Actions for WestConnex: Assurance to the Government
WestConnex: Assurance to the Government
This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.
The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.
This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.
Parliamentary reference - Report number #247 - released 18 December 2014
Actions for Volume Six 2014 focusing on Premier and Cabinet
Volume Six 2014 focusing on Premier and Cabinet
All agencies in the NSW Premier and Cabinet cluster received unqualified audit opinions for the year ended 30 June 2014. Overall financial reporting has improved. Agencies submitted their financial statements earlier than last year and for the third year in a row there has been a reduction in the number of misstatements identified during audits.
Actions for Volume One 2014 - Areas of focus from 2013
Volume One 2014 - Areas of focus from 2013
Today the Auditor-General of New South Wales, Grant Hehir, released his Volume One Report to Parliament for 2014. The observations included in this report are designed to inform readers of common findings from the 2013 financial and performance audits so agencies and audit committees can use them to identify issues that may be relevant to their organisations.
Actions for Solar Bonus Scheme
Solar Bonus Scheme
A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme.
By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced from 60 to 20 cents reducing the estimated cost to $1.954 billion.
It was a statutory requirement that when 50 mega watts of installed capacity was reached, the Government would review the Scheme. By the time the review was completed the installed capacity had reached 101 mega watts.
Actions for Two Ways Together - NSW Aboriginal Affairs Plan
Two Ways Together - NSW Aboriginal Affairs Plan
To date the Two Ways Together Plan (the Plan) has not delivered the improvement in overall outcomes for Aboriginal people that was intended. Stronger partnerships between the government and Aboriginal people are only beginning to emerge. The disadvantage still experienced by some of the estimated 160,000 Aboriginal people in NSW is substantial. For example, the unemployment rate for Aboriginal people is at least three times higher than the rate for all NSW residents and hospital admissions for diabetes are also around three times higher.
Parliamentary reference - Report number #213 - released 18 May 2011
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006