The Auditor-General for New South Wales, Margaret Crawford, released her report today on the NSW Planning and Environment cluster. The report focuses on key observations and findings from the most recent financial audits of these agencies. Unqualified audit opinions were issued for all agencies' financial statements. However, some cultural institutions had challenges valuing collection assets in 2017–18. These issues were resolved before the financial statements were finalised.

This report analyses the results of our audits of financial statements of the Planning and Environment cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides parliament and other users of the Planning and Environment cluster agencies' financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • service delivery.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making is enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Planning and Environment cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all agencies' financial statements. The quality of financial reporting remains high across the cluster.
2.2 Key accounting issues
There were errors in some cultural institutions' collection asset valuations. Recommendation: Collection asset valuations could be improved by:
  • early engagement with key stakeholders regarding the valuation method and approach
  • completing revaluations, including quality review processes earlier 
  • improving the quality of asset data by registering all items in an electronic database. 
2.3 Timeliness of financial reporting
Except for two agencies, the audits of cluster agencies’ financial statements were completed within the statutory timeframe.  Issues with asset revaluations delayed the finalisation of two environment and heritage agencies' financial statement audits. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Planning and Environment cluster for 2018
  • the areas of focus identified in the Audit Office work program.

The Audit Office annual work program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.

Observation Conclusions and recommendations
3.1 Internal controls
One in five internal control weaknesses reported in 2017–18 were repeat issues. Delays in implementing audit recommendations can prolong the risk of fraud and error.
Recommendation (repeat issue): Management letter recommendations to address internal control weaknesses should be actioned promptly, with a focus on addressing repeat issues.
One extreme risk was identified relating to the National Art School. The School does not have an occupancy agreement for the Darlinghurst campus. Lack of formal agreement creates uncertainty over the School's continued occupancy of the Darlinghurst site.

The School should continue to liaise with stakeholders to formalise the occupancy arrangement. 
 
3.2 Information technology controls
The controls and governance arrangements when migrating payroll data from the Aurion system to SAP HR system were effective. Data migration from the Aurion system to SAP HR system had no significant issues.
The Department can improve controls over user access to SAP system. The Department needs to ensure the SAP user access controls are appropriate, including investigation of excess access rights and resolving segregation of duties issues. 
3.3 Annual work program
Agencies used different benchmarks to monitor their maintenance expenditure. The cluster agencies under review operate in different industries. As a result, they do not use the same benchmarks to assess the adequacy of their maintenance spend. 

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited. 

We report this information on service delivery to provide additional context to understand the operations of the Planning and Environment cluster, and to collate and present service information for different segments of the cluster in one report. 

In our recent performance audit, ‘Progress and measurement of Premier's Priorities’, we identified 12 limitations of performance measurement and performance data. We recommended the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all relevant agency data sources.

Published

Actions for Transport 2018

Transport 2018

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Risk
Service delivery
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford released her report today on key observations and findings from the 30 June 2018 financial statement audits of agencies in the Transport cluster. Unqualified audit opinions were issued for all agencies' financial statements. However, assessing the fair value of the broad range of transport related assets creates challenges.

This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides Parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all agencies' financial statements Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
2.2 Key accounting issues
Valuation of assets continues to create challenges. Although agencies complied with the requirements of the accounting standards and Treasury policies on valuations, we identified some opportunities for improvements at RMS.

RMS incorporated data from its asset condition assessments for the first time in the valuation methodology which improved the valuation outcome. Overall, we were satisfied with the valuation methodology and key assumptions, but we noted some deficiencies in the asset data in relation to asset component unit rates and old condition data for some components of assets. 

Also, a bypass and tunnel were incorrectly excluded from RMS records and valuation process since 2013. This resulted in an increase for these assets’ value by $133 million.

The valuation inputs for Wetlands and Moorings were revised this year to better reflect the assets' characteristics resulting in a $98.0 million increase.

2.3 Timeliness of financial reporting
Residual Transport Corporation did not submit its financial statements by the statutory reporting deadline. Residual Transport Corporation remained a dormant entity with no transactions for the year ended 30 June 2018.
With the exception of Residual Transport Corporation, all agencies completed early close procedures and submitted financial statements within statutory timeframes. Early close procedures allow financial reporting issues and risks to be addressed early in the reporting and audit process.
2.4 Financial sustainability
NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations reported negative net assets of $75.7 million and $89,000 respectively at 30 June 2018.  NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations continue to require letters of financial support to confirm their ability to pay liabilities as they fall due. 
2.5 Passenger revenue and patronage
Transport agencies revenue growth increased at a higher rate than patronage. Public transport passenger revenue increased by $114 million (8.3 per cent) in 2017–18, and patronage increased by 37.1 million (5.1 per cent) across all modes of transport based on data provided by TfNSW. 
Negative balance Opal Cards resulted in $3.8 million in revenue not collected in 2017–18 and $7.8 million since the introduction of Opal. A total of 1.1 million Opal cards issued since its introduction have negative balances. Transport for NSW advised it is liaising with the ticketing vendor to implement system changes and are investigating other ways to reduce the occurrences.
2.6 Cost recovery from public transport users
Overall cost recovery from users has decreased. Overall cost recovery from public transport users (on rail and bus services by STA) decreased from 23.2 per cent to 22.4 per cent between 2016–17 and 2017–18. The main reason for the decrease is due to expenditure increasing at a faster rate than revenue in 2017–18.


 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Transport cluster for 2018
  • the areas of focus identified in the Audit Office annual work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters. 

Observation Conclusions and recommendations
3.1 Internal controls 
There was an increase in findings on internal controls across the Transport cluster. Key themes related to information technology, employee leave entitlements and asset management. Eighteen per cent of all issues were repeat issues.
3.2 Audit Office Annual work program
The Transport cluster wrote-off over $200 million of assets which were replaced by new assets or technology.

Majority of this write-off was recognised by RMS, with $199 million relating to the write-off of existing assets which have been replaced during the year. 

RailCorp is expected to convert to TAHE from 1 July 2019. Several working groups are considering different aspects of the TAHE transition including its status as a for-profit Public Trading Enterprise and which assets to transfer to TAHE. We will continue to monitor developments on TAHE for any impact to the financial statements.
RMS' estimated maintenance backlog at 30 June 2018 of $3.4 billion is lower than last year. Sydney Trains' estimated maintenance backlog at 30 June 2018 increased by 20.6 per cent to $434 million. TfNSW does not quantify its backlog maintenance. TfNSW advised it is liaising with Infrastructure NSW to develop a consistent definition of maintenance backlog across all transport service providers. 
Not all agencies monitor unplanned maintenance across the Transport cluster. Unplanned maintenance can be more expensive than planned maintenance. TfNSW should develop a consistent approach to define, monitor and track unplanned maintenance across the cluster.

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited. 

We report this information on service delivery to provide additional context to understand the operations of the Transport cluster and to collate and present service information for different modes of transport in one report. 

In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.

Published

Actions for Internal Controls and Governance 2018

Internal Controls and Governance 2018

Education
Community Services
Finance
Health
Industry
Justice
Planning
Premier and Cabinet
Transport
Treasury
Whole of Government
Environment
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management

The Auditor-General for New South Wales Margaret Crawford found that as NSW state government agencies’ digital footprint increases they need to do more to address new and emerging information technology (IT) risks. This is one of the key findings to emerge from the second stand-alone report on internal controls and governance of the 40 largest NSW state government agencies.

This report analyses the internal controls and governance of the 40 largest agencies in the NSW public sector for the year ended 30 June 2018.

This report covers the findings and recommendations from our 2017–18 financial audits that relate to internal controls and governance at the 40 largest agencies (refer to Appendix three) in the NSW public sector.

This report offers insights into internal controls and governance in the NSW public sector

This is our second report dedicated to internal controls and governance at NSW State Government agencies. The report provides insights into the effectiveness of controls and governance processes in the NSW public sector by:

  • highlighting the potential risks posed by weaknesses in controls and governance processes
  • helping agencies benchmark the adequacy of their processes against their peers
  • focusing on new and emerging risks, and the internal controls and governance processes that might address those risks.

Without strong governance systems and internal controls, agencies increase the risks associated with effectively managing their finances and delivering services to citizens. The way agencies deliver services increasingly relies on contracts and partnerships with the private sector. Many of these arrangements deliver front line services, but others provide less visible back office support. For example, an agency may rely on an IT service provider to manage a key system used to provide services to the community. The contract and service level agreements are only truly effective where they are actively managed to reduce risks to continuous quality service delivery, such as interruptions caused by system outages, cyber security attacks and data security breaches.

Our audits do not review all aspects of internal controls and governance every year. We select a range of measures, and report on those that present heightened risks for agencies to mitigate. This report divides these into the following five areas:

  1. Internal control trends
  2. Information technology (IT), including IT vendor management
  3. Transparency and performance reporting
  4. Management of purchasing cards and taxis
  5. Fraud and corruption control.

The findings in this report should not be used to draw conclusions on the effectiveness of individual agency control environments and governance arrangements. Specific financial reporting, controls and service delivery comments are included in the individual 2018 cluster financial audit reports, which will be tabled in Parliament from November to December 2018.

The focus of the report has changed since last year

Last year's report topics included asset management, ethics and conduct, and risk management. We are reporting on new topics this year. We plan to introduce new topics and re-visit our previous topics in subsequent reports on a cyclical basis. This will provide a baseline against which to measure the NSW public sectors’ progress in implementing appropriate internal controls and governance processes to mitigate existing, new and emerging risks in the public sector.

Agencies selected for the volume account for 95 per cent of the state's expenditure

While we have covered only 40 agencies in this report, those selected are a large enough group to identify common issues and insights. They represent about 95 per cent of total expenditure for all NSW public sector agencies.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of findings, level of risk and the most common deficiencies we found across agencies. The rest of this volume presents this year’s controls and governance findings in more detail.

Observation Conclusions and recommendations
2.1 High risk findings
We found six high risk findings (seven in 2016–17), one of which was repeated from both last year and 2015–16. Recommendation: Agencies should reduce risk by addressing high risk internal control deficiencies as a priority.
2.2 Common findings
We found several internal controls and governance findings common to multiple agencies. Conclusion: Central agencies or the lead agency in a cluster can play a lead role in helping ensure agency responses to common findings are consistent, timely, efficient and effective.
2.3 New and repeat findings
Although internal control deficiencies decreased over the last four years, this year has seen a 42 per cent increase in internal control deficiencies. The increase in new IT control deficiencies and repeat IT control deficiencies signifies an emerging risk for agencies.
IT control deficiencies feature in this increase, having risen by 63 per cent since last year. The number of repeat IT control deficiencies has doubled and is driven by the increasing digital footprint left by agencies as government prioritises on-line interfaces with citizens, and the number of transactions conducted through digital channels increases

Recommendation: Agencies should reduce IT risks by:

  • assigning ownership of recommendations to address IT control deficiencies, with timeframes and actions plans for implementation
  • ensuring audit and risk committees and agency management regularly monitor the implementation status of recommendations.

 

Government agencies’ financial reporting is now heavily reliant on information technology (IT). IT is also increasingly important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our audits reviewed whether agencies have effective controls in place to manage both key financial systems and IT service contracts.

Observation Conclusions and recommendations
3.1 Management of IT vendors
Contract management framework 
Although 87 per cent of agencies have a contract management policy to manage IT vendors, one fifth require review.
 

Conclusion: Agencies can more effectively manage IT vendor contracts by developing policies and procedures to ensure vendor management frameworks are kept up to date, plans are in place to manage vendor performance and risk, and compliance with the framework is monitored by:

  • internal audit focusing on key contracting activities
  • experienced officers who are independent of contract administration performing spot checks or peer reviews
  • targeted analysis of data in contract registers.
Contract risk management
Forty-one per cent of agencies are not using contract management plans and do not assess contract risks. Half of the agencies that did assess contract risks, had not updated the risk assessments since the commencement of the contract.
 
Conclusion: Instead of applying a 'set and forget' approach in relation to management of contract risks, agencies should assess risk regularly and develop a plan to actively manage identified risks throughout the contract lifecycle - from negotiation and commencement, to termination.

Performance management
Eighty-six per cent of agencies meet with vendors to discuss performance. 

Only 24 per cent of agencies sought assurance about the accuracy of vendor reporting against KPIs, yet sixty-seven per cent of the IT contracts allow agencies to determine performance based payments and/or penalise underperformance.

Conclusion: Agencies are monitoring IT vendor performance, but could improve outcomes and more effectively manage under-performance by:

  • a more active, rigorous approach to both risk and performance management
  • checking the accuracy of vendor reporting against those KPIs and where appropriate seeking assurance over their accuracy
  • invoking performance based payments clauses in contracts when performance falls below agreed standards.

Transitioning services
Forty-three per cent of the IT vendor contracts did not contain transitioning-out provisions.

Where IT vendor contracts do make provision for transitioning-out, only 28 per cent of agencies have developed a transitioning-out plan with their IT vendor.

Conclusion: Contract transition/phase out clauses and plans can mitigate risks to service disruption, ensure internal controls remain in place, avoid unnecessary costs and reduce the risk of 'vendor lock-in'.
Contract Registers
Eleven out of forty agencies did not have a contract register, or have registers that are not accurate and/or complete.

Conclusion: A contract register helps to manage an agency’s compliance obligations under the Government Information (Public Access) Act 2009 (the GIPA Act). However, it also helps agencies more effectively manage IT vendors by:

  • monitoring contract end dates and contract extensions, and commence new procurements through their central procurement teams in a timely manner
  • managing their contractual commitments, budgeting and cash flow requirements.

Recommendation: Agencies should ensure their contract registers are complete and accurate so they can more effectively govern contracts and manage compliance obligations.

3.2 IT general controls
Governance
Ninety-five per cent of agencies have established policies to manage key IT processes and functions within the agency, with ten per cent of those due for review.
 
Conclusion: Regular review of IT policies ensures risks are considered and appropriate strategies and procedures are implemented to manage these risks on a consistent basis. An absence of policies can lead to ad-hoc responses to risks, and failure to consider emerging IT risks and changes to agency IT environments. 

User access administration
Seventy-two deficiencies were identified related to user access administration, including:

  • thirty issues related to granting user access across 43 per cent of agencies
  • sixteen issues related to removing user access across 30 per cent of agencies
  • twenty-six issues related to periodic reviews of user access across 50 per cent of agencies.
Recommendation: Agencies should strengthen the administration of user access to prevent inappropriate access to key systems.
Privileged access
Forty per cent of agencies do not periodically review logs of the activities of privileged users to identify suspicious or unauthorised activities.

Recommendation: Agencies should:

  • review the number of, and access granted to privileged users, and assess and document the risks associated with their activities
  • monitor user access to address risks from unauthorised activity.
Password controls
Twenty-three per cent of agencies did not comply with their own policy on password parameters.
Recommendation: Agencies should ensure IT password settings comply with their password policies.
Program changes
Fifteen per cent of agencies had deficient IT program change controls mainly related to segregation of duties and authorisation and testing of IT program changes prior to deployment.
Recommendation: Agencies should maintain appropriate segregation of duties in their IT functions and test system changes before they are deployed.

 

This chapter outlines our audit observations, conclusions and recommendations from our review of how agencies reported their performance in their 2016–17 annual reports. The Annual Reports (Statutory Bodies) Regulation 2015 and Annual Reports (Departments) Regulation 2015 (annual reports regulation) currently prescribes the minimum requirements for agency annual reports.

Observation Conclusion or recommendation
4.1 Reporting on performance

Only 57 per cent of agencies linked reporting on performance to their strategic objectives.

The use of targets and reporting performance over time was limited and applied inconsistently.

Conclusion: There is significant disparity in the quality and consistency of how agencies report on their performance in their annual reports. This limits the reliability and transparency of reported performance information.

Agencies could improve performance reporting by clearly linking strategic objectives to reported outcomes, and reporting on performance against targets over time. NSW Treasury may need to provide more guidance to agencies to support consistent and high-quality performance reporting in annual reports.

There is no independent assurance that the performance metrics agencies report in their annual reports are accurate.

Prior performance audits have noted issues related to the collection of performance information. For example, our 2016 Report on Red Tape Reduction highlighted inaccuracies in how the dollar-value of red tape reduction had been reported.

Conclusion: The ability of Parliament and the public to rely on reported information as a relevant and accurate reflection of an agency's performance is limited.

The relevance and accuracy of performance information is enhanced when:

  • policies and guidance support the consistent and accurate collection of data
  • internal review processes and management oversight are effective
  • independent review processes are established to provide effective challenge to the assumptions, judgements and methodology used to collect the reported performance information.
4.2 Reporting on reports

Agency reporting on major projects does not meet the requirements of the annual reports regulation.

Forty-seven per cent of agencies did not report on costs to date and estimated completion dates for major works in progress. Of the 47 per cent of agencies that reported on major works, only one agency reported detail about significant cost overruns, delays, amendments, deferments or cancellations.

NSW Treasury produce an annual report checklist to help agencies comply with their annual report obligations.

Recommendation: Agencies should comply with the annual reports regulation and report on all mandatory fields, including significant cost overruns and delays, for their major works in progress.

The information the annual reports regulation requires agencies to report deals only with major works in progress. There is no requirement to report on completed works.

Sixteen of 30 agencies reported some information on completed major works.

Conclusion: Agencies could improve their transparency if they reported, or were required to report:

  • on both works in progress and projects completed during the year
  • actual costs and completion dates, and forecast completion dates for major works, against original and revised budgets and original expected completion dates
  • explanations for significant cost overruns, delays and key project performance metrics.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency preventative and detective controls over purchasing card and taxi use for 2017–18.

Observation Conclusion or recommendation
5.1 Management of purchasing cards
Volume of credit card spend
Purchasing card expenditure has increased by 76 per cent over the last four years in response to a government review into the cost savings possible from using purchasing cards for low value, high volume procurement.
 
Conclusion: The increasing use of purchasing cards highlights the importance of an effective framework for the use and management of purchasing cards.
Policy framework
We found all agencies that held purchasing cards had a policy in place, but 26 per cent of agencies have not reviewed their purchasing card policy by the scheduled date, or do not have a scheduled revision date stated within their policy.
Recommendation: Agencies should mitigate the risks associated with increased purchasing card use by ensuring policies and purchasing card frameworks remain current and compliant with the core requirements of TPP 17–09 'Use and Management of NSW Government Purchasing Cards'.
Preventative controls
We found that:
  • all agencies maintained purchasing card registers
  • seventy-six per cent provided training to cardholders prior to being issued with a card
  • eighty-nine per cent appointed a program administrator, but only half of these had clearly defined roles and responsibilities
  • thirty-two per cent of agencies place merchant blocks on purchasing cards
  • forty-seven per cent of agencies place geographic restrictions on purchasing cards.

Agencies have designed and implemented preventative controls aimed at deterring the potential misuse of purchasing cards.

Conclusion: Further opportunities exist for agencies to better control the use of purchasing cards, such as:

  • updating purchasing card registers to contain all mandatory fields required by TPP17–09
  • appointing a program administrator for the agency's purchasing card framework and defining their role and responsibility for the function
  • strengthening preventive controls to prevent misuse.

Detective controls
Ninety-two per cent of agencies have designed and implemented at least one control to monitor purchasing card activity.

Major reviews, such as data analytics (29 per cent of agencies) and independent spot checks (49 per cent of agencies) are not widely used.

Agencies have designed and implemented detective controls aimed at identifying potential misuse of purchasing cards.

Conclusion: More effective monitoring using purchasing card data can provide better visibility over spending activity and can be used to:

  • detect misuse and investigate exceptions
  • analyse trends to highlight cost saving opportunities.
5.2 Management of taxis
Policy framework
Thirteen per cent of agencies have not developed and implemented a policy to manage taxi use. In addition:
  • a further 41 per cent of agencies have not reviewed their policies by the scheduled revision date, or do not have a scheduled revision date
  • more than half of all agencies’ policies do not offer alternative travel options. For example, only 36 per cent of policies promoted the use of general Opal cards.
Conclusion: Agencies can promote savings and provide more options to staff where their taxi use policies:
  • limit the circumstances where taxi use is appropriate
  • offer alternate, lower cost options to using taxis, such as general Opal cards and rideshare.
Detective controls
All agencies approve taxi expenditure by expense reimbursement, purchasing card and Cabcharge, and have implemented controls around this approval process. However, beyond this there is minimal monitoring and review activity, such as data monitoring, independent spot checks or internal audit reviews.
Conclusion: Taxi spend at agencies is not significant in terms of its dollar value, but it is significant from a probity perspective. Agencies can better address the probity risk by incorporating taxi use into a broader purchasing card or fraud monitoring program.

 

Fraud and corruption control is one of the 17 key elements of our governance lighthouse. Recent reports from ICAC into state agencies and local government councils highlight the need for effective fraud control and ethical frameworks. Effective frameworks can help protect an agency from events that risk serious reputational damage and financial loss.

Our 2016 Fraud Survey found the NSW Government agencies we surveyed reported 1,077 frauds over the three year period to 30 June 2015. For those frauds where an estimate of losses was made, the reported value exceeded $10.0 million. The report also highlighted that the full extent of fraud in the NSW public sector could be higher than reported because:

  • unreported frauds in organisations can be almost three times the number of reported frauds
  • our 2015 survey did not include all NSW public sector agencies, nor did it include any NSW universities or local councils
  • fraud committed by citizens such as fare evasion and fraudulent state tax self-assessments was not within the scope of our 2015 survey
  • agencies did not estimate a value for 599 of the 1,077 (56 per cent) reported frauds.

Commissioning and outsourcing of services to the private sector and the advancement of digital technology are changing the fraud and corruption risks agencies face. Fraud risk assessments should be updated regularly and in particular where there are changes in agency business models. NSW Treasury Circular TC18-02 NSW Fraud and Corruption Control Policy now requires agencies develop, implement and maintain a fraud and corruption control framework, effective from 1 July 2018. 

Our Fraud Control Improvement Kit provides guidance and practical advice to help organisations implement an effective fraud control framework. The kit is divided into ten attributes. Three key attributes have been assessed below; prevention, detection and notification systems.

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency fraud and corruption controls for 2017–18.

Observation Conclusion or recommendation
6.1 Prevention systems

Prevention systems
Ninety-two per cent of agencies have a fraud control plan in place, 81 per cent maintain a fraud database and 79 per cent report fraud and corruption matters as a standing item on audit and risk committee agendas.

Only 54 per cent of agencies have an employment screening policy and all agencies have IT security policies, but gaps in IT security controls could undermine their policies.

Conclusion: Most agencies have implemented fraud prevention systems to reduce the risk of fraud. However poor IT security along with other gaps in agency prevention systems, such as employment screening practices heightens the risk of fraud and inappropriate use of data.

Agencies can improve their fraud prevention systems by:

  • completing regular fraud risk assessments, embedding fraud risk assessment into their enterprise risk management process and reporting the results of the assessment to the audit and risk committee
  • maintaining a fraud database and reviewing it regularly for systemic issues and reporting a redacted version of the database on the agency's website to inform corruption prevention networks
  • developing policies and procedures for employee screening and benchmarking their current processes against ICAC's publication ‘Strengthening Employment Screening Practices in the NSW Public Sector’
  • developing and maintaining up to date IT security policies and monitoring compliance with the policy.
Twenty-three per cent of agencies were not performing fraud risk assessments and some agency fraud risk assessments may not be as robust as they could be.  Conclusion: Agencies' systems of internal controls may be less effective where new and emerging fraud risks have been overlooked, or known weaknesses have not been rectified.
6.2 Detection systems
Detection systems
Several agencies reported they were developing a data monitoring program, but only 38 per cent of agencies had already implemented a program.
 

Studies have shown data monitoring, whereby entire populations of transactional data are analysed for indicators of fraudulent activity, is one of the most effective methods of early detection. Early detection decreases the duration a fraud remains undetected thereby limiting the extent of losses.

Conclusion: Data monitoring is an effective tool for early detection of fraud and is more effective when informed by a comprehensive fraud risk assessment.

6.3 Notification systems
Notification system
All agencies have notification systems for reporting actual or suspected fraud and corruption. Most agencies provide multiple reporting lines, provide training and publicise options for staff to report actual or suspected fraud and corruption.
Conclusion: Training staff about their obligations and the use of fraud notification systems promotes a fraud-aware culture

 

Published

Actions for Mobile speed cameras

Mobile speed cameras

Transport
Compliance
Financial reporting
Information technology
Internal controls and governance
Management and administration
Regulation
Service delivery

Key aspects of the state’s mobile speed camera program need to be improved to maximise road safety benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. Mobile speed cameras are deployed in a limited number of locations with a small number of these being used frequently. This, along with decisions to limit the hours that mobile speed cameras operate, and to use multiple warning signs, have reduced the broad deterrence of speeding across the general network - the main policy objective of the mobile speed camera program.

The primary goal of speed cameras is to reduce speeding and make the roads safer. Our 2011 performance audit on speed cameras found that, in general, speed cameras change driver behaviour and have a positive impact on road safety.

Transport for NSW published the NSW Speed Camera Strategy in June 2012 in response to our audit. According to the Strategy, the main purpose of mobile speed cameras is to reduce speeding across the road network by providing a general deterrence through anywhere, anytime enforcement and by creating a perceived risk of detection across the road network. Fixed and red-light speed cameras aim to reduce speeding at specific locations.

Roads and Maritime Services and Transport for NSW deploy mobile speed cameras (MSCs) in consultation with NSW Police. The cameras are operated by contractors authorised by Roads and Maritime Services. MSC locations are stretches of road that can be more than 20 kilometres long. MSC sites are specific places within these locations that meet the requirements for a MSC vehicle to be able to operate there.

This audit assessed whether the mobile speed camera program is effectively managed to maximise road safety benefits across the NSW road network.

Conclusion

The mobile speed camera program requires improvements to key aspects of its management to maximise road safety benefits. While camera locations have been selected based on crash history, the limited number of locations restricts network coverage. It also makes enforcement more predictable, reducing the ability to provide a general deterrence. Implementation of the program has been consistent with government decisions to limit its hours of operation and use multiple warning signs. These factors limit the ability of the mobile speed camera program to effectively deliver a broad general network deterrence from speeding.

Many locations are needed to enable network-wide coverage and ensure MSC sessions are randomised and not predictable. However, there are insufficient locations available to operate MSCs that meet strict criteria for crash history, operator safety, signage and technical requirements. MSC performance would be improved if there were more locations.

A scheduling system is meant to randomise MSC location visits to ensure they are not predictable. However, a relatively small number of locations have been visited many times making their deployment more predictable in these places. The allocation of MSCs across the time of day, day of week and across regions is prioritised based on crash history but the frequency of location visits does not correspond with the crash risk for each location.

There is evidence of a reduction in fatal and serious crashes at the 30 best-performing MSC locations. However, there is limited evidence that the current MSC program in NSW has led to a behavioural change in drivers by creating a general network deterrence. While the overall reduction in serious injuries on roads has continued, fatalities have started to climb again. Compliance with speed limits has improved at the sites and locations that MSCs operate, but the results of overall network speed surveys vary, with recent improvements in some speed zones but not others.
There is no supporting justification for the number of hours of operation for the program. The rate of MSC enforcement (hours per capita) in NSW is less than Queensland and Victoria. The government decision to use multiple warning signs has made it harder to identify and maintain suitable MSC locations, and impeded their use for enforcement in both traffic directions and in school zones. 

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #308 - released 18 October 2018

Published

Actions for Planning and Environment 2017

Planning and Environment 2017

Planning
Environment
Asset valuation
Information technology
Internal controls and governance
Management and administration
Project management

The following report highlights results of financial audits of agencies in the Planning and Environment cluster. The report focuses on key observations and findings from the most recent audits of these agencies.

The audits were completed for most agencies in the cluster and unqualified audit opinions issued. Issues identified during the financial statement audits of seven small agencies delayed their finalisation beyond the statutory deadline, and six of these remain incomplete. Apart from these small agencies, the quality of financial reporting across the cluster remained at a high standard.

1. Financial reporting and controls

Financial reporting Unqualified audit opinions were issued for 39 of the 45 cluster agencies. Issues identified during the financial statement audits of seven small agencies delayed their finalisation beyond the statutory deadline. Six of these audits remain incomplete at the date of this report.
  Agencies completed early close procedures mandated by the Treasury. We noted opportunities for agencies to improve the effectiveness of these procedures.
Internal Controls One in six internal control weaknesses identified during the financial audits were repeat issues. Agencies should action audit recommendations promptly.
  User administration over financial systems needs to be strengthened to prevent inappropriate access to financial information.

2. Service Delivery

 
Housing completions Australian Bureau of Statistics data indicates the Department of Planning and Environment achieved the Premier's priority for housing completions in 2016–17. 
Increasing housing supply Australian Bureau of Statistics data shows the Department of Planning and Environment achieved the annual target of delivering over 50,000 housing approvals over the past three years.
Major project assessment Progress against the State priority target to reduce time taken to assess planning applications for State significant developments is difficult to determine as the measure is unclear.
Litter management The Environment Protection Authority's data indicates that progress towards the Premier's priority target for litter reduction slowed in 2016–17.
Cultural participation The Department of Planning and Environment’s data indicates overall attendance at cultural venues and events in New South Wales increased by 16 per cent in 2015–16.

This report provides Parliament and others with the audit results, observations and recommendations for Planning and Environment cluster agencies. The report has been structured into two chapters focussing on financial reporting and controls and service delivery.

The Planning and Environment cluster plays a role in ensuring each community across New South Wales receives the services and infrastructure it needs.

This chapter outlines our audit observations and recommendations related to financial reporting and controls of Planning and Environment cluster agencies for 2016–17.

Observation Conclusion or recommendation

2.1 Quality of financial reporting

Unqualified audit opinions were issued for 39 of the 45 cluster agencies' financial statements.

Issues identified during the financial statement audits of seven smaller agencies delayed their completion. Six audits remain incomplete at the date of this report.

Apart from these seven small agency audits, the quality of financial reporting across the cluster remained at a high standard.

2.2 Timeliness of financial reporting

Seven agencies' financial statement audits were not completed by the statutory deadline with six audits incomplete at the date of this report.

Issues identified during the financial statement audits of seven smaller agencies delayed their finalisation beyond the statutory deadline. These agencies would benefit from performing additional early close procedures in future reporting periods.

2.3 Financial and sustainability analysis

Water and Electricity utility agencies continue to operate with low liquidity ratios.

A liquidity ratio below one is an indicator that an entity may not be able to pay its debts as and when they fall due.

Whilst liquidity ratios were below one, utility agencies demonstrated they can continue to support ongoing operations due to:

  • access to regulated revenue streams

  • assets with long useful lives to generate revenue

  • debt funding limits approved by the NSW Treasurer under the Public Authorities (Financial Arrangements) Act 1987.

2.5 Internal controls

One in six internal control weaknesses reported in 2016–17 were repeat issues.

Delays in implementing audit recommendations can prolong the risk of fraud and error.

Recommendation (repeat issue): anagement letter recommendations to address internal control weaknesses should be actioned promptly, with a focus on addressing repeat issues.

Nine of these internal control weaknesses related to the creation, modification, deletion and review of user access to financial systems.

These control weaknesses may compromise the integrity and security of financial data.

Recommendation (repeat issue): Management of user administration over financial systems should be strengthened to prevent inappropriate access to financial information.

This chapter outlines our audit observations, conclusions and recommendations relating to service delivery for 2016–17.

Observation Conclusion or recommendation

3.1 Premier's and State priorities

The Planning and Environment cluster is responsible for delivering five Premier's and State priorities.

One priority target was achieved in 2016–17, two targets are on track to be achieved and progress towards one target slowed.

Progress against one target cannot be determined.

3.2 Planning

Housing Completion

 
There were 63,506 housing completions in
2016–17. This was 4.1 per cent above the Premier’s priority target of delivering 61,000 housing completions per year.
The Australian Bureau of Statistics data shows the housing completions target was achieved in
2016–17.

Housing supply

The number of approvals for new houses in
2016–17 was 72,472 against the State priority target of more than 50,000 approvals per year.
The Australian Bureau of Statistics data indicates the housing approvals target was achieved in
2016–17.

Major project assessment

 
State significant developments are not clearly defined for the purposes of reporting against the State priority target. The Department of Planning and Environment will clarify with the Department of Premier and Cabinet which developments are captured by the State priority target.
The Department of Planning and Environment’s data shows the time taken to assess complex State significant developments increased by 16 per cent in 2016–17 while the time taken to assess less complex developments reduced by 20 per cent. The Department of Planning and Environment considers it is on track to meet the State priority target of halving the time taken to assess State significant developments, despite uncertainty over the target measure.

Housing acceleration fund

 

Program business cases were not developed for projects in Housing Acceleration Fund Rounds 1 to 4.

The Department advised a program business case will be developed for Housing Acceleration Fund Round 5 projects.

A program business case is necessary to ensure related projects are evaluated, managed and coordinated effectively.
 

A benefit realisation review process has not yet been approved for Housing Acceleration Fund projects.

The Department of Planning and Environment advised it is developing a benefit realisation review process.

A benefit realisation review process is necessary to determine whether funded projects achieved intended outcomes.

Greater Sydney Commission

 
The Greater Sydney Commission forecasts a further 725,000 dwellings in the greater Sydney region will be required up to 2036 to meet housing demand. In response to population growth, the Commission has set a five-year housing supply target of 189,100 houses across the five Greater Sydney Commission districts.

ePlanning system

 
The Department of Planning and Environment did not perform a benefit realisation review for phase one of the ePlanning project. It has committed to performing a benefit realisation review after completion of phase two in 2018. It cannot be determined if phase one of the project delivered expected outcomes as a benefit realisation review was not performed.

3.3. Environment and Heritage

Litter volume in New South Wales was 6.6 litres per 1,000 square metres in 2016–17, an increase of 16 per cent from the prior year. This is above the Premier's priority litter volume target of 4.2 litres per 1,000 square metres by 2020. The Environment Protection Authority's data indicates the progress towards the target of reducing the volume of litter by 40 per cent by 2020 has slowed.
The NSW Government plans to invest $240 million to facilitate strategic biodiversity conservation on private land. Performance measures have not yet been developed for the private land conservation program.

3.4 Water

IPART reduced water usage charges for most Sydney Water Corporation customers in 2016–17. Water usage prices in New South Wales compare favourably to larger water utilities in other jurisdictions.

Hunter Water Corporation's water recycling and water conservation performance has been stable over recent years.

The volume of Sydney Water Corporation’s recycled water reduced by 12 per cent in 2016–17 compared to the previous year.

Sydney Water Corporation experienced reduced industry demand for recycled water. Several large industrial customers relocated away from Sydney.

3.5 Arts and culture

A State priority target is to increase overall attendance at cultural venues and events in New South Wales by 15 per cent from 2014–15 levels by 2019. The Department of Planning and Environment's data indicates overall attendance increased by 16 per cent in 2015–16, although attendance fluctuated across individual venues and events. This indicates progress towards achieving the overall target by 2019.

Published

Actions for Transport 2017

Transport 2017

Transport
Asset valuation
Information technology
Internal controls and governance
Project management

The following report focuses on key observations and findings from the most recent financial statement audits of agencies in the Transport cluster.

Unqualified audit opinions were issued for all agencies' financial statements. However, the report notes the agencies can improve their asset revaluation processes.

1. Financial reporting and controls

Audit opinions

Unqualified audit opinions were issued for all agencies' financial statements.

Early close

Early close procedures continue to facilitate timely preparation of financial statements and completion of audits, but agencies can improve their asset revaluation processes. The revaluations were not completed by the early close deadline.
Key audit matters The cluster corrected the value of rail tunnels and earthworks by recording an additional $8.5 billion in infrastructure assets.
Passenger revenue and patronage Revenue increased by seven per cent at a similar rate to patronage. Opal fare structure changes came into effect on 5 September 2016. Continued rises in patronage can increase pressure on public transport punctuality.
Negative balances on Opal Cards

There was $2.6 million in revenue not collected during 2016–17 financial year through negative balance Opal Cards. This represents 0.2 per cent of total annual passenger revenue. Transport advise the cumulative balance of negative balance Opal Cards is $4.2 million as at 30 June 2017.

Recommendation: Transport for NSW (TfNSW) should implement measures to prevent loss of revenue from passengers tapping off with negative balance Opal Cards.

Investment in infrastructure Agencies spent $8.5 billion on assets in 2016–17 and have contractual capital commitments of $11.3 billion over the next five years.
Internal controls IT systems user access administration remains an area of weakness.


2. Service Delivery

Punctuality According to Transport data, average punctuality is above target for Sydney Trains, Ferries and Light Rail, but below target for NSW Trains services. State Transit Authority of NSW (STA) is not meeting punctuality targets. STA continued working with TfNSW on delivering improved punctuality.
Public transport capacity Passenger crowding is above benchmark for many morning peak suburban rail services, as indicated by Transport data. Eleven of the 14 bus contract regions had full buses.

Bus crowding

There are no target measures on crowding for bus operators in any contract region.

Recommendation: TfNSW should develop target measures on crowding for bus operators in all contract regions and publish the results.

Customer satisfaction

Surveys conducted by Transport indicate customer satisfaction exceeded target for all modes of public transport.

This report provides Parliament and other users of Transport cluster agencies' financial statements with audit results, observations, conclusions and recommendations in the following areas:

  • Financial reporting and controls
  • Service delivery.

Confidence in public sector decision-making and transparency is enhanced when financial reporting is accurate and timely. Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies.

This chapter outlines our audit observations, conclusions or recommendations related to financial reporting and controls of Transport cluster agencies for 2016–17.

Observation Conclusion or recommendation
Quality of financial reporting
Unqualified opinions were issued for all agencies’ financial statements. Unqualified audit opinions were issued on the 2016–17 financial statements of all agencies in the Transport cluster. Agencies complied with the new disclosure requirements required under accounting standard AASB 124 'Related Party Disclosures'.
Old tunnels and earthworks valued. The cluster corrected the value of rail tunnels and earthworks by recording an additional $8.5 billion in infrastructure assets.
Timeliness of financial reporting  
Most agencies complied with the statutory timeframes for completion of early close procedures and preparation and audit of financial statements. Early close procedures continue to facilitate timely preparation of financial statements and completion of audits, but agencies can make further improvement in the revaluation process.
TfNSW and RailCorp completed asset revaluations after the early close deadline. While all revaluation matters were resolved and corrected, completing the revaluation process earlier would enable more timely review, identification and resolution of matters.
Passenger revenue, patronage and cost recovery
Revenue increased by 7 per cent at a similar rate to patronage. Public transport passenger revenue increased by $93 million (seven per cent) in 2016–17, and patronage increased by 49 million (seven per cent) across all modes of transport. There were some changes in the method of calculating reported patronage between 2015–16 and 2016–17. If the methods had been consistent, the patronage increase would be 6.5 per cent. Opal fare structure changes came into effect on 5 September 2016.
Value of negative balance Opal Cards doubled since last year.

There was $2.6 million in revenue not collected during 2016–17 financial year through negative balance Opal Cards. This represents 0.2 per cent of total annual passenger revenue. Transport advise the cumulative balance of negative balance Opal Cards is $4.2 million as at 30 June 2017.

Recommendation: TfNSW should implement measures to prevent the loss of revenue from passengers tapping off with negative balance Opal cards.

The overall cost recovery from users of public transport increased slightly to 21.3 per cent. Cost of service per passenger journey for buses and ferries decreased. Revenue per passenger journey for all modes remained fairly stable.
Investment in infrastructure
There was a significant investment in transport assets in 2016–17. Agencies spent $8.5 billion on assets in 2016–17, including $3.8 billion on rail systems and $3.8 billion on road and maritime infrastructure systems.
Transport cluster have capital commitment of $11.3 billion over the next five years.
 
The transport cluster has significant contractual commitments over the next five years on rail and road infrastructure projects.
 

Internal controls

User access administration over systems remains an area of weakness. We identified six moderate and eight low risk issues related to user systems access administration across four agencies. This included review of highly privileged/super user account transactions not performed effectively and user access reviews not performed. These weaknesses increase the risk of users having excessive or unauthorised access to critical financial systems and information.

Achievement of government outcomes can be improved through effective delivery of the right mix of services, whether from the public, private or not‑for‑profit sectors. Service delivery reform will be most successful if there is clear accountability for service delivery outcomes, decisions are aligned to strategic direction and performance is monitored and evaluated.

This chapter outlines our audit observations, conclusions or recommendations related to service delivery in the Transport cluster agencies for 2016–17.

Observations Conclusion or recommendation

Punctuality

Average punctuality is above target for Sydney Trains, but below target for NSW Trains services. Punctuality targets are not met by all bus operators. Meeting punctuality targets is a continuing challenge for NSW Trains’ and STA bus services.
The 2017 performance audit 'Passenger Rail Punctuality' reported that based on forecast patronage increases, rail agencies will find it hard to maintain punctuality after 2019 unless the capacity of the network to carry trains and people is increased significantly. The 2017 performance audit found that given the likely lead times involved with major infrastructure projects, there remains a significant risk of poor punctuality after 2019. Transport advised it is currently either delivering or planning rail network upgrades to address current growth and longer-term future demand. This includes investments such as procurement of suburban and intercity trains, Sydney Metro services and further timetable planning into the 2020s.
 
After reaching its punctuality target in 2015–16 for the first time in 13 years, NSW Trains regional services was below the target in 2016–17. NSW Trains regional services achieved an average of 75 per cent punctuality in 2016–17, four per cent less than 2015–16.
The bus contracts do not have an option to impose financial penalties on STA for poor punctuality performance. In 2015–16, we recommended TfNSW should consider including financial penalties for not meeting each punctuality KPI in future contracts with bus operators. An opportunity to implement the recommendation requires a contract renewal process to be finalised with STA, which did not occur during 2016–17.

Public transport capacity

There are no target measures on crowding for bus operators in any contract region. Recommendation: TfNSW should develop target measures on crowding for bus operators in all contract regions and publish the results.

Customer Satisfaction

Customers on ferries continued to be most satisfied, followed by those on light rail. Sydney Trains and NSW Trains had fewer complaints in 2016–17. Customer satisfaction exceeded target for all modes of transport.

Project management

Transport cluster manages many of the State high profile/high risk projects. Major Transport projects include WestConnex, Sydney Metro Northwest, Sydney Metro City and Southwest, Woolgoolga to Ballina - Pacific Highway upgrade, NorthConnex, CBD and South East Light Rail and Newcastle Light Rail.
Safety performance
Road fatalities decreased by eight per cent between July 2016 and June 2017, from 390 to 359 deaths. Road fatalities mainly involved speed, fatigue and vehicle occupants not wearing available restraints.
 

Maintenance

RMS’ maintenance backlog of $3.7 billion is higher than the $3.4 billion reported in 2016. Transport cluster agencies manage $134 billion in property, plant and equipment. The total backlog maintenance of $4.1 billion at 30 June 2017 represents 3.1 per cent of those assets.

Published

Actions for Agency compliance with NSW Government travel policies

Agency compliance with NSW Government travel policies

Education
Community Services
Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Transport
Treasury
Universities
Whole of Government
Compliance
Internal controls and governance
Procurement

Overall, agencies materially complied with NSW Government travel policies.

However, the Auditor-General found some agencies:

  • did not always book official travel through the approved supplier
  • had weaknesses in their travel approval processes
  • had travel policies that were inconsistent with the NSW Government policy
  • did not adequately manage their travel records.   

Last year the NSW Government spent almost $250 million on travel. The government’s travel policies aim to help agencies make better travel decisions and reduce costs. The Department of Finance, Services and Innovation (DFSI) is responsible for the government’s travel policy and manages the government contract with an approved private sector provider to procure travel services.

This audit assessed how effective agency processes were to ensure compliance with:

  • the ‘Policy on Official Travel within Australia and Overseas’ issued by the Department of Premier and Cabinet in Circular OFS-2014–07 ‘Official Travel in Australia and Overseas’ (the former policy)
  • the ‘NSW Government Travel and Transport Policy’ issued by DFSI (the new policy), effective from 28 September 2016.

We examined 15 agencies from different NSW Government clusters with significant travel expenditure. For a list of participating agencies, refer to the Appendix two.

Conclusion

We found that overall, agencies materially complied with NSW Government travel policies. However, some agencies:

  • did not always book official travel through the approved supplier
  • had weaknesses in their travel approval processes
  • had travel policies that were inconsistent with the government policy
  • did not adequately manage their travel records.

Self-assessments indicate agencies comply with most aspects of the new policy. Agencies also believe more guidance from DFSI about certain aspects of the policy would increase compliance.

We asked the 15 participating agencies to complete a self assessment of the processes they have implemented to comply with the new policy. The key observations are summarised below.

Published

Actions for State Finances 2017

State Finances 2017

Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Treasury
Universities
Whole of Government
Environment
Asset valuation
Financial reporting
Information technology
Internal controls and governance

Total State Sector Accounts received an unqualified audit opinion for the fifth consecutive year.

There was a $5.7 billion State budget surplus and continued investment in new infrastructure, in part funded by the long-term leases of Ausgrid and Endeavour Energy assets. This report also comments on key accounting matters, including the correction of some previously reported balances and the first time reporting of combined Cabinet members’ compensation in the Total State Sector Accounts.

Pursuant to the Public Finance and Audit Act 1983, I present my Report on State Finances 2017.

You will note that the format of this report has changed from previous years.

The intent of this change is to draw attention to the key matters that have been the focus of our audit and highlight significant factors that have contributed to the outcome.

First, it is pleasing to report once again that I issued a clear audit opinion on the State’s consolidated financial statements. This outcome demonstrates the Government’s continued focus on the quality of financial reporting across the NSW public sector.

High quality financial management and reporting are crucial to properly inform the public and build community confidence in our system of government.

The Treasury’s Financial Management Transformation program also aims to improve financial governance, budgeting and reporting arrangements across the sector. My Office is working collaboratively with The Treasury on reforms to reduce the burden of reporting, without weakening established safeguards.

The reforms should include measures to provide independent assurance of the budget process, of outcome reporting by agencies, and the power to “follow the dollar” given the increasing use of non-government organisations to deliver Government programs.

This Report also highlights another year of strong financial performance. The State’s budget result was a $5.7 billion surplus, and investment in new infrastructure has continued, in part funded by the long-term leases of Ausgrid and Endeavour Energy assets.

Finally, could I take this opportunity to thank the staff of The Treasury for the way they approached this audit. Our partnership is critical to ensuring NSW is an exemplar of quality financial management and reporting.

02_Margaret_signature.jpg

Margaret Crawford 
24 October 2017

A clear audit opinion on the State’s consolidated financial statements was issued.

Timely and accurate financial reporting is essential for informed decision making, effective management of public funds and enhancing public accountability.

This year’s clear audit opinion reflects the Government’s continued efforts to improve the quality of financial reporting across the NSW public sector.

Since the introduction of ‘early close procedures’ in 2011-12, the number of significant errors in financial statements of agencies has generally fallen largely due to identifying and resolving complex accounting issues early. Agencies’ 2016-17 financial statements submitted for audit contained nine errors exceeding $20 million. All errors were subsequently corrected in the individual agencies financial statements.

Agencies should continue to respond to key accounting issues as soon as they are identified. Where issues are identified, accounting position papers should be prepared for consideration by the Audit Office, their Audit and Risk Committee members, and when relevant, The Treasury.

The State addressed the following key accounting matters during 2016-17. 

The State recognised rail tunnels and earthworks valued at $8.5 billion.

Some rail tunnels and earthworks have never been valued by the State. These include the City Circle, the country rail network and other tunnels and earthworks built before the year 2000. Some of these tunnels and earthworks date back to the early 1900s.

For many years, the State did not account for these assets as they believed that their value could not be reliably measured. This year an independent valuer was engaged to perform a comprehensive valuation. The methodology used demonstrated
that the assets could have been reflected in the financial statements earlier.

The State recorded an additional $8.5 billion to correct the value of infrastructure assets at 1 July 2016.

Cabinet member’s compensation and related party transactions were reviewed.

Due to changes in Accounting Standards, the State had to consider 'related party information' in the financial statements. Previously this only applied to for-profit entities.

This year, requirements to report related party information extended to members of Cabinet, considered to be “key management personnel” of the State, as defined by Accounting Standards.

The Treasury implemented a process to assess and report Cabinet member’s compensation, and transactions between Cabinet members and/or their close family members, and government agencies.

Collectively, Cabinet members’ remuneration was $8.8 million, which was mainly salaries and allowances, and $3.5 million of non-monetary benefits such as security and drivers. The Treasury determined there were no other specific “related party” transactions or balances that required disclosure in the State’s financial statements.

Information system limitations continue at TAFE NSW.

TAFE NSW has experienced ongoing issues with its student administration system.

TAFE NSW has again implemented additional processes to verify the accuracy and completeness of revenue from sales of goods and services.

TAFE NSW expects to spend up to $89 million on a new information system to address these issues. Modules of the new student enrolment system are expected to be in place for the 2018 enrolment period.

Restatements relating to the General Government Sector's investment in the commercial sector.

The State corrected two previously reported balances relating to the General Government Sector’s investment in the commercial sector.

Accounting Standards require the General Government Sector to effectively store gains or losses related to its investment in the commercial sector in reserves until the investment is derecognised.

When these investments are disposed of, the cumulative gains and losses must be cleared and recognised in the operating result. However, the Government had previously cleared the cumulative gains and losses directly to Accumulated Funds within equity.

To comply with Accounting Standards, a total of $6 billion previously reported as a movement in equity  at 30 June 2016, has now been corrected to the operating result.

In addition, Accounting Standards only allow gains or losses on its investments to be stored in reserves. In past years, the State recognised all changes in the value of its investment in Available for Sale Reserves, including the capital contributed to establish the State’s investment. In 2016-17, a total of $23.4 billion of contributed capital was corrected to accumulated funds at 1 July 2015.

The State’s budget result was a $5.7 billion surplus, $2.0 billion higher than the budget estimate.

The Total State Sector comprises 310 entities controlled by the NSW Government.

Of the total, the General Government Sector comprises 215 entities that provide goods and services not directly paid for by consumers.

The non-General Government Sector comprises 95 Government businesses that provide goods and services such as water and electricity, or financial services.

A principal measure of a Government’s overall performance is its Net Operating Balance, or Budget Result. The Net Operating Balance reports the difference between the cost of General Government service delivery and the revenue earned to fund these sectors.

The State has recorded budget surpluses and exceeded the original budget result in nine of the last ten years.

The State maintained its AAA credit rating.

The object of the Act is to maintain the AAA credit rating.

NSW’s finances are managed in alignment with the Fiscal Responsibility Act 2012 (the Act).

The Act established the framework for fiscal responsibility and strategy needed to protect the State’s AAA credit rating and service delivery to the people of NSW.

The purpose of maintaining the AAA credit rating is to reduce the cost of, and ensure the broadest access to, borrowings.

A triple-A credit rating also helps maintain business and consumer confidence so economic activity and employment are sustained. The legislation sets out targets and principles for financial management to achieve this.

New South Wales has credit ratings of AAA/Negative from Standard & Poor’s and Aaa/Stable from Moody’s Investors Service.

The fiscal targets for achieving this objective are:

General Government expenditure growth is lower than long term revenue growth.

General Government expenditure growth was 4.2 per cent in 2016-17, below the long-term revenue growth of 5.6 per cent.

Eliminating unfunded superannuation liabilities by 2030.

The Act sets a target of eliminating unfunded defined benefit superannuation liabilities by 2030. The State’s net superannuation liability was $58.6 billion at 30 June 2017 ($71.2 billion at 30 June 2016).

The Government predicts the 2030 target will be achieved. The State’s funding plan is to contribute amounts escalated by five per cent each year so the schemes will be fully funded by 2030. In 2016-17, the State made employer contributions of $1.5 billion, which is largely consistent with contributions over the past five years.

The liability values in the graph below do not reflect the values recorded in the Total State Sector Accounts. For financial reporting purposes, Accounting Standards (AASB 119 Employee Benefits) require the State to discount its superannuation liability using the government bond rate (refer to page 10 of this report). 

The relevant government bond rate in the current economic climate is 2.62 per cent.

The State’s target for the unfunded superannuation liability is measured using AASB 1056 Superannuation Entities. This is because it adopts a measurement basis that reflects expected earnings on fund assets, which are currently between 5.9 and 7.4 per cent. Using these rates, the liability is $15.0 billion at 30 June 2017 ($16.1 billion at 30 June 2016). The unfunded liability is $2.4 billion less than when the Act was introduced.

The State’s assets grew by $31.6 billion during 2016-17 to $409 billion.

Valuing the State’s physical assets.

When we audit the financial statements, we focus on areas we consider as higher risk. These areas are often complex, and require the use of estimates and judgements.

The State has $307.2 billion of physical assets measured at fair value in accordance with Australian Accounting Standards. Fair value calculations are inherently complex and sensitive to assumptions and estimates, increasing the risk these assets are incorrectly valued.

In our audits, we assess the reasonableness and appropriateness of assumptions used in valuing physical assets. This includes obtaining an understanding of the valuation methodologies applied and judgements made. We also review the completeness of asset registers, and the mathematical accuracy of valuation models.

Net movements between years includes additions, disposals, depreciation and valuations. This year, valuations of physical assets added $16.2 billion to the State’s assets, comprising: 

  • Transport for NSW and Railcorp $8.5 billion

  • New South Wales Land and Housing Corporation $4.8 billion

  • Roads and Maritime Services $930 million

  • Crown Entity $400 million.    

The State’s financial assets increased $27.5 billion in 2016-17

The State’s financial assets have increased by 88 per cent over the past four years. In 2016-17, financial assets increased primarily due to proceeds from the sale of government assets and businesses.

The Government implemented reforms to better use the State’s financial assets. A key element was the creation of an Asset and Liability Committee (ALCO) to provide advice on ways to improve balance sheet management.

Since the creation of the ALCO, reforms include:

  • Establishment of the New South Wales Infrastructure Future Fund (NIFF). The net proceeds from the State’s asset recycling program are invested into the NIFF, which is managed by TCorp, with a balance of $14.6 billion by 30 June 2017. Funds raised are invested through the NIFF until the Government requires them for critical infrastructure projects that are part of the Restart NSW and Rebuilding NSW program of works. ALCO and TCorp provide advice on the NIFF’s performance and management

  • Establishment of the Social and Affordable Housing Fund ($1.1 billion at 30 June 2017). ALCO oversees the Fund to ensure an appropriate investment approach that will maintain funding certainty for new social and affordable housing stock

  • Cash and liquidity management reforms to centralise cash previously held by agencies in the Treasury Banking System. This reform is designed to ensure agencies have adequate levels of liquidity but with surplus funds invested centrally for better returns.

The State’s liabilities decreased by $13.1 billion during 2016-17 to $182 billion.

Valuing the State’s liabilities relies on an actuarial assessment.

Nearly half of the State’s liabilities relate to its employees. This includes unfunded superannuation, and employee benefits, such as long service and recreation leave.

Valuation of these obligations is subject to complex estimation techniques and significant judgements. Small changes in assumptions can materially impact the financial statements.

We address the risk associated with auditing these balances:

  • using actuarial specialists

  • testing controls around underlying employee data used in data models, and testing the accuracy of the calculations

  • evaluating assumptions applied in calculating employee entitlements such as the discount rate and the probability of long service leave vesting conditions being met.

The State’s superannuation obligations reduced by $12.6 billion in 2016-17.

The State’s $58.6 billion superannuation liability represents obligations for past and present employees, less the value of assets set aside to meet those obligations. The superannuation liability decreased from $71.2 billion to $58.6 billion, largely due to an increase in the discount rate from 1.99 per cent to 2.62 per cent. This alone reduced the liability by $9.2 billion

The State’s borrowings totalled $70.6 billion at 30 June 2017.

The State’s borrowings totalled $70.6 billion at 30 June 2017, $9.5 billion less than the previous year. This was largely due to the repayment of borrowings when the assets of Ausgrid and Endeavour Energy were leased to the private sector.

TCorp issues bonds to raise funds for NSW Government agencies. The bonds are actively traded in financial markets providing price transparency and liquidity to public sector borrowers and institutional investors. All TCorp bonds are guaranteed by the NSW Government.

The Government manages its debt liabilities through its balance sheet management strategy. The strategy extends to TCorp, which applies an active risk management strategy to the Government’s debt portfolio.

General Government Sector debt is being restructured by replacing shorter-term debt with longer-term debt. This lengthens the portfolio to better match liabilities with the funding requirements of infrastructure assets and reduces refinancing risks. It also allows the Government to take advantage of the low interest rate environment.

The State recorded revenue of $83.5 billion in  2016-17, an increase of $5.3 billion from 2015-16.

The State’s results are underpinned by revenue growth in taxation, fees and fines.

Taxation, fees, fines and other revenue comprises $30.5 billion of taxation ($28.7 billion in 2015-16) and $5.3 billion of fees, fines and other revenue ($4.6 billion).

Tax revenue for the Total State Sector increased by $1.8 billion, or 6.4 per cent compared to 2015-16, primarily due to:

  • one-off business asset sales and lease transactions, including $718 million in transfer duty from the Ausgrid and Endeavour Energy lease transactions

  • $385 million increase in payroll tax from growth in NSW employment and average employee compensation

  • a $426 million increase in land taxes.

Growth in stamp duty is expected to slow over the next 4 years.

General Government Sector stamp duties have increased from $6.2 billion in 2012-13 to $11.5 billion in 2016-17, an annual average growth rate of 16.5 per cent. The Government’s budget forecasts the growth in stamp duties to decline, to an average annual growth rate of 2.6 per cent between 2016-17 and 2020-21.

The State received Commonwealth grants and subsidies of $30.8 billion in 2016-17.

The State received $30.8 billion from the Commonwealth Government in 2016-17, $1.6 billion more than in 2015-16. This was primarily due to transaction based asset recycling grants of $1.0 billion and a $720 million increase in national land transport grants. This increase was offset by a $435 million decrease in General Purpose Grants, which mainly comprises New South Wales’ share of the Goods and Services Tax (GST). 

The State spent $79.4 billion in 2016-17 to deliver services to the community, an increase of $3.9 billion from 2015-16.

Overall expenses increased 5.2 per cent from last year. Most of the increase was due to higher employee costs and operating costs.

Total salaries and wages increased by 4.2 per cent from 2015-16.

Total salaries and wages increased to $30 billion from $28.8 billion in 2015-16. The Government wages policy aims to limit the growth in remuneration and other employee costs to no more than 2.5 per cent per annum.

Operating expenses increased by 12.4 per cent from 2015-16.

Within operating expenses, payments for supplies, services and other expenses increased, in part, due to the State:

  • reacquiring mining licenses worth $482 million and additional land remediation costs of $101 million

  • spending more on health including additional drug supplies relating to Hepatitis C.

State spend on transport and communications increased by 68.1 per cent since 2012-13.

While spending on health and education remain the largest functional areas provided by Government, expenditure on transport and communication increased, on average, by 13.9 per cent annually between 2012-13 and 2016-17. This increase reflects the Government’s investment in transport infrastructure such as the Sydney Metro and Westconnex. Over the same period, spending on health increased by $3.9 billion.

Expenditure on fuel and energy has decreased by an average of 44.7 per cent since 2012-13, reflecting the State’s leases of electricity network assets.

In 2011, the Government established Restart NSW to fund high priority infrastructure projects.

Restart NSW projects are primarily funded from the proceeds from the asset recycling program enabling Government to deliver new infrastructure investment.

Restart NSW provides funding for the delivery of Rebuilding NSW, which is the Government’s 10-year plan to invest $20 billion in new infrastructure.

The State finalised long-term leases of Ausgrid and Endeavour Energy assets.

In June 2017, the Government finalised its long-term lease of 50.4 per cent of Endeavour Energy. This transaction follows on from the long-term leases of TransGrid in December 2015 and 50.4 per cent of Ausgrid in December 2016. Net proceeds of $15.0 billion were paid into Restart NSW relating to these transactions.

The Government also finalised an arrangement for the private sector to provide land titling and registry services to the public for 35 years. The State, through Restart NSW, received an upfront payment of $2.6 billion from the new operator.

Restart NSW is funding $29.8 billion of new infrastructure.

The Government has detailed its plan to invest $20 billion into the Rebuilding NSW plan from Restart NSW.

At 30 June 2017, around $2.9 billion has already been spent on Rebuilding NSW projects from Restart NSW, with a further $9 billion included in the budget aggregates. The Government has also earmarked a further $8.1 billion in Restart NSW for future projects.

The most significant project is the Sydney Metro. The Government has committed $7.0 billion from Restart NSW to build a 30-kilometre metro line, linking Sydney Metro Northwest at Chatswood, through new stations in the lower North Shore, the Sydney CBD and southwest to Bankstown. At 30 June 2017, $2.4 billion has been spent on this project from Restart NSW.

Other significant projects funded by Restart NSW include a $1.8 billion contribution to WestConnex and reserved funding of $1 billion towards the State’s Major Stadia Network program.

The Treasury initiated the Financial Management Transformation (FMT) program with the aim of changing and improving financial governance, budgeting and reporting arrangements of the New South Wales public sector.

FMT aims to deliver better outcomes for the people of New South Wales and focuses on transparency and accountability for expenditure, and better value for money.

New Financial Management System

PRIME is the Information Technology (IT) solution component of the FMT program, replacing several historical systems. PRIME will provide both financial and performance information within one IT platform for all agencies in the NSW public sector.

It is expected to give Government more timely information to plan and deliver its policy priorities and the budget.

Independent assurance over the budget process would improve confidence in the reliability of the State’s financial information.

Published

Actions for Energy rebates for low income households

Energy rebates for low income households

Planning
Industry
Compliance
Fraud
Internal controls and governance
Management and administration

The Department of Planning and Environment provides more than $245 million in energy rebates to around 27 percent of NSW households. This report highlights that the department is not monitoring the rebate schemes to understand whether they are delivering the best outcomes.

Most rebates are ongoing payments applied directly to energy bills reducing the amount payable by the householder. The structure of these rebates is complex and can be inequitable. Some households are eligible for four different rebates, each with its own eligibility criteria.  Also, some households in very similar circumstances receive different levels of support depending on what type of energy is used in their home or which adult in the house is the energy account holder. For example, a household using both electricity and gas receives more assistance than a household with electricity alone even if total energy bills are the same. 

The Department of Planning and Environment (Department) administers five energy rebate schemes targeted to low-income households. The five rebates are of two key types:

1. Ongoing support to pay energy bills
2. Crisis Support  

More than one million rebates are paid each year to over 800,000, or around 27 per cent, of NSW households. Households learn about rebates from a variety of sources including: Service NSW, government and energy retailer websites, energy retailer welcome packs, Department marketing efforts, information on energy bills, and Centrelink.  

The budget for energy rebates is increasing every year and in 2017–18 is more than $245 million. The Department delivers most rebates through a network of partnership arrangements with:

  • energy retailers, who apply rebates directly onto energy bills
  • more than 340 charities and other NGOs who assess households' eligibility for crisis support and distribute support through the Energy Accounts Payment Assistance scheme (EAPA)
  • Service NSW, who informs NSW households about rebates through their call centre.

The energy rebates budget is substantial and the distribution arrangements are complex. The objective of the audit was to assess whether the current design and distribution of energy rebates schemes is effective.

Conclusion
The Department administers the rebate schemes using partners to ensure funds are directed towards energy bills as intended. Ongoing support schemes provide assistance to low-income households as intended, but have no measurable objectives or outcome measures and therefore can't be assessed for their effectiveness. Crisis support (EAPA) has a clear objective, to keep households experiencing financial crisis connected to energy services, but the Department does not monitor the performance of EAPA against this objective.  

The structure of rebates providing ongoing support is complex and can be inequitable for some households. Reducing the number of separate schemes and simplifying eligibility requirements offers the most scope for improving effectiveness of ongoing support schemes.  

The growth of embedded networks1 represents a future administrative risk to the Department.

Partnering with energy retailers, charities and NGOs delivers advantages, but stronger oversight is required over partner organisations.

The Department and partner organisations administer the rebate schemes as designed

The Department oversees a complex package of rebate schemes in partnership with 25 retailers and around 340 charities and NGOs. The partnership arrangements ensure that funds are distributed directly to energy bills as intended. The schemes provide support to recipients and are administered in line with government decisions about eligibility.  

Communication about rebates does not reach all eligible households

Households learn about rebate schemes through a mix of communication channels including retailer websites and call centres, Department websites, Centrelink, financial counsellors, EAPA Providers, the Energy and Water Ombudsman and Service NSW. Some low-income groups, such as those with poor English language skills, do not find out about energy rebates.

Scheme objectives are not measurable

Rebate schemes that provide ongoing support do not have measurable objectives or outcome measures. Without clear and measurable objectives, the Department cannot report to government on whether the schemes are achieving the intended policy outcomes, nor recommend improvements to ensure the schemes deliver the greatest benefit to the most financially vulnerable households.

The EAPA crisis support scheme has a clearer objective in that it aims to keep households experiencing financial crisis connected to energy services. However, the Department does not measure outcomes from providing this type of support, and does not know if the crisis support achieves this objective.  

The structure of rebate schemes for ongoing support is complex

The Low Income Household Rebate accounts for 80 per cent of the budget for ongoing support rebates. The remaining 20 per cent of the budget is administered through four separate schemes: Gas Rebate, Medical Energy Rebate, Family Energy Rebate and Life Support Rebate.

Each of these rebates has its own eligibility criteria and some require separate application processes. The Family Energy Rebate is complex to access and apply for, and around one third of households do not reapply each year. Eligible households that receive energy through embedded networks apply directly to the Department for rebates, which are paid by the Department into bank accounts. Embedded networks are energy supply arrangements where the manager of a residential facility such as a caravan park, retirement village or apartment block, buys energy in bulk and then on-sells it to residents. The Department is yet to develop strategies to address a forecast increase in such households.

The design of the rebate schemes creates some inequities

Households in similar circumstances can receive different levels of assistance depending on which adult in the house is the energy account holder, the mix of energy types used in the home, or the EAPA Provider they turn to when in financial crisis.

Households with both gas and electricity connections receive more assistance than those with only electricity. Households in rural and regional areas receive the same value rebate as households closer to Sydney, despite higher distribution charges. Family Energy Rebate is a two-tier payment, with a higher amount available to families with greater means. Lower-income families receive a much smaller Family Energy Rebate on the assumption that they already receive Low Income Household Rebate. Charities and NGOs distributing EAPA crisis support apply inconsistent standards when assessing household need, which leads to inequitable levels of assistance.

Departmental oversight of energy retailers and EAPA Providers is not strong enough

While partnering with energy retailers and EAPA Providers delivers advantages, stronger management is needed to ensure that partners follow Departmental guidelines and to minimise the potential for fraud. The Department's accreditation process for potential EAPA Providers does not consider the applicant's financial governance standards and the most recent audit of EAPA Providers was 2013.


[1] Embedded networks are energy supply arrangements where the manager of a residential facility such as a caravan park, retirement village or apartment block, buys energy in bulk and then on-sells it to residents.

By September 2018, the Department of Planning and Environment should:

  1. Ensure effective strategies are in place to make information about rebates available to all eligible, low-income households
     
  2. Evaluate alternative models and develop advice for government to reduce complexity and improve equity of ongoing rebates
     
  3. Establish measurable objectives for schemes that provide ongoing support, and monitor and measure performance of all schemes against objectives and outcome measures
     
  4. Assess the impacts of the forecast increase in embedded networks and develop strategies to manage any increased administrative risk
     
  5. Strengthen assurance that EAPA is being provided in accordance with its objectives and guidelines by implementing accreditation and compliance programs
     
  6. Ensure those eligible for EAPA financial support are not disadvantaged by inflexible payments, inconsistent provider practices, or inability to access an EAPA provider in a timely manner. Options include:
    • moving from a fixed-value voucher to a flexible payment based on need irrespective of energy type
    • establishing a ‘Provider of Last Resort’ facility for households that cannot access an EAPA Provider.

Appendix one - Response from the Agency

Appendix two - About the audit

 

Parliamentary reference - Report number #292 - released 19 September 2017 

Published

Actions for Sydney Road Maintenance Contracts

Sydney Road Maintenance Contracts

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

In November 2013, Roads and Maritime Services (RMS) outsourced the maintenance of State roads in the Sydney region south and west zones using an innovative contracting approach called the Stewardship Maintenance Contract (SMC). The SMC links risk to reward, and uses a performance framework where outcomes should drive improved performance over time.

RMS’ SMC contract management includes most elements of good practice, including governance and dispute resolution mechanisms. However, key elements are missing which reduces its effectiveness.

Roads and Maritime Services (RMS) is responsible for the Sydney region State roads network This includes over 2,800 kilometres of roads and associated road corridor infrastructure such as bridges, tunnels and drainage structures. RMS divides the network into three geographical areas: south, west and north zones.

In 1995, RMS first outsourced road corridor infrastructure maintenance for the north zone through a Performance Specified Maintenance Contract (PSMC). The current 10-year PSMC for the north zone will expire in October 2018. Prior to November 2013, RMS maintained roads in the south and west zones through its Road and Fleet Services unit. 

In November 2013, RMS outsourced road maintenance services for the south and west zones using Stewardship Maintenance Contracts (SMC). The contracts run for seven years with an option for a further three years at RMS’ discretion. RMS estimated that the annual cost of these contracts was around $240 million in total. In March 2018, the contract prices are due to be reset by negotiation to reflect the contractors’ experience with, and better information about, the road networks and routine maintenance requirements. 

The SMC model adopted stewardship principles to improve value for money. RMS defined stewardship principles as a broad set of values, attitudes and behaviours, required of the contractor to effectively manage the assets on behalf of RMS. The SMC also includes commercial principles, such as linking risk to reward, and a performance framework where outcomes drive performance.

This audit assessed whether RMS had effectively managed the outsourcing of road maintenance in the Sydney region south and west zones. In making this assessment, we answered the following questions:

  1. Did RMS justify the decision to adopt the SMC model?
  2. Do SMCs include key performance indicators (KPIs) and incentives which promote efficiency and effectiveness? 
  3. Does RMS collect high quality information on contractor performance and take action to correct performance deficiencies?
  4. Are the expected benefits being achieved?

Conclusion

RMS developed an innovative contracting approach with the SMC. RMS has realised some benefits in the first year, including savings, from outsourcing road maintenance in the Sydney region south and west zones using the SMC. However, RMS’ management of the SMC has key elements missing which reduces its effectiveness.

The SMC includes performance measures and incentives to drive efficiency and effectiveness improvements over time.  

RMS has established a contract management framework which includes most elements of good practice, including governance and dispute resolution mechanisms. However, it does not have procedures to guide its contract managers in managing specific provisions of the SMC. Consequently, RMS has not exercised several significant SMC requirements, such as having the contractor account for an efficiency dividend in its pricing at the start of each three-year works period. It also has not done enough to assure itself that the contractor provided performance and financial data are correct. This is important because the data is used to measure performance and calculate contractor payments.  

RMS assessed that it had achieved around 80 per cent of the expected cost benefit in the initial year of the SMC. However, it has not tracked its achievement of benefits since then.

The Stewardship Maintenance Contract

RMS justified adopting the SMC model and included KPIs to drive efficiency and effectiveness

The SMC model includes features that RMS had not previously used for road maintenance contracts. These included adopting stewardship principles and transferring price risk to the contractor over time as the contractor becomes familiar with the assets being maintained.

The SMC model meets RMS’ requirements for flexibility in pricing models, the need for collaboration in asset maintenance planning, promoting innovation and effective performance management.

RMS used many good practices to develop the SMC model, including:

  • preparing a robust business case comparing the SMC model to RMS maintaining the road network itself, as well as assessing whether two other contracting models
    (traditional and alliance) would meet its requirements
  • assessing experiences with similar arrangements in other jurisdictions and identifying elements that worked to get the best outcomes
  • developing a robust performance framework, which included a mix of efficiency and effectiveness KPIs that reflected NSW Government policy and RMS priorities
  • incorporating risk and reward incentives delivered through cost sharing arrangements which change as the contract matures
  • using a contract duration that supports RMS priorities and provides an incentive for better quality outcomes.

RMS uses data provided by the contractor to measure performance and calculate payments to the contractor. The SMC includes a specific sanction if RMS finds that the contractor provided incorrect performance data, but no specific sanction if the contractor provides incorrect financial data. If RMS finds that the contactor provided incorrect performance or financial data, RMS can only recover over-payments which may have been made using the incorrect data.  

To provide a stronger incentive for the contractor to ensure data it provides is accurate, RMS should consider whether to incorporate stronger sanctions when negotiating the commercial reset due in mid-2018 for south and west zones. RMS should also consider this for the new contract for the north zone when the current PSMC contract expires in October 2018.

RMS' contract management approach and benefits realization

RMS can improve the effectiveness of its oversight and management of the SMC

RMS does not have SMC specific contract procedures to guide its contract managers. Consequently, RMS has not exercised several significant SMC requirements, such as having the contractors account for an efficiency dividend in their pricing at the start of each three-year works period. Effective contract management should be supported by contract specific procedures, with explanations of, and allocation of responsibility for, the various interventions that RMS may be required to exercise in the SMC.

Performance and financial reporting under the SMC is based on a mix of RMS and contractor provided data. While there are a range of audits of contractor provided performance and financial data that RMS can conduct each year under the SMC, it does not have a schedule of audits it will conduct and when.  
During the first year of the SMC, RMS commissioned some limited audits of financial data. In the first three years of the SMC, RMS did not conduct any audits of performance data. Had there been SMC specific procedures in place, this would have reduced the risk of RMS not implementing a systematic audit program to give it reasonable assurance on the quality of the data that the contractor has provided. This is important because the data is used to measure performance and calculate contractor payments.

RMS has been aware of data quality issues since 2015. While RMS advised that it commenced addressing some data quality issues in response to a series of reviews conducted in 2015, a recent internal audit report indicates that RMS has not resolved the data quality issues.  

RMS achieved benefits in the first year, but has not tracked benefits since

As part of the business case, RMS agreed to implement a benefits realisation strategy, including a benefits tracking tool. RMS commenced tracking benefits, but did not establish a comparative baseline pre-SMC on non-financial benefits, and has not tracked benefits past year one.

In 2015, a benchmarking study commissioned by RMS found that it had achieved 80 per cent of the expected recurrent cost savings and other benefits, such as improved workplace safety, in the first full year of the SMC. However, there was no clear baseline to measure
non-financial performance. The study was qualified due to gaps in available data. The study also did not reconcile the actual one-off transition costs to the business case estimate.

During the course of the audit, RMS advised that it intends to repeat this type of study to determine whether it has achieved all expected benefits (and their value), and that it would use the results to inform its negotiation with the SMC contractors as part of the commercial reset due in mid-2018.

Roads and Maritime Services is responsible for the State Roads network in the Sydney region

Roads and Maritime Services (RMS) is responsible for the Sydney region State roads network. This includes over 2,800 kilometres of roads and associated road corridor infrastructure such as bridges, tunnels and drainage structures. The network is divided into three geographical areas: south, west and north zones. Prior to November 2013, RMS maintained roads in the Sydney region south and west zones through its Road and Fleet Services unit.  

In 1995, RMS first outsourced road corridor infrastructure maintenance for the north zone through a Performance Specified Maintenance Contract (PSMC). The current 10-year PSMC for the north zone will expire in October 2018. This contract is worth around $35 million per annum.  

NSW Government priorities and road maintenance

Efficient and effective road maintenance contributes to the following NSW Government priorities:

  • improving road travel reliability
  • ensuring on-time running of public transport
  • reducing road fatalities
  • improving government services
  • keeping our environment clean.

The NSW Commission of Audit recommended outsourcing the maintenance of State roads

The NSW Commission of Audit in its Final Report on Government Expenditure (May 2012) recommended contestability as an appropriate strategy to consider for improving road maintenance service delivery for State roads.  

The Commission benchmarked RMS’ road surface quality and cost per lane kilometre against those of Western Australia, Victoria, and Queensland. This showed that New South Wales lagged the other states on both these measures.  

Exhibit 1: Interjurisdictional comparison of road maintenance outcomes 2009–10
  WA VIC QLD NSW
Roads managed (lane kms) 52,659 50,510 71,353 80,348
Estimated spend ($/lane km) 5,000 4,500 6,000 7,000
Road quality measure (%) 99 99 94 91

Source: NSW Commission of Audit Final Report May 2012.

The Commission noted that RMS had conducted two independent reviews to examine the potential for extending road maintenance contestability. The Commission found that there was inadequate and inconclusive benchmarking to establish the efficiency of RMS’ Road and Fleet Services unit when compared to outsourcing. It recommended that RMS bring forward a proposal to conduct a competitive tender for the road maintenance of the Sydney region south zone road network to inform the feasibility of a progressive rollout of road maintenance contestability across other areas of the State. In August 2012, the NSW Government adopted the Commission’s recommendation.

The NSW Government introduced road maintenance contestability through Stewardship Maintenance Contracts

In April 2013, the NSW Government announced that it would introduce road maintenance contestability across the Sydney region, using a Stewardship Maintenance Contract (SMC) model to improve value for money. In doing so, it excluded RMS’ Road and Fleet Services unit from tendering.  

The SMC model is based on the following key commercial and performance principles set by RMS:

  • performance driven by outcomes
  • flexible and adaptable
  • transparent and measurable
  • linking risk to reward
  • continuous improvement
  • criteria for selection of, and transition to, different payment models.

The following key stewardship principles underpin the SMC’s broad set of values, attitudes and behaviours, which are required of the contractor to effectively manage the assets on behalf of RMS:

  • putting RMS’ customers (road users and the general public) first and being responsive to them
  • being responsible and accountable for the outcomes resulting from the management of the assets
  • managing the assets diligently, efficiently and effectively with limited direction from RMS
  • working collaboratively with RMS to deliver services that are tailored to meet RMS’ evolving needs
  • acting with integrity and transparency in performing the services
  • performing the services in the best interests of RMS and asset users.

Other key features of the SMC include:

  • service requirements which describe the scope of the services, and the standards the contractor must meet
  • a commercial framework which defines how payments are structured, how performance assessment will impact on payments and outlines the key commercial principles. SMCs primarily divide payments into two main mechanisms, these being the priced component (or fixed price) and the target cost calculated as follows:
    • fixed price – the contractor is paid a pre-agreed amount for specific services being provided, regardless of the actual costs incurred
    • target cost – RMS and the contractor agree on a target cost for a project, and any cost overruns or underruns are shared between them
  • a performance framework which provides mechanisms for assessing contractor performance. This includes a comprehensive listing of the key result areas (KRAs) and key performance indicators (KPIs) against which RMS measures the contractor’s performance. The framework also outlines the scoring methodology that RMS uses to determine whether the contractor’s bid margin (profit and overheads) is reduced due to less than satisfactory performance or whether a bonus is paid if a threshold performance score is exceeded.

Road maintenance under SMCs for Sydney region south and west zones commenced in November 2013

In November 2013, RMS awarded SMCs to the Leighton Boral Amey consortium, now named Ventia Boral Amey (VBA), for the south zone and the DownerMouchel (DM) consortium for the west zone. The contracts run for seven years with an option for a further three years at RMS’ discretion. In April 2014, full services commenced following a four-month transition period. RMS estimated that the annual cost of these contracts was around $240 million in total. In March 2018, the contract prices are due to be reset by negotiation to reflect the contractors’ experience with, and better information about, the road networks and routine maintenance requirements. 

  1. Roads and Maritime Services should consider whether to incorporate stronger sanctions in the Stewardship Maintenance Contract if the contractor provides incorrect performance or financial data to RMS, when:
     
    1. negotiating the commercial reset for the next works period with the Sydney region south and west zone contractors due in July 2018.
    2. finalising a new SMC contract for the Sydney region north zone, due to commence in October 2018.

Roads and Maritime Services should, by September 2017:

2.  Review its contract management framework for SMCs to ensure that all authorities and accountabilities of
     contract managers are clearly defined, including:

a) accountability and procedures for exercising all operational clauses in the SMC where RMS may opt to, or be required to intervene, or make a decision

b) authority to approve or initiate the interventions RMS is required to, or may, exercise under the SMC

c) the audits that RMS will conduct to systematically validate the performance and financial data that the SMC contractors provide

d) the accountabilities of RMS contract managers to systematically review audits and quality reviews that the SMC contractors must conduct to demonstrate compliance with their service plans

e) the accountabilities of RMS contract managers to check that the monthly and annual reports provided by SMC contractors do not contain errors, omissions or inaccuracies.

3.  Improve its management of benefits realisation by:

a) initiating a further benefits realisation review and record the benefits delivered against those
    estimated following the tender process, including the one-off transition costs

b) identify any benefits, including savings, not yet attained and develop strategies to address any short-falls

c) establish a tool to track the ongoing realisation of benefits.