2017, the department launched the $1 billion Safe and Secure Water Program to ensure town water infrastructure in regional NSW is secure and meets current health and environmental standards. The program was initially established under the Restart NSW Fund.

This audit examined whether the department has effectively supported the planning for and funding of town water infrastructure in regional NSW. It focused on the department’s activities since 2014. This audit follows a previous Audit Office of NSW report which found that the department had helped to promote better management practices in the LWU sector, up to 2012–13.

Conclusion

The Department of Planning, Industry and Environment has not effectively supported or overseen town water infrastructure planning in regional NSW since at least 2014. It has also lacked a strategic, evidence-based approach to target investments in town water infrastructure.

A continued focus on coordinating town water planning, investments and sector engagement is needed for the department to more effectively support, plan for and fund town water infrastructure, and work with Local Water Utilities to help avoid future shortages of safe water in regional towns and cities.

The department has had limited impact on facilitating Local Water Utilities’ (LWU) strategic town water planning. Its lack of internal procedures, records and data mean that the department cannot demonstrate it has effectively engaged, guided or supported the LWU sector in Integrated Water Cycle Management (IWCM) planning over the past six years. Today, less than ten per cent of the 92 LWUs have an IWCM strategy approved by the department.

The department did not design or implement a strategic approach for targeting town water infrastructure investment through its $1 billion Safe and Secure Water Program (SSWP). Most projects in the program were reviewed by a technical panel but there was limited evidence available about regional and local priorities to inform strategic project assessments. About a third of funded SSWP projects were recommended via various alternative processes that were not transparent. The department also lacks systems for integrated project monitoring and program evaluation to determine the contribution of its investments to improved town water outcomes for communities. The department has recently developed a risk-based framework to inform future town water infrastructure funding priorities.

The department does not have strategic water plans in place at state and regional levels: a key objective of these is to improve town water for regional communities. The department started a program of regional water planning in 2018, following the NSW Government’s commitment to this in 2014. It also started developing a state water strategy in 2020, as part of an integrated water planning framework to align local, regional and state priorities. One of 12 regional water strategies has been completed and the remaining strategies are being developed to an accelerated timeframe: this has limited the department’s engagement with some LWUs on town water risks and priorities.

Regional New South Wales (NSW) is home to about a third of the state's population. Infrastructure that provides safe and reliable water and sewer services (also known simply as 'town water infrastructure') is essential for community health and wellbeing, environmental protection, and economic productivity. Planning for and meeting these infrastructure needs, as well as identifying when non-infrastructure options may be a better solution, involves a strategic and integrated approach to water resource management in regional NSW.

We examined whether the department has effectively supported planning for town water infrastructure since 2014. This assessment was made in the context of its current approach to LWU sector regulation. The findings below focus on whether the department has an effective framework including governance arrangements for town water issues to inform state-wide strategic water planning, and whether (at the local level) the department has effectively overseen and facilitated town water infrastructure planning through its Integrated Water Cycle Management (IWCM) planning guidance to LWUs.

We examined whether the department has effectively targeted town water infrastructure funding to policy objectives, with a focus on the design and implementation of the Safe and Secure Water Program (SSWP) since its commencement in 2017. The program’s aim was to fund town water infrastructure projects that would deliver health, social and environmental benefits, and support economic growth and productivity. We also assessed the department’s capacity to demonstrate the outcomes of the SSWP funding and the contributions of its town water infrastructure investments more broadly. Finally, we identified risks to the effectiveness of the department’s work underway since 2018–19, which is intended to enhance its strategic water planning and approach to prioritising investments in reducing town water risks.

Appendix one – Response from agency

Appendix two – Key terms

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #341 - released 24 September 2020

Published

Actions for Governance and internal controls over local infrastructure contributions

Governance and internal controls over local infrastructure contributions

Local Government
Planning
Environment
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today on how well four councils managed their local infrastructure contributions during the 2017-18 and 2018-19 financial years. 

Local infrastructure contributions, also known as developer contributions, are collected from developers to pay for local infrastructure such as drainage, local roads, open space and community facilities. Controls over local infrastructure contributions help to ensure that all contributions owed are collected, funds are spent as intended, and any contributions paid in the form of works-in-kind or dedicated land are correctly valued.

The audit found that Blacktown City Council and City of Sydney Council provided effective governance over their local infrastructure contributions whereas Central Coast and Liverpool City Councils’ governance arrangements require improvement.

The audit found that three councils had spent local infrastructure contributions in accordance with approved contributions plans. Central Coast Council and the former Gosford City Council had spent $13.2 million on administration costs in breach of the Environmental Planning and Assessment Act 1979. These funds were repaid into the council’s local infrastructure fund during the course of the audit.

The Auditor-General made a number of recommendations for each council relating to improving controls over contributions and increasing transparency. 

Read full report (PDF)
 

This audit examined the effectiveness of governance and internal controls over local infrastructure contributions, also known as developer contributions, held by four councils during the 2017–18 and 2018–19 financial years.

This performance audit was conducted with reference to the legislative and regulatory planning framework that was in place during that period.

Our work for this performance audit was completed at the end of March 2020 when we issued the final report to the four audited councils and the Department of Planning, Industry and Environment. We received their respective formal responses to the report’s recommendations during April and May 2020.

Concurrently to this audit, we sought Crown Solicitor’s advice (the ‘Advice’) regarding the use of local infrastructure contributions collected by local councils under the Environmental Planning and Assessment Act 1979 (‘the EPA Act’) for our financial audit work. The Advice clarified the applicable legislative requirements with reference to the application, investment and pooling of local infrastructure contributions. The Advice is included in Appendix 2 of this report. The Advice has not impacted on the findings and recommendations of this report.

Councils collect Local Infrastructure Contributions (LICs) from developers under the Environmental Planning and Assessment Act (1979), the Local Government Act (1993) and the City of Sydney Act (2000) (EP&A Act, LG Act and City of Sydney Act) to fund infrastructure required to service and support new development. At 30 June 2018, councils across NSW collectively held more than $3.0 billion in LICs collected from developers. Just over $1.37 billion in total was held by ten councils. Councils collecting LICs must prepare a contributions plan, which outlines how LICs will be calculated and apportioned across different types of infrastructure. Councils that deliver water and sewer services prepare a development servicing plan (DSP) which allows them to collect contributions for water and sewer infrastructure.

Development timeframes are such that there is often several years between when LICs are collected and the infrastructure is required. Good governance and internal controls are needed over these funds to ensure they are available when needed and spent appropriately.

This audit assessed the effectiveness of governance and internal controls over LICs collected by four councils during the 2017–18 and 2018–19 financial years: Blacktown City Council, Central Coast Council, City of Sydney Council and Liverpool City Council. As at June 2018 these councils held the four highest LIC balances, each in excess of $140 million.

Audit Conclusion

Three of the four councils audited were currently compliant with legislation, regulations and Ministerial Directions regarding LICs. All had gaps in governance and controls over LICs which limited effective oversight.

Three of the councils included in the audit complied with legislation, regulations and Ministerial Directions relating to LICs. Central Coast Council breached the EP&A Act between 2001 and 2019 when it used LICs for administration costs. These funds were repaid in late 2019.

While controls over the receipt and expenditure of contributions funds were largely in place at all councils, there were some exceptions relating to valuing work and land delivered in lieu of cash. Three councils do not provide probity guidance in policies relating to LICs delivered through works-in-kind. Three of the councils had contributions plans that were more than five years old.

Staff at all four councils are knowledgeable about LICs but not all councils keep procedures up to date. Three councils' governance frameworks operate effectively with senior officers from across the council involved in decisions about spending LICs, entering into voluntary planning agreements (VPAs) and reviewing contributions plans.

Transparency over key information relating to LICs is important for senior management so they can make informed decisions, and for the community who pay LICs and expect infrastructure to be provided. During the period of the audit, none of the councils included in the audit provided sufficient information to senior management or their councillors about the projected financial status of contributions plans. This information would be valuable when making broader strategic and financial decisions. Information about LIC levies and intended infrastructure is available to the community but not always easy to find.

A strong governance framework is important at each council to ensure that the funds are managed well, available when needed and spent as intended. The audit examined the following features of each council's governance framework as they apply to LICs:

  • decision-making by councillors and council officers relating to LICs
  • monitoring delivery of contributions plans and DSPs including:
    • reviewing assumptions underlying the plans
    • monitoring projected status of plans.

Internal controls over LICs are important to promote accountability, prevent fraud and deliver infrastructure to the required standard at the best possible price. If financial controls are weak or are not implemented well, there is a risk that LICs are misspent or that councils pay too much for infrastructure.

Not all councils' internal controls adequately addressed risks associated with the administration of LICs

The audit examined a number of internal controls that manage risks related to LICs. These included:

  • financial controls over receipt and expenditure of LIC funds
  • management of conflicts-of-interest when dealing with developers
  • independent valuations of works-in-kind and dedicated land
  • ensuring delivery and quality of works-in-kind, and obtaining security from developers in the event of non-delivery or poor quality work
  • management of variations to VPAs and works-in-kind agreements.

We reviewed controls included in policies and procedures and then checked samples of work to ensure that controls were implemented. We found variation in the controls that councils implemented, and some weaknesses in controls. It is a matter for each council to assess their financial risk and develop internal controls that support the collection, management, and expenditure of LICs. However, councils must be able to assure their communities and developers that they are doing everything possible to collect all LICs owing and that work conducted by developers in lieu of cash payments is properly valued and carried out to the required standard.

Further information about audit findings in relation to internal controls for each council are included in chapters five to eight. The exhibit below demonstrates variation in several controls implemented in the audited councils.

In a 2018 report, the Independent Commission Against Corruption noted that 'the appetite for transparency is expanding in both the public and private sectors'.

The Practice Note and S64 Guidance refer to transparency, including the importance of transparency over:

  • calculation and apportionment of LICs
  • funding of infrastructure, including where and when infrastructure is delivered
  • arrangements made with developers through VPAs.

The LIC system is largely transparent for community members who know where to look

Contributions plans and DSPs are public documents, exhibited to the public before being adopted by council. Councils included in the audit publish their contributions plans and DSPs on their websites and meet statutory requirements with regard to reporting and accessibility of information.

However, other public information relating to the LIC system is fragmented across different websites and reports and varies in detail across councils.

Exhibit 10: Published information about LICs at the four audited councils
  Blacktown City Council Central Coast Council City of Sydney Council Liverpool City Council
Financial details about contributions collected and spent Financial statements Financial statements Financial statements Financial statements
Implementation plans for spending LICs Contribution plans S64 implementation plans in DSPs. S7.11 & S7.12 implementation plans developed annually within capital works plan Contribution plans Developed annually within capital works plan
Capital works underway or completed, funded by LICs Capital works plan and annual report Not published Not published Capital works plan
Source: Audit Office analysis.

The Practice Note states that councils are accountable for providing the infrastructure for which contributions are collected. Demonstrating that infrastructure has been provided is difficult with fragmented information. As an example of transparent reporting, Blacktown City Council's 2018–19 annual report includes information about infrastructure that has been delivered for every contributions plan, providing transparency over how LICs have been spent.

Use of LICs collected under VPAs is not always transparent

Contributions collected under VPAs are not required to demonstrate the same relationship to a development as LICs collected under section 7.11 of the EP&A Act. VPAs are often negotiated because a developer requests a change to a planning instrument, and it is important that these arrangements, and their outcomes, are transparent to the community.

The EP&A Regulation includes mechanisms to ensure that VPAs are partially transparent. VPAs are exhibited to the public and approved by the elected council. Councils must maintain a VPA Register and make the VPA Deeds of Agreement available on request. However, there is no obligation on council to report on the outcomes or delivery of developers' obligations under VPAs. The four audited councils vary in transparency and accessibility of information available about VPAs.

Exhibit 11: Published information about VPAs at the four audited councils
  Blacktown City Council Central Coast Council City of Sydney Council Liverpool City Council
VPA Register Council website and annual report Annual report Annual report Council website and annual report
VPA Deeds of Agreement Council website Available on request Available on request Council website
Intended use of LICs collected under VPAs In Deeds of Agreement In Deeds of Agreement In VPA Register and most Deeds of Agreement In VPA Register and most Deeds of Agreement
Completion of work funded by cash collected under VPAs Not published Not published Not published Not published
Delivery of works-in-kind or land negotiated under VPAs Not published Not published In VPA Register Not published
Source: Audit Office analysis.

The Practice Note suggests that councils incorporate the intended use of LICs collected under VPAs in the Deed of Agreement, but there is no guidance relating to transparency over where and when funds have actually been spent. There is merit in councils providing greater transparency over public benefits delivered through VPAs to give communities confidence in VPAs as a planning tool.

Credit arrangements with developers are not always well documented or monitored

When levying LICs, section 7.11(6) of the EP&A Act requires councils to take into account land, money, or works-in-kind that the developer has contributed on other development sites over and above their LIC obligations. This section of the EP&A Act allows a developer to offset a LIC owed on one site against land or works contributed on another. This leads to some developers carrying 'credits' for work delivered to councils, to be paid back by reduced LICs on a future development. Blacktown City Council and Central Coast Council allow developers to carry credits. Liverpool City Council and City of Sydney Council do not permit credits and instead pay the developers for any additional work undertaken.

Councils should formally document credit arrangements and have a robust process to validate and keep track of credit balances and report on them. Central Coast Council does not keep good track of credit arrangements and neither Blacktown City Council or Central Coast Council aggregate or report on outstanding credit balances.

Blacktown City Council manages the largest LIC fund in NSW and negotiates more VPAs than any other council. Overall, Blacktown City Council demonstrates effective governance over the LIC funds but there is scope for improved oversight of the projected financial status of contributions plans and credit arrangements with developers. Blacktown City Council also needs to update its operating procedures relating to LICs and improve security over key information.

Blacktown City Council is managing areas with high growth. There is a risk that Blacktown City Council will be unable to collect sufficient LICs to fund the infrastructure required to support that growth. However, Blacktown City Council does not assess and report to senior management or its Audit, Risk and Improvement Committee about the projected financial status of contributions plans.

Blacktown City Council has policies in place to guide the management of LICs although management of credit arrangements with developers requires greater oversight. Policies relating to works-in-kind agreements provide no guidance about probity in negotiations with developers and valuations of works-in-kind are not independent as they are paid for by the developer. Blacktown City Council's S7.11 committee structure could act as a model for other councils. Blacktown City Council is spending LICs according to its contributions plans. Staff managing LICs demonstrate good knowledge of the regulatory environment. However, a number of administrative processes need attention such as outdated procedures, lack of security over key spreadsheets, and inappropriate retention of sensitive personal data.

Recommendations

By December 2020, Blacktown City Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. update council's works-in-kind policy to address probity risks during negotiations with developers
  3. mitigate risks associated with lack of independence in valuations of works-in-kind
  4. improve public reporting about expenditure of cash collected under VPAs
  5. improve management oversight of credit arrangements with developers
  6. update procedures for managing LICs
  7. implement security measures over critical or personal information and spreadsheets. 

Central Coast Council's governance and internal controls over LICs were not fully effective. Between 2001 and 2019, more than $13.0 million in LICs was misspent on administration costs in breach of the EP&A Act. There is scope for improved oversight of the projected financial status of contributions plans and credit arrangements with developers. Policies and procedures from the two former councils are not aligned.

In May 2016, the newly amalgamated Central Coast Council inherited 53 contributions plans from the former Gosford City and Wyong Shire Councils. Managing this number of contributions plans fragments the available funds and increases complexity. Central Coast Council is currently working on consolidating these plans. Between June 2016 and June 2019, its LIC balance doubled from $90.0 million to $196 million. Central Coast Council does not assess and report to senior management or its Audit, Risk and Improvement Committee about the projected financial status of contributions plans. Central Coast Council has a LIC committee but it has no formal charter and senior officers do not regularly attend meetings. This limits the committee's effectiveness as a decision-making body. A draft policy relating to works-in-kind agreements provide no guidance about probity in negotiations with developers. Valuations of works-in-kind and land dedications are not independent as they are paid for by the developer.

Central Coast Council has adjusted its accounts in 2018–19 by $13.2 million to repay the LIC fund for administration expenses that were not provided for in 40 contributions plans.

Recommendations

By June 2020, Central Coast Council should:

1. obtain independent validation of the adjustment made to the restricted asset accounts and general fund to repay LICs spent on administration, and adjustments made to each infrastructure category within the contributions plans

2. publish current contributions plans from the former Gosford City Council on the Central Coast Council website.

By December 2020, Central Coast Council should:

3. regularly report to senior management on the projected financial status of contributions plans

4. increase transparency of information available to the public about LIC works planned and underway, including intended use of contributions collected under VPAs

5. consolidate existing plans, ensuring the new contributions plans includes a regular review cycle

6. develop a formal charter for the developer contributions committee and increase the seniority of membership

7. complete and adopt council's works-in-kind policy currently under development, ensuring it addresses probity risks during negotiations with developers

8. mitigate risks associated with lack of independence in valuations of works-in-kind and dedicated land

9. improve public reporting about expenditure of cash collected under VPAs

10. improve management oversight of credit arrangements with developers

11. implement security measures to ensure the integrity of key spreadsheets used to manage LICs

12. align policies and procedures relating to LICs across the amalgamated council including developing policies and procedures for the management of S64 LICs

13. update council's VPA policy to address increased or indexed bank guarantees to accommodate cost increases.

City of Sydney Council manages a complex development environment across the Sydney CBD and inner suburbs. Overall, governance and internal controls over LICs are effective although there is scope for improved oversight of the projected financial status of contributions plans.

City of Sydney Council maintains a large balance of LICs, although not excessive relative to the annual level of LIC expenditure. Unspent contributions are largely associated with open space infrastructure that cannot be delivered until suitable land is available. Thirty per cent of cash contributions are collected under VPAs and there is limited transparency over how these funds are spent. City of Sydney Council does not assess and report to management or its Audit, Risk and Compliance Committee about the projected financial status of contributions plans.

In 2017–18 and 2018–19, LICs were spent in accordance with the corresponding contributions plans. City of Sydney Council staff are knowledgeable about the regulatory environment and are supported by up-to-date policies and procedures.

Recommendations

By December 2020, City of Sydney Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. improve public reporting about expenditure of cash collected under VPAs
  3. periodically review the risk of unpaid LICs associated with complying development certificates and assess whether additional controls are required
  4. implement security measures to ensure the integrity of key spreadsheets used to manage LICs. 

During the audit period 2017–18 and 2018–19, Liverpool City Council did not have effective governance and internal controls over LICs. Liverpool City Council is addressing deficiencies and risks identified through an internal audit published in December 2018 although further work is required. There is scope for improved oversight of the projected financial status of contributions plans.

In the two years to 30 June 2019, the balance of unspent LICs increased by more than 60 per cent against a relatively low pattern of expenditure. Prior to an internal audit completed in late 2018, there was no regular reporting on the status of LICs and a lack of transparency when prioritising the expenditure of LIC funds. During 2019, and following the internal audit, Liverpool City Council engaged additional skilled resources to improve focus and accountability for LICs. A LIC committee has been established to manage contributions plans and support business units to initiate relevant infrastructure projects, although it is too early to assess whether this committee is operating effectively. From February 2019, Liverpool City Council commenced monthly reporting to its Chief Executive Officer (CEO) about the point-in-time status of LIC funds, and to its Audit, Risk and Improvement Committee about risks associated with LICs and the implementation of internal audit recommendations. There is limited reporting to senior management about the projected financial status of some contributions plans. Our audit found no evidence of misuse of funds during the audited period. Methods for valuing work and land are not aligned with policies and procedures and are implemented inconsistently. In addition, valuations of works-in-kind and land dedications are not independent as they are paid for by the developer. The policy relating to works-in-kind provides no guidance about managing probity risks when negotiating with developers.

Recommendations

By December 2020, Liverpool City Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. update council's policies and procedures to provide consistent guidance about how works and land offered by developers should be valued
  3. update council's Works-in-Kind and Land Acquisition Policy to address probity risks during negotiations with developers
  4. improve public reporting about expenditure of cash collected under VPAs
  5. mitigate risks associated with lack of independence in valuations of works-in-kind and dedicated land
  6. implement security measures over critical or private information. 

Appendix one – Responses from councils and the Department of Planning, Industry and Environment

Appendix two – Advice from the Crown Solicitor

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #339 - released 17 August 2020

Published

Actions for Health capital works

Health capital works

Health
Compliance
Infrastructure
Procurement
Project management

This report examines whether NSW Health effectively planned and delivered major capital works to meet the demand for health services in New South Wales.

The report found that NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, the program was driven by Local Health District priorities without assessment of the State’s broader and future‑focussed health requirements.

The report found that unclear decision making roles and responsibilities between Health Infrastructure and the Ministry of Health limited the ability of NSW Health to effectively test and analyse investment options.

Project delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

The Auditor‑General recommends that NSW Health ensure its capital projects offer the greatest value to New South Wales by establishing effective policy guidance and enhancing project governance and management systems.

Read full report (PDF)

Since 2011–12, NSW Health has aimed to improve its facilities and build 'future focused' infrastructure. The NSW Government’s 2015–16 election commitments established a four-year $5.0 billion capital program for NSW Health to build and upgrade more than 60 hospitals and health services. The 2019–20 State Budget committed a further $10.1 billion over four years for another 29 projects. This is the largest investment to date on health capital works in New South Wales.

Recent reviews of infrastructure have recognised that population and demographic growth will require a change in the delivery and composition of health infrastructure, including considering greater use of non-traditional, non-capital health service options and assets.

To ensure that expenditure on capital works represents the best value for money, NSW Health's business cases need to be robust and supported by evidence that demonstrates they are worthy investments. The NSW Process of Facility Planning has been the main framework guiding the detailed planning and development of NSW Health's capital works proposals. This framework was developed by the then NSW Department of Health in 2010. Its aim is to ensure investment proposals are supported by rigorous planning processes that address health service needs and provide value for money.

Infrastructure projects of the complexity and scale being delivered by NSW Health carry inherent risks. For example, unplanned cost escalations can potentially impact on the State’s finances. Unforeseen delays can also reduce the intended benefits. The growth in the State’s health capital spend and project profile, means its exposure to such risks has increased over time.

The objective of this audit was to assess the effectiveness of planning and delivery of major capital works to meet demand for health services in New South Wales. To address this objective, the audit examined whether:

  • the Ministry of Health has effective procedures for planning and prioritising investments in major health capital works
  • Health Infrastructure develops robust business cases for initiated major capital works that reliably inform government decision making
  • Health Infrastructure has effective project governance and management systems that support delivering projects on-time, within budget and achievement of intended benefits.

The audit focused on the Ministry of Health and Health Infrastructure – being the lead agencies within NSW Health responsible for prioritising, planning and delivering major health capital works across the State. The audit examined 13 business cases for eight discrete projects over a ten-year period.

Conclusion

NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, its planning and prioritisation processes were not assessed against a long-term statewide health infrastructure plan and lacked rigorous assessment against non-capital options creating a risk that they do not maximise value for New South Wales.

The scale of NSW Health's capital investment is significant and has grown substantially in recent years. The NSW Government’s election commitments in 2015–16 and 2019–20 collectively set out a $15.0 billion capital program to build and upgrade 89 hospitals and health services. NSW Health developed this infrastructure program in the absence of a statewide health infrastructure strategy and investment framework to focus its planning and decisions on the types of capital investments required to meet the long-term needs of the NSW health system.

Consequently, locally focused priorities of the State’s 17 Local Health Districts have been the primary drivers of NSW Health’s capital investments since 2015–16. Local Health District investment proposals for hospitals were developed without consideration of alternative health options such as community health service models, technology-driven eHealth care, or private sector options. Without rigorous assessment against a range of potential health service options, there is a risk that selected projects do not maximise value for New South Wales.

In recognition of the need for a statewide approach to infrastructure planning, the Ministry of Health recently developed a 20-year Health Infrastructure Strategy and prioritisation framework in 2019. The strategy was approved by the NSW Government in April 2020.

NSW Health's ability to effectively test and analyse its capital investment options has been compromised by unclear decision-making roles and responsibilities between its Health Infrastructure and the Ministry of Health agencies.

While both Health Infrastructure and the Ministry of Health have responsibilities for the assessment of business cases for proposed infrastructure projects, confusion about the roles of each agency at key steps compromised the efficacy of the process. Health Infrastructure and the Ministry of Health have differing views about which agency is responsible for testing business case inputs and conducting comprehensive options appraisals.

As a result of this confusion, Health Infrastructure and the Ministry of Health did not rigorously test Local Health District capital investment proposals against defined statewide health infrastructure investment priorities. The NSW Process of Facility Planning does not clarify the responsibilities of all parties in validating and prioritising Local Health District's Clinical Service Plans and progressing them to business cases.

NSW Health's infrastructure priorities are not sufficiently supported by transparent documentation of selection methodology and the rationale for decisions. Consequently, there is a risk that recommended options, whilst having some economic and health service merit, do not represent the greatest value.

Substantial delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

Health Infrastructure did not fully comply with NSW Government guidelines for developing business cases and making economic appraisals for proposed capital investments. These weaknesses, along with delays and budget overruns on some projects, demonstrate a need for Health Infrastructure to strengthen its project governance, management and quality control systems.

 

Over the period of review, NSW Government policies for business case development and submission have emphasised that effective governance arrangements are critical to a proposal's successful implementation.

NSW Health's Process of Facility Planning similarly highlights the importance of effective governance and project management for achieving good outcomes. It prescribes a general governance structure managed by Health Infrastructure that can be tailored to the planning and delivery of health infrastructure projects greater than $10.0 million.

Project challenges indicate opportunities for strengthening governance and project management

The three major hospital redevelopments examined in metropolitan, regional and rural areas had a combined Estimated Total Cost of more than $1.2 billion and comprised eight discrete projects and 13 separate business cases.

Almost all these projects experienced delivery challenges which impacted achievement of their original objectives and intended benefits. This is expected in complex and large-scale health infrastructure programs. However, in some projects the impacts were significant and resulted in substantial delays, unforeseen costs, and diversion of resources from other priority areas.

Our review of the selected case studies highlighted opportunities for enhancing governance and project management. Specifically, it indicates a need for improving transparency in the management of contingencies, risk management and assessments particularly relating to adverse site conditions and the selection of contractors. There is also a need to strengthen forward planning for options to address unfunded priorities within business cases that risk complicating the delivery of future project stages resulting in unforeseen costs and potentially avoidable budget overruns.

Need for increased transparency and accountability in the management of contingency funds

In February 2017, the Ministry's Capital Strategy Group approved the use of surplus funds of $13.76 million from Stage 1 of the Hornsby Ku-ring-gai Hospital Redevelopment for new works deemed needed to support Stage 2. Following this decision, Health Infrastructure finalised and submitted a business case addendum for Stage 1 to the Ministry in March 2017, addressing the new works comprising a two-storey building for medical imaging and paediatric floors. The business case addendum also addressed options to fit out and procure major medical imaging equipment. The Ministry approved the Stage 1 business case in July 2017, noting the Ministry's Capital Strategy Group had already approved the use of remaining Stage 1 funds to deliver the new works.

Stage 1 was completed in 2015, almost two years before the Stage 1 business case addendum was prepared in February 2017.

The Ministry's decision to approve the new works using $13.76 million of surplus Stage 1 funds did not comply with the NSW Treasury Circular TC 12/20. This policy establishes the Treasurer's approval must be sought and received before a new capital project with an Estimated Total Cost of $5.0 million or more can be approved by NSW Health. The Ministry therefore exceeded its delegated authority in making this decision, as it was not evident it had sought and received the Treasurer's approval prior to doing so.

Consequently, the surplus Stage 1 funds should not have been used by the Ministry to deliver new works in the circumstances. Instead, they should have been released from the Stage 1 project in accordance with established NSW Health procedures, and the Stage 1 Estimated Total Cost revised down accordingly. This did not occur, and NSW Health ultimately directed $11.0 million in surplus Stage 1 funds to the new works.

These circumstances indicate a need to strengthen transparency and accountability within NSW Health for the approval of new projects, and how contingency funds are used in the management of major health capital works. They also demonstrate the impact of weaknesses with options appraisal as the initial Stage 1 business case did not consider alternative options for addressing the initially unfunded works later covered by the Stage 1 business case addendum and ultimately funded from the Stage 1 contingency provision.

Weaknesses in service delivery planning resulted in unaccounted-for costs

In addition to proposing the above-noted new works, the 2017 Stage 1 Business Case Addendum for the Hornsby-Ku-ring-gai development sought to retrospectively address the estimated funding gap of around $14.0 million for the internal fit out, supply of major medical imaging equipment, and cost to operate the medical imaging service at Hornsby Ku-ring-gai Hospital also not addressed in the originally Stage 1 business case.

The Stage 1 business case addendum considered various procurement options to purchase and run the medical imaging services ranging from State operation purchase options to private operation purchase options.

It recommended outsourcing the operation and provision of equipment to the private sector based on estimated savings to the public sector initially of around $650,000 per annum reducing over time to $270,000. The Ministry endorsed this option in June 2017, but it did not ultimately proceed.

A July 2018 report to the Executive Steering Committee on the project shows NSW Health later decided to deliver operation of the medical imaging unit 'traditionally' with an updated estimate of the cost at approximately $16.4 million. The report also shows the Ministry supported the costs now being met by the Northern Sydney Local Health District.

This means the funding gap previously identified in the Stage 1 business case addendum for fitting out the medical imaging building and supply of major medical equipment would need to be met fully by the State, representing a $16.4 million cost overrun for the project.

Examined reports to the Executive Steering Committee show this was largely funded by the Northern Sydney Local Health District via the disposal of land realising approximately $15.0 million in proceeds.

This initially unforeseen cost, along with the additional $11.0 million for the new works approved under the Stage 1 business case addendum, were ultimately merged with the Stage 2 project initially approved in 2017–18 with an Estimated Total Cost of $200 million.

The extent of budget variation on the Hornsby Kur-ring-gai development has not been transparent

The 2019–20 State Budget provided an additional $65.0 million for a further Stage 2A to deliver additional built capacity to support outpatient services, enhanced allied health services, re-housed community health services and the delivery of prioritised clinical services unfunded as part of Stage 2. The funds were approved based on an Investment Decision Template (IDT) that examined two options in addition to the base case representing scoping alternatives to the preferred master planned capital solution.

However, we found the IDT showed around 23 per cent of the $65.0 million sought (i.e. $15.0 million) was to be allocated to fund the deficit in Stage 2, which had arisen as a result of project delays due to adverse site conditions. This was not discussed in the IDT.

The February 2020 report to the Executive Steering Committee shows a combined Stage 2 and 2A final forecast cost of $292.6 million against a potential budget of $290.7 million representing an overall deficit for the project of around 0.6 per cent.

However, this favourable final budget position does not transparently show the funding challenges experienced over the project's implementation to-date. The three major budget issues include:

  • inappropriate use of around $11.0 million in Stage 1 contingency for originally unfunded works contrary to Treasury policy
  • the additional $16.4 million cost unforeseen in the Stage 1 business case for delivering medical imaging services mostly funded through the sale of land
  • an additional $15.0 million from Stage 2A to cover the budget overrun in Stage 2 due to adverse site conditions.

The cumulative impact of these events is that Stages 1 and 2 of the Hornsby project cost approximately $42.4 million than it should have in the circumstances around 14 per cent more than what the revised combined Estimated Total Cost for both stages should have been after releasing the $11.0 million in surplus Stage 1 funds, with Stage 2 delayed by around 14 months.

Opportunity for strengthening risk management for adverse site conditions

Major construction projects often experience adverse site conditions which can be difficult to fully detect in advance. However, we found this was a common occurrence in the projects we examined sometimes with significant time and/or budget impacts indicating scope to enhance related risk and cost assessments. Specifically:

  • Hornsby Ku-ring-gai Hospital Redevelopment Stage 2: adverse site conditions during demolition works resulted in an 11-month delay for delivering the medical imaging unit and 14-month delay completing Stage 2 main works including need for additional $15.0 million in funds to cover the resultant budget deficit for the project.
  • Blacktown Mt Druitt Hospital Redevelopment Stage 2: adverse site conditions combined with project complexity delayed completion of the early works by approximately five months. This contributed to the delay in completing the main construction works which occurred around nine months later than planned in the business case.
  • Dubbo Health Service Redevelopment Stages 3 and 4: Health Infrastructure advised adverse site conditions including asbestos containing materials and ground conditions delayed works for the main building with completion forecast for March 2021, around 21 months later than planned in the final business case. This resulted in the need for additional $13.5 million to cover increased construction costs and risks, increasing the Stage 3 and 4 forecast final cost from $150 million to $163.5 million as at February 2020.

These examples indicate a risk the cumulative impact of adverse site conditions may be substantial when measured across both time and Health Infrastructure's full delivery program. They also point to potential for Health Infrastructure to achieve efficiencies and improved outcomes from strengthening its approach to assessing and mitigating the risks from adverse site conditions.

Limited due diligence with prospective contractors risks avoidable delays and costs

Main construction works on Stage 1 of the Dubbo Health Service Redevelopment were completed in October 2015, approximately 13 months later than planned in the final business case. Delays were mainly due to insolvency of the early works contractor resulting in their departure from the project. The ensuing 11-month delay in completing the early works significantly impacted the overall schedule and delivery of main construction works.

The insolvency event was significant as it affected nine separate Health Infrastructure projects – three of which had yet to reach practical completion. It also affected state-funded projects in other sectors. It resulted in the need for additional funding of $11.5 million that was provided in the 2014–15 State Budget increasing the total Stage 1 and 2 budget from $79.8 million to $91.3 million.

Health Infrastructure’s analysis of lessons learned shows it worked actively to mitigate the impacts of the insolvency event across all affected projects. However, it also indicates a risk the lessons were mainly focused on mitigating the impacts after an insolvency event occurred rather than on prevention.

Although Health Infrastructure initially commissioned a financial assessment of the now insolvent early works contractor before engagement, it did not detect any risks of the impending insolvency and instead concluded the contractor was in a strong financial position. However, the contractor became insolvent shortly after commencement approximately seven months later. This indicates a risk of weaknesses in the assessment performed that was not explicitly addressed by the lessons learned.

Delivery of the main construction works were further impacted by disputes with the main works contractor over the scope of works for the renal unit resulting in Health Infrastructure terminating the contract in November 2016 following lengthy negotiations over several months.

The scope of works relating to the renal unit were ultimately transferred to Stages 3 and 4 and were delivered in December 2019, around five years later than originally planned in the business case.

Health Infrastructure advised the delay was ultimately beneficial to the project because the refurbishment works for the renal unit, initially scheduled for Stages 1 and 2, would have been demolished to accommodate the new Western Cancer Centre proposed after Stages 1 and 2 and currently being delivered in parallel with Stages 3 and 4.

Health Infrastructure advised the actual cost of Stages 1 and 2 was $84.7 million against the budget of $91.3 million. The residual $6.6 million relates to the renal works not delivered during Stage 1 and 2 and transferred to Stage 3 and 4.

Health Infrastructure advised the contractual provisions for mitigating insolvency events 'in-flight' are limited highlighting the importance of proactive and effective due diligence prior to engaging contractors for significant construction projects.

Need for a quality framework linked to staff training and capability development

Health Infrastructure's 2017-20 Corporate Plan identifies the development of a quality framework to support delivery of future-focused outcomes as a key organisational priority. Related initiatives within the Corporate Plan describe a framework underpinned by a Quality Committee providing advice on:

  • records management, to meet the requirements of the State Records Act 1998
  • project assurance, to ensure future focused outcomes and enhance Health Infrastructure's Standards, Policies, Procedures and Guidelines, Templates and Design Guidance Notes
  • knowledge management and library services, to promote and leverage from project learnings.

Although Health Infrastructure has some elements of a quality framework it is not yet fully in place. Health Infrastructure advised it had yet to establish the quality framework and related committee described in its Corporate Plan due in part to its focus on responding to the growth of its capital program.

Health Infrastructure's Development and Innovation team has been active in supporting continuous improvement in knowledge and project management including development of business cases. Although useful, these initiatives have relied heavily on leveraging and disseminating insights from Gateway reviews and have not formed part of a systematic quality and continuous improvement framework.

The limited focus on the quality of business cases is reflected in internal performance monitoring and reporting which focuses mainly on tracking the delivery of projects against internal benchmarks, often revised from the baselines in the business case, and expenditure against cashflow targets. There is no evident internal monitoring and/or reporting to the Chief Executive and Board on defined quality metrics linked to business case development and staff capability.

Performance reporting on balanced scorecard metrics has similarly focused mainly on process rather than quality and has been inconsistent in recent years.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

Appendix four – Ministry of Health planning tools and guidelines

Appendix five – Streamlined investment decision process for Health Capital Projects

Appendix six – Timeline of business cases and relevant policy guidelines

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #338 - released 12 August 2020

Published

Actions for Water conservation in Greater Sydney

Water conservation in Greater Sydney

Environment
Industry
Infrastructure
Internal controls and governance
Management and administration
Regulation
Risk

This report examines whether the Department of Planning, Industry and Environment, and Sydney Water have effectively progressed water conservation initiatives in Greater Sydney.

The report found that the department and Sydney Water have not effectively investigated, implemented or supported water conservation initiatives in Greater Sydney. The agencies have not met key requirements of the current Metropolitan Water Plan and Sydney Water has not met all its operating licence requirements for water conservation. There has been little policy or regulatory reform, little focus on identifying new options and investments, and limited planning and implementation of water conservation initiatives.

As a result, Greater Sydney's water supply may be less resilient to population growth and climate variability, including drought.

The Metropolitan Water Plan states that water conservation, including recycling water, makes the drinking water supply go further. The plan also states that increasing water conservation efforts may be cheaper than building new large-scale supply options and can delay the timing of investment in new supply infrastructure.

The Auditor-General recommends the department develop a clear policy and regulatory position on water conservation options, improve governance and funding for water conservation, and work with Sydney Water to assess the viability of water conservation initiatives. The report also recommends improvements to Sydney Water’s planning for and reporting on water conservation, including the transparency of this information.

This report is part of a multi-volume series on the theme of water. Refer to ‘Support for regional town water infrastructure’ and ‘Water management and regulation – undertaking in 2020-21’.

Read full report (PDF)

The current, 2017 Metropolitan Water Plan states that water conservation, including recycling water, makes the drinking water supply go further. The plan also states that increasing water conservation efforts may be cheaper than building new large-scale supply options and can delay the timing of investment in new supply infrastructure.

Water conservation refers to water recycling, leakage management and programs to enhance water efficiency. Water recycling refers to both harvesting stormwater for beneficial use and reusing wastewater.

This audit examined whether water conservation initiatives for the Greater Sydney Metropolitan area are effectively investigated, implemented and supported. We audited the Department of Planning, Industry and Environment (the Department) and the Sydney Water Corporation (Sydney Water), with a focus on activities since 2016.

The Department is responsible for the integrated and sustainable management of the state’s water resources under the Water Management Act 2000, which includes encouraging ‘best practice in the management and use of water’ as an objective. The Department is also responsible for strategic water policy and planning for Greater Sydney, including implementing the Metropolitan Water Plan.

Sydney Water is a state-owned corporation and the supplier of water, wastewater, recycled water and some stormwater services to more than five million people in Greater Sydney. It is regulated by an operating licence that is issued by the Governor on the recommendation of the Independent Pricing and Regulatory Tribunal (IPART). The Tribunal determines Sydney Water’s maximum prices, reviews its operating licence and monitors compliance. Sydney Water's operating licence and reporting manual set out requirements for its planning, implementing and reporting of water conservation.

From 2007 to 2012, the Climate Change Fund was a source of funds for water conservation activities to be undertaken by the Department and Sydney Water. The Climate Change Fund was established under the Energy and Utilities Administration Act 1987. Four of its six objectives relate to water savings. Water distributors such as Sydney Water can be issued with orders to contribute funds for water-related programs. The Fund is administered by the Department.

In 2016, Sydney Water developed a method for determining whether and how much to invest in water conservation. Known as the ‘Economic Level of Water Conservation’ (ELWC), the method identifies whether it costs less to implement a water conservation initiative than the value of the water saved, in which case the initiative should be implemented.

Conclusion

The Department and Sydney Water have not effectively investigated, implemented or supported water conservation initiatives in Greater Sydney.

The agencies have not met key requirements of the Metropolitan Water Plan and Sydney Water has not met all its operating licence requirements for water conservation. There has been little policy or regulatory reform, little focus on identifying new options and investments, and limited planning and implementation of water conservation initiatives.

As a result, Greater Sydney's water supply may be less resilient to population growth and climate variability, including drought.

The Department has not undertaken an annual assessment of Sydney Water’s level of investment in water conservation against water security risks and the capacity to respond when drought conditions return, as required by the Metropolitan Water Plan. It did not complete identified research and planning activities to support the plan, such as developing and using a framework for assessing the potential for water conservation initiatives for Greater Sydney, and developing a long-term strategy for water conservation and water recycling. It also did not finalise a monitoring, evaluation, reporting and improvement strategy to support the plan.

Sydney Water has been ineffective in driving water conservation initiatives, delivering detailed planning and resourcing for ongoing initiatives, and in increasing its investment in water conservation during drought. These were requirements of the Metropolitan Water Plan. Sydney Water's reporting on water conservation has not met all its operating licence requirements and lacked transparency with limited information on key aspects such as planning for leakage management, how the viability of potential initiatives were assessed, and how adopted initiatives are tracking.

The Department and Sydney Water did not put in place sufficient governance arrangements, including clarifying and agreeing responsibilities for key water conservation planning, delivery and reporting activities. There has also been limited collaboration, capacity building and community engagement to support water conservation, particularly outside times of drought.

Appendix one – Responses from agencies

Appendix two – About the audit

Appendix three – Glossary

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #336 - released 23 June 2020

Published

Actions for Integrity of data in the Births, Deaths and Marriages Register

Integrity of data in the Births, Deaths and Marriages Register

Justice
Premier and Cabinet
Whole of Government
Cyber security
Fraud
Information technology
Internal controls and governance
Management and administration

This report outlines whether the Department of Customer Service (the department) has effective controls in place to ensure the integrity of data in the Births, Deaths and Marriages Register (the register), and to prevent unauthorised access and misuse.

The audit found that the department has processes in place to ensure that the information entered in the register is accurate and that any changes to it are validated. Although there are controls in place to prevent and detect unauthorised access to, and activity in the register, there were significant gaps in these controls. Addressing these gaps is necessary to ensure the integrity of information in the register.

The Auditor-General made nine recommendations to the department, aimed at strengthening controls to prevent and detect unauthorised access to, and activity in the register. These included increased monitoring of individuals who have access to the register and strengthening security controls around the databases that contain the information in the register.

The NSW Registry of Births Deaths and Marriages is responsible for maintaining registers of births, deaths and marriages in New South Wales as well as registering adoptions, changes of names, changes of sex and relationships. Maintaining the integrity of this information is important as it is used to confirm people’s identity and unauthorised access to it can lead to fraud or identity theft.

Read full report (PDF)

The NSW Registry of Births Deaths and Marriages (BD&M) is responsible for maintaining registers of births, deaths and marriages in New South Wales. BD&M is also responsible for registering adoptions, changes of name, changes of sex and relationships. These records are collectively referred to as 'the Register'. The Births, Deaths and Marriages Registration Act 1995 (the BD&M Act) makes the Registrar (the head of BD&M) responsible for maintaining the integrity of the Register and preventing fraud associated with the Register. Maintaining the integrity of the information held in the Register is important as it is used to confirm people's identity. Unauthorised access to, or misuse of the information in the Register can lead to fraud or identity theft. For these reasons it is important that there are sufficient controls in place to protect the information.

BD&M staff access, add to and amend the Register through the LifeLink application. While BD&M is part of the Department of Customer Service, the Department of Communities and Justice (DCJ) manages the databases that contain the Register and sit behind LifeLink and is responsible for the security of these databases.

This audit assessed whether BD&M has effective controls in place to ensure the integrity of data in the Births, Deaths and Marriages Register, and to prevent unauthorised access and misuse. It addressed the following:

  • Are relevant process and IT controls in place and effective to ensure the integrity of data in the Register and the authenticity of records and documents?
  • Are security controls in place and effective to prevent unauthorised access to, and modification of, data in the Register?

Conclusion

BD&M has processes and controls in place to ensure that the information entered in the Register is accurate and that amendments to the Register are validated. BD&M also has controls in place to prevent and detect unauthorised access to, and activity in the Register. However, there are significant gaps in these controls. Addressing these gaps is necessary to ensure the integrity of the information in the Register.

BD&M has detailed procedures for all registrations and amendments to the Register, which include processes for entering, assessing and checking the validity and adequacy of source documents. Where BD&M staff have directly input all the data and for amendments to the Register, a second person is required to check all information that has been input before an event can be registered or an amendment can be made. BD&M carries out regular internal audits of all registration processes to check whether procedures are being followed and to address non-compliance where required.

BD&M authorises access to the Register and carries out regular access reviews to ensure that users are current and have the appropriate level of access. There are audit trails of all user activity, but BD&M does not routinely monitor these. At the time of the audit, BD&M also did not monitor activity by privileged users who could make unauthorised changes to the Register. Not monitoring this activity created a risk that unauthorised activity in the Register would not be detected.

BD&M has no direct oversight of the database environment which houses the Register and relies on DCJ's management of a third-party vendor to provide the assurance it needs over database security. The vendor operates an Information Security Management System that complies with international standards, but neither BD&M nor DCJ has undertaken independent assurance of the effectiveness of the vendor's IT controls.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #330 - released 7 April 2020.

Published

Actions for Environmental impact assessment of major projects in NSW

Environmental impact assessment of major projects in NSW

Environment
Management and administration
Regulation
Service delivery

The Audit Office is of the opinion that the basis for environmental impact assessment of major projects in NSW is sound. The key concept of 'environmental significance' is well defined. The system is closely specified. The Department of Urban Affairs and Planning (DUAP) leads a whole-of-government approach to environmental impact assessment and its assessments are comprehensive. However, the Audit Office considers that there are opportunities for improvement by more actively managing the participants and the performance of the environmental impact assessment system. DUAP needs to strengthen its internal documentation and must ensure the public have greater involvement.

 

Parliamentary reference - Report number #92 - released 28 November 2001

Published

Actions for Use of the internet and related technologies to improve public sector performance

Use of the internet and related technologies to improve public sector performance

Whole of Government
Cyber security
Information technology
Procurement
Service delivery
Shared services and collaboration
Workforce and capability

Notwithstanding the considerable effort, it is not apparent that the Government's vision can be fully achieved without increased efforts. Based on the current position, to ensure that the Government's vision can be achieved the Audit Office is of the view that the following key issues need to be urgently addressed: 

  • more robust mechanisms are needed to monitor, review and report publicly on progress and benefits

  • a greater emphasis should be placed on central coordination to ensure that agencies act in a more uniform and integrated manner  

  • the achievement of significant reform of business processes will require a substantial strengthening of accountability mechanisms and more comprehensive, rigorous and systematic approaches to e-government project and risk management. 

  • despite an array of guidance material and support provided by central agencies, line agency needs for assistance do not seem to be being met to sufficiently advance matters across the sector at the pace and scope desired

  • the Government’s e-government aspirations and funding are not always effectively harmonised. Agencies typically have limited resources available to trial or experience new technologies, and display an aversion to the associated risks.

 

Parliamentary reference - Report number #87 - released 19 September 2001