Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate. In our opinion, however, the Government, Treasury an

Planned

Actions for Advice on major decisions

Advice on major decisions

Premier and Cabinet
Compliance
Financial reporting
Internal controls and governance
Management and administration
Procurement
Risk

The public service is responsible for providing accurate, evidence-based, and impartial advice to government, and implementing government’s commitments in a responsive and professional manner. Quality advice from the public service is required to support good decision making. This audit may examine 2-3 major decisions to determine whether the advice provided meets good practice standards. It will also assess the effectiveness of the whole of government

Planned

Actions for A compliance review

A compliance review

Whole of Government
Asset valuation
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Service delivery
Shared services and collaboration
Workforce and capability

We will conduct at least one compliance review to confirm that specific legislation, directions and regulations have been adhered to.