Reports
Actions for Volume Five 2015 Premier and Cabinet
Volume Five 2015 Premier and Cabinet
Volume Five 2015 covered Premier and Cabinet agencies such as the Department of Premier and Cabinet, Office of Sport, Venues NSW, Barangaroo Delivery Authority and Infrastructure NSW.
Actions for Volume Three 2015 Members' Additional Entitlements
Volume Three 2015 Members' Additional Entitlements
NSW Members of Parliament, when spending their additional entitlements, generally complied with the requirements of the Parliamentary Remuneration Tribunal’s Determination for the year ended 30 June 2014.
The Sydney Allowance and Member declarations about loyalty/incentive schemes continue to be the areas where members are most likely not to follow the Tribunal’s Determination.
Actions for Implementing performance audit recommendations
Implementing performance audit recommendations
NSW Government agencies have sound processes for implementing performance audit recommendations in Auditor-General’s Reports to Parliament. There are many cases of good practice. For example, some agencies formed a steering committee and developed a detailed plan to implement recommendations. Another incorporated the implementation of recommendations into both its business plan and the work plans of individual officers who were managing projects. Most agencies also used their Audit and Risk Committees to monitor recommendations.
We found some cases where agencies can improve how they coordinate actions to address recommendations. Most agencies were not revisiting these actions to determine whether they remain appropriate.
Parliamentary reference - Report number #254 - released 24 June 2015
Actions for Government advertising 2015
Government advertising 2015
The Government Advertising Act 2011 requires the Auditor-General to conduct an annual performance audit to check NSW Government agency compliance with the Act.
This audit focused on the Department of Premier and Cabinet’s (DPC) role in monitoring government agencies compliance with government advertising requirements, and examined advertising campaigns run by Destination NSW and the Sydney Opera House.
Parliamentary reference - Report number #253 - released 22 June 2015
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.
Parliamentary reference - Report number #252 - released 7 May 2015
Actions for Areas of focus from 2014
Areas of focus from 2014
Actions for Solar Bonus Scheme
Solar Bonus Scheme
A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme.
By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced from 60 to 20 cents reducing the estimated cost to $1.954 billion.
It was a statutory requirement that when 50 mega watts of installed capacity was reached, the Government would review the Scheme. By the time the review was completed the installed capacity had reached 101 mega watts.
Actions for Prequalification Scheme: Performance and Management Services
Prequalification Scheme: Performance and Management Services
There have been tangible improvements in the time it takes NSW Government agencies to engage consultants through the Government’s Prequalification Scheme. The Scheme was introduced in February 2008 to improve agencies’ procurement of consultants. More than 300 service providers have been prequalified and over $300 million worth of consultancy services have been provided. Ideally agencies should know what assignments each consultant has won, for what services, what their rates are and how well they have performed. Agencies should then be free to contact other agencies before engaging a consultant.
Parliamentary reference - Report number #216 - released 28 September 2011
Actions for Two Ways Together - NSW Aboriginal Affairs Plan
Two Ways Together - NSW Aboriginal Affairs Plan
To date the Two Ways Together Plan (the Plan) has not delivered the improvement in overall outcomes for Aboriginal people that was intended. Stronger partnerships between the government and Aboriginal people are only beginning to emerge. The disadvantage still experienced by some of the estimated 160,000 Aboriginal people in NSW is substantial. For example, the unemployment rate for Aboriginal people is at least three times higher than the rate for all NSW residents and hospital admissions for diabetes are also around three times higher.
Parliamentary reference - Report number #213 - released 18 May 2011
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006