Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project. The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money. This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and

Published

Actions for Solar Bonus Scheme

Solar Bonus Scheme

Premier and Cabinet
Compliance
Infrastructure
Management and administration
Project management
Regulation
Risk
Service delivery

A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme. By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate. In our opinion, however, the Government, Treasury an

Planned

Actions for Advice on major decisions: redevelopment of the Sydney Football Stadium

Advice on major decisions: redevelopment of the Sydney Football Stadium

Premier and Cabinet
Asset valuation
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery
Shared services and collaboration
Workforce and capability

The NSW Government makes decisions that involve the spending of significant sums, and that have substantial impacts on citizens. This audit will focus on the advice provided for the redevelopment of the Sydney Football Stadium. This audit may examine the adequacy of planning and risk management approaches and whether these: were informed by appropriate and robust departmental advice complied with relevant procurement and assurance frameworks.