Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.

In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.

 

Parliamentary reference - Report number #152 - released 31 May 2006

Published

Actions for Northside Storage Tunnel Project

Northside Storage Tunnel Project

Planning
Environment
Infrastructure
Internal controls and governance
Procurement
Project management
Service delivery

The Northside Storage Tunnel was the first major public sector construction project using an alliance approach. In our opinion, the outcome of the project suggests that an alliance approach, when applied to a suitable project and managed appropriately, can support positive project outcomes. And in many respects the Alliance worked well. There are, however, a number of issues that we believe need to be addressed for future alliances.

 

Parliamentary reference - Report number #113 - released 24 July 2003

Published

Actions for Protecting Our Rivers

Protecting Our Rivers

Environment
Internal controls and governance
Regulation
Shared services and collaboration

The Audit Office is of the opinion that responsibility for protecting the quality of river water is not clearly delineated. The current arrangements lack the structure to ensure success. There is no lead entity to co-ordinate efforts to protect river water. New South Wales has no overarching water quality or river health strategy and no water quality management plans to ensure clear outcomes and responsibilities for protecting river water quality and integrated decision-making to protect areas of greatest risk to water quality.

 