Actions for Newcastle Urban Transformation and Transport Program
Newcastle Urban Transformation and Transport Program
The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.
The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.
This audit had two objectives:
- To assess the economy of the approach chosen to achieve the objectives of the Program.
- To assess the effectiveness of the consultation and oversight of the Program.
We addressed the audit objectives by answering the following questions:
a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.
Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.
2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.
Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.
The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
- providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
- providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
- making business cases available to the public.
The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.
The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.
Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
- work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received.
There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.
There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public.
Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations.
The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.
Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.
The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.
Recommendations
For future infrastructure programs, NSW Government agencies should:
- develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
- establish whole-of-government oversight early in the program to guide major decisions. This should include:
- agreeing on objectives and ensuring all agencies understand these
- clearly defining roles and responsibilities for all agencies
- establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.
By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:
- setting measurable targets for the desired benefits
- clearly allocating ownership for achieving the desired benefits
- monitoring progress toward achieving the desired benefits and reporting publicly on the results.
Appendix one - Response from agencies
Appendix two - About the audit
Appendix three - Performance auditing
Parliamentary reference - Report number #310 - released 12 December 2018
Actions for Internal Controls and Governance 2018
Internal Controls and Governance 2018
The Auditor-General for New South Wales Margaret Crawford found that as NSW state government agencies’ digital footprint increases they need to do more to address new and emerging information technology (IT) risks. This is one of the key findings to emerge from the second stand-alone report on internal controls and governance of the 40 largest NSW state government agencies.
This report analyses the internal controls and governance of the 40 largest agencies in the NSW public sector for the year ended 30 June 2018.
This report covers the findings and recommendations from our 2017–18 financial audits that relate to internal controls and governance at the 40 largest agencies (refer to Appendix three) in the NSW public sector.
This report offers insights into internal controls and governance in the NSW public sector
This is our second report dedicated to internal controls and governance at NSW State Government agencies. The report provides insights into the effectiveness of controls and governance processes in the NSW public sector by:
- highlighting the potential risks posed by weaknesses in controls and governance processes
- helping agencies benchmark the adequacy of their processes against their peers
- focusing on new and emerging risks, and the internal controls and governance processes that might address those risks.
Without strong governance systems and internal controls, agencies increase the risks associated with effectively managing their finances and delivering services to citizens. The way agencies deliver services increasingly relies on contracts and partnerships with the private sector. Many of these arrangements deliver front line services, but others provide less visible back office support. For example, an agency may rely on an IT service provider to manage a key system used to provide services to the community. The contract and service level agreements are only truly effective where they are actively managed to reduce risks to continuous quality service delivery, such as interruptions caused by system outages, cyber security attacks and data security breaches.
Our audits do not review all aspects of internal controls and governance every year. We select a range of measures, and report on those that present heightened risks for agencies to mitigate. This report divides these into the following five areas:
- Internal control trends
- Information technology (IT), including IT vendor management
- Transparency and performance reporting
- Management of purchasing cards and taxis
- Fraud and corruption control.
The findings in this report should not be used to draw conclusions on the effectiveness of individual agency control environments and governance arrangements. Specific financial reporting, controls and service delivery comments are included in the individual 2018 cluster financial audit reports, which will be tabled in Parliament from November to December 2018.
The focus of the report has changed since last year
Last year's report topics included asset management, ethics and conduct, and risk management. We are reporting on new topics this year. We plan to introduce new topics and re-visit our previous topics in subsequent reports on a cyclical basis. This will provide a baseline against which to measure the NSW public sectors’ progress in implementing appropriate internal controls and governance processes to mitigate existing, new and emerging risks in the public sector.
Agencies selected for the volume account for 95 per cent of the state's expenditure
While we have covered only 40 agencies in this report, those selected are a large enough group to identify common issues and insights. They represent about 95 per cent of total expenditure for all NSW public sector agencies.
Internal controls are processes, policies and procedures that help agencies to:
- operate effectively and efficiently
- produce reliable financial reports
- comply with laws and regulations
- support ethical government.
This chapter outlines the overall trends for agency controls and governance issues, including the number of findings, level of risk and the most common deficiencies we found across agencies. The rest of this volume presents this year’s controls and governance findings in more detail.
Observation | Conclusions and recommendations |
---|---|
2.1 High risk findings | |
We found six high risk findings (seven in 2016–17), one of which was repeated from both last year and 2015–16. | Recommendation: Agencies should reduce risk by addressing high risk internal control deficiencies as a priority. |
2.2 Common findings | |
We found several internal controls and governance findings common to multiple agencies. | Conclusion: Central agencies or the lead agency in a cluster can play a lead role in helping ensure agency responses to common findings are consistent, timely, efficient and effective. |
2.3 New and repeat findings | |
Although internal control deficiencies decreased over the last four years, this year has seen a 42 per cent increase in internal control deficiencies. | The increase in new IT control deficiencies and repeat IT control deficiencies signifies an emerging risk for agencies. |
IT control deficiencies feature in this increase, having risen by 63 per cent since last year. The number of repeat IT control deficiencies has doubled and is driven by the increasing digital footprint left by agencies as government prioritises on-line interfaces with citizens, and the number of transactions conducted through digital channels increases |
Recommendation: Agencies should reduce IT risks by:
|
Government agencies’ financial reporting is now heavily reliant on information technology (IT). IT is also increasingly important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our audits reviewed whether agencies have effective controls in place to manage both key financial systems and IT service contracts.
Observation | Conclusions and recommendations |
---|---|
3.1 Management of IT vendors | |
Contract management framework Although 87 per cent of agencies have a contract management policy to manage IT vendors, one fifth require review. |
Conclusion: Agencies can more effectively manage IT vendor contracts by developing policies and procedures to ensure vendor management frameworks are kept up to date, plans are in place to manage vendor performance and risk, and compliance with the framework is monitored by:
|
Contract risk management Forty-one per cent of agencies are not using contract management plans and do not assess contract risks. Half of the agencies that did assess contract risks, had not updated the risk assessments since the commencement of the contract. |
Conclusion: Instead of applying a 'set and forget' approach in relation to management of contract risks, agencies should assess risk regularly and develop a plan to actively manage identified risks throughout the contract lifecycle - from negotiation and commencement, to termination. |
Performance management Only 24 per cent of agencies sought assurance about the accuracy of vendor reporting against KPIs, yet sixty-seven per cent of the IT contracts allow agencies to determine performance based payments and/or penalise underperformance. |
Conclusion: Agencies are monitoring IT vendor performance, but could improve outcomes and more effectively manage under-performance by:
|
Transitioning services Where IT vendor contracts do make provision for transitioning-out, only 28 per cent of agencies have developed a transitioning-out plan with their IT vendor. |
Conclusion: Contract transition/phase out clauses and plans can mitigate risks to service disruption, ensure internal controls remain in place, avoid unnecessary costs and reduce the risk of 'vendor lock-in'. |
Contract Registers Eleven out of forty agencies did not have a contract register, or have registers that are not accurate and/or complete. |
Conclusion: A contract register helps to manage an agency’s compliance obligations under the Government Information (Public Access) Act 2009 (the GIPA Act). However, it also helps agencies more effectively manage IT vendors by:
Recommendation: Agencies should ensure their contract registers are complete and accurate so they can more effectively govern contracts and manage compliance obligations. |
3.2 IT general controls | |
Governance Ninety-five per cent of agencies have established policies to manage key IT processes and functions within the agency, with ten per cent of those due for review. |
Conclusion: Regular review of IT policies ensures risks are considered and appropriate strategies and procedures are implemented to manage these risks on a consistent basis. An absence of policies can lead to ad-hoc responses to risks, and failure to consider emerging IT risks and changes to agency IT environments. |
User access administration
|
Recommendation: Agencies should strengthen the administration of user access to prevent inappropriate access to key systems. |
Privileged access Forty per cent of agencies do not periodically review logs of the activities of privileged users to identify suspicious or unauthorised activities. |
Recommendation: Agencies should:
|
Password controls Twenty-three per cent of agencies did not comply with their own policy on password parameters. |
Recommendation: Agencies should ensure IT password settings comply with their password policies. |
Program changes Fifteen per cent of agencies had deficient IT program change controls mainly related to segregation of duties and authorisation and testing of IT program changes prior to deployment. |
Recommendation: Agencies should maintain appropriate segregation of duties in their IT functions and test system changes before they are deployed. |
This chapter outlines our audit observations, conclusions and recommendations from our review of how agencies reported their performance in their 2016–17 annual reports. The Annual Reports (Statutory Bodies) Regulation 2015 and Annual Reports (Departments) Regulation 2015 (annual reports regulation) currently prescribes the minimum requirements for agency annual reports.
Observation | Conclusion or recommendation |
4.1 Reporting on performance | |
Only 57 per cent of agencies linked reporting on performance to their strategic objectives. The use of targets and reporting performance over time was limited and applied inconsistently. |
Conclusion: There is significant disparity in the quality and consistency of how agencies report on their performance in their annual reports. This limits the reliability and transparency of reported performance information. Agencies could improve performance reporting by clearly linking strategic objectives to reported outcomes, and reporting on performance against targets over time. NSW Treasury may need to provide more guidance to agencies to support consistent and high-quality performance reporting in annual reports. |
There is no independent assurance that the performance metrics agencies report in their annual reports are accurate. Prior performance audits have noted issues related to the collection of performance information. For example, our 2016 Report on Red Tape Reduction highlighted inaccuracies in how the dollar-value of red tape reduction had been reported. |
Conclusion: The ability of Parliament and the public to rely on reported information as a relevant and accurate reflection of an agency's performance is limited. The relevance and accuracy of performance information is enhanced when:
|
4.2 Reporting on reports | |
Agency reporting on major projects does not meet the requirements of the annual reports regulation. Forty-seven per cent of agencies did not report on costs to date and estimated completion dates for major works in progress. Of the 47 per cent of agencies that reported on major works, only one agency reported detail about significant cost overruns, delays, amendments, deferments or cancellations. |
NSW Treasury produce an annual report checklist to help agencies comply with their annual report obligations. Recommendation: Agencies should comply with the annual reports regulation and report on all mandatory fields, including significant cost overruns and delays, for their major works in progress. |
The information the annual reports regulation requires agencies to report deals only with major works in progress. There is no requirement to report on completed works. Sixteen of 30 agencies reported some information on completed major works. |
Conclusion: Agencies could improve their transparency if they reported, or were required to report:
|
This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency preventative and detective controls over purchasing card and taxi use for 2017–18.
Observation | Conclusion or recommendation |
5.1 Management of purchasing cards | |
Volume of credit card spend Purchasing card expenditure has increased by 76 per cent over the last four years in response to a government review into the cost savings possible from using purchasing cards for low value, high volume procurement. |
Conclusion: The increasing use of purchasing cards highlights the importance of an effective framework for the use and management of purchasing cards. |
Policy framework We found all agencies that held purchasing cards had a policy in place, but 26 per cent of agencies have not reviewed their purchasing card policy by the scheduled date, or do not have a scheduled revision date stated within their policy. |
Recommendation: Agencies should mitigate the risks associated with increased purchasing card use by ensuring policies and purchasing card frameworks remain current and compliant with the core requirements of TPP 17–09 'Use and Management of NSW Government Purchasing Cards'. |
Preventative controls We found that:
|
Agencies have designed and implemented preventative controls aimed at deterring the potential misuse of purchasing cards. Conclusion: Further opportunities exist for agencies to better control the use of purchasing cards, such as:
|
Detective controls Major reviews, such as data analytics (29 per cent of agencies) and independent spot checks (49 per cent of agencies) are not widely used. |
Agencies have designed and implemented detective controls aimed at identifying potential misuse of purchasing cards. Conclusion: More effective monitoring using purchasing card data can provide better visibility over spending activity and can be used to:
|
5.2 Management of taxis | |
Policy framework Thirteen per cent of agencies have not developed and implemented a policy to manage taxi use. In addition:
|
Conclusion: Agencies can promote savings and provide more options to staff where their taxi use policies:
|
Detective controls All agencies approve taxi expenditure by expense reimbursement, purchasing card and Cabcharge, and have implemented controls around this approval process. However, beyond this there is minimal monitoring and review activity, such as data monitoring, independent spot checks or internal audit reviews. |
Conclusion: Taxi spend at agencies is not significant in terms of its dollar value, but it is significant from a probity perspective. Agencies can better address the probity risk by incorporating taxi use into a broader purchasing card or fraud monitoring program. |
Fraud and corruption control is one of the 17 key elements of our governance lighthouse. Recent reports from ICAC into state agencies and local government councils highlight the need for effective fraud control and ethical frameworks. Effective frameworks can help protect an agency from events that risk serious reputational damage and financial loss.
Our 2016 Fraud Survey found the NSW Government agencies we surveyed reported 1,077 frauds over the three year period to 30 June 2015. For those frauds where an estimate of losses was made, the reported value exceeded $10.0 million. The report also highlighted that the full extent of fraud in the NSW public sector could be higher than reported because:
- unreported frauds in organisations can be almost three times the number of reported frauds
- our 2015 survey did not include all NSW public sector agencies, nor did it include any NSW universities or local councils
- fraud committed by citizens such as fare evasion and fraudulent state tax self-assessments was not within the scope of our 2015 survey
- agencies did not estimate a value for 599 of the 1,077 (56 per cent) reported frauds.
Commissioning and outsourcing of services to the private sector and the advancement of digital technology are changing the fraud and corruption risks agencies face. Fraud risk assessments should be updated regularly and in particular where there are changes in agency business models. NSW Treasury Circular TC18-02 NSW Fraud and Corruption Control Policy now requires agencies develop, implement and maintain a fraud and corruption control framework, effective from 1 July 2018.
Our Fraud Control Improvement Kit provides guidance and practical advice to help organisations implement an effective fraud control framework. The kit is divided into ten attributes. Three key attributes have been assessed below; prevention, detection and notification systems.
This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency fraud and corruption controls for 2017–18.
Observation | Conclusion or recommendation |
6.1 Prevention systems | |
Prevention systems Only 54 per cent of agencies have an employment screening policy and all agencies have IT security policies, but gaps in IT security controls could undermine their policies. |
Conclusion: Most agencies have implemented fraud prevention systems to reduce the risk of fraud. However poor IT security along with other gaps in agency prevention systems, such as employment screening practices heightens the risk of fraud and inappropriate use of data. Agencies can improve their fraud prevention systems by:
|
Twenty-three per cent of agencies were not performing fraud risk assessments and some agency fraud risk assessments may not be as robust as they could be. | Conclusion: Agencies' systems of internal controls may be less effective where new and emerging fraud risks have been overlooked, or known weaknesses have not been rectified. |
6.2 Detection systems | |
Detection systems Several agencies reported they were developing a data monitoring program, but only 38 per cent of agencies had already implemented a program. |
Studies have shown data monitoring, whereby entire populations of transactional data are analysed for indicators of fraudulent activity, is one of the most effective methods of early detection. Early detection decreases the duration a fraud remains undetected thereby limiting the extent of losses. Conclusion: Data monitoring is an effective tool for early detection of fraud and is more effective when informed by a comprehensive fraud risk assessment. |
6.3 Notification systems | |
Notification system All agencies have notification systems for reporting actual or suspected fraud and corruption. Most agencies provide multiple reporting lines, provide training and publicise options for staff to report actual or suspected fraud and corruption. |
Conclusion: Training staff about their obligations and the use of fraud notification systems promotes a fraud-aware culture |
Actions for Regional Assistance Programs
Regional Assistance Programs
Infrastructure NSW effectively manages how grant applications for regional assistance programs are assessed and recommended for funding. Its contract management processes are also effective. However, we are unable to conclude whether the objectives of these programs have been achieved as the relevant agencies have not yet measured their benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.
In 2011, the NSW Government established Restart NSW to fund new infrastructure with the proceeds from the sale and lease of government assets. From 2011 to 2017, the NSW Government allocated $1.7 billion from the fund for infrastructure in regional areas, with an additional commitment of $1.3 billion to be allocated by 2021. The NSW Government allocates these funds through regional assistance programs such as Resources for Regions and Fixing Country Roads. NSW councils are the primary recipients of funding provided under these programs.
The NSW Government announced the Resources for Regions program in 2012 with the aim of addressing infrastructure constraints in mining affected communities. Infrastructure NSW administers the program, with support from the Department of Premier and Cabinet.
The NSW Government announced the Fixing Country Roads program in 2014 with the aim of building more efficient road freight networks. Transport for NSW and Infrastructure NSW jointly administer this program, which funds local councils to deliver projects that help connect local and regional roads to state highways and freight hubs.
This audit assessed whether these two programs (Resources for Regions and Fixing Country Roads) were being effectively managed and achieved their objectives. In making this assessment, we answered the following questions:
- How well are the relevant agencies managing the assessment and recommendation process?
- How do the relevant agencies ensure that funded projects are being delivered?
- Do the funded projects meet program and project objectives?
The audit focussed on four rounds of Resources for Regions funding between 2013–14 to 2015–16, as well as the first two rounds of Fixing Country Roads funding in 2014–15 and 2015–16.
The project selection criteria are consistent with the program objectives set by the NSW Government, and the RIAP applied the criteria consistently. Probity and record keeping practices did not fully comply with the probity plans.
The assessment methodology designed by Infrastructure NSW is consistent with2 the program objectives and criteria. In the rounds that we reviewed, all funded projects met the assessment criteria.
Infrastructure NSW developed probity plans for both programs which provided guidance on the record keeping required to maintain an audit trail, including the use of conflict of interest registers. Infrastructure NSW and Transport for NSW did not fully comply with these requirements. The relevant agencies have taken steps to address this in the current funding rounds for both programs.
NSW Procurement Board Directions require agencies to ensure that they do not engage a probity advisor that is engaged elsewhere in the agency. Infrastructure NSW has not fully complied with this requirement. A conflict of interest arose when Infrastructure NSW engaged the same consultancy to act as its internal auditor and probity advisor.
While these infringements of probity arrangements are unlikely to have had a major impact on the assessment process, they weaken the transparency and accountability of the process.
Some councils have identified resourcing and capability issues which impact on their ability to participate in the application process. For both programs, the relevant agencies conducted briefings and webinars with applicants to provide advice on the objectives of the programs and how to improve the quality of their applications. Additionally, Transport for NSW and the Department of Premier and Cabinet have developed tools to assist councils to demonstrate the economic impact of their applications.
The relevant agencies provided feedback on unsuccessful applications to councils. Councils reported that the quality of this feedback has improved over time.
Recommendations
- By June 2018, Infrastructure NSW should:
- ensure probity reports address whether all elements of the probity plan have been effectively implemented.
- By June 2018, Infrastructure NSW and Transport for NSW should:
- maintain and store all documentation regarding assessment and probity matters according to the State Records Act 1998, the NSW Standard on Records Management and the relevant probity plans
Infrastructure NSW is responsible for overseeing and monitoring projects funded under Resources for Regions and Fixing Country Roads. Infrastructure NSW effectively manages projects to keep them on track, however it could do more to assure itself that all recipients have complied with funding deeds. Benefits and outcomes should also start to be measured and reported as soon as practicable after projects are completed to inform assessment of future projects.
Infrastructure NSW identifies projects experiencing unreasonable delays or higher than expected expenses as 'at‑risk'. After Infrastructure NSW identifies a project as 'at‑risk', it puts in place processes to resolve issues to bring them back on track. Infrastructure NSW, working with Public Works Advisory regional offices, employs a risk‑based approach to validate payment claims, however this process should be strengthened. Infrastructure NSW would get better assurance by also conducting annual audits of compliance with the funding deed for a random sample of projects.
Infrastructure NSW collects project completion reports for all Resources for Regions and Fixing Country Roads funded projects. It applies the Infrastructure Investor Assurance Framework to Resources for Regions and Fixing Country Roads at a program level. This means that each round of funding (under both programs) is treated as a distinct program for the purposes of benefits realisation. It plans to assess whether benefits have been realised once each project in a funding round is completed. As a result, no benefits realisation assessment has been done for any project funded under either Resources for Regions or Fixing Country Roads. Without project‑level benefits realisation, future decisions are not informed by the lessons from previous investments.
Recommendations
- By December 2018, Infrastructure NSW should:
- conduct annual audits of compliance with the funding deed for a random sample of projects funded under Resources for Regions and Fixing Country Roads
- publish the circumstances under which unspent funds can be allocated to changes in project scope
- measure benefits delivered by projects that were completed before December 2017
- implement an annual process to measure benefits for projects completed after December 2017
- By December 2018, Transport for NSW and Infrastructure NSW should:
- incorporate a benefits realisation framework as part of the detailed application.
Appendix one - Response from agencies
Appendix two - Maps of funded projects
Appendix three - About the audit
Appendix four - Performance auditing
Parliamentary reference - Report number #300 - released 17 May 2018
Actions for Agency compliance with NSW Government travel policies
Agency compliance with NSW Government travel policies
Overall, agencies materially complied with NSW Government travel policies.
However, the Auditor-General found some agencies:
- did not always book official travel through the approved supplier
- had weaknesses in their travel approval processes
- had travel policies that were inconsistent with the NSW Government policy
- did not adequately manage their travel records.
We asked the 15 participating agencies to complete a self assessment of the processes they have implemented to comply with the new policy. The key observations are summarised below.
Actions for Energy rebates for low income households
Energy rebates for low income households
The Department of Planning and Environment provides more than $245 million in energy rebates to around 27 percent of NSW households. This report highlights that the department is not monitoring the rebate schemes to understand whether they are delivering the best outcomes.
Most rebates are ongoing payments applied directly to energy bills reducing the amount payable by the householder. The structure of these rebates is complex and can be inequitable. Some households are eligible for four different rebates, each with its own eligibility criteria. Also, some households in very similar circumstances receive different levels of support depending on what type of energy is used in their home or which adult in the house is the energy account holder. For example, a household using both electricity and gas receives more assistance than a household with electricity alone even if total energy bills are the same.
By September 2018, the Department of Planning and Environment should:
- Ensure effective strategies are in place to make information about rebates available to all eligible, low-income households
- Evaluate alternative models and develop advice for government to reduce complexity and improve equity of ongoing rebates
- Establish measurable objectives for schemes that provide ongoing support, and monitor and measure performance of all schemes against objectives and outcome measures
- Assess the impacts of the forecast increase in embedded networks and develop strategies to manage any increased administrative risk
- Strengthen assurance that EAPA is being provided in accordance with its objectives and guidelines by implementing accreditation and compliance programs
- Ensure those eligible for EAPA financial support are not disadvantaged by inflexible payments, inconsistent provider practices, or inability to access an EAPA provider in a timely manner. Options include:
- moving from a fixed-value voucher to a flexible payment based on need irrespective of energy type
- establishing a ‘Provider of Last Resort’ facility for households that cannot access an EAPA Provider.
Parliamentary reference - Report number #292 - released 19 September 2017
Actions for 2016 - An overview
2016 - An overview
This report focuses on key observations and findings from 2016 audits and highlights key areas of focus for financial and performance audits in 2017.
Financial reporting | |
Observation | Conclusion |
Only one qualified audit opinion was issued on the 2015–16 financial statements of NSW public sector agencies, compared to two in 2014–15. | The quality of financial reporting continued to improve across the NSW public sector. |
More 2015–16 financial statements and audit opinions were signed within three months of the year end. | Timely financial reporting was facilitated by more agencies resolving significant accounting issues early, completing asset valuations on time and compiling sufficient evidence to support financial statement balances. |
NSW Treasury’s early close procedures in 2015–16 were again successful in improving the quality and timeliness of financial reporting, largely facilitated by the early resolution of accounting issues. For 2016–17, NSW Treasury has narrowed the scope of mandatory early close procedures. |
The narrowed scope of mandatory early close procedures may diminish the good performance in ensuring the quality and timeliness of financial reporting achieved in recent years. To mitigate this risk, NSW Treasury has mandated that agencies perform non-financial asset valuations and prepare proforma financial statements in their early close procedures. It also encourages them to continue with the good practices embedded in recent years. |
Although most agencies complied with NSW Treasury’s early close asset revaluation procedures we identified areas where they can improve. | Asset revaluations need to commence early enough to ensure all assets are identified and the results are analysed, recorded and reflected accurately in the early close financial statements. |
Number of misstatements | |||||
Year ended 30 June | 2015-16 | 2014-15 | 2013-14 | 2012-13 | 2011-12 |
Total reported misstatements | 298 | 396 | 459 | 661 | 1,077 |
All material misstatements identified by agencies and audit teams were corrected before the financial statements and audit opinions were signed. A material misstatement relates to an incorrect amount, classification, presentation or disclosure in the financial statements that could reasonably be expected to influence the economic decisions of users.
Significant matters reported to the portfolio Minister, Treasurer and Agency Head
In 2015–16, we reported the following significant matters to the portfolio Minister, Treasurer and agency head in our Statutory Audit Reports:
Appropriate financial controls help ensure the efficient and effective use of resources and the implementation and administration of agency policies. They are essential for quality and timely decision making.
In 2015–16, our audit teams made the following key observations on the financial controls of NSW public sector agencies.
Financial controls | |
Observation | Conclusion |
More needs to be done to implement audit recommendations on a timely basis. We found 212 internal control issues identified in previous audits had not been adequately addressed by 30 June 2016. |
Delays in implementing audit recommendations can impact the quality of financial information and the effectiveness of decision making. Agencies need to ensure they have action plans, timeframes and assigned responsibilities to address recommendations in a timely manner. |
Agencies continue to face challenges managing information security. Most information technology issues we identified related to poor IT user administration in areas like password controls and inappropriate access. | Agencies should review the design and effectiveness of information security controls to ensure data is adequately protected. |
We found shared service provider agreements did not always adequately address information security requirements. |
Where agencies use shared service providers they should consider whether the service level arrangements adequately address information security. |
Thirteen of 108 agencies required to attest to having a minimum set of information security controls did not do so in their 2015 annual reports. | The 'NSW Government Digital Information Security Policy' recognises the growing need for effective information security. With cyber security threats continuing to increase as digital services expand we plan to look at cyber security as part of our 2017–18 performance audit program. |
We identified instances where service level agreements with shared service providers were outdated, signed too late or did not exist. | Corporate and shared service arrangements are more effective when service level arrangements are negotiated and signed in time, clearly detail rights and responsibilities and include meaningful KPIs, fee arrangements and dispute resolution processes. |
Internal controls at GovConnect, the private sector provider of transactional and information technology services to many NSW public sector agencies were ineffective in 2015–16. We found mitigating actions taken to manage transition risks from ServiceFirst to GovConnect were ineffective in ensuring effective control over client transactions and data. | The Department of Finance, Services and Innovation should ensure GovConnect addresses the control deficiencies. It should also examine the breakdowns in the transition of the shared service arrangements and apply the learnings to other services being transitioned to the private sector. |
Maintenance backlogs exist in several NSW public sector agencies, including Roads and Maritime Services, Sydney Trains, NSW Health, the Department of Education and the Department of Justice. | To address backlog maintenance it is important for agencies to have asset lifecycle planning strategies that ensure newly built and existing assets are funded and maintained to a desired service level. |
Actions for Assessing major development applications
Assessing major development applications
The Planning Assessment Commission (the Commission) has improved its decision-making processes for major development applications in recent years. The Commission has improved how it consults the public and manages conflicts of interest, and now also publishes records of its meetings with applicants and stakeholders.
The Planning Assessment Commission (the Commission) is an independent body established in 2008 under the Environmental Planning and Assessment Act 1979 (the EP&A Act). It makes decisions on major development applications in New South Wales. Along with the Department of Planning and Environment (the Department) and the Land and Environment Court, it is one of three bodies that have a role in making decisions on these applications.
The Department refers development applications to the Commission where 25 or more objections have been received from the community, a local council objects to the proposal, or the applicant has donated to a political party.
These applications are often complex and controversial, and can attract a high level of public interest. This may mean that, regardless of the process, not all stakeholders are satisfied with the outcome.
The Commission is required to take into account section 79C of the EP&A Act when making decisions. Section 79C includes consideration of the likely environmental, social and economic impacts of the development.
This audit assessed the extent to which the Commission’s decisions on major development applications are made in a consistent and transparent manner. To assist us in making this assessment, we asked whether the Commission:
- has sound processes in place to help it make decisions on major development applications that are informed and made in a consistent manner
- ensures its decisions are free from bias and transparent to stakeholders and the public.
Conclusion
Over the last two years, the Commission has improved its decision-making process. It has improved how it consults the public and manages conflicts of interest, and now also publishes records of its meetings with applicants and stakeholders.
However, there are still some vital issues to be addressed to ensure it makes decisions in a consistent and transparent manner. Most importantly, the Commission was not able to show in every decision we reviewed how it met its statutory obligation to consider the matters in section 79C of the EP&A Act.
Despite improved probity measures put in place by the Commission, there is a perception among some stakeholders that it is not independent of the Department. The reasons for some of these concerns are outside of the Commission’s control. For example, the Commission becomes involved after the Department has prepared an assessment report which recommends whether a development should proceed. This creates the perception that the Commission is acting on the recommendation of the Department. The Department’s assessment report should state whether an application meets relevant legislative and policy requirements, but not recommend whether a development should be approved or not.
More can also be done to improve transparency in decision-making and the public’s perception of the independence of Commissioners. The Commission should continue to improve how it communicates the reasons for its decisions and also publish on its website a summary of Commissioners’ conflict of interest declarations for each development application.
Decision-making processes have improved but some key aspects need to be addressed
Although not articulated in one document, there is a framework in place to assist Commissioners make decisions on major development applications. This includes setting out the information to be considered, who to consult, and that a report is to be prepared. The Commission has recently improved how it conducts public meetings and the level of support provided to Commissioners to ensure they understand the decision-making process. The Commissioners we interviewed all showed a good understanding of their role.
As a consent authority, the Commission is required to consider the matters in section 79C of the EP&A Act when making a decision. However, it was not able to show how it met this requirement in every decision we reviewed. We found some evidence of these considerations in six of the nine cases we reviewed, for example in meeting notes or in its report on a decision. Of these six cases, the degree to which the Commission considered all matters under section 79C varied considerably. The larger, more complex applications were more likely to address these considerations. To demonstrate compliance with the EP&A Act, the Commission must be able to show how it considers all matters in section 79C for each decision it makes.
We found that the Commission has access to relevant information to make a decision and consults stakeholders for their views of the development. The level of consultation depends on the size and complexity of an application. If Commissioners decide they need more information to make a decision, they consult local councils, the community, other government agencies and experts as needed.
The Commission’s public meetings are a valuable part of the decision-making process, where new perspectives or issues are often raised. However, some aspects could be improved. For example, many stakeholders thought the five minutes allowed for individual speakers was insufficient. The Commission could be more flexible with this timeframe. Identifying new ways to notify the public of its meetings, other than advertisements on its website and in newspapers, would also ensure it reaches as many interested parties as possible.
Improved transparency and probity but the Commission is not seen by some as impartial
The Commission has sound processes in place to ensure that its decisions are impartial and transparent to the community. It has improved its probity measures over the last two years, following a review by the NSW Ombudsman in 2014. We found that the Commission:
- has probity policies and procedures which are available on its website
- has improved its record keeping of some processes, such as meetings with applicants and stakeholders
- publishes its decision and supporting documentation, such as meeting notes, on its website.
Conflicts of interest are a significant risk for the Commission because they could lead to corruption, abuse of public office, and affect the public’s view of its independence. The Commission manages this risk well. It has a policy in place to address potential, perceived or actual conflicts. Commissioners update their conflicts of interest records annually, and declare any conflicts when the Commission assigns them to a development application. Unlike the Commission’s probity polices, Commissioners’ conflict of interest declarations are not available on its website. Providing a summary of this information on its website when Commissioners are allocated to a development application would further improve transparency around conflicts of interest.
The Commission has been improving how it communicates its decisions to the public. It now produces fact sheets for its decisions on matters that attract a high level of public interest. Its reports on decisions for complex applications also discuss issues raised by the community. However, the level of detail varied in the decisions we reviewed, and it was not always clear how conditions placed on a development would resolve identified issues. Similarly, the reports did not clearly address the matters under section 79C of the EP&A Act. Reporting this would further improve the transparency of its decisions, and clearly demonstrate compliance with the EP&A Act.
While we did not find any issues that would make us question the integrity or independence of Commissioners, there remains a perception among some stakeholders that the Commission is not impartial. Some of these concerns are within the Commission’s control to fix, such as allowing individual speakers at public meetings extra time to discuss their issues, therefore avoiding perceptions of bias.
Other perceptions, such as the Commission being part of the Department and not an independent decision making authority, are outside the Commission’s immediate control. For example, the Commission receives applications at the end of the assessment process, after the Department has prepared an assessment report recommending whether the application should be approved. This means there are effectively two reports on an application; the Department’s assessment report and the Commission’s report on its decision. However, there is only one decision-maker: the Commission. This may cause community confusion about the roles of the Department and the Commission in the decision-making process. Clearer separation of their roles in assessing applications and preparing reports is needed.
To minimise the perception that the Commission is simply ‘rubber stamping’ the Department’s recommendations, assessment reports should not recommend whether or not a project be approved. Instead, they should provide the Department’s views on whether a project meets relevant legislative and policy requirements. The Commission should also be involved earlier in the process, so it can establish key facts and identify relevant issues sooner. It should request that the Department’s assessment report covers matters Commissioners consider particularly important when assessing projects under section 79C. Earlier referral of applications should also help the Commission to plan its work in assessing applications, and may reduce the time taken to reach a decision.
Unless these issues are addressed, stakeholders will continue to believe the Commission does not act in a transparent and impartial manner, which could erode public confidence in the Commission.
The Planning Assessment Commission
The Planning Assessment Commission (the Commission) is a planning authority established in 2008 under the Environmental Planning and Assessment Act 1979 (the EP&A Act). One of its functions is to make decisions on major development applications.
The Commission is independent of the Department of Planning and Environment (the Department) and the Minister for Planning. This means its decisions are not subject to the direction or control of the Department or the Minister.
The Department refers applications for major development to the Commission, including state significant development and infrastructure applications. These projects are generally initiated by the private sector. Applications are referred to the Commission when one or more of the following criteria are met:
- more than 25 objections are received about the proposal
- the local council objects to the proposal
- the applicant has donated $1,000 or more to a political party or member of parliament.
These applications are often controversial and may attract a high level of public interest. Of the 29 development applications the Commission received in 2015–16, almost 40 per cent were in the mining and energy sectors, and another 40 per cent related to urban development.
Section 79C of the EP&A Act outlines the matters the Commission must consider when making decisions about major development applications. These include:
- any relevant environmental and planning instruments
- likely environmental, social and economic impacts of the development
- suitability of the site for the development
- submissions received about the application
- the public interest.
In addition to making decisions about major development applications, the Commission also reviews major developments as part of the planning process, and provides independent expert advice to the government on planning and development matters. Since the Commission’s inception, it has provided advice on 76 matters, conducted 39 reviews, and made 444 decisions on development applications.
Process for approving major development applications
The Commission is one of three bodies that have a role in the planning and approval process for major development applications in New South Wales, as seen in Exhibit 1. The other two bodies are the Department of Planning and Environment, and the Land and Environment Court.
The Department determines the outcomes of major development applications. When an application meets one of the criteria listed above, it refers these to the Commission to make the decision. In certain circumstances, the Land and Environment Court hears appeals against decisions made by either the Department or the Commission.
A Memorandum of Understanding between the Commission and the Department sets out timeframes the Commission must meet when making a decision, specifically:
- two weeks where no stakeholder meetings are required
- three weeks where stakeholder meetings are required
- six weeks when a public meeting is required.
Parliamentary reference - Report number #279 - released 19 January 2017
Actions for Grants Administration
Grants Administration
We found no significant difference in the funding of government and opposition electorates. However, more money was given to electorates that were safely held by the major parties. These seats received $1.29 for every dollar given to marginal and independent seats with government marginals getting the least. Electorates also receive different levels of funding according to which region they are in. Such variations may reflect valid agency objectives such as meeting State Plan targets or addressing socio-economic disadvantage.
But while agencies publish who gets what, they do not adequately evaluate or explain what grant programs have achieved. As a result, there is a risk that New South Wales may not get the best value for its spending. We recommend that agencies regularly evaluate their grant programs and publish the results.
Parliamentary reference - Report number #186 - released 6 May 2009
Actions for Controlling and reducing pollution from industry
Controlling and reducing pollution from industry
The regulatory framework introduced under the Protection of the Environment Operations Act 1997, along with other initiatives progressively being implemented by the Environment Protection Authority (EPA), should enhance the overall effectiveness of environment protection in NSW. The Audit Office is of the opinion that the framework is consistent with best practice and once fully implemented, should contribute to the achievement of further improvements in the environmental performance of industry.
However while the legislative framework supports best practice in regulation and enforcement, there are a number of issues which limit the effectiveness of the reforms. Some of the problems, such as the quality of licences and the effectiveness of compliance activities, have been identified by the EPA and may be addressed through recent initiatives.
Parliamentary reference - Report number #82 - released 18 April 2001