Reports
Actions for Procurement and reporting of consultancy services
Procurement and reporting of consultancy services
NSW Government agencies engage consultants to provide professional advice to inform their decision‑making. The spend on consultants is measured and reported in different ways for different purposes and the absence of a consistently applied definition makes quantification difficult.
The NSW Government’s procurement principles aim to help agencies obtain value for money and be fair, ethical and transparent in their procurement activities. All NSW Government agencies, with the exception of State Owned Corporations, must comply with the NSW Procurement Board’s Direction when engaging suppliers of business advisory services. Business advisory services include consultancy services. NSW Government agencies must disclose certain information about their use of consultants in their annual reports. The table below illustrates the detailed procurement and reporting requirements.
Relevant guidance | Requirements | |
---|---|---|
Procurement of consultancy services | PBD 2015 04 Engagement of major suppliers of consultancy and other services (the Direction) including the Standard Commercial Framework (revised on 31 January 2018, shortly before it was superseded by 'PBD 2018 01') |
Required agencies to seek the Agency Head or Chief Financial Officer's approval for engagements over $50,000 and report the engagements in the Major Suppliers' Portal (the Portal). |
PBD 2018 01 Engagement of professional services suppliers (replaced 'PBD 2015 04' in May 2018) |
Requires agencies to seek the Agency Head or Chief Financial Officer's approval for engagements that depart from the Standard Commercial Framework and report the engagements in the Portal. Exhibit 3 in the report includes the key requirements of these three Directions. |
|
Reporting of consultancy expenditure | Annual Reports (Departments) Regulation 2015 and Annual Reports (Statutory Bodies) Regulation 2015 | Requires agencies to disclose, in their annual reports, details of consultants engaged in a reporting year. |
Premier's Memorandum 'M2002 07 Engagement and Use of Consultants' |
Outlines additional reporting requirements for agencies to describe the nature and purpose of consultancies in their annual reports. |
We examined how 12 agencies complied with their procurement and reporting obligations for consultancy services between 1 July 2016 and 31 March 2018. Participating agencies are listed in Appendix two. We also examined how NSW Procurement supports the functions of the NSW Procurement Board within the Department of Finance, Services and Innovation.
This audit assessed:
- agency compliance with relevant procurement requirements for their use of consultants
- agency compliance with disclosure requirements about consultancy expenditure in their annual reports
- the effectiveness of the NSW Procurement Board (the Board) in fulfilling its functions to oversee and support agency procurement of consultancy services.
Actions for Regional Assistance Programs
Regional Assistance Programs
Infrastructure NSW effectively manages how grant applications for regional assistance programs are assessed and recommended for funding. Its contract management processes are also effective. However, we are unable to conclude whether the objectives of these programs have been achieved as the relevant agencies have not yet measured their benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.
In 2011, the NSW Government established Restart NSW to fund new infrastructure with the proceeds from the sale and lease of government assets. From 2011 to 2017, the NSW Government allocated $1.7 billion from the fund for infrastructure in regional areas, with an additional commitment of $1.3 billion to be allocated by 2021. The NSW Government allocates these funds through regional assistance programs such as Resources for Regions and Fixing Country Roads. NSW councils are the primary recipients of funding provided under these programs.
The NSW Government announced the Resources for Regions program in 2012 with the aim of addressing infrastructure constraints in mining affected communities. Infrastructure NSW administers the program, with support from the Department of Premier and Cabinet.
The NSW Government announced the Fixing Country Roads program in 2014 with the aim of building more efficient road freight networks. Transport for NSW and Infrastructure NSW jointly administer this program, which funds local councils to deliver projects that help connect local and regional roads to state highways and freight hubs.
This audit assessed whether these two programs (Resources for Regions and Fixing Country Roads) were being effectively managed and achieved their objectives. In making this assessment, we answered the following questions:
- How well are the relevant agencies managing the assessment and recommendation process?
- How do the relevant agencies ensure that funded projects are being delivered?
- Do the funded projects meet program and project objectives?
The audit focussed on four rounds of Resources for Regions funding between 2013–14 to 2015–16, as well as the first two rounds of Fixing Country Roads funding in 2014–15 and 2015–16.
The project selection criteria are consistent with the program objectives set by the NSW Government, and the RIAP applied the criteria consistently. Probity and record keeping practices did not fully comply with the probity plans.
The assessment methodology designed by Infrastructure NSW is consistent with2 the program objectives and criteria. In the rounds that we reviewed, all funded projects met the assessment criteria.
Infrastructure NSW developed probity plans for both programs which provided guidance on the record keeping required to maintain an audit trail, including the use of conflict of interest registers. Infrastructure NSW and Transport for NSW did not fully comply with these requirements. The relevant agencies have taken steps to address this in the current funding rounds for both programs.
NSW Procurement Board Directions require agencies to ensure that they do not engage a probity advisor that is engaged elsewhere in the agency. Infrastructure NSW has not fully complied with this requirement. A conflict of interest arose when Infrastructure NSW engaged the same consultancy to act as its internal auditor and probity advisor.
While these infringements of probity arrangements are unlikely to have had a major impact on the assessment process, they weaken the transparency and accountability of the process.
Some councils have identified resourcing and capability issues which impact on their ability to participate in the application process. For both programs, the relevant agencies conducted briefings and webinars with applicants to provide advice on the objectives of the programs and how to improve the quality of their applications. Additionally, Transport for NSW and the Department of Premier and Cabinet have developed tools to assist councils to demonstrate the economic impact of their applications.
The relevant agencies provided feedback on unsuccessful applications to councils. Councils reported that the quality of this feedback has improved over time.
Recommendations
- By June 2018, Infrastructure NSW should:
- ensure probity reports address whether all elements of the probity plan have been effectively implemented.
- By June 2018, Infrastructure NSW and Transport for NSW should:
- maintain and store all documentation regarding assessment and probity matters according to the State Records Act 1998, the NSW Standard on Records Management and the relevant probity plans
Infrastructure NSW is responsible for overseeing and monitoring projects funded under Resources for Regions and Fixing Country Roads. Infrastructure NSW effectively manages projects to keep them on track, however it could do more to assure itself that all recipients have complied with funding deeds. Benefits and outcomes should also start to be measured and reported as soon as practicable after projects are completed to inform assessment of future projects.
Infrastructure NSW identifies projects experiencing unreasonable delays or higher than expected expenses as 'at‑risk'. After Infrastructure NSW identifies a project as 'at‑risk', it puts in place processes to resolve issues to bring them back on track. Infrastructure NSW, working with Public Works Advisory regional offices, employs a risk‑based approach to validate payment claims, however this process should be strengthened. Infrastructure NSW would get better assurance by also conducting annual audits of compliance with the funding deed for a random sample of projects.
Infrastructure NSW collects project completion reports for all Resources for Regions and Fixing Country Roads funded projects. It applies the Infrastructure Investor Assurance Framework to Resources for Regions and Fixing Country Roads at a program level. This means that each round of funding (under both programs) is treated as a distinct program for the purposes of benefits realisation. It plans to assess whether benefits have been realised once each project in a funding round is completed. As a result, no benefits realisation assessment has been done for any project funded under either Resources for Regions or Fixing Country Roads. Without project‑level benefits realisation, future decisions are not informed by the lessons from previous investments.
Recommendations
- By December 2018, Infrastructure NSW should:
- conduct annual audits of compliance with the funding deed for a random sample of projects funded under Resources for Regions and Fixing Country Roads
- publish the circumstances under which unspent funds can be allocated to changes in project scope
- measure benefits delivered by projects that were completed before December 2017
- implement an annual process to measure benefits for projects completed after December 2017
- By December 2018, Transport for NSW and Infrastructure NSW should:
- incorporate a benefits realisation framework as part of the detailed application.
Appendix one - Response from agencies
Appendix two - Maps of funded projects
Appendix three - About the audit
Appendix four - Performance auditing
Parliamentary reference - Report number #300 - released 17 May 2018
Actions for WestConnex: Assurance to the Government
WestConnex: Assurance to the Government
This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.
The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.
This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.
Parliamentary reference - Report number #247 - released 18 December 2014
Actions for Volume Seven 2014 Focusing on Transport
Volume Seven 2014 Focusing on Transport
All agencies in transport cluster received unqualified audit opinions for the year ended 30 June 2014. The quality of financial reporting continues to improve with the number of misstatements identified during audits falling for the fifth year in a row.
Actions for Volume Six 2014 focusing on Premier and Cabinet
Volume Six 2014 focusing on Premier and Cabinet
All agencies in the NSW Premier and Cabinet cluster received unqualified audit opinions for the year ended 30 June 2014. Overall financial reporting has improved. Agencies submitted their financial statements earlier than last year and for the third year in a row there has been a reduction in the number of misstatements identified during audits.
Actions for Volume Four 2014 focusing on New South Wales State Finances
Volume Four 2014 focusing on New South Wales State Finances
For the second consecutive year, the General Government and Total State Sector Accounts received an unqualified auditor’s opinion following more than a decade of qualifications. The quality and timeliness of financial reporting across the NSW public sector has continued to improve. Compared to previous years, there were fewer errors in agencies’ 2013–14 financial statements submitted for audit and used for whole-of-government financial reporting.
Actions for Volume Three 2014 focusing on Parliamentarian Entitlements
Volume Three 2014 focusing on Parliamentarian Entitlements
New South Wales Members of Parliament, when spending their additional entitlements, substantially complied with the Parliamentary Remuneration Tribunal’s Determination for the year-ended 30 June 2013.
Actions for Regional Road Funding - Block Grant and REPAIR Programs
Regional Road Funding - Block Grant and REPAIR Programs
In 2013–14, Roads and Maritime Services (RMS) provided over $170 million to local councils through the Block Grant and REPAIR programs to spend on Regional Roads. Regional Roads are the link between State Roads and Local Roads.
Parliamentary reference - Report number #241 - released 8 May 2014
Actions for Volume One 2014 - Areas of focus from 2013
Volume One 2014 - Areas of focus from 2013
Today the Auditor-General of New South Wales, Grant Hehir, released his Volume One Report to Parliament for 2014. The observations included in this report are designed to inform readers of common findings from the 2013 financial and performance audits so agencies and audit committees can use them to identify issues that may be relevant to their organisations.
Actions for Volume Eight 2011 Focus on Transport and Ports
Volume Eight 2011 Focus on Transport and Ports
The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effectiveness of program initiatives for increasing container freight movements by rail. The Corporation should review the underlying causes hindering growth in the rail mode and develop and implement strategies to address the unfavourable trend.