Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.

The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.

This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.

 

Parliamentary reference - Report number #247 - released 18 December 2014

Published

Actions for Volume Six 2014 focusing on Premier and Cabinet

Volume Six 2014 focusing on Premier and Cabinet

Premier and Cabinet
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management

All agencies in the NSW Premier and Cabinet cluster received unqualified audit opinions for the year ended 30 June 2014. Overall financial reporting has improved. Agencies submitted their financial statements earlier than last year and for the third year in a row there has been a reduction in the number of misstatements identified during audits.

Published

Actions for Volume One 2014 - Areas of focus from 2013

Volume One 2014 - Areas of focus from 2013

Education
Community Services
Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Transport
Treasury
Universities
Whole of Government
Environment
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management
Risk

Today the Auditor-General of New South Wales, Grant Hehir, released his Volume One Report to Parliament for 2014. The observations included in this report are designed to inform readers of common findings from the 2013 financial and performance audits so agencies and audit committees can use them to identify issues that may be relevant to their organisations.

Published

Actions for Cost of Alcohol Abuse to the NSW Government

Cost of Alcohol Abuse to the NSW Government

Treasury
Justice
Health
Premier and Cabinet
Management and administration
Regulation

The NSW Government does not estimate or report the total cost of alcohol abuse. The Audit Office of New South Wales’ sponsored research estimates it costs the government over $1 billion a year, or around $416 from each NSW household.

 

Parliamentary reference - Report number #235 - released 6 August 2013

Published

Actions for Monitoring Local Government

Monitoring Local Government

Local Government
Premier and Cabinet
Compliance
Internal controls and governance
Management and administration

The Division of Local Government (DLG) has helped many NSW councils improve their long-term financial planning and asset management practice. Many councils are serving their communities well. However, because DLG lacks the power, it finds it difficult to respond effectively when things go wrong.

 

Parliamentary reference - Report number #225 - released 26 September 2012

Published

Actions for Settling Humanitarian Entrants in New South Wales -  Services to permanent residents who come to New South Wales through the humanitarian migration scheme

Settling Humanitarian Entrants in New South Wales -  Services to permanent residents who come to New South Wales through the humanitarian migration scheme

Community Services
Premier and Cabinet
Internal controls and governance
Management and administration

Support for humanitarian entrants living in New South Wales is poorly coordinated.  Humanitarian entrants in New South Wales are doing less well than in other states on the key indicators of health, housing and employment. Unlike some States, New South Wales does not have a single point of contact that humanitarian entrants can go to assist them with settling in a new country.

 

Parliamentary reference - Report number #221 - released 23 May 2012

Published

Actions for Volume One 2012 focusing on themes from 2011

Volume One 2012 focusing on themes from 2011

Health
Industry
Premier and Cabinet
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Shared services and collaboration

The following overview of audits from 2011 found agency restructures significantly impacted agency financial reporting processes, agencies are having difficulty establishing and enforcing compliance with their own policies and procedures, agencies experienced problems complying with regulations and providing adequate documentation to support their financial statements, the poor quality of some financial statements with 1,256 misstatements identified, 540 so significant they had to be corrected, deficiencies in information security exist across many agencies, computer system disaster recovery plans for financial systems not existing or outdated, do not align with agencies’ business recovery requirements, do not properly identify and assess critical systems and processes and testing is incomplete.

Published

Actions for Sick Leave

Sick Leave

Premier and Cabinet
Whole of Government
Management and administration
Workforce and capability

NSW public sector sick leave is higher than other States. The NSW public sector has the highest reported public sector sick leave in Australia. Public sector efforts to reduce sick leave over the last five years has seen a fall of a quarter of a day since 2004-05, less than its target of one day. On average, public sector workers take just over eight days sick leave annually. Recent surveys of public and private sector organisations show that sick leave in the public sector is higher than the private sector.

 

Parliamentary reference - Report number #209 - released 8 December 2010

Published

Actions for Severance Payments to Special Temporary Employees

Severance Payments to Special Temporary Employees

Premier and Cabinet
Compliance
Internal controls and governance
Management and administration
Workforce and capability

In reviewing both the severance pay guidelines and a sample of payments, we found the guidelines to be clear and all except two payments were made in accordance with them. In these two cases the severance payment was stipulated in the employment contract guaranteeing the STE a minimum of six months pay on termination, irrespective of the length of service.

 

Parliamentary reference - Report number #201 - released 16 June 2010

Published

Actions for Injury Management in the NSW Public Sector

Injury Management in the NSW Public Sector

Premier and Cabinet
Treasury
Finance
Management and administration
Workforce and capability

We found that during Working Together, agencies reduced the impact of workplace injuries. Most of the results have been positive in both our sample agencies and the public sector, and savings have been achieved. Between 2005 and 2008, while the number of claims in the sample agencies remained at around 15,000, the average cost of claims reduced by around 22 per cent from $22,349 to $17,360. The incidence rate of claims for the sample agencies also decreased by nine per cent to 7.3 claims per 100 staff.

 