Reports
Actions for Volume Five 2015 Premier and Cabinet
Volume Five 2015 Premier and Cabinet
Volume Five 2015 covered Premier and Cabinet agencies such as the Department of Premier and Cabinet, Office of Sport, Venues NSW, Barangaroo Delivery Authority and Infrastructure NSW.
Actions for Government advertising 2015
Government advertising 2015
The Government Advertising Act 2011 requires the Auditor-General to conduct an annual performance audit to check NSW Government agency compliance with the Act.
This audit focused on the Department of Premier and Cabinet’s (DPC) role in monitoring government agencies compliance with government advertising requirements, and examined advertising campaigns run by Destination NSW and the Sydney Opera House.
Parliamentary reference - Report number #253 - released 22 June 2015
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.
Parliamentary reference - Report number #252 - released 7 May 2015
Actions for Areas of focus from 2014
Areas of focus from 2014
Actions for Government Advertising 2012-13
Government Advertising 2012-13
The following report assessed the activities of the two agencies in relation to their government advertising campaigns in 2012-13 and tested compliance by tracking a campaign through from development to dissemination.
Parliamentary reference - Report number #236 - released 23 September 2013
Actions for The Cross City Tunnel Project
The Cross City Tunnel Project
In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.
In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.
Parliamentary reference - Report number #152 - released 31 May 2006