Refine search Expand filter

Reports

Published

Actions for Internal controls and governance 2020

Internal controls and governance 2020

Education
Environment
Community Services
Finance
Health
Industry
Justice
Premier and Cabinet
Transport
Treasury
Compliance
Cyber security
Information technology
Internal controls and governance
Management and administration
Procurement

The Auditor-General for New South Wales, Margaret Crawford today released her report on the findings and recommendations from the 2019–20 financial audits that relate to internal controls and governance at 40 of the largest agencies in the NSW public sector. The bushfire and flood emergencies and the COVID‑19 pandemic continue to have a significant impact on the people and public sector of New South Wales. The scale of the government response

Published

Actions for Internal Controls and Governance 2019

Internal Controls and Governance 2019

Education
Community Services
Finance
Health
Industry
Justice
Planning
Premier and Cabinet
Transport
Treasury
Whole of Government
Compliance
Cyber security
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management

This report covers the findings and recommendations from the 2018–19 financial audits that relate to internal controls and governance at 40 of the largest agencies in the NSW public sector. The 40 agencies selected for this report constitute around 84 per cent of total expenditure for all NSW public sector agencies. The report provides insights into the effectiveness of controls and governance processes across the NSW public sector. It ev

Published

Actions for Volume Five 2015 Premier and Cabinet

Volume Five 2015 Premier and Cabinet

Premier and Cabinet
Asset valuation
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management
Risk

Volume Five 2015 covered Premier and Cabinet agencies such as the Department of Premier and Cabinet, Office of Sport, Venues NSW, Barangaroo Delivery Authority and Infrastructure NSW.

Published

Actions for Government advertising 2015

Government advertising 2015

Premier and Cabinet
Environment
Whole of Government
Compliance
Internal controls and governance
Procurement
Project management

The Government Advertising Act 2011 requires the Auditor-General to conduct an annual performance audit to check NSW Government agency compliance with the Act. This audit focused on the Department of Premier and Cabinet’s (DPC) role in monitoring government agencies compliance with government advertising requirements, and examined advertising campaigns run by Destination NSW and the Sydney Opera House.   Parliamentary reference - Report number #2

Published

Actions for Large construction projects

Large construction projects

Treasury
Transport
Health
Industry
Planning
Premier and Cabinet
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.   This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non

Published

Actions for Areas of focus from 2014

Areas of focus from 2014

Education
Community Services
Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Transport
Treasury
Universities
Whole of Government
Environment
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management
Risk

The 2014 audits showed that the quality and timeliness of financial reporting have continued to improve. However, many agencies do not have financial sustainability indicators that provide early warning of management issues, such as an inability to meet financial obligations. Weaknesses were identified in information security, management of leave balances, asset management and internal controls.   Governance issues and gaps in performance informat

Published

Actions for Solar Bonus Scheme

Solar Bonus Scheme

Premier and Cabinet
Compliance
Infrastructure
Management and administration
Project management
Regulation
Risk
Service delivery

A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme. By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate. In our opinion, however, the Government, Treasu