Refine search Expand filter

Reports

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Unsolicited proposal process for the lease of Ausgrid

Unsolicited proposal process for the lease of Ausgrid

Premier and Cabinet
Asset valuation
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery
Shared services and collaboration

In October 2016, the NSW Government accepted an unsolicited proposal from IFM Investors and AustralianSuper to lease 50.4 per cent of Ausgrid for 99 years. The deal followed the Federal Government’s rejection of two bids from foreign investors, for national security reasons.

A performance audit of the lease of Ausgrid has found shortcomings in the unsolicited proposal process. Releasing the audit findings today, the Auditor-General for New South Wales, Margaret Crawford said ‘this transaction involved a $20 billion asset owned by the people of New South Wales. As such, it warranted strict adherence to established guidelines’.

Ausgrid is a distributor of electricity to eastern parts of Sydney, the Central Coast, Newcastle and the Hunter Region.

In June 2014, the then government announced its commitment to lease components of the state's electricity network as part of the Rebuilding NSW plan. Implementation of the policy began after the government was re-elected in 2015. Between November 2015 and August 2016, the NSW Government held a competitive tender process to lease 50.4 per cent of Ausgrid for 99 years. The NSW Government abandoned the process on 19 August 2016 after the Australian Treasurer rejected two bids from foreign investors, for national security reasons. That day, the Premier and Treasurer released a media statement clarifying the government's objective to complete the transaction via a competitive process in time to include the proceeds in the 2017–18 budget.

On 31 August 2016, the state received an unsolicited proposal from IFM Investors and AustralianSuper to acquire an interest in Ausgrid under the same terms proposed by the state during the tender process. In October 2016, the government accepted the unsolicited proposal. 

This audit examined whether the unsolicited proposal process for the partial long-term lease of Ausgrid was effectively conducted and in compliance with the government’s 2014 Unsolicited Proposals: Guide for Submission and Assessment (Unsolicited Proposals Guide or the Guide). 

The audit focused on how the government-appointed Assessment Panel and Proposal Specific Steering Committee assessed key requirements in the Guide that unsolicited proposals must be demonstrably unique and represent value for money. 

Conclusion

The evidence available does not conclusively demonstrate the unsolicited proposal was unique, and there were some shortcomings in the negotiation process, documentation and segregation of duties. That said, before the final commitment to proceed with the lease, the state obtained assurance that the proposal delivered value for money. 

It is particularly important to demonstrate unsolicited proposals are unique, in order to justify the departure from other transaction processes that offer greater competition, transparency and certainty about value for money.

The Assessment Panel and the Proposal Specific Steering Committee determined the Ausgrid unsolicited proposal was unique, primarily on the basis that the proponent did not require foreign investment approval from the Australian Treasurer, and the lease transaction could be concluded earlier than through a second tender process. However, the evidence that persuaded the Panel and Committee did not demonstrate that no other proponent could conclude the transaction in time to meet the government’s deadline. 

It is not appropriate to determine an unsolicited proposal is unique because it delivers an earlier outcome than possible through a tender process. The Panel and Committee did not contend, and it is not evident, that the unsolicited proposal was the only way to meet the government’s transaction deadline.

The evidence does not demonstrate that the proponent was the only party that would not have needed foreign investment approval to participate in the transaction. It also does not demonstrate that the requirement for foreign investment approval would have reduced the pool of foreign buyers to the degree that it would be reasonable to assume none would emerge. 

The Panel, Committee and financial advisers determined that the final price represented value for money, and that retendering offered a material risk of a worse financial outcome. However, an acceptable price was revealed early in the negotiation process, and doing so made it highly unlikely that the proponent would offer a higher price than that disclosed. The Department of Premier and Cabinet (DPC) and NSW Treasury were not able to provide a documented reserve price, bargaining strategy or similar which put the negotiations in context. It is not evident that the Panel or Committee authorised, justified or endorsed negotiations in advance. 

Key aspects of governance recommended by the Guide were in place. Some shortcomings relating to role segregation, record keeping and probity assurance weakened the effectiveness of the unsolicited proposal process adopted for Ausgrid.

The reasons for accepting that the proposal and proponent were unique are not compelling.

The Unsolicited Proposals Guide says the 'unique benefits of the proposal and the unique ability of the proponent to deliver the proposal' must be demonstrated. 

The conclusion reached by the Panel and Committee that the proposal offered a ‘unique ability to deliver (a) strategic outcome’ was primarily based on the proponent not requiring foreign investment approval from the Australian Treasurer, and allowing the government to complete the lease transaction earlier than by going through a second tender process. 

It is not appropriate to determine an unsolicited proposal is unique because it delivers an earlier outcome than possible through a tender process. The Panel and Committee did not contend, and it is not evident, that the unsolicited proposal was the only way to meet the government’s transaction deadline.

The evidence does not demonstrate that the proponent was the only party that would not have needed foreign investment approval to participate in the transaction. Nor does it demonstrate that the requirement for foreign investment approval would have reduced the pool of foreign buyers to the degree that it would be reasonable to assume none would emerge. 

That said, the Australian Treasurer’s decision to reject the two bids from the previous tender process created uncertainty about the conditions under which he would approve international bids. The financial advisers engaged for the Ausgrid transaction informed the Panel and Committee that:

  • it was not likely another viable proponent would emerge soon enough to meet the government’s transaction deadline
  • the market would be unlikely to deliver a better result than offered by the proponent
  • going to tender presented a material risk of a worse financial result. 

The Unsolicited Proposals Guide says that a proposal to directly purchase or acquire a government-owned entity or property will generally not be unique. The Ausgrid unsolicited proposal fell into this category. 

Recommendations:
DPC should ensure future Assessment Panels and Steering Committees considering a proposal to acquire a government business or asset:

  • recognise that when considering uniqueness they should: 
    • require very strong evidence to decide that both the proponent and proposal are the only ones of their kind that could meet the government’s objectives 
    • give thorough consideration to any reasonable counter-arguments against uniqueness.
  • rigorously consider all elements of the Unsolicited Proposals Guide when determining whether a proposal should be dealt with as an unsolicited proposal, and document these deliberations and all relevant evidence
  • do not use speed of transaction compared to a market process as justification for uniqueness.
The process to obtain assurance that the final price represented value for money was adequate. However, the negotiation approach reduced assurance that the bid price was maximised. 

The Panel and Committee concluded the price represented value for money, based on peer-reviewed advice from their financial advisers and knowledge acquired from previous tenders. The financial advisers also told the Panel and Committee that there was a material risk the state would receive a lower price than offered by the unsolicited proposal if it immediately proceeded with a second market transaction. 

The state commenced negotiations on price earlier than the Guide says they should have. Early disclosure of a price that the state would accept reduced the likelihood of achieving a price greater than this. DPC says the intent of this meeting was to quickly establish whether the proponents could meet the state’s benchmark rather than spending more time and resources on a proposal which had no prospect of proceeding.

DPC and NSW Treasury were not able to provide a documented reserve price, negotiation strategy or similar which put the negotiations and price achieved in context. It was not evident that the Panel or Committee authorised, justified or endorsed negotiations in advance. However, the Panel and Committee endorsed the outcomes of the negotiations. 

The negotiations were informed by the range of prices achieved for similar assets and the specific bids for Ausgrid from the earlier market process.

Recommendations:
DPC should ensure any future Assessment Panels and Steering Committees considering a proposal to acquire a government business or asset:

  • document a minimum acceptable price, and a negotiating strategy designed to maximise price, before commencing negotiations
  • do not communicate an acceptable price to the proponent, before the negotiation stage of the process, and then only as part of a documented bargaining strategy.
Key aspects of governance recommended by the Guide were in place, but there were some shortcomings around role segregation, record keeping and probity assurance.

The state established a governance structure in accordance with the Unsolicited Proposals Guide, including an Assessment Panel and Proposal Specific Steering Committee. The members of the Panel and Steering Committee were senior and experienced officers, as befitted the size and nature of the unsolicited proposal. 

The separation of negotiation, assessment and review envisaged by the Guide was not maintained fully. The Chair of the Assessment Panel and a member of the Steering Committee were involved in negotiations with the proponent. 

DPC could not provide comprehensive records of some key interactions with the proponent or a documented negotiation strategy. The absence of such records means the Department cannot demonstrate engagement and negotiation processes were authorised and rigorous. 

The probity adviser reported there were no material probity issues with the transaction. The probity adviser also provided audit services. This is not good practice. The same party should not provide both advisory and audit services on the same transaction.

Recommendations:
DPC should ensure any future Assessment Panels and Steering Committees considering a proposal to acquire a government entity or asset:
•    maintain separation between negotiation, assessment and review in line with the Unsolicited Proposals Guide
•    keep an auditable trail of documentation relating to the negotiation process
•    maintain separation between any probity audit services engaged and the probity advisory and reporting services recommended in the current Guide.

Published

Actions for Transport 2018

Transport 2018

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Risk
Service delivery
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford released her report today on key observations and findings from the 30 June 2018 financial statement audits of agencies in the Transport cluster. Unqualified audit opinions were issued for all agencies' financial statements. However, assessing the fair value of the broad range of transport related assets creates challenges.

This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides Parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all agencies' financial statements Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
2.2 Key accounting issues
Valuation of assets continues to create challenges. Although agencies complied with the requirements of the accounting standards and Treasury policies on valuations, we identified some opportunities for improvements at RMS.

RMS incorporated data from its asset condition assessments for the first time in the valuation methodology which improved the valuation outcome. Overall, we were satisfied with the valuation methodology and key assumptions, but we noted some deficiencies in the asset data in relation to asset component unit rates and old condition data for some components of assets. 

Also, a bypass and tunnel were incorrectly excluded from RMS records and valuation process since 2013. This resulted in an increase for these assets’ value by $133 million.

The valuation inputs for Wetlands and Moorings were revised this year to better reflect the assets' characteristics resulting in a $98.0 million increase.

2.3 Timeliness of financial reporting
Residual Transport Corporation did not submit its financial statements by the statutory reporting deadline. Residual Transport Corporation remained a dormant entity with no transactions for the year ended 30 June 2018.
With the exception of Residual Transport Corporation, all agencies completed early close procedures and submitted financial statements within statutory timeframes. Early close procedures allow financial reporting issues and risks to be addressed early in the reporting and audit process.
2.4 Financial sustainability
NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations reported negative net assets of $75.7 million and $89,000 respectively at 30 June 2018.  NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations continue to require letters of financial support to confirm their ability to pay liabilities as they fall due. 
2.5 Passenger revenue and patronage
Transport agencies revenue growth increased at a higher rate than patronage. Public transport passenger revenue increased by $114 million (8.3 per cent) in 2017–18, and patronage increased by 37.1 million (5.1 per cent) across all modes of transport based on data provided by TfNSW. 
Negative balance Opal Cards resulted in $3.8 million in revenue not collected in 2017–18 and $7.8 million since the introduction of Opal. A total of 1.1 million Opal cards issued since its introduction have negative balances. Transport for NSW advised it is liaising with the ticketing vendor to implement system changes and are investigating other ways to reduce the occurrences.
2.6 Cost recovery from public transport users
Overall cost recovery from users has decreased. Overall cost recovery from public transport users (on rail and bus services by STA) decreased from 23.2 per cent to 22.4 per cent between 2016–17 and 2017–18. The main reason for the decrease is due to expenditure increasing at a faster rate than revenue in 2017–18.


 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Transport cluster for 2018
  • the areas of focus identified in the Audit Office annual work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters. 

Observation Conclusions and recommendations
3.1 Internal controls 
There was an increase in findings on internal controls across the Transport cluster. Key themes related to information technology, employee leave entitlements and asset management. Eighteen per cent of all issues were repeat issues.
3.2 Audit Office Annual work program
The Transport cluster wrote-off over $200 million of assets which were replaced by new assets or technology.

Majority of this write-off was recognised by RMS, with $199 million relating to the write-off of existing assets which have been replaced during the year. 

RailCorp is expected to convert to TAHE from 1 July 2019. Several working groups are considering different aspects of the TAHE transition including its status as a for-profit Public Trading Enterprise and which assets to transfer to TAHE. We will continue to monitor developments on TAHE for any impact to the financial statements.
RMS' estimated maintenance backlog at 30 June 2018 of $3.4 billion is lower than last year. Sydney Trains' estimated maintenance backlog at 30 June 2018 increased by 20.6 per cent to $434 million. TfNSW does not quantify its backlog maintenance. TfNSW advised it is liaising with Infrastructure NSW to develop a consistent definition of maintenance backlog across all transport service providers. 
Not all agencies monitor unplanned maintenance across the Transport cluster. Unplanned maintenance can be more expensive than planned maintenance. TfNSW should develop a consistent approach to define, monitor and track unplanned maintenance across the cluster.

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited. 

We report this information on service delivery to provide additional context to understand the operations of the Transport cluster and to collate and present service information for different modes of transport in one report. 

In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.

Published

Actions for Progress and measurement of the Premier's Priorities

Progress and measurement of the Premier's Priorities

Premier and Cabinet
Compliance
Internal controls and governance
Management and administration
Project management
Risk
Service delivery
Shared services and collaboration
Workforce and capability

The Premier’s Implementation Unit uses a systematic approach to measuring and reporting progress towards the Premier’s Priorities performance targets, but public reporting needed to improve, according to a report released today by the Auditor-General of NSW, Margaret Crawford.

The Premier of New South Wales has established 12 Premier’s Priorities. These are key performance targets for government.

The 12 Premier's Priorities
  • 150,000 new jobs by 2019

  • Reduce the volume of litter by 40 per cent by 2020

  • 10 key projects in metro and regional areas to be delivered on time and on budget, and nearly 90 local infrastructure projects to be delivered on time

  • Increase the proportion of NSW students in the top two NAPLAN bands by eight per cent by 2019

  • Increase the proportion of women in senior leadership roles in the NSW Government sector from 33 to 50 per cent by 2025 and double the number of Aboriginal and Torres Strait Islander people in senior leadership roles in the NSW Government sector, from 57 to 114

  • Increase the proportion of young people who successfully move from Specialist Homelessness Services to long-term accommodation to more than 34 per cent by 2019

  • 61,000 housing completions on average per year to 2021

  • Reduce the proportion of domestic violence perpetrators reoffending by 25 per cent by 2021

  • Improve customer satisfaction with key government services every year, this term of government to 2019

  • Decrease the percentage of children and young people re-reported at risk of significant harm by 15 per cent by 2020

  • 81 per cent of patients through emergency departments within four hours by 2019

  • Reduce overweight and obesity rates of children by five percentage points by 2025


Source: Department of Premier and Cabinet, Premier’s Priorities website.

Each Premier’s Priority has a lead agency and minister responsible for achieving the performance target.

The Premier’s Implementation Unit (PIU) was established within the Department of Premier and Cabinet (DPC) in 2015. The PIU is a delivery unit that supports agencies to measure and monitor performance, make progress toward the Premier’s Priorities targets, and report progress to the Premier, key ministers and the public.

This audit assessed how effectively the NSW Government is progressing and reporting on the Premier's Priorities.

 


The Premier’s Implementation Unit (PIU) is effective in assisting agencies to make progress against the Premier’s Priorities targets. Progress reporting is regular but transparency to the public is weakened by the lack of information about specific measurement limitations and lack of clarity about the relationship of the targets to broader government objectives.The PIU promotes a systematic approach to measuring performance and reporting progress towards the Premier’s Priorities’ performance targets. Public reporting would be improved with additional information about the rationale for choosing specific targets to report on broader government objectives.

The PIU provides a systematic approach to measuring performance and reporting progress towards the Premier's Priorities performance targets. Public reporting would be improved with additional information about the rationale for choosing specific targets to report on broader government objectives. The data used to measure the Premier’s Priorities comes from a variety of government and external datasets, some of which have known limitations. These limitations are not revealed in public reporting, and only some are revealed in progress reported to the Premier and ministers. This limits the transparency of reporting.

The PIU assists agencies to avoid unintended outcomes that can arise from prioritising particular performance measures over other areas of activity. The PIU has adopted a collaborative approach to assisting agencies to analyse performance using data, and helping them work across organisational silos to achieve the Premier’s Priorities targets.


 


Data used to measure progress for some of the Premier’s Priorities has limitations which are not made clear when progress is reported. This reduces transparency about the reported progress. Public reporting would also be improved with additional information about the relationship between specific performance measures and broader government objectives.

The PIU is responsible for reporting progress to the Premier, key ministers and the public. Agencies provide performance data and some play a role in preparing progress reports for the Premier and ministers. For 11 of the Premier's Priorities, progress is reported against measurable and time-related performance targets. For the infrastructure priority, progress is reported against project milestones.

Progress of some Priorities is measured using data that has known limitations, which should be noted wherever progress is reported. For example, the data used to report on housing completions does not take housing demolitions into account, and is therefore overstating the contribution of this performance measure to housing supply. This known limitation is not explained in progress reports or on the public website.

Data used to measure progress is sourced from a mix of government and external datasets. Updated progress data for most Premier’s Priorities is published on the Premier’s Priorities website annually, although reported to the Premier and key ministers more frequently. The PIU reviews the data and validates it through fieldwork with front line agencies. The PIU also assists agencies to avoid unintended outcomes that can arise from prioritising single performance measures. Most, but not all, agencies use additional indicators to check for misuse of data or perverse outcomes.

We examined the reporting processes and controls for five of the Premier’s Priorities. We found that there is insufficient assurance over the accuracy of the data on housing approvals.

The relationships between performance measures and broader government objectives is not always clearly explained on the Premier’s Priority website, which is the key source of public information about the Premier’s Priorities. For example, the Premier’s Priority to reduce litter volumes is communicated as “Keeping our Environment Clean.” While the website explains why reducing litter is important, it does not clearly explain why that particular target has been chosen to measure progress in keeping the environment clean.

By December 2018, the Department of Premier and Cabinet should:

  1. improve transparency of public reporting by:
    • providing information about limitations of reported data and associated performance
    • clarifying the relationship between the Premier’s Priorities performance targets and broader government objectives.
  2. ensure that processes to check and verify data are in place for all agency data sources
  3. encourage agencies to develop and implement additional supporting indicators for all Premier’s Priority performance measures to prevent and detect unintended consequences or misuse of data.

 


The Premier's Implementation Unit is effective in supporting agencies to deliver progress towards the Premier’s Priority targets.

The PIU promotes a systematic approach to monitoring and reporting progress against a target, based on a methodology used in delivery units elsewhere in the world. The PIU undertakes internal self-evaluation, and commissions regular reviews of methodology implementation from the consultancy that owns the methodology and helped to establish the PIU. However, the unit lacks periodic independent reviews of their overall effectiveness. The PIU has adopted a collaborative approach and assists agencies to analyse performance using data, and work across organisational silos to achieve the Premier’s Priorities targets.

Agency representatives recognise the benefits of being responsible for a Premier's Priority and speak of the value of being held to account and having the attention of the Premier and senior ministers.

By June 2019, the Department of Premier and Cabinet should:

  1. establish routine collection of feedback about PIU performance including:
    • independent assurance of PIU performance
    • opportunity for agencies to provide confidential feedback.

 

 

Published

Actions for Volume Eight 2011 Focus on Transport and Ports

Volume Eight 2011 Focus on Transport and Ports

Transport
Industry
Asset valuation
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effectiveness of program initiatives for increasing container freight movements by rail. The Corporation should review the underlying causes hindering growth in the rail mode and develop and implement strategies to address the unfavourable trend.

Published

Actions for Volume Six 2011 focus on Environment, Water and Regional Infrastructure

Volume Six 2011 focus on Environment, Water and Regional Infrastructure

Planning
Industry
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Workforce and capability

The Environment Protection Authority’s expenditure for the financial year 2010/11 was $92 million - $76 million of this was for environment protection and regulation. The Office of Environment and Heritage and the Environment Protection Authority commenced 145 prosecutions for environmental offences and 106 were completed in the financial year 2010/11, down from the 134 prosecutions completed in 2009/10. Financial penalties for 2010/11 totalled $969,000 down from $1,403,000 in 2009/10. The average fine decreased from $10,468 in 2009/10 to $9,141 in 2010/11.

Published

Actions for Prequalification Scheme: Performance and Management Services

Prequalification Scheme: Performance and Management Services

Premier and Cabinet
Finance
Compliance
Internal controls and governance
Management and administration
Regulation
Risk
Workforce and capability

There have been tangible improvements in the time it takes NSW Government agencies to engage consultants through the Government’s Prequalification Scheme. The Scheme was introduced in February 2008 to improve agencies’ procurement of consultants. More than 300 service providers have been prequalified and over $300 million worth of consultancy services have been provided. Ideally agencies should know what assignments each consultant has won, for what services, what their rates are and how well they have performed. Agencies should then be free to contact other agencies before engaging a consultant.

 

Parliamentary reference - Report number #216 - released 28 September 2011

Published

Actions for Volume One 2011

Volume One 2011

Industry
Planning
Finance
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Workforce and capability

The level of non compliance with the requirements of this Premier’s Memorandum is concerning, particularly considering the NSW Procurement Reforms were effective since 2006. The implementation strategy for procurement reform was announced as early as 2001. We recommend the governing bodies of agencies and management review, not only the processes their agencies have in place to comply with procurement reforms and requirements, but also more broadly how agencies identify and comply with laws, regulations, Treasury policy pronouncements, Premier’s memoranda and other obligations. 

Published

Actions for Agencies working together to improve services

Agencies working together to improve services

Premier and Cabinet
Treasury
Justice
Transport
Education
Internal controls and governance
Service delivery
Shared services and collaboration

In the cases we examined, we found that agencies working together can improve services or results. However, the changes were not always as great as anticipated or had not reached maximum potential. Establishing the right governance framework and accountability requirements between partners at the start of the project is critical to success. And joint responsibility requires new funding and reporting arrangements to be developed.

 

Parliamentary reference - Report number #149 - released 22 March 2006